WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Council – 28 August 2024
___________________________________________________________________
Subject: General Services Revenue Budgetary Control Report to 30 June 2024
(Period 3)
1. Purpose
1.1 The purpose of this report is to advise Council of the 2024/25 Revenue
Budget position at 30 June 2024 and the forecast position of the General
Fund Reserve as at 31 March 2025.
2. Recommendations
2.1 Council is asked to note a current projected annual underlying adverse
variance on the revenue account of £2.542m (0.88% of total budget).
3. Background
3.1 At the meeting of West Dunbartonshire Council (the Council) on 6 March
2024, Members agreed the revenue estimates for 2024/2025. A total net
budget of £284.668m was approved for General Services.
3.2 Since the budget was agreed, as reported to Council in June 2024, additional
funding has been provided by the Scottish Government of £3.916m to fund
the pay uplift to a minimum rate of £12 per hour for workers providing direct
adult social care in the third and independent sectors. Also reported to Council
in June was further budget adjustments due to:
• £1.129m to support the freezing of Council Tax.
• £0.860m from the release of an unspent matched European Structural
Fund balance (ESF) which was returned to the general fund.
• £1.051m made available from the revised reduction in employer pension
contributions.
3.3 The budget has also been adjusted to remove the effects of the Criminal
Justice specific grant which is paid direct to HSCP; removing both the cost
and income from the General Services budget while maintaining a 2024/25
balanced budget.  The revised 2024/25 Revenue Budget of £289.927m
(excluding earmarked reserves) is made up as follows:
ITEM 12

Page 2

Service £m £m
Agreed budget 6 March 2024   284.668
Additional Resources:   
Additional Share of £230m for
Social Care Uplift 
HSCP Requisition 3.916 
Share of £62.7m in relation to
Council Tax Freeze 
Strategy to rebuild
reserves
1.129 
Release of unspent matched
ESF funding 
Strategy to rebuild
reserves
0.860 
Increased Pension benefit Strategy to rebuild
reserves
1.051 
Total Additional Resources   6.956
Base Budget Adjustment:   
Removal of Criminal Justice
Specific Grant 
Criminal Justice
Requisition 
(1.697)
Total adjustments   5.259
Revised budget as at Period 3   289.927  
4. Main Issues 
4.1 The summary report at Appendix 1 highlights a projected net annual
underlying adverse variance (overspend) of £2.542m (0.88% of the total
budget). Appendix 2 provides more detailed service reports by Chief Officer.
The main reason for this overspend is detailed in the table below with
explanations provided in Appendix 3.  In addition, services are projecting the
use of £0.668m of earmarked reserves.   
£m £m
Service Variances  
Roads and Neighbourhoods – Adverse - A working
group has been established to review where any
anticipated overspends can be reduced and where there
may be options for additional income generation.
2.329 
Education, Learning and Attainment - Adverse  0.395 
Citizens, Culture and Facilities -  Favourable (0.190) 
People and Technology – Adverse 0.053 
Other service variance less than £0.050m  - Favourable (0.045) 
Total Service Variance  2.542
Strategy to rebuild reserves:  
Reduction in employer pension contribution rate (1.051) 
Additional RSG funding re Council Tax Freeze (1.129) 
Release of Matched ESF funding (0.860) 
Transfer to reserves re SPFO reductions – after in year
savings of £5.332m  
(1.978) 
Transfer to Earmarked reserves  (5.018)
Projected spend of earmarked balances  0.668
Total Variance at Period 3  (1.808)

Page 3

4.2 In June (as per paragraph 3.2) a strategy was agreed to replenish general
reserves from:
• additional funding from the Revenue Support Grant in relation to the
council tax freeze
• the release of matched ESF funding
• additional revised benefit from reduction in employer pension
contributions. 
The saving from the employer pension contribution rate as explained at
paragraph 4.5, would be smoothed over 4 years thus generating £5.332m in
savings in the years 2024/25-2027/28.  Additional savings from the reduction
in pension contributions will be added to an earmarked reserve to be used to
balance the budget in future years.   
4.3 Information on any projected annual variances in excess of £0.050m are
highlighted and noted within Appendix 3, with additional information on action
being taken to minimise or mitigate overspends where possible. 
4.4 A list of agreed efficiencies and management adjustments totalling £6.649m is
shown within Appendix 4.  Current indications show, £6.556m is on target to
be achieved.  However, Appendix 4 also shows that it is anticipated that
£0.093m will not be achieved and will be funded by the smoothing fund for
2024/25 only, with the expectation that the full saving will be achieved in
future years. 
4.5 On 20 December 2023, a report to Council presented the financial benefit to
the Council as a consequence of the Strathclyde Pension Fund (SPF) Board
reducing the employer pension contribution rate in the years 2024/25 and
25/26 from 19.3% to 6.5%.  Service superannuation budgets have been
reduced via a virement to a central reserve, to reflect the saving.  The Council
agreed to smooth the total saving over 4 years thus generating £5.332m in
savings in 2024/25 with the balance to be used in future years as agreed at
Council on 6 March 2024.  The budgeted transfer to Reserves to date is
£7.310m which reflects the current in year reduction of the service budget.
The underspend of £1.978m will be transferred to an earmarked reserve to be
used to balance the budget in future years. 
General Fund Reserves Position  
4.6 Appendix 5 shows the latest position in respect of Unallocated and Earmarked
Reserves and shows the projected balance as at 31 March 2025: 
Unearmarked
Balance (£m)
Earmarked
Balance (£m)
Total General Fund
Reserves (£m)
As at 31 March 2024
(draft)
4.418 9.115 13.533
In year movements 1.607 4.844 6.451
Projected in year use
of reserves
(2.542) (0.668) (3.210)
Projected Balance 
as at 31 March 2025
3.483 13.291 16.774

Page 4

4.7 A breakdown of the 2024/25 earmarked balances and the movements in
reserves is summarised in Appendix 6.  
4.8 The Council’s General Fund contingency (Prudential Target) is set at 3% of
net expenditure for 2024/25 and amounts to £5.400m. After taking into
consideration the forecast adverse outturn position of £2.542m at 30 June
2024, the Council is currently forecast to have £1.917m below the current
Prudential Target.  The services have mitigating actions to reduce their
projected adverse variances.  In addition, the June Finance Update advised
how the additional benefit from the reduction in pension contributions would
continue to rebuild reserves with an additional £1.621m over 2025-2027. 
5. Option Appraisal 
5.1 No option appraisal was required for this report. 
6. People Implications 
6.1 There are no people implications. 
7. Financial and Procurement Implications 
7.1 The report notes the projected in-year financial position for both General
Services revenue and capital budgets. 
8. Risk Analysis 
8.1 The main risks are as follows: 
(a) The present variances should be viewed in the knowledge that there are
a number of variable factors which could arise between now and 31
March which could affect the year end; 
(b) As a consequence of current market conditions, capital receipts may
either not be received or they may be less than anticipated. The budget
assumption is that all capital receipts achieved in 2024/25 will be used to
the principal and premium repayments within the loan charges budget.
Any shortfall in capital receipts below that budgeted will affect the
revenue budget position. This is being closely monitored and any issues
will be reported to Council; 
(c) As a consequence of current market conditions, inflation is at an all-time
high and interest rates continue to rise. To forecast for the full year costs
budget assumptions have been required (particularly around energy and
interest costs). These assumptions continue to change regularly and
therefore it is likely that the projected year end budgetary position will
change from that reported;

Page 5

9. Equalities Impact Assessment (EIA) 
9.1 No equalities impact assessment was required in relation to this report. 
10. Environmental Sustainability 
10.1 No assessment of environmental sustainability was required in relation to this
report. 
11. Consultation 
11.1 All services involved in delivering the revenue and capital budgets have been
consulted in the compilation of this report. 
12. Strategic Assessment 
12.1 Proper budgetary control and sound financial practice are cornerstones of
good governance and support Council and officers to pursue the strategic
priorities of the Council’s current Strategic Plan. This report forms part of the
financial governance of the Council. 
__________________
Laurence Slavin
Chief Officer – Resources
Date: 28 August 2024
__________________________________________________________________
Person to Contact: Carol Alderson. Finance Manager 
Council Offices, Church Street, Dumbarton  
E-mail: carol.alderson@west-dunbarton.gov.uk 
Appendices: Appendix 1 - Revenue Budgetary Control 2024/25 
– Corporate Summary; 
Appendix 2 -  Revenue Budgetary Control 2024/25
– Chief Officer Summaries;
Appendix 3 - Analysis of Revenue Variances over 
£50,000; 
Appendix 4 -  Monitoring of Efficiencies 
Appendix 5 -  Reconciliation of General Fund Reserves
Appendix 6 - Monitoring of Earmarked Balances 
Background Papers: 
• Ledger output – Period 3;
• General Services Revenue Estimates 2024/25   
Wards Affected           All Wards