Supplementary
Agenda
West Dunbartonshire Council
Date: Wednesday, 30 October 2024
Time: 16:00
Format: Hybrid Meeting
Contact:  Carol-Ann Burns, Senior Democratic Services Officer
Email: carol-ann.burns@west-dunbarton.gov.uk
committee.admin@west-dunbarton.gov.uk
Dear Member
ITEM TO FOLLOW
I refer to the agenda for the above meeting that was issued on 17 October 2024 and
now enclose a copy of the undernoted report relating to Item 9 which was not
available for issue at that time. 
Yours faithfully
PETER HESSETT
Chief Executive
Note referred to:-/

Page 2

Note referred to:-
ITEM 9.  EXXON INFRASTRUCTURE PROJECT UPDATE  265 – 269
Submit report by the Chief Officer – Regulatory and Regeneration; -
(a) advising of the recent cost pressures that have impacted on the Exxon
Infrastructure Project;
(b) seeking agreement of a revised scope for the Project and to increase the
budget by £0.8m so that the Project’s outcomes can continue to be
delivered; and
(c) to agree to seek approval from City Region for these changes.
Distribution:-
Provost Councillor Karen Murray Conaghan Councillor June McKay
Councillor James Bollan  Councillor John Millar
Councillor Ian Dickson Councillor Lawrence O’Neill
Councillor Diane Docherty Councillor Lauren Oxley
Councillor Fiona Hennebry Councillor Chris Pollock
Councillor Gurpreet Singh Johal Councillor Martin Rooney
Councillor Daniel Lennie Councillor Gordon Scanlan
Councillor David McBride Councillor Hazel Sorrell
Councillor Jonathan McColl Councillor Clare Steel
Councillor James McElhill Councillor Sophie Traynor
Councillor Michelle McGinty
Chief Executive
Chief Officers
Date of issue: 24 October 2024

Page 3

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officers (Roads & Neighbourhood) & (Regeneration and
Regulatory)
Council: 30 October 2024
Subject: Exxon Infrastructure Project Update
1. Purpose
1.1 To note the recent cost pressures that have impacted on the Exxon
Infrastructure Project, to agree a revised scope for the Project and to
increase the budget by £0.8m so that the Project’s outcomes can continue to
be delivered, and to seek approval from City Region for those changes.
2. Recommendations
2.1 It is recommended that Council:
i) notes the inflationary and utility price increases that have impacted on the
Project costs since 2023.
ii) notes that an additional contribution is expected from Glasgow City
Region to offset some of the additional capital costs.
iii) approves the revised scope, at a cost of an additional £0.8m capital
funding which has an additional borrowing requirement of £21,000 per
annum.
iv) submits a Change Control Request to Glasgow City Region.
v) proceeds with the finalisation and signing of the construction contracts.
vi) notes that the marketing of the site will commence.
vii) notes the anticipated future income from sales and leasing of the
development platforms.
viii) notes the potential future availability of the £1m payment from Esso to
contribute towards the project.
ix) approves the continuation of discussions on future funding from Glasgow
City Region, and any other external funding source.
3. Background
3.1 At its meeting on 21 June 2023, Council approved the £44.325m Final
Business Case for the infrastructure proposals for the Exxon site and agreed
that the Business Case be presented to Glasgow City Region for approval.
Council also agreed to commence discussions with the City Region regarding
ITEM 9
Page 265

Page 4

securing funding that might be available from the Region following a region-
wide project reprogramming exercise. At the June 2023 meeting, Council
agreed to commit up to £20.344m towards the project, with the City Region
committing to funding the balance of £23.991m. The revenue cost associated
with borrowing £20.334m is estimated as £10.675m over 20 years,
approximately £534k per annum (based on current interest rates).  There is
further capital funding anticipated from City Region as a result of the surplus
funds that became available when the Glasgow Airport Rail Link was
withdrawn from the City Region programme.
3.2 The main elements of the approved project are the construction of a spine
road through the site, a new railway underpass transport access at the
western end of the site, a new overpass at the east, and creation of three
development platforms, or large development plots, across the site. Both the
infrastructure and development platforms provide the site with a strategic
advantage and de-risk the site for potential developers and operators, making
it more marketable than a site without any infrastructure investment. The
anticipated economic growth of 520.8, expressed in the Final Business Case
as Gross Value Added (GVA), is derived in part from the construction jobs
created during the construction period, but mainly from the more sustainable
jobs and growth from new industry and commerce as the site is built out.
These long term benefits flow directly from the platforming of the site. The
preparation and servicing of the development platforms results in immediately
developable land. The approved project has a Benefit Cost Ratio of 11 i.e. for
each pound spent, there is an anticipated benefit to the wider economy of
£11.  This and the GVA levels are considered some of the highest within the
Glasgow City Region projects to date.
4. Main Issues
4.1 The detailed project design required some refinement after the Full Business
Case was approved by Council, because at the time contractors had to make
assumptions about the costs of key structures such as the eastern overbridge
and the underpass structures at the western junctions, and the traffic
signalisation of the Dunglass roundabout, which had to be linked to the traffic
signals at the Western Junction per Transport Scotland requirements. The
impact of traffic management costs in particular could not be fully understood
at the time, and the development of the design in conjunction with the
requirements of Transport Scotland alone has increased the total cost by
£0.6m.
4.2 The project programme has also been impacted by a 10-month delay on
Esso’s land remediation due to the complexity of the site contamination. This
delay has had a substantial inflationary impact on the final project cost,
however one of the most significant costs increases has been the utility
diversions, which has increased from £1.2m to £2.44m. This has been an
issue common to many other major construction projects, and has been the
experience in other City Deal projects across the Region.
4.3 The Council’s contractor for the main works contract, Balfour Beatty provided
their finalised construction cost at the end of September 2024. Taking
account of the inflationary and traffic management factors mentioned above
the construction cost increase is £4.41m, and together with the utility costs
Page 266

Page 5

increases of £1.24m, the total cost of delivering the project in full has
increased from £44.325m to £49.965m. There are further staffing and project
management costs that take the total cost to £50.201m. With the anticipated
additional funds from City Deal, the net cost of the approved project would be
£48.375m.  The possession approval process is underway for the required
possession date.  Network Rail have advised that the costs are anticipated to
remain the same as previously quoted however cost certainty will be received
when the requested possession date is confirmed by them.  Confirmation is
imminent.
4.4 Since receiving notification of the increased costs from Balfour Beatty, the
Exxon Project Board have undertaken an appraisal that considers the
financial and economic consequences of altering the scope and minimising
additional project costs. All of the major transport infrastructure including the
spine road and access to the site at either side and one development
platform at the most central part of the site can be achieved with an increase
of £0.8m. With the anticipated income from City Deal, the net cost is
£45.105m. The revised project has a GVA of 331.4 and a Benefit Cost Ratio
of 7.4. This will de-risk the site to some extent but it will require additional
infrastructure at a cost to the developer. Initial discussions have taken place
with the City Region Programme Management Office. Any change to the
project, significant or otherwise will be subject to a Change Control Request,
but it is anticipated that the revised values will be acceptable as they remain
higher than most, in terms of GVA and Benefit Cost Ratio. Due to the minimal
risk that the Change Control Request won’t be approved, it is recommended
that Council proceeds with the finalisation of the construction contracts (the
Balfour Beatty contract plus the Network Rail plus the Western Underbridge
works) pending the Change Control Request being  approved in order to
maintain the programme and fix costs.  If there is a need to change any
element of the project it can be dealt with as a Compensation Event
mechanisms within the contracts.
4.5 The Exxon Project Board has recommended that the promotion and
marketing of the site to developers gets underway. The most up to date
valuation of the site indicates that upwards of £3m in capital receipts can be
anticipated from sale or lease of the development plots, which will go some
way to offsetting initial capital costs. The inclusion of platforming on one part
of the site not only enhances the value of the site, it is also understood that it
increases the likelihood of early sale. It is recommended to Council that a
marketing strategy which includes the potential for a development partner or
developers to share the costs of the remaining platforms is produced. In
doing this, we may also be able to demonstrate the relative attractiveness of
the platforms, and therefore quantify the financial benefit of bringing
development platforms to market, compared with unfinished ground.
4.6 The revised scope has been appraised by the Council’s planning service.
The Chief Planning Officer has confirmed that it is unlikely to raise any
significant planning issues and can be carried out under the existing
consents on the site, subject to compliance with current planning conditions.
4.7 Previous reports have noted that Esso Petroleum Limited are due to provide
a “dowry” sum of £1M to the Council on the transfer of land.  There is a
possibility that this sum may in whole or part be used to effect Environmental
Page 267

Page 6

Insurance.  The Council’s Insurance and geotechnical / environmental
advisers will be asked to review previous assumptions in this regard and any
sums not required for insurance may be available to offset costs.  This may
only be fully understood once platforming operations have been completed
but is mentioned here for completeness. 
4.8 Finally it should be noted that the assumptions around land sales have not to
date included the area of around 5 acres or so to the north of the railway line
which accommodated the former Highland Fuels Depot.  The disposal of this
land in due course is likely to bring an additional receipt to the Council.
5. People Implications
5.1 There are no personnel issues.
6. Financial Implications
6.1 Taking account of the additional contribution anticipated from City Deal,
the capital cost increase to the Council for the revised scope is £0.8m.
This additional borrowing requirement of £0.8m has an estimated revenue
implication of £0.420m which will be spread over the life of the loan (at
approximately £21k per annum – an estimate is based on a 20 year loan
at 5% - this is indicative as the actual amount will depend on the interest
rate when the borrowing occurs). Other avenues to offset costs will be
explored as noted above, albeit there is no current indication of further
direct grant funding for the project beyond the sums noted from the City
Region.
6.2 Future disposals are not accounted for in the cost breakdown of the
works above, however as noted in paragraph(s) 4.5 and 4.8 above,
income is expected from land sales.
7. Risk Analysis
7.1 There are a number of project risks associated with the development at
the Exxon project site and these are contained within the project risk
register and updated by the Project Board on a regular basis. The Project
Board is made up of senior officers from all key services.
7.2 Mitigation measures on early value engineering of design options were
taken before costs were refined, therefore reducing some risks related to
cost increases, as previously identified.
7.3 The additional contribution from City Deal is subject to final agreement by
UK and Scottish Governments, however it is considered that the risk of
this not being forthcoming is minimal.
7.4 There is a risk that reducing the immediately developable land on site will
have a detrimental effect on the marketability of the site and the
anticipated capital receipts and GVA will not be realised or will be
significantly delayed.
Page 268

Page 7

7.5 There is a remote risk that the City Region will not approve the Change
Control Request as we anticipate.  This has been mitigated through
advance discussions with City Region Programme Management Office
staff and the form of contract would permit any changes required by the
Programme Management Office to be instructed at a later point with the
cost of such changes being arrived at in a clear and transparent manner.
8. Equalities Impact Assessment
8.1 A completed EIA was undertaken as part of the Outline Business Case, and
there have been no material changes in terms of impact on people with
protected characteristics since.
9. Consultation
9.1 Consultation with all key stakeholders is progressing as we continue to work
as part of the Glasgow City Region.
9.2 Legal Services, Finance, Planning and the Corporate Procurement Unit are
regularly consulted through their participation in the Exxon project board.
10. Strategic Assessment
10.1 At its meeting on 26 October 2022, the Council agreed that one of its main
strategic priorities for the Strategic Plan 2022 - 2027 is:
• Our economy is strong and flourishing
10.2 The proposals within this report are specifically designed to deliver on this
priority.
Alan Douglas
Chief Officer: Regulation and Regeneration
Gail Macfarlane
Chief Officer: Roads and Neighbourhood
Date: 24/10/24
Person to Contact: Gillian McNamara
gillian.mcnamara@west-dunbarton.gov.uk
Appendix: None
Background Papers: City Region Update December 2023
Exxon Site Project Full Business Case June 2023
Equalities Impact Assessment November 2018.
Environmental Impact Assessment -DC20/088 – Planning
Application – Documents.
Wards Affected: All