Democracy Spraffa

Item 11 - Capital Monitoring Report

West Dunbartonshire Council · 28 August 2024
Back to West Dunbartonshire Council — 28 August 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Council 28 August 2024
___________________________________________________________________
Subject: General Services Capital Budgetary Control Report 2024/25 to
Period 3 (30 June 2024)
1. Purpose
1.1 This report provides an update on the General Services capital financial
performance to 30 June 2024.
2. Recommendations
2.1 Committee is asked to:
i) Note the current position of the 2024/25 General Services capital
budget.
ii) Approve £0.04m of additional capital budget for the Agresso
Development project.
iii) Approve the revised completion dates detailed in appendix 3.
iv) Note an in-year variance of £15.786m due to reprofiling of projects.
3. Background
3.1 On 6 March 2024 the Council approved the updated General Services Capital
Plan for 2024/2025 to 2032/33.  The three years from 2024/25 to 2026/27
were approved in detail with the remaining years being indicative. The budget
agreed was £76.757m for 2024/25 and £318.357m for the project life budget.
ITEM 11

Page 2

3.2 Since then budget adjustments have taken place which result in a revised 
General Services capital budget as set out in Exhibit 1.
Exhibit 1: Revised Capital Budget
2024/25
(£m)
Project Life
(£m)
Capital Budget Agreed 6 March 2024 76.757 318.357
Capital Projects Removed (Para 4.6) (0.09) (0.017)
Add Res7 Community Capital Fund 0.150 0,150
Add Res8 Community Sports Success Capital
Fund
0.250 0.250
Capital Project Added (Para 4.6) 1.197 2.000
Developers Contributions for Clydebank Can on
the Canal
0.050 0.050
New Scottish Government Funding – Nature
Restoration
0.034 0.034
New Scottish Government Funding – Cycling,
Walking and Safer Streets
0.389 0.389
Revised Capital Budget as at Period 3 78.737 315.501
4. Main Issues
4.1 Progress against the 2024/25 capital plan is detailed in:
Appendix 1 – Project Life Summary by Chief Officer
Appendix 2 – Off Track Projects
Appendix 3 – Changes to Capital Plan for Noting
Appendix 4 – All Approved Projects
4.2 The overall programme summary report at Appendix 1 shows that planned
expenditure is higher than the budget agreed by £0.040m (0.14% of budget)
due to an anticipated overspend the Agresso Development Plan.
4.3 Appendix 2 highlights thirteen projects currently showing as off-track.  One
due to additional budget required (Agresso Development) and twelve due to
revised completion dates. These are:
 Agresso Development
 Transformation of Infrastructure Libraries and Museums
 Legal Case Management System (RR1)
 Installation of Solar PV at Clydebank Leisure Centre
 Replace failed heating controls/valves & recommission - Original
 Levelling Up Capacity
 Auld Street Clydebank – Bond
 Riverbank Erosion Repair – Levenhowe
 Pavement Improvements
 Waste Transfer Station
 Park Improvements and Multi Games Area - Goldenhill Park

Page 3

 Kilmaronock Cemetery Expansion
 Digital Inclusion
4.4 Appendix 3 highlights thirty six projects where the project expenditure requires
to be reprofiled but there is no need for additional budget.
4.5 Appendix 4 shows all projects with approved in year and project life budgets
as well as anticipated expenditure. It highlights that the 2024/25 budget is
£78.737m with current forecast spend of £62.951m, a variance of £15.786m,
(20.05%) relating to projects which require reprofiling.  The spend as at period
3 is £8.298m (13.18%) of the current forecast spend of £62.951m. 
4.6 Other minor changes to the capital plan already included in the summarised
plan in appendix 4 are:
 The Clyde Mission Catalyst Fund has been added onto the Capital Plan
(Project RR13). This is not a new project and funding for it was received 16
April 2021 from Scottish Government. It was omitted from the Capital Plan
in March 2024 as it has been managed through a different method. The
presentation has been corrected and the project will be monitored through
the capital plan moving forward. This has no impact on funding as it is fully
funded.
 Early Early Years Early Learning and Childcare Funding project has been
removed. It was anticipated that there would be a carry forward of budget
into 2024/25 from 2023/24. However, projects were completed by 31
March 2024 and therefore no carry forward was required
 The Demolition 215 main street electronic insurance projects have been
removed as they are both complete.
5. Option Appraisal
5.1 No option appraisal was required for this report.
6. People Implications
6.1 There are no people implications.
7. Financial and Procurement Implications
7.1 The report notes the projected in-year financial position for capital budgets.
8. Risk Analysis
8.1 The main risks are as follows:
(a) The reported variances should be viewed in the knowledge that there are
a number of variable factors which could arise between now and 31
March which could affect the year end results for capital budgets.

Page 4

(b) As a consequence of current market conditions, inflation is at an all-time
high and interest rates continue to be volatile. To forecast for the full year
costs budget assumptions have been required. These assumptions
continue to change regularly and therefore it is likely the projected year
end budgetary position will change from that reported.
9. Equalities Impact Assessment (EIA)
9.1 No equalities impact assessment was required in relation to this report.
10. Environmental Sustainability
10.1 No assessment of environmental sustainability was required in relation to this
report.
11. Consultation
11.1 All services involved in delivering the capital budgets have been consulted in
the compilation of this report.
12. Strategic Assessment
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council.
________________
Laurence Slavin
Chief Officer – Resources
Date: 8 August 2024
Person to Contact: Jackie Thomson
Council Offices, Church Street, Dumbarton
E-mail: jackie.nicolthomson@west-dunbarton.gov.uk
Appendices: Appendix 1 - Project Life Summary
Appendix 2- Off Track Projects
Appendix 3 - Reprofiling and Acceleration of Projects
Appendix 4 - Details of all Projects.
Background Papers:
General Services Capital Plan Update - Council 6 March 2024.
Wards Affected           All Wards