Page 1

APPENDIX 5
WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
OVERALL PROGRAMME SUMMARY
MONTH END DATE
PERIOD 12
Spend to
Date Spend to Date
£000 £000
Red
28 90.3% 56,127 99.9% 28 90.3% 56,127 99.9%
Green
3 9.7% 36 0.1% 3 9.7% 36 0.1%
31 100% 56,163 100% 31 100% 56,163 100%
Budget Spend to
Date
Forecast
Spend Forecast Variance Budget Spend to Date Actual Spend Actual Variance Reprofiled Over/
(Under)
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000
359,792 56,127 295,303 (64,489) 124,709 56,127 56,127 (68,583) (5,491) (63,091)
6,936 36 6,336 (600) 136 36 36 (101) 0 (101)
366,729 56,163 301,639 (65,088) 124,846 56,163 56,163 (68,683) (5,491) (63,192)
366,729 56,163 301,639 65,088 124,846 56,163 56,163 68,683
0 0 0 0 0 0 0 0
Projects are on target both in relation to overall budget and the forecast
stages in the project life cycle and no issues are anticipated at this time
31 March 2024
Project Status Analysis
Project Life Status Analysis Current Year Project Status Analysis
Number of
Projects at
RAG Status
% Projects at
RAG Status
% Project Spend at
RAG Status
Number of
Projects at
RAG Status
% Projects at
RAG Status
% Project
Spend at RAG
Status
Red
Projects are forecast to be overspent and/or experience material delay
to completion
Green
Project Status Analysis
Project Life Financials Current Year Financials
Red
TOTAL RESOURCES
NET EXPENDITURE
Projects are forecast to be overspent and/or significant delay to
completion
Green
Projects are on target both in relation to overall budget and the forecast
stages in the project life cycle and no issues are anticipated at this time
TOTAL EXPENDITURE

Page 2

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 12
Budget Forecast/ Actual
Spend
£000 £000 % £000 £000 %
1
Project Life Financials 3,216 642 20% 3,258 42 1%
Current Year Financials 600 642 107% 642 42 7%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
2
Project Life Financials 2,814 3,102 110% 5,391 2,577 92%
Current Year Financials 525 3,102 591% 3,102 2,577 491%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
3
Project Life Financials 1,493 56 4% 1,493 0 0%
Current Year Financials 529 56 11% 56 (473) -89%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
4
Project Life Financials 10,000 103 1% 10,000 0 0%
Current Year Financials 2,000 103 5% 103 (1,897) -95%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Environmental Sensors Programme 
Environmental sensors programme, funded by enhanced housing investment programme. 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Project introduced as part of the enhanced capital programme, with aim to install an environmental sensor in every Council owned property. 
Installation of sensors has commenced, albeit later than originally anticipated.  Remaining current year budget to be rephased to 24/25 for
continuation of project.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
A number of priority initiatives, supported by the Better Homes Project Board,  are being investigated and are envisaged to have a positive
impact on the current council housing stock and budget.  Due to time taken to progress projects, unspent budget is required to be reprofiled
to 24/25.
Main Issues / Reason for Variance
Budget is overspent due to costs and demand for budget being higher than anticipated at time of budget setting.
Mitigating Action
None available at this time.
Anticipated Outcome
Project to complete over budget.
31 March 2024
Budget Details
Project Life Financials
Spend to Date Variance
Special needs adaptations
None available at this time
Anticipated Outcome
Full budget spend
Capitalised minor works
This is a budget to undertake specific minor ad hoc capital projects that arise on demand throughout the
financial year. 
Planned End Date  Forecast End Date 
Adaptations to Housing for Special Needs 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Overspend incurred in 2023/24 due to price increases and demand levels rising.
Mitigating Action
Better Homes Priority Budget
Priority projects as prioritised by the Better Homes Group

Page 3

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 12
Budget Forecast/ Actual
Spend
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend to Date Variance
5
Project Life Financials 750 0 0% 750 0 0%
Current Year Financials 250 0 0% 0 (250) -100%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-25
6
Project Life Financials 203 10 5% 98 (106) -52%
Current Year Financials 116 10 9% 10 (106) -91%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
7
Project Life Financials 209 0 0% 138 (71) -34%
Current Year Financials 71 0 1% 0 (71) -99%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
8
Project Life Financials 17 0 0% 17 0 0%
Current Year Financials 17 0 0% 0 (17) -100%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Works to progress as part of enhanced capital programme for 23/24 and to be led by Council CCTV team.  Due to survey and planning
time, works are commencing later than anticipated, with unspent budget required to be rephased to 24/25 for project progression.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Community Safety Projects
Community Safety Projects 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Budget required to be rephased to 24/25
Main Issues / Reason for Variance
Programme being progressed with revised budget in 24/25 capital plan.
Mitigating Action
None available
Anticipated Outcome
Works to prgress in 24/25
Anticipated Outcome
Full budget spend
Gypsy Travellers Site
Gypsy/ Traveller Site improvements 
Planned End Date  Forecast End Date 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance 
Development of QL system to carry on through 24/25.  Salaries of staff directly involved with development of system to be coded to direct
project support.
Mitigating Action
None required
QL Development
This budget relates to the costs associated with the development of the Integrated Housing Management
System
Housing CCTV Installation Programme
CCTV Installation Programme, funded by enhanced housing investment programme

Page 4

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 12
Budget Forecast/ Actual
Spend
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend to Date Variance
9
Project Life Financials 96 0 0% 96 0 0%
Current Year Financials 96 0 0% 0 (96) -100%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
10
Project Life Financials 32,986 5,125 16% 32,986 0 0%
Current Year Financials 6,146 5,125 83% 5,125 (1,021) -17%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
11
Project Life Financials 19,286 3,404 18% 15,713 (3,573) -19%
Current Year Financials 5,679 3,404 60% 3,404 (2,275) -40%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
Anticipated Outcome
Scheduled works to complete under current year budget.
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Works expected to meet revised timescales which will be less than current year budget and therefore project will report an in year
underspend.
Mitigating Action
None required
Mitigating Action
None available at this time
Anticipated Outcome
Full budget spend over project life
Roof Coverings
Building external component renewals, roofs/chimneys/flashings/fascias/gutters/svp
Targeted SHQS /EESSH compliance works
This budget is to focus on work required to maintain the SHQS compliance and energy efficiency  with
WDC housing stock.   
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Works progressing well, however unspent budget to be rephased to 24/25.
Main Issues / Reason for Variance
West Dunbartonshire Council are no longer eligible for match funding from Glasgow Airport Association, following assessment of properties
within West Dunbartonshire.  West Dunbartonshire is not deemed to have any commercial or residential properties that fall within the scope
of the scheme to be eligible for match funding, and budget therefore has been reduced from £0.192m to £0.096m.  The remaining budget
will be used to develop a programme of works following engagement with an aircraft noise consultant, who will work with Officers to make
adaptations to previously identified properties.  The budget will be reprofiled as required.
Mitigating Action
None required
Anticipated Outcome
Full budget spend in future year
Airport Noise
Noise Insulation Project 
Planned End Date  Forecast End Date

Page 5

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 12
Budget Forecast/ Actual
Spend
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend to Date Variance
12
Project Life Financials 17,937 4,417 25% 17,937 0 0%
Current Year Financials 4,547 4,417 97% 4,417 (130) -3%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
13
Project Life Financials 242 78 32% 275 32 13%
Current Year Financials 45 78 171% 78 32 71%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
14
Project Life Financials 242 22 9% 219 (24) -10%
Current Year Financials 45 22 48% 22 (24) -52%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
15
Project Life Financials 606 41 7% 534 (72) -12%
Current Year Financials 113 41 37% 41 (72) -63%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
Mitigating Action
None required
Anticipated Outcome
Works complete as required
Statutory/regulatory compliance works (lifts/electrical/legionnella/fire etc)
This budget will be used to upgrade / replace components / installations in order to comply with the
relevant standards / legislation / health and safety in relation to housing stock. 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
23/24 demand for budget less than anticipated at time of budget setting therefore there has been an underspend in the current year.
Main Issues / Reason for Variance
This programme always presents challenges with owner liaison and reaching agreements to install door entry where none exists, this
contributes directly to achieving SHQS compliance for this element.  As a result an in year underspend has been achieved.
Mitigating Action
Officers continue to liaise with owners to encourage agreement for install.
Anticipated Outcome
It is likely that this will not to meet full spend in the current year despite best efforts but officers will endeavour to gain owners agreement.
Anticipated Outcome
Full budget spend
Secure entry component renewals
This budget is to focus on secure door entry component renewals as identified and recommended from
the housing stock condition survey and appropriate council officer referrals. 
Planned End Date  Forecast End Date 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Demand for budget higher than anticipated at time of budget setting, with overspend in 23/24.
Mitigating Action
None required
External stores/garages/bin stores/drainage component renewals
This budget is to focus on external stores/garages/bin stores etc. component renewals as identified and
recommended from the housing stock condition survey.
Main Issues / Reason for Variance
Project is progressing well in 23/24, however element of unspent budget required to be rephased to 24/25.
Mitigating Action
None required at this time
Anticipated Outcome
Full budget spend
Doors/window component renewals
Doors/Windows Component Renewals 
Planned End Date  Forecast End Date

Page 6

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 12
Budget Forecast/ Actual
Spend
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend to Date Variance
16
Project Life Financials 9,872 2,248 23% 10,280 408 4%
Current Year Financials 1,840 2,248 122% 2,248 408 22%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
17
Project Life Financials 303 7 2% 254 (49) -16%
Current Year Financials 57 7 13% 7 (49) -87%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
18
Project Life Financials 17,775 3,333 19% 17,873 98 1%
Current Year Financials 3,235 3,333 103% 3,333 98 3%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
19
Project Life Financials 103 0 0% 0 (103) -100%
Current Year Financials 103 0 0% 0 (103) -100%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
Anticipated Outcome
In year underspend
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Budget not utilised in 23/24
Mitigating Action
None required
Mitigating Action
Officers will work to minimise any overspend whilst being mindful of tenant demand.
Anticipated Outcome
Full budget spend, possibility of overspend.
Improvement works (Risk St)
Risk Street Over clad
Modern facilities and services
New Kitchens, Bathrooms and Showers 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Pace of installations were ahead of targets.  Budget therefore has overspent in 23/24.
Main Issues / Reason for Variance
23/24 demand for budget less than anticipated at time of budget setting.  Current year underspend to be carried forward to future years.
Mitigating Action
None required
Anticipated Outcome
Works complete as required
Anticipated Outcome
Full budget spend, likely overspend.
Energy improvements/energy efficiency works
Energy improvements/ efficiency works (e.g. loft insulation, pipe/tank insulation, draught exclusion) 
Planned End Date  Forecast End Date 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Demand has exceeded expectations.  Due to the nature of this project (ensuring heating and hot water availbility) there is no option for a
conscious reduction of installs.  Project has therefore overspent in 23/24.
Mitigating Action
Whilst demand is leading spend, officers will work to minimise any budget overspend.
Heating improvement works
Carry out works to renew inefficient boilers/full systems as identified from the stock condition survey and
renewal of obsolete/damaged boilers.

Page 7

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 12
Budget Forecast/ Actual
Spend
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend to Date Variance
20
Project Life Financials 13,900 6,683 48% 17,584 3,683 26%
Current Year Financials 3,000 6,683 223% 6,683 3,683 123%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
21
Project Life Financials 3,835 490 13% 3,448 (387) -10%
Current Year Financials 877 490 56% 490 (387) -44%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
22
Project Life Financials 5,454 1,287 24% 5,723 269 5%
Current Year Financials 1,017 1,287 126% 1,287 269 26%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
23
Project Life Financials 1,212 102 8% 1,088 (124) -10%
Current Year Financials 226 102 45% 102 (124) -55%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
Mitigating Action
None required
Anticipated Outcome
Spend as required
Asbestos management works
This budget is to fund work associated with the management of current asbestos legislation and the
Council's asbestos policy within housing stock. 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Budget underspent in 23/24.
Main Issues / Reason for Variance
Work progressed well and ahead of spend targets, therefore budget has incurred an in year overspend.
Mitigating Action
None available at this time
Anticipated Outcome
Overspend incurred in current year
Anticipated Outcome
Spend as required
Environmental renewal works, paths/fences/walls/parking area's
Environmental renewal works, paths/fences/walls/parking areas 
Planned End Date  Forecast End Date 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Works expected to meet revised timescales which will be less than current year budget and therefore project has an in year underspend.
Mitigating Action
None required
Defective structures/component renewals
Defective structures 
Main Issues / Reason for Variance
Void works continued in 2023/24 to bring void properties up to a lettable standard.  The high number of voids and costs associated has led
to a higher than expected demand for this budget, resulting in an overspend in 2023/24. 
Mitigating Action
None available at this time
Anticipated Outcome
Void properties to be brought up to lettable standard, budget to overspend.
Void house strategy programme
Spend on Void Properties to bring them up to letting standard 
Planned End Date  Forecast End Date

Page 8

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 12
Budget Forecast/ Actual
Spend
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend to Date Variance
24
Project Life Financials 5,050 65 1% 5,050 0 0%
Current Year Financials 1,300 65 5% 65 (1,235) -95%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
25
Project Life Financials 21,073 4,065 19% 21,073 0 0%
Current Year Financials 4,435 4,065 92% 4,065 (371) -8%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
Main Issues / Reason for Variance
The main objective of the Buy Back Scheme is to bring former council properties that were sold through the RTB scheme, back into council
use.  These properties must assist the council with reducing housing need on the waiting list and where appropriate assist with external
capital works.  From 23/24, over 5 years, the buy back back scheme is benefiting from an additional £2m investment each year, included in
this revised budget, totaling £10m over 5 years, to futher reduce the waiting list.  £0.371m of the 23/24 budget remains and to be carried to
24/25.
Mitigating Action
None required.
Anticipated Outcome
Budget spend incurred, as criteria is met.
Anticipated Outcome
Full budget spend
Buy Backs
This is a budget to undertake specific projects that will deliver housing policies/strategies, example: Ex
local authority and mortgage to rent buy-back scheme 
Planned End Date  Forecast End Date 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Works taking longer to progress than anticipated.  Budget required to be rephased to 24/25.
Mitigating Action
None required
Multi Story Flats  ( including Fire Risk Assessment Works)
High Rise Fire Safety Measures

Page 9

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 12
Budget Forecast/ Actual
Spend
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend to Date Variance
26
Project Life Financials 177,132 17,961 10% 109,786 (67,346) -38%
Current Year Financials 85,209 17,961 21% 17,961 (67,248) -79%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
Variance to
23/24 Budget
Site/ Spend £000  Overspend   Underspend  Reprofiling
Haldane Primary School 77 77 0 0
Clydebank East (13,861) 0 (13,861) 0
Queens Quay Site B (99) 0 (99) 0
Queens Quay Site C (9,423) 0 (9,423) 0
Pappert (10,177) 0 (10,177) 0
Bank Street (3,570) 0 (3,570) 0
Clydebank Health Centre (4,668) 0 (4,668) 0
Willox Park Phase1 (5,402) 0 (5,402) 0
Mount Pleasant (8,479) 0 (8,479) 0
Silverton (2,557) 0 (2,557) 0
Gap sites (5,756) 0 (5,756) 0
Fees, Staffing Costs,
contingency (3,333) 0 (3,333) 0
TOTAL OF ALL PROJECTS (67,248) 77 (67,325) 0
Affordable Supply Programme
Affordable Housing Supply Programme 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
The £67.248m variance is made up of £0.077m overspend, and underspend of £67.235m. Revised budgets profilied in 24/25 capital plan. 
Summary of reprofiled sites together with site specific updates as follows:-
Variance Category

Page 10

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 12
Budget Forecast/ Actual
Spend
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend to Date Variance
27
Project Life Financials 0 184 #DIV/0! 184 184 #DIV/0!
Current Year Financials 0 184 #DIV/0! 184 184 #DIV/0!
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
28
Project Life Financials 13,984 2,703 19% 14,058 73 1%
Current Year Financials 2,629 2,703 103% 2,703 73 3%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
TOTAL OF RED PROJECTS
Project Life Financials 359,792 56,127 16% 295,303 (64,489) -18%
Current Year Financials 124,709 56,127 45% 56,127 (68,583) -55%
Demoliton related costs incurred as required
Demolitions
Costs associated with demolition of surplus stock 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Costs associated with demolition of old lock ups and stock surplus to requirements
Mitigating Action
None required
Anticipated Outcome
Mitigating Action
Mount Pleasant -19 units to be completed on site by March 2025.  Demolition now complete and contractor award appointment made in
September.  £0.250m estimated to be spent this financial year with remaining current year budget to be reprofiled to 2024/25 for site start in
March 2024.
Bonhill Gap Site - Spend reprofiled from 2023/24 to 2024/25 as design team procurement was delayed.  Projected spend in 2023/24 was on
design and statutory fees.
Mitigating Action
Staff will work closely with all stakeholders to try and ensure timely resolutions of issues as they arise.
Anticipated Outcome
Project will still complete and will meet revised spend profiles .
Clydebank East - 88 units to be completed by March 2025.  Project delivery reprofiled due to extensive groundworks. Project on site and
programme adhering to amended delivery plan.
Queens Quay Site B - 29 units completed on site in 2022/23.  Project completed, retention figure included and associated costs in terms
with road construction.
Queens Quay Site C - 20 units to be completed on site, however no further progress due to land owner issue.  At the time it is assumed
approximately £2m will be spent on land purchase, but this will be reviewed in early 2024, with the remaining current year budget to be
reprofiled in 2024/25.
Pappert - 26 units to be completed on site by April 2025.  Planning delay negated anticipated spend profile for 2023/24, however Planning
approval received 20 September 2023 and site start in 2024 planned.
Bank Street - 22 units to be completed on site.  Spend reprofiled from 2023/24 to 2024/25 as design team procurement was delayed. 
Spend in 2023/24 consisted of design and statutory fees.
Willox Park Phase1 - 17 units to be completed on site.   Spend reprofiled from 2023/24 to 2024/25 as design team procurement was
delayed.  Projected spend in 2023/24 was on design and statutory fees.
None required
Anticipated Outcome
Full budget spend
Salaries/central support/offices
Allocation of costs from other WDC services who support the HRA capital programme 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Budget utilised for salaries and support of the HRA capital programme.
Haldane - Site complete, retention paid in 2023/24
Clydebank Health Centre - Physical site start will not be achieved until 2024/25.

Page 11

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 12
Budget Forecast/ Actual
Spend
£000 £000 % £000 £000 %
1
Project Life Financials 36 36 99% 36 (1) -1%
Current Year Financials 36 36 99% 36 (0) -1%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
2
Project Life Financials 6,400 0 0% 6,400 0 0%
Current Year Financials 0 0 #DIV/0! 0 0 #DIV/0!
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
3
Project Life Financials 500 0 0% (100) (600) -120%
Current Year Financials 100 0 0% 0 (100) -100%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
TOTAL OF RED PROJECTS
Project Life Financials 6,936 36 1% 6,336 (601) -9%
Current Year Financials 136 36 26% 36 (101) -74%
31 March 2024
Budget Details
Project Life Financials
Spend to Date Variance
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Redployable CCTV Cameras
Purchase of 5 redeployable CCTV cameras for Housing use 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Works for this project complete in April 23/24.
Main Issues / Reason for Variance
Works expected to commence next financial year, therefore no Issues to report at this time.  Project anticipated to meet full spend
and targets.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
District Heating 
District Heating Connection to the Dalmuir and Littleholm multi storey flats 
Planned End Date  Forecast End Date
Contingencies
This is a contingent budget for unforeseen matters which may arise during the year. 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Contingent budget held for unplanned spend.  Not utilised in 23/24.
Mitigating Action
None required
Anticipated Outcome
Spend as required

Page 12

APPENDIX 5
WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
ANALYSIS OF RESOURCES
MONTH END DATE
PERIOD 12
Budget Forecast/ Actual
Spend
£000 £000 % £000 £000 %
1
Project Life Financials (46,875) (8,258) 18% (27,078) 19,797 -42%
Current Year Financials (28,055) (8,258) 29% (8,258) 19,797 -71%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
2
Project Life Financials (8,646) 0 0% (6,917) 1,729 -20%
Current Year Financials (1,729) 0 0% 0 1,729 -100%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
3
Project Life Financials (311,208) (44,920) 14% (264,660) 46,548 -15%
Current Year Financials (95,062) (44,920) 47% (44,920) 50,142 -53%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
4
Project Life Financials 0 (2,985) #DIV/0! (2,985) (2,985) #DIV/0!
Current Year Financials 0 (2,985) #DIV/0! (2,985) (2,985) #DIV/0!
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
Main Issues / Reason for Variance
31 March 2024
Budget Details
Project Life Financials
Spend to Date Variance
New Build Grant
Grant to facilitate the building of new build housing 
Planned End Date  Forecast End Date
Mitigating Action
Income received in line with spend incurred.
Mitigating Action
None required
Anticipated Outcome
Income due to be received
CFCR
This is capital spend which is funded by revenue budgets
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Contribution to Capital from Revenue not possible in 23/24 due to cost pressures in revenue.
Prudential borrowing incurred as required
None required
Anticipated Outcome
Income to Capital if possible
Prudential Borrowing
Prudential borrowing is long term borrowing from financial institutions that has been approved
for the purposes of funding capital expenditure
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Prudential borrowing is impacted by programme delivery.
Mitigating Action
None available at this time.
Anticipated Outcome
Mitigating Action
None available
Anticipated Outcome
Income will be received when due
Other Capital Income
Other Income to capital
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Grant from Scottish Government in relation to properties bought back into Council stock.

Page 13

WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
ANALYSIS OF RESOURCES
MONTH END DATE
PERIOD 12
Budget Forecast/ Actual
Spend
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend to Date Variance
New Build GrantTOTAL RESOURCES
Project Life Financials (366,729) (56,163) 15% (301,639) 65,089 -18%
Current Year Financials (124,846) (56,163) 45% (56,163) 68,683 -55%

Page 14

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF AFFORDABLE HOUSING SUPPLY PROGRAMME
MONTH END DATE
PERIOD 12
Budget Spend to Date Forecast/ Actual
Spend
£000 £000 £000 £000 %
RAG
Status
Haldane Primary School -                                                                            77                           77                                  77                                    #DIV/0! 
Aitkenbar Primary School -                                                                            -                          -                                -                                   #DIV/0! 
Clydebank East 37,992                                                                     14,979                    24,131                          13,861-                             -36% 
Creveul Court -                                                                            -                          -                                -                                   #DIV/0! 
Dumbarton Harbour Ph 3  -                                                                            -                          -                                -                                   #DIV/0! 
Queens Quay Site B 660                                                                           562                         562                               99-                                    -15% 
Queens Quay Site C 25,175                                                                     3                              15,753                          9,423-                               -37% 
Pappert 13,276                                                                     517                         3,100                            10,177-                             -77% 
Bank Street 5,751                                                                        13                           2,181                            3,570-                               -62% 
Clydebank Health Centre 11,016                                                                     690                         6,348                            4,668-                               -42% 
Willox Park Phase1 6,185                                                                        120                         783                               5,402-                               -87% 
Willox Park Phase2 7,500                                                                        -                          7,500                            -                                   0% 
Mount Pleasant 8,717                                                                        238                         238                               8,479-                               -97% 
Silverton 2,590                                                                        33                           33                                  2,557-                               -99% 
0 -                                                                            -                          -                                -                                   #DIV/0! 
Gap sites
Gap sites budget remaining 9,182                                                                        -                          4,081                            5,101-                               -56% 
Bonhill Gap Site - all Bonhill Sites 245                                                                           0                              0                                    245-                                  -100% 
Bonhill Gap Site - Old Bonhill/ Campbell Street -                                                                            35                           -                                -                                   
Bonhill Gap Site - O'Hare -                                                                            28                           -                                -                                   0% 
Bonhill Gap Site - Braehead -                                                                            36                           -                                -                                   #DIV/0! 
Clydebank Gap Sites ( prev Lilac Avenue) - unallocated 13,622                                                                     -                          13,000                          622-                                  -5% 
Clydebank Gap Sites ( prev Lilac Avenue) - 7-9 Gilmour Avenue 50                                                                             39                           39                                  11-                                    -21% 
Clydebank Gap Sites ( prev Lilac Avenue) - Queen Mary Avenue 50                                                                             32                           32                                  18-                                    -35% 
Future New build sites 27,000                                                                     -                          27,000                          -                                   0% 
28 Bridge Street Alexandria 23                                                                             165                         165                               141                                  605% 
Fees, Staffing Costs, contingency 8,097                                                                        396                         4,764                            3,333-                               -41% 
Total Expenditure 177,132 17,961 109,786 (67,346) 
31 March 2024
Site
Project Life Financials
Variance