Changes to Capital Plan and Implications Appendix 3
RESOURCES
Project  - RES9 2023/24
Reprofiling 
Current
Year 2024/25  2025/26  2026/27  2027/28  Future Years  Total Capital
Plan
Strathleven Place (formerly part of Glencairn House project) - Original 50                1,540           -              -          -         -                                1,590
Strathleven Place (formerly part of Glencairn House project) -
Revised 1,590           -              -          -         -                                1,590
Explanation
Project delayed due to internal resources and impact of Glencairn House project completion.
Project  - RES11 2023/24
Reprofiling 
Current
Year 2024/25  2025/26  2026/27  2027/28  Future Years  Total Capital
Plan
Building Upgrades and H&S - lifecycle & reactive building upgrades -
original 331              2,791           2,781          2,781      2781 13,905                         25,370
Building Upgrades and H&S - lifecycle & reactive building
upgrades - Revised 3,122           2,781          2,781      2,781     13,905                         25,370
Explanation
Carry forward required for retentions for projects and projects agreed in pipeline
Project - RES13
2023/24
Reprofiling 
Current
Year 2024/25  2025/26  2026/27  2027/28  Future Years  Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Depot Rationalisation - Original 238              500              3,000          4,590      -         -                                8,328
Depot Rationalisation - Revised 500              3,000          4,828      -         -                                8,328
Explanation
Awaiting feasibility report on garage replacement. Once received the will be reviewed by services and progress to detailed design.

Page 2

CITIZENS CULTURE AND FACILITIES
Project - CCF 1
2023/24
Reprofiling
Current Year
2024/25 2025/26 2026/27 2027/28 Future Years  Total Capital
Plan
£'000 £'000 £'000 £'000 £'000 £'000 £'000
Heritage Capital Fund (132) 389              -              -          -         -                                   257
Heritage Capital Fund 257              -              -          -         -                                   257
Explanation
Acceleration of works
Project - CCF 2
2023/24
Reprofiling
Current Year
2024/25 2025/26 2026/27 2027/28 Future Years  Total Capital
Plan
£'000 £'000 £'000 £'000 £'000 £'000 £'000
Transformation of Infrastructure Libraries and Museums - Original 95                -               -              -          -         -                                     95
Transformation of Infrastructure Libraries and Museums - Revised 95                -              -          -         -                                     95
Explanation
Earmarked for future works within retained libraries
Project - RR2
2023/24
Reprofiling
Current Year
2024/25 2025/26 2026/27 2027/28 Future Years  Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Re -imagine Antonine Wall - Original 5                  10                -              -          0 -                                     15
Re -imagine Antonine Wall - Revised 15                -              -          -         -                                     15
Explanation
Multi year project
Project - RR7
2023/24
Reprofiling 
Current
Year 2024/25  2025/26  2026/27  2027/28  Future Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Regeneration Fund - Original 265              350              1,530          974         970                4,089
Regeneration Fund - Revised 615              1,530          974         970                        4,089
Explanation
These are multi-year programmes of work/projects that are subject to external factors.

Page 3

Project - RR8
2023/24
Reprofiling 
Current
Year 2024/25  2025/26  2026/27  2027/28  Future Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Place Based Investment - Original 219              310              471             471         0 -                                1,471
Place Based Investment - Revised 529              -         -                                   529
Explanation
Project - RR10
2023/24
Reprofiling 
Current
Year 2024/25  2025/26  2026/27  2027/28  Future Years  Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000
Level Up Funding - Original 1,171           11,959         2,200          -          -         -                              15,330
Level Up Funding - Revised 11,959         3,371          -          -         -                              15,330
Explanation
These are multi-year programmes of work/projects that are subject to external factors.
Project - RR12
2023/24
Reprofiling 
Current
Year 2024/25  2025/26  2026/27  2027/28  Future Years  Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000
District Heating Network Expansion - Original 140              2,500           4,609          3,095      760        -                              11,104
District Heating Network Expansion - Revised 1,500           5,000          3,595      1,009     -                              11,104
Explanation
Unable to commence construction works until agreements are in place with Golden Jubilee Hospital and other partners.
ROADS & NEIGHBOURHOOD
Project - R&N1
2023/24
Reprofiling 
Current
Year 2024/25  2025/26  2026/27  2027/28  Future Years  Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Infrastructure - Roads (90) 2,544           2,544          2,544      2,544     12,720                         22,806
Infrastructure - Roads 2,454           2,544          2,544      2,544     12,720                         22,806
Explanation
Acceleration of Works
These are multi-year programmes of work/projects that are subject to external factors. Project has been reduced as it is not clear yet whether there will be further funding
provided.

Page 4

Project - R&N3
2023/24
Reprofiling 
Current
Year 2024/25  2025/26  2026/27  2027/28  Future Years  Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  R  £'000
Street lighting and associated electrical infrastructure - Original 14                -               -              -          -         -                                     14
Street lighting and associated electrical infrastructure - Revised 14                -              -          -         -                                     14
Explanation
Rolling programme of column upgrade works. Some delay in finalising programme for last year but will continue into 24/25
Project - R&N4
2023/24
Reprofiling 
Current
Year 2024/25  2025/26  2026/27  2027/28  Future Years  Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Flood Prevention - Original 189              150 -              -          -         -                                   339
Flood Prevention - Revised 339 -              -          -         -                                   339
Explanation
Limited uptake on property level protection however scheme will be continued into 24/25. Additional evaluation of Clydebank Surface Water Plan and River Leven
Study planned for 2024/25
Project - R&N5
2023/24
Reprofiling 
Current
Year 2024/25  2025/26  2026/27  2027/28  Future Years  Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Vehicle Replacement - Original (135) 3,000 1,939          1,040      1,040     5,200                           12,084
Vehicle Replacement - Revised 2,865 1,939          1,040      1,040     5,200                           12,084
Explanation
Acceleration of Project
Project - R&N9
2023/24
Reprofiling 
Current
Year 2024/25  2025/26  2026/27  2027/28  Future Years  Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Roads Plant - Original 66                -               -              -          -         -                                     66
Roads Plant - Revised 66                                     66
Explanation
Plant purchased, awaiting invoices

Page 5

Project - R&N10
2023/24
Reprofiling 
Current
Year 2024/25  2025/26  2026/27  2027/28  Future Years  Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
A813 Road Improvement Phase 1 - Original 150              493 -              -          -         -                                   643
A813 Road Improvement Phase 1 - Revised 643 -              -          -         -                                   643
Explanation
Project - R&N12
2023/24
Reprofiling 
Current
Year 2024/25  2025/26  2026/27  2027/28  Future Years  Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Traffic Signal Upgrades - Original 26                -               -              -          -         -                                     26
Traffic Signal Upgrades - Revised 26                -              -          -         -                                     26
Explanation
Works delayed awaiting funding decision from LUF.Further lighting upgrades will be completed this year.
Project - R&N13
2023/24
Reprofiling 
Current
Year 2024/25  2025/26  2026/27  2027/28  Future Years  Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Gruggies Burn Flood Prevention - Original 363              7,270 6,820 -          -         -                              14,453
Gruggies Burn Flood Prevention - Revised 551              742             6,340      6,820     -                              14,453
Explanation
Project - R&N14
2023/24
Reprofiling 
Current
Year 2024/25  2025/26  2026/27  2027/28  Future Years  Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Electrical Charging Points - Rapid Charge Original 15                -               -              -          -         -                                     15
Electrical Charging Points - Rapid Charge Revised 15                -              -          -         -                                     15
Explanation
New chargers installed however delay to commissioning and testing. Will be delivered 24/25
Road Upgrade completed however delay in undertaking footway extension whilst land ownership resolved. Designs ready to go to start construction on the footway
upgrade
Priority given to progressing consultation and concept design due to notification submission target of March 2024. Outline design will be delivered over 2024/25 with
detailed design also progressed with planned delivery December 2025. Significant costs associated with design elements.

Page 6

Project - R&N16
2023/24
Reprofiling 
Current
Year 2024/25  2025/26  2026/27  2027/28  Future Years  Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Vehicle Replacement Strategy - Original 500              900              -              -          -         -                                1,400
Vehicle Replacement Strategy - Revised 1,400           -              -          -         -                                1,400
Explanation
This budget complement the wider vehicle replacement budget with a focus this year on Greenspace plant/vehicles.
Project - R&N18
2023/24
Reprofiling 
Current
Year 2024/25  2025/26  2026/27  2027/28  Future Years  Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Public non-adopted paths and roads - Original 394              225              225             225         225        1,125                             2,419
Public non-adopted paths and roads - Revised 619              225             225         225        1,125                             2,419
Explanation
Projects have been identified and are currently being developed for tendering.
Project - R&N20
2023/24
Reprofiling 
Current
Year 2024/25  2025/26  2026/27  2027/28  Future Years  Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Vale of Leven Cemetery - original 60                -               -              -          -         -                                     60
Vale of Leven Cemetary - revised 60                -              -          -         -                                     60
Explanation
Retentions for project have extended inti 24/25. The project works are complete.
Project - R&N21
2023/24
Reprofiling 
Current
Year 2024/25  2025/26  2026/27  2027/28  Future Years  Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Allotment Development - Original 91                186                       277
Allotment Development  - Revised 150 127             -          -         -                                   277
Explanation
Tender documents currently being developed.

Page 7

Project - R&N23
2023/24
Reprofiling 
Current
Year 2024/25  2025/26  2026/27  2027/28  Future Years  Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Play Area Upgrade Programme - Original 32                449 100             100         100        534                               1,315
Play Area Upgrade Programme - Revised 481 100             100         100        534                               1,315
Explanation
Longer than anticipated lead time for steel used in construction of play equipment.
Project - R&N25
2023/24
Reprofiling 
Current
Year 2024/25  2025/26  2026/27  2027/28  Future Years  Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Whitecrook Tennis Court Upgrade - Original 15                -               -              -          -         -                                     15
Whitecrook Tennis Court Upgrade - Revised 15                -              -          -         -                                     15
Explanation
Retentions to be paid 24/25
Project - R&N26
2023/24
Reprofiling
Current Year
2024/25 2025/26 2026/27 2027/28 Future Years  Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
East End Park Resurfacing - Original (6) 385              -              -          -         -                                   379
East End Park Resurfacing - Revised 379              -              -          -         -                                   379
Explanation
Acceleration of Project
Project - R&N28
2023/24
Reprofiling
Current Year
2024/25 2025/26 2026/27 2027/28 Future Years  Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Balloch Mountain Bike Track - Original 10                590 -              -          -         -                                   600
Balloch Mountain Bike Track - Revised 600 -              -          -         -                                   600
Explanation
Awaiting match funding decision from Sportscotland

Page 8

Project - R&N29
2023/24
Reprofiling
Current Year
2024/25 2025/26 2026/27 2027/28 Future Years  Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Pappert 2G Pitch - Original 12                230 -              -          -         -                                   242
Pappert 2G Pitch - Revised 242 -              -          -         -                                   242
Explanation
Tender documents are currently being developed
Project - R&N31
2023/24
Reprofiling
Current Year
2024/25 2025/26 2026/27 2027/28 Future Years  Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Exxon City Deal - Original 10,797         9,845 10,820 4,277 1,162               36,901
Exxon City Deal - Revised 3,000           20,000 11,067    2,834     -                              36,901
Explanation
EDUCATION
Project - Educ1
2023/24
Reprofiling
Current Year
2024/25 2025/26 2026/27 2027/28 Future Years  Total Capital
Plan
AV Equipment - Education - Original 9                  100 100 100 100 167                                  576
AV Equipment - Education - Revised 109              100             100         100        167                                  576
The reason for reprofiling is that the construction start was delayed due to a delay of the Esso Remediation and third party land  acquisitions. The 28 May 2023 Council
paper confirms that the  increased project cost of £44.325m, which will be split between City Deal £23.991m and Council £20.334m. The original total budget has been
profiled to reflect on the Council paper.
Explanation
Delay in spend in year 1-2 due to covid,  limited access to school and external suppliers. The project has been approached as a roll out programme over a 10 year
period. The current estate consists of ~650 AV Screens (30 Early years, 400 Primary and 220 Secondary) of the 650, 100 were faulty and have now been replaced. 105
screens were of the same age as the failing 100 and have since been replaced. The life expectancy of a board is 7 years. The remaining screens were bought on an ad
hoc basis and as such are being replaced on an ad hoc basis as and when required, either due to failure or incompatibility with modern peripherals/devices regardless of
age. It is impossible to determine when a board will fail hence the non-linear spend. Replacement programme is essential to ensuring a fit for purpose digital learning
environment in all classrooms and early learning centres.

Page 9

Project - Educ4
2023/24
Reprofiling
Current Year
2024/25 2025/26 2026/27 2027/28 Future Years  Total Capital
Plan
Schools Estate Improvement Plan - Original (177) 4,242 0 -                                4,065
Schools Estate Improvement Plan - Revised 4,065 -         -                                4,065
HSCP
Project - HSCP2
2023/24
Reprofiling
Current Year
2024/25 2025/26 2026/27 2027/28 Future Years  Total Capital
Plan
ICT Modernisation HSCP - Original 9                  659              125             125         125 625                               1,668
ICT Modernisation HSCP - Revised 125              397             397         125 625                               1,668
Explanation
Project - HSCP3
2023/24
Reprofiling
Current Year
2024/25 2025/26 2026/27 2027/28 Future Years  Total Capital
Plan
Community Alarm upgrade - Original 23                412 0 0 154 308                                  897
Community Alarm upgrade - Revised 155              333             67           67          276                                  897
Explanation
The Scotland Excel framework for the alarms & peripherals is due to be released July 2023, EDC/WDC now have access to Chubb platform for the call handling (ARC). 
We hope  to go live with this October 2024.  With a live digital platform, we can then start installing the digital alarms and peripherals (Procurement exercise still needs to
be completed). Currently we plan to install 600 alarms and peripherals in 2024/25 and the remaining 1200 alarms and peripherals in 2025/26
The digital strategy is across 2022/27, so covering 2024/25, 2025/26 and 2026/27 financial years. This will drive spend over that period, given where we are in 2024/25
and the position with it going to the board and spend related to this would need to be weighted towards the next 2 financial years. Depending on progress on a
replacement case management system, and if some of that is funded from this budget (whether costs for licences, resources etc) that is also likely to feature in the next
two financial years. Given the procurement exercise required for this, and following experience of other HSCPs who are further forward,these costs are likely to be more
across the next two financial years than the current one.  Come 2027 we'll need to have a new strategy in place for the 2027/28 financial year.
Explanation
Acceleration of projects to deliver the service requirements within a shorter timeframe.

Page 10

PEOPLE & TECHNOLOGY
Project P&T 1
2023/24
Reprofiling
Current Year
2024/25 2025/26 2026/27 2027/28 Future Years  Total Capital
Plan
£'000 £'000 £'000 £'000 £'000 £'000 £'000
ICT Modernisation - Original (69) 551              696             554         806        2,180                             4,718
ICT Modernisation - Revised 482              696             554         806        2,180                             4,718
Explanation
Acceleration of projects
Project P&T 2
2023/24
Reprofiling
Current Year
2024/25 2025/26 2026/27 2027/28 Future Years  Total Capital
Plan
£'000 £'000 £'000 £'000 £'000 £'000 £'000
ICT Security & DR - Original 138              504              792             387         387        1,935                             4,143
ICT Security & DR - Revised 642              792             387         387        1,935                             4,143
Explanation
We were still researching suitable infrastructure upgrade options for end of life equipment, this has now been complete and will be spent this year.
Project P&T 3
2023/24
Reprofiling
Current Year
2024/25 2025/26 2026/27 2027/28 Future Years  Total Capital
Plan
£'000 £'000 £'000 £'000 £'000 £'000
365 Implementation - Original 85                240 240 0 -                                   565
365 Implementation - Revised 325 240 0                   565
Explanation
Reprofiled to ensure that we continue the deployment of sharepoint and one drive through 2025/26.