WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
OVERALL PROGRAMME SUMMARY
PERIOD END DATE
PERIOD 12
Spend to Date Spend to
Date
£000 £000
Red
75 80.6% 80,037 93.8% 75 80.6% 28,980          85.2%
Amber
0 0.0% 0 0.0% 0 0.0% 0 0.0%
Green
18 19.4% 5,298 6.2% 18 19.4% 5,039 14.8%
93 100% 85,335 100% 93 100% 34,019 100%
Budget Spend to
Date
Forecast
Spend
Forecast
Variance Budget Spend at
31/3/24
Actual
Variance Re-profiling Over/ (Under)
£000 £000 £000 £000 £000 £000 £000 £000 £000
226,010 80,037          225,998 (12) 91,583 28,980 (62,603) (63,698) 2,785
0 0 0 0 0 0 0 0 0
5,298 4,089 5,039 (258) 2,120 1,908 (212) (275) (1,627)
231,307 84,126 231,037 (270) 93,703 30,888 (62,815) (63,973) 1,158
(231,307) (84,126) (231,037) 270 (93,703) (30,888) 62,815
0 0 0 (0) 0 (0) (0)
Projects are on target both in relation to overall budget and the forecast
stages in the project life cycle and no issues are anticipated at this time
TOTAL EXPENDITURE
TOTAL RESOURCES
NET EXPENDITURE
Projects are forecast to be overspent and/or significant delay to
completion
Amber
Projects are either at risk of being overspent and/or delay in completion
(although this is unquantifiable at present) or the project has any issues
that require to be reported at this time
Green
TOTAL EXPENDITURE
Project Status Analysis
Project Life Financials Current Year Financials
Red
Red
Projects are forecast to be overspent and/or experience material delay
to completion
Amber
Projects are either at risk of being overspent and/or delay in completion
(although this is unquantifiable at present) or the project has any issues
that require to be reported at this time
Green
Projects are on target both in relation to overall budget and the forecast
stages in the project life cycle and no issues are anticipated at this time
31 March 2024
Project Status Analysis
Project Life Status Analysis Current Year Project Status Analysis
Number of Projects
at RAG Status
% Projects at
RAG Status
% Project
Spend at
RAG Status
Number of
Projects at RAG
Status
% Projects at
RAG Status
% Project
Spend at
RAG Status

Page 2

No embedded text on this page.

Page 3

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 12
Budget Forecast
Spend
£000 £000 % £000 £000 %
1
Project Life Financials 50 43 86% 50 0 0%
Current Year Financials 7 0 0% 0 (7) -100%
Project Description
Project Manager Karen Shannon
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-23 31-Mar-24
2
Project Life Financials 30 5 16% 30 (0) 0%
Current Year Financials 25 0 0% 0 (25) -100%
Project Description
Project Manager Karen Shannon
Chief Officer Laurence Slavin
Project Lifecycle 30-Sep-23 30-Nov-23
3
Project Life Financials 62 62 100% 62 0 0%
Current Year Financials 23 55 244% 55 32 144%
Project Description
Project Manager Adrian Gray
Chief Officer Laurence Slavin
Project Lifecycle 30-Apr-24 30-Apr-24
Main Issues / Reason for Variance
Work to significantly reduce the database size to facilitate a system upgrade has now been completed. Upgrade work can now commence, ICT currently building required
servers in preparation for new version to be installed, configured and tested.
Mitigating Action
None required
Anticipated Outcome
Anticipate completion of upgrade during 23-24 financial year.
Anticipated Outcome
Enhancements to the cash receipting system including PCI compliant telephone payment system.
Agresso development
The purpose of this project is to carry out an upgrade of the Agresso Finance System which was last upgraded in 2015. The
requirement to upgrade is to maintain a level of support available from Unit 4 who have advised that support for older
versions of the system is being reduced.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Budget has been reprofiled to Financial Year 2024-2025. Version 2 of the upgrade was completed Jan 2023.  Call Secure Module went Live in October 2023.
Mitigating Action
None required at this time.
Mitigating Action
None required at this time.
Anticipated Outcome
Upgraded Electronic Insurance System.
Enhancements to Cash Receipting System
To enhance the cash receipting system in the way payments are made and allocated to back office by increasing the level
of security that is required for online payments made by customers
Electronic Insurance System
Acquisition of a claims/incident management system supported by an electronic document management system.
Planned End Date Forecast End Date
Main Issues / Reason for Variance 
Budget has been reprofiled to Financial Year 2024-2025.
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance

Page 4

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 12
Budget Forecast
Spend
£000 £000 % £000 £000 %
Electronic Insurance System
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
4
Project Life Financials 5 0 0% 5 0 0%
Current Year Financials 5 0 0% 0 (5) -100%
Project Description
Project Manager Jackie Nicol Thomson
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-23 31-Mar-24
5
Project Life Financials 1,540 0 0% 1,540 0 0%
Current Year Financials 1,590 0 0% 0 (1,590) -100%
Project Description
Project Manager Michelle Lynn
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-24 31-Mar-25
6
Project Life Financials 1,146 1,146 100% 1,146 (0) 0%
Current Year Financials 5 2 33% 2 (4) -67%
Project Description
Project Manager Michelle Lynn
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-22 30-Apr-23
Mitigating Action
None required.
Anticipated Outcome
To create new community facilities with additional space for early years provisions.
Dalmonach CE Centre
To create new community facilities with additional space for early years provisions.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project complete and final account to be agreed.
Main Issues / Reason for Variance
This project is linked to Glencairn House and Depot Rationalisation and will free up the current museum store and office space in Poplar Road. Opportunities exist to
attract external funding. Detailed design work ongoing for Glencairn House and the budget will be reprofiled into 2024/25.
Mitigating Action
None available at this time
Anticipated Outcome
Project delivered with required specifications
Strathleven Place
Re-development of Strathleven.
Planned End Date Forecast End Date
Mitigating Action
None available at this time.
Anticipated Outcome
Completion of project by 31 March 2025
IFRS 16 Database
This is a system which will ensure that WDC has the correct level of information and adheres to correct reporting of IFRS16 -
Leasing. 
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Database not implemented in 2023/24 and budget will be reprofiled into 2024/25

Page 5

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 12
Budget Forecast
Spend
£000 £000 % £000 £000 %
Electronic Insurance System
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
7
Project Life Financials 2,980 2,658 89% 2,980 0 0%
Current Year Financials 2,980 2,658 89% 2,658 (321) -11%
Project Description
Project Manager Michelle Lynn
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-24 31-Mar-24
8
Project Life Financials 349 9 3% 349 0 0%
Current Year Financials 340 0 0% 0 (340) -100%
Project Description
Project Manager Michelle Lynn
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-24 31-Mar-25
9
Project Life Financials 270 270 100% 270 0 0%
Current Year Financials 134 254 190% 254 120 90%
Project Description
Project Manager Michelle Lynn
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-21 31-Mar-24
10
Project Life Financials 2,366 113 5% 2,366 (0) 0%
Current Year Financials 1,085 22 2% 22 (1,062) -98%
Project Description
Project Manager Michelle Lynn
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-22 31-Mar-25
Anticipated Outcome
To deliver new community centre.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
A bid for RCGF funding was unsuccessful. Council agreed to remove this project from the capital programme when agreeing the 2024/25 budget however Council officers
will continue to support the group in terms of any future funding bids.  (Note this decision was taken after P10 which this report relates to however as it is a significant
change it was felt appropriate to update the narrative to reflect the most up to date position
Mitigating Action
None available at this time
Mitigating Action
None available at this time
Anticipated Outcome
To deliver new sports changing facility.
New Westbridgend Community Centre
New Westbridgend Community Centre
New Sports Changing Facility at Lusset Glen in Old Kilpatrick
New Sports Changing Facility at Lusset Glen in Old Kilpatrick
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project had been delayed due to a number of COVID-19 related issues and utilities issues. Unit is now in production but delay to site due to the utility disconnection and
demolition works. Demolition works complete.
Main Issues / Reason for Variance
No confirmation of start date. Can't  be confirmed until works commence on the wider housing site. Budget will be reprofiled into 2024/25
Mitigating Action
None available at this time
Anticipated Outcome
To deliver new sports changing facility.
Anticipated Outcome
Projects delivered to required specifications
New Sports Changing Facility Dumbarton West (Old OLSP site) 
New Sports Changing Facility Dumbarton West (Old OLSP site) 
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works progressing and remaining budget will be reprofiled into 2024/25
Mitigating Action
None required at this time
Building Upgrades and H&S - lifecycle & reactive building upgrades
Lifecycle and reactive building upgrades.

Page 6

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 12
Budget Forecast
Spend
£000 £000 % £000 £000 %
Electronic Insurance System
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
11
Project Life Financials 33 0 0% 33 0 0%
Current Year Financials 33 0 0% 0 (33) -100%
Project Description
Project Manager Alan Douglas
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
12
Project Life Financials 25 15 61% 25 0 0%
Current Year Financials 10 5 54% 5 (5) -46%
Project Description
Project Manager Pamela Clifford
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
13
Project Life Financials 155 145 94% 155 0 0%
Current Year Financials 10 0 0% 0 (10) -100%
Project Description
Project Manager Pamela Clifford
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
14
Project Life Financials 4 4 100% 4 (0) 0%
Current Year Financials 58 1 1% 1 (57) -99%
Project Description
Project Manager Rachel Moir
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-25
Mitigating Action
None required
Anticipated Outcome
Works to be undertaken in 24/25
Installation of Solar PV at Clydebank Leisure Centre
Installation of Solar PV at Clydebank Leisure Centre.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Tender works delayed due to Energy Officer being off sick. Work underway and will be undertaken in 24/25.
Main Issues / Reason for Variance
This outstanding money is being sought through the recharging order and through debtors.
Mitigating Action
No action required at this time in the hands of Legal
Anticipated Outcome
Demolition of 215 Main Street.
Anticipated Outcome
Anticipate full budget spend.
Demolition 215 Main Street Alexandria
Demolition of 215 Main Street Alexandria.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This goes into the overall Antonine Project budget - 5 Councils and Historic Environment Scotland - Unspent budget will be reprofiled into 2024/25
Mitigating Action
No action required
Re -imagine Antonine Wall  
Council's capital contribution towards the multi-partner (five local authorities and Historic Environment Scotland)
Rediscovering the Antonine Wall project which is also funded by the Heritage Lottery Fund.
Main Issues / Reason for Variance
Budget has been rephased from 2022/23. Project was originally delayed due to COVID19 restrictions and a decision was made to resume project once Microsoft 365 was
implemented. Budget will be reprofiled into 2024/25
Mitigating Action
None available at this time.
Anticipated Outcome
Legal Case Management System
Legal Case Management System
Legal Case Management System
Planned End Date Forecast End Date

Page 7

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 12
Budget Forecast
Spend
£000 £000 % £000 £000 %
Electronic Insurance System
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
15
Project Life Financials 92 85 92% 92 0 0%
Current Year Financials 79 85 107% 85 5 7%
Project Description
Project Manager Rachel Moir
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-24
16
Project Life Financials 14 14 100% 14 0 0%
Current Year Financials 7 1 19% 1 (6) -81%
Project Description
Project Manager Rachel Moir
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-24
17
Project Life Financials 290 64 22% 290 0 0%
Current Year Financials 227 1 0% 1 (226) -100%
Project Description
Project Manager Rachel Moir
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-24
18
Project Life Financials 8,964 1,004 11% 8,964 0 0%
Current Year Financials 2,983 410 14% 410 (2,572) -86%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-25
Main Issues / Reason for Variance
LED budget is invested across our town centres and strategic sites and is used to develop and implement projects as well as providing match funding to lever in external
funding. During 2023/2024 the key projects developed and delivered include a Alexandria Town Centre Masterplan projects (Smollet Fountain, Green heritage Corridors),
and in Clydebank implementation of the Development Framework. Many regeneration projects are subject to factors outwith Council control and close monitoring of the
programming is required. Enabling works at Mitchell Way  have been delayed as they are subject to the timescale of the developer. Activity Centre in Clydebank is
delayed and now planned to be delivered in 2024/2025. A contingency is included for increasing costs and new funding opportunities. The remaining budget will be
reprofiled into 2024/25
Mitigating Action
none required
Anticipated Outcome
projects delivered on time and on budget
Regeneration/Local Economic Development
Budget to facilitate the delivery of Regeneration throughout West Dunbartonshire, aligned to the Economic Strategy.
External funding will be sought to maximise opportunities for redevelopment of these sites.
Planned End Date Forecast End Date
Mitigating Action
None required.
Anticipated Outcome
Delivery of project with full budget spend.
Leisure Energy projects - air handling units, upgrade lighting, circulating pumps, and draught proofing
Measures to be installed at both Meadow Centre & Vale of Leven Swimming Pool; new pool hall Air Handling Units, upgrade
lighting, circulating pumps Vale of Leven Swimming Pool, internal and external lighting and draught proofing.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works have been delayed due to flooding issues. Tender process due to be undertaken shortly; however, due to additional issues identified, the current budget may
require review. The budget will be reprofiled into 2024/25
Main Issues / Reason for Variance
Expected completion in 24/25
Mitigating Action
None required.
Anticipated Outcome
Delivery of project with full budget spend.
Anticipated Outcome
Works to be undertaken in 24/25
Replace failed heating controls/valves & recommission
Replace failed heating controls/valves & recommission.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works are currently being undertaken to upgrade controls in Clydebank Town Hall and remaining budget will be reprofiled into 24/25
Mitigating Action
None required
Replace existing main hall Air Handling unit at Clydebank Town Hall
Replace existing main hall Air Handling unit at Clydebank Town Hall.

Page 8

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 12
Budget Forecast
Spend
£000 £000 % £000 £000 %
Electronic Insurance System
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
19
Project Life Financials 10,931 4,907 45% 10,931 0 0%
Current Year Financials 4,098 9 0% 9 (4,089) -100%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-25
20
Project Life Financials 2,650 1,398 53% 2,650 0 0%
Current Year Financials 1,147 618 54% 618 (529) -46%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-24
21
Project Life Financials 747 40 5% 747 0 0%
Current Year Financials 707 0 0% 0 (707) -100%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Dec-22 30-Jun-24
22
Project Life Financials 322 161 50% 322 0 0%
Current Year Financials 221 62 28% 62 (159) -72%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 30-Jun-24
23
Project Life Financials 23,271 6,849 29% 23,271 0 0%
Current Year Financials 21,665 4,733 22% 4,733 (16,932) -78%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-25 31-Mar-25
Anticipated Outcome
Projects delivered on budget
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Artizan Masterplan approved by IRED in Nov 2023, deigns progressing as planned but some delay to early enabling works (demolition) and commencement of the
delivery phase (Glencairn House). The remaining budget will be reprofiled into 2024/25
Mitigating Action
None available at this time
Mitigating Action
None available at this time
Anticipated Outcome
Projects delivered on budget
LUF
Year one LUF spend includes acquisition cost of Artizan Centre, and design development for Glencairn House and
Connecting Dumbarton
Levelling Up Capacity
Successful LUF applications that meet UK Government's over-riding objective of Levelling Up and transformational
regeneration.
Planned End Date Forecast End Date
Main Issues / Reason for Variance 
This capacity funding is used to fund consultancy work associated with current and future LUF projects development and remaining budget will be reprofiled into 2024/25
Main Issues / Reason for Variance
Kier is appointed to design and deliver the Activities Centre at Clydebank Town Centre. Design of the project is underway and a commencement date for construction will
be later in 2024.
Mitigating Action
None available at this time
Anticipated Outcome
Projects delivered on budget
Anticipated Outcome
Projects delivered on budget
Clydebank Can On The Canal
New activities centre in Clydebank Town Centre.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects continue progressing. Remaining budget will be reprofiled into 2024/25.
Mitigating Action
None required at this time
Mitigating Action
None required
Anticipated Outcome
Projects will be delivered.
Place Based Investment Programme
Scottish Government Funding to establish a Place-Based Investment Programme to ensure that all place based
investments are shaped by the needs and aspirations of local communities.
Regeneration Fund
Funding to implement major regeneration projects linked to community charrettes. 
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Progress being made by Malin Group with expenditure of Clyde Mission funding at the Scottish Marine Technology Park. Remaining projects are multi-year and remaining
budget will be reprofiled into 2024/25.

Page 9

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 12
Budget Forecast
Spend
£000 £000 % £000 £000 %
Electronic Insurance System
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
24
Project Life Financials 10,924 (40) 0% 10,924 0 0%
Current Year Financials 7,209 (40) -1% (40) (7,249) -101%
Project Description
Project Manager Patricia Rowley/ Craig Jardine
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
25
Project Life Financials 2,880 2,504 87% 2,880 0 0%
Current Year Financials 814 556 68% 556 (257) -32%
Project Description
Project Manager Michelle Lynn
Chief Officer Amanda Graham
Project Lifecycle 31-Mar-23 30-Sep-24
Anticipated Outcome
Budget to be taken per Council savings option 
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Administration budget commitment.  All projects progressing with unspent budget reprofiled into 2024/25.
Mitigating Action
Unallocated budget to be taken per Council savings option 
Heritage Capital Fund
00 January 1900
Main Issues / Reason for Variance  
Network expansion to GJNH (Golden Jubilee National Hospital) will commence pending approval to proceed by the GJNH Board including agreeing tariff rates .  Unable
to confirm exact programme until approval has been given.
Mitigating Action
Network expansion to Golden Jubilee is discussed at every District Heating Project Board
Anticipated Outcome
Project to be delivered on programme and within budget once it has been fully set.
District Heating Network Expansion
District Heating Network Expansion.
Planned End Date Forecast End Date

Page 10

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 12
Budget Forecast
Spend
£000 £000 % £000 £000 %
Electronic Insurance System
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
26
Project Life Financials 478 84 18% 478 0 0%
Current Year Financials 478 84 18% 84 (394) -82%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
27
Project Life Financials 446 228 51% 446 0 0%
Current Year Financials 446 169 38% 169 (277) -62%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 30-Sep-24
28
Project Life Financials 37 45 122% 45 8 23%
Current Year Financials 13 0 0% 0 (13) -100%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
29
Project Life Financials 250 14 6% 250 0 0%
Current Year Financials 250 0 0% 0 (250) -100%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-25
30
Project Life Financials 4,316 5,902 137% 6,045 1,729 40%
Current Year Financials 864 1,462 169% 1,462 598 69%
Project Description
Project Manager Craig Jardine
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-Mar-24
Anticipated Outcome
New sports Hub delivered
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Scottish Water connection now complete.  Programme to completion being finalised by Contractor.
Mitigating Action
None available at this time
Mitigating Action
None required at this time.
Anticipated Outcome
Sustainable burial environment for local residents.
Posties Park Sports Hub - New sports hub to include gym & running track
Creation of a sports hub at Posties/Marinecraft to include a new changing pavilion/Gym, new all-weather 6 lane running
track, conversion of blaze sports pitch to grass, new fencing, upgrade of existing floodlights and additional car parking.  This
combines the budget approved by the Council in February 2015 for Community Sports Facilities at Posties Park, draw down
of budget from the generic sports facilities budget line.
Cemetery Extension, North Dalnotter
Cemetery Extension, North Dalnotter
Planned End Date Forecast End Date
Main Issues / Reason for Variance
North Dalnotter will now be delivered in financial year 24/25
Main Issues / Reason for Variance
Project Underway with remaining budget being reprofiled into 2024/25.
Mitigating Action
None available at this time
Anticipated Outcome
Sustainable burial environment for local residents.
Anticipated Outcome
Additional allotments delivered within budget
Kilmaronock Cemetery Expansion
Expansion of existing cemetery at Kilmaronock. 
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works Progressing. Remaining budget will be reprofiled into 2024/25
Mitigating Action
None required at this time.
Mitigating Action
None required at this time.
Anticipated Outcome
Better access with parks, cemeteries and open spaces.
Allotment Development
To develop an allotment site.
Public non-adopted paths and roads
Upgrades to drainage and lighting to enhance the lifespan of paths and roads within  facilities in public parks, cemeteries
and civic spaces.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Full budget committed. Works progressing in 2024/25.

Page 11

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 12
Budget Forecast
Spend
£000 £000 % £000 £000 %
Electronic Insurance System
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
31
Project Life Financials 876 876 100% 876 (0) 0%
Current Year Financials 529 589 111% 589 60 11%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-25
32
Project Life Financials 381 6 2% 381 0 0%
Current Year Financials 385 6 2% 6 (379) -98%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-25
33
Project Life Financials 1,338 123 9% 1,338 (0) 0%
Current Year Financials 380 65 17% 65 (316) -83%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-28 31-Mar-28
34
Project Life Financials 600 0 0% 600 0 0%
Current Year Financials 200 0 0% 0 (200) -100%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 30-Nov-23 31-Mar-25
Mitigating Action
None required at this time.
Anticipated Outcome
Balloch Mountain Bike Track
Balloch Mountain Bike Track
Develop a mountain bike skills trail at Balloch Castle Country Park.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Design undertaken this financial year. Work is due to progress during financial year 2024/25.
Main Issues / Reason for Variance
Tender documentation complete, commencement programmed February 24 with remaining budget being reprofiled into 2024/25.
Mitigating Action
None required at this time.
Anticipated Outcome
Renewal of play parks
Anticipated Outcome
Resurfacing of 3G pitch at East End Park.
Play Parks Grant Funding
Renew and replace play park equipment
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
External funding confirmed and design commencing.  Project will progress in 2024/25.
Mitigating Action
None required.
Mitigating Action
None available at this time.
Anticipated Outcome
Extension to existing cemetery providing a sustainable burial environment.
East End Park Resurfacing
Resurfacing of 3G pitch at East End Park.
Vale of Leven Cemetery Extension
Extension of existing cemetery in Vale of Leven.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project will be completed Summer 2024

Page 12

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 12
Budget Forecast
Spend
£000 £000 % £000 £000 %
Electronic Insurance System
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
35
Project Life Financials 3 3 100% 3 0 0%
Current Year Financials 214 0 0% 0 (214) -100%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
36
Project Life Financials 561 482 86% 561 0 0%
Current Year Financials 561 482 86% 482 (79) -14%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
37
Project Life Financials 358 358 100% 358 0 0%
Current Year Financials 42 0 0% 0 (42) -100%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Main Issues / Reason for Variance
Works instructed for link path to be combined with Golden Jubilee Active travel contributions.  Budget will be reprofiled into 2024/25.
Mitigating Action
None available at this time.
Anticipated Outcome
To complete remaining civil works required.
Anticipated Outcome
To improve connectivity and enhanced Cycling routes within West Dunbartonshire.
Auld Street Clydebank - Bond
Footpath still to be done after xmas spend.  Part funded by Golden jubie £20k.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works for a footway/cycleway improvement at Bellsmyre Avenue are now complete. Dropped kerbs at various locations are underway. Proposed further works to
cycleways will progress in 2024/25.
Mitigating Action
None required at this time.
Mitigating Action
None available at this time.
Anticipated Outcome
To improve journey times and reliability of bus services.
Cycling, Walking and Safer Streets
Introduction of enhanced walking routes and traffic calming schemes to introduce safer streets within West Dunbartonshire.
Bus Rapid Deployment Fund
Funding has been awarded from Sustrans to assist with social distancing measures required as a result of the COVID-19
pandemic.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Funding no longer available.  Will be removed from capital progamme in 2024/25

Page 13

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 12
Budget Forecast
Spend
£000 £000 % £000 £000 %
Electronic Insurance System
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
38
Project Life Financials 55 55 100% 55 0 0%
Current Year Financials 5 0 0% 0 (5) -100%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
39
Project Life Financials 299 299 100% 299 (0) 0%
Current Year Financials 56 41 73% 41 (15) -27%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
40
Project Life Financials 500 161 32% 500 0 0%
Current Year Financials 500 161 32% 161 (339) -68%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
41
Project Life Financials 801 181 23% 801 0 0%
Current Year Financials 620 0 0% 0 (620) -100%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-26
Anticipated Outcome
Project should be completed within budget.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Awaiting outcome of Scottish Government & SEPA consideration of submitted study .  Budget will be reprofiled into 2024/25.
Mitigating Action
None required at this time.
Mitigating Action
None required at this time.
Anticipated Outcome
Projects should be complete within budget.
River Leven Flood Prevention Scheme
River Leven Flood Prevention Scheme.
Flood Prevention
Various flood prevention projects.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Limited uptake on property level protection. Remaining budget will be reprofiled into 2024/25.
Anticipated Outcome
To provide Electric Vehicle Charging points within West Dunbartonshire.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Balloch Park 50kw EVC to be upgraded with unspent budget reprofiled into 2024/25.
Mitigating Action
None required at this time.
Mitigating Action
None required at this time.
Anticipated Outcome
Traffic calming to be installed in Dumbarton East.
Electrical Charging Points - Rapid Charge
Funding has been awarded from Transport Scotland for the Installation of electrical charging points
Turnberry Homes - traffic calming/ management at Turnberry housing development off Castle Road
Funding has been received from Turnberry Homes and will be used to introduce traffic calming and traffic management
measures to mitigate the impact of additional traffic accessing the housing development off Castle Road, Dumbarton.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project progressing with remaining unspent budget reprofiled into 2024/25.

Page 14

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 12
Budget Forecast
Spend
£000 £000 % £000 £000 %
Electronic Insurance System
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
42
Project Life Financials 1,781 951 53% 1,781 0 0%
Current Year Financials 650 154 24% 154 (496) -76%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
43
Project Life Financials 2,195 2,285 104% 2,285 90 4%
Current Year Financials 2,195 2,285 104% 2,285 90 4%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
44
Project Life Financials 99 99 100% 99 (0) 0%
Current Year Financials 29 31 107% 31 2 7%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
45
Project Life Financials 14,781 691 5% 14,781 (0) 0%
Current Year Financials 1,530 237 16% 237 (1,293) -84%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-27
Mitigating Action
None available at this time.
Anticipated Outcome
Project should be completed within budget.
Gruggies Burn Flood Prevention
Commission of Gruggies Flood Prevention Scheme.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Detailed design underway. Design will be completed 24/25
Main Issues / Reason for Variance
Detailed design underway. Design will be completed 24/25
Mitigating Action
None available at this time.
Anticipated Outcome
Intention is to complete works within budget.
Depot Improvement Works
Improvement of WDC Roads Depot.
Planned End Date Forecast End Date
Mitigating Action
None required at this time.
Anticipated Outcome
Intention is to complete various surfacing works by the end of March 2024.
Infrastructure - Roads
Infrastructure - Roads.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Roads Operations have completed an extensive surfacing program . A programme of structural patching is ongoing.
Main Issues / Reason for Variance
For Bus Infrastructure a program of works Is being developed. For A8014 Kilbowie Rd works are being planned awaiting further feedback from Utilities, For A814
Congestion measures further development & expansion of vehicle detection systems and for Balloch P & R Consultants are appointed, agreement in principal with
Network Rail & further investigatory works are planned for 2024/25.
Mitigating Action
None required at this time.
Anticipated Outcome
Improve accessibility to Public Transport and improve journey time reliability.
Strathclyde Partnership for Transport - Bus, cycling and walking infrastructure improvements & Park and Rides
Strathclyde Partnership for Transport - Bus, cycling and walking infrastructure improvements.
Planned End Date Forecast End Date

Page 15

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 12
Budget Forecast
Spend
£000 £000 % £000 £000 %
Electronic Insurance System
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
46
Project Life Financials 1,550 1,057 68% 1,550 0 0%
Current Year Financials 693 50 7% 50 (643) -93%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-26 31-Mar-27
47
Project Life Financials 50 0 0% 50 0 0%
Current Year Financials 50 0 0% 0 (50) -100%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
48
Project Life Financials 4,303 4,215 98% 4,303 (0) 0%
Current Year Financials 138 54 39% 54 (85) -61%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-Mar-24
49
Project Life Financials 14 14 100% 14 0 0%
Current Year Financials 75 9 12% 9 (66) -88%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
50
Project Life Financials 274 274 100% 274 0 0%
Current Year Financials 26 0 0% 0 (26) -100%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
Main Issues / Reason for Variance
Upgrade of obsolete equipment budget will be reprofiled in 2024/25.
Mitigating Action
None required.
Anticipated Outcome
To upgrade traffic signals.
Anticipated Outcome
To purchase equipment.
Traffic Signal Upgrades
Upgrade Traffic Signals
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
New plant has been purchased. Budget will be reprofiled into 2024/25.
Mitigating Action
None required.
Mitigating Action
None available at this time.
Anticipated Outcome
Project will enhance the A814 through Clydebank.
Roads Plant
Purchase of Roads plant and equipment.
Clydebank Charrette, A814
Clydebank Charrette, A814
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works complete and on maintenance period - retention payment to be paid.
Main Issues / Reason for Variance
New funding which will be allocated to appropriate projects.
Mitigating Action
None required at this time.
Anticipated Outcome
Projects will be delivered.
Anticipated Outcome
To provide an improved A813.
Roads Safety
Roads Safety
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Initial works commencing March 23 with majority of works to be delivered 24/25
Mitigating Action
None required at this time.
A813 Road Improvement Phase 1
A813 Road Improvement Phase 1.

Page 16

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 12
Budget Forecast
Spend
£000 £000 % £000 £000 %
Electronic Insurance System
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
51
Project Life Financials 900 0 0% 900 0 0%
Current Year Financials 1,400 0 0% 0 (1,400) -100%
Project Description
Project Manager Craig Jardine
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
52
Project Life Financials 3,314 590 18% 3,314 0 0%
Current Year Financials 3,314 590 18% 590 (2,724) -82%
Project Description
Project Manager Craig Jardine
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 30-May-24
53
Project Life Financials 1,780 0 0% 1,780 0 0%
Current Year Financials 1,980 0 0% 0 (1,980) -100%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Dec-25
Mitigating Action
None Required.
Anticipated Outcome
Project delivered within budget.
Waste Transfer Station
The design, development and construction of a recycling and bulk waste transfer facility that will ensure all recycling
material can be sorted and disposed off appropriately to ensure compliance with landfill ban in 2025.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Detailed design ongoing - budget will be reprofiled into 2024/25.
Main Issues / Reason for Variance
Vehicles have been ordered including bin lorries, sweepers and tractors.  Expected delivery of bin lorries between April and July 2024.
Mitigating Action
None Required.
Anticipated Outcome
Replacement of fleet within budget.
Anticipated Outcome
Replacement of refuse collection vehicles.
Vehicle Replacement
Replacement of vehicles which have reached end of programmed lifespan (7 year heavy vehicles, 10 year light vehicles).
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Bin lorries ordered and build slot allocated in 2023/24.  Budget will be reprofiled in 2024/25.
Mitigating Action
None available.
Vehicle Replacement Strategy
Replacement of refuse collection vehicles.

Page 17

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 12
Budget Forecast
Spend
£000 £000 % £000 £000 %
Electronic Insurance System
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
54
Project Life Financials 72 44 61% 72 0 0%
Current Year Financials 89 5 5% 5 (84) -95%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
55
Project Life Financials 150 0 0% 0 (150) 0%
Current Year Financials 150 0 0% 0 (150) -100%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-25
56
Project Life Financials 0 115 0% 115 115 0%
Current Year Financials 0 115 0% 115 115 0%
Project Description
Project Manager Craig Jardine
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
Main Issues / Reason for Variance
Further invoices to be processed in 2024/25.
Mitigating Action
None Required.
Anticipated Outcome
Office Rationalisation
Anticipated Outcome
Project delivered within  budget.
Office Rationalisation
Office Rationalisation
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
MUGA due for commencement in February and environmental improvements complete.  Budget will be reprofiled into 2024/25.
Mitigating Action
None Required.
Park Improvements and Multi Games Area - Goldenhill Park
Park Improvements and Multi Games Area - Goldenhill Park
Main Issues / Reason for Variance
Project in progress. Remaining budget will be reprofiled into 2024/25.
Mitigating Action
None Required.
Anticipated Outcome
ELECTRIC VEHICLE INFRASTRUCTURE
ELECTRIC VEHICLE INFRASTRUCTURE
Electric Vehicle Infrastructure
Planned End Date Forecast End Date

Page 18

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 12
Budget Forecast
Spend
£000 £000 % £000 £000 %
Electronic Insurance System
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
57
Project Life Financials 32,326 6,780 21% 32,326 0 0%
Current Year Financials 11,845 2,834 24% 2,834 (9,011) -76%
Project Description
Project Manager Patricia Rowley
Chief Officer Gail McFarlane
Project Lifecycle 31-Mar-27 31-Mar-27
Anticipated Outcome
Delivery of the project on time and within the increased budget
Planned End Date Forecast End Date
Main Issues / Reason for Variance 
Regular updates are provided at every Council meeting and monthly Project Board meetings and to City Deal.  The main issues contained within the new Council's
approved Outline Business Case are still valid, which include Exxon's remediation strategy, land transfer arrangements and issues relating to adjoining owners.  WDC
Consultants are monitoring the remediation process to ensure compliance with specification, also Esso are independently monitoring the remediation works.  Final
Business Case submission was June 2023. Through the Scape framework we are working closely with Balfour Beatty to achieve a formal pre construction agreement to
allow the detailed design works to commence and the full construction programme to be developed. Agreements in principle are progressing with third party land owners.
Mitigating Action
None Required
Exxon City Deal
As part of the City Deal project the WDC Exxon site at Bowling regeneration with alternative A82 route included.

Page 19

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 12
Budget Forecast
Spend
£000 £000 % £000 £000 %
Electronic Insurance System
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
58
Project Life Financials 8,774 684 8% 8,774 (0) 0%
Current Year Financials 2,238 339 15% 339 (1,900) -85%
Project Description
Project Manager Craig Jardine
Chief Officer Gail McFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
59
Project Life Financials 238 8 3% 238 0 0%
Current Year Financials 250 8 3% 8 (242) -97%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
60
Project Life Financials 39 39 100% 39 0 0%
Current Year Financials 60 39 65% 39 (21) -35%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
61
Project Life Financials 859 292 34% 859 0 0%
Current Year Financials 397 31 8% 31 (366) -92%
Project Description
Project Manager David Jones/ Julie McGrogan
Chief Officer Laura Mason
Project Lifecycle 31-Mar-29 31-Mar-29
Mitigating Action
None required at this time.
Anticipated Outcome
Purchase of AV Equipment for Education.
AV Equipment - Education
Purchase of AV Equipment for Education.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Progressing as expected. Spend is not linear AV boards replaced as a when they fail.
Main Issues / Reason for Variance
Project progressing in 2024/25.
Mitigating Action
None available at this time
Anticipated Outcome
Deliver project outcomes within agreed budget
Anticipated Outcome
Deliver project outcomes within agreed budget
Switched on Fleet 
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Expecting work to commence in financial year 2024/25. Budget will be reprofiled into 2024/25.
Mitigating Action
None available at this time
Pappert 2G pitch
Resurfacing of blaze pitch to 3G all weather surface
Main Issues / Reason for Variance
Committee approval given to upgrade and improve depots.  Project delivery will be phased, work underway to determine phasing of spend and scope.  Garage facilities
will be treated as a priority
Mitigating Action
None available at this time
Anticipated Outcome
Deliver project outcomes within agreed budget
Depot Rationalisation
Depot Rationalisation.
Planned End Date Forecast End Date

Page 20

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 12
Budget Forecast
Spend
£000 £000 % £000 £000 %
Electronic Insurance System
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
62
Project Life Financials 365 344 94% 365 (0) 0%
Current Year Financials 41 9 21% 9 (32) -79%
Project Description
Project Manager David Jones/ Julie McGrogan
Chief Officer Laura Mason
Project Lifecycle 31-Mar-23 31-Mar-24
63
Project Life Financials 48,377 16,269 34% 48,377 0 0%
Current Year Financials 4,222 699 17% 699 (3,523) -83%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-24 31-Mar-24
64
Project Life Financials 6,638 2,396 36% 6,638 0 0%
Current Year Financials 3,495 1,591 46% 1,591 (1,904) -54%
Project Description
Project Manager Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-26 31-Jul-27
65
Project Life Financials 823 823 100% 823 0 0%
Current Year Financials 122 251 206% 251 129 106%
Project Description
Project Manager Michelle Lynn
Chief Officer Laura Mason
Project Lifecycle 31-Mar-24 31-Mar-24
66
Project Life Financials 8,854 9,230 104% 9,230 376 4%
Current Year Financials 287 439 153% 439 153 53%
Project Description
Project Manager Michelle Lynn
Chief Officer Laura Mason
Project Lifecycle 31-Mar-24 31-Mar-24
Main Issues / Reason for Variance
Works completed . Linnvale PS ELCC adaptations will commence in 2024/25 this is due to the delay in receiving  a building warrant.
Mitigating Action
None at this time
Anticipated Outcome
The project will be completed to deliver the requirements of the Early Years expansion plans.
Anticipated Outcome
Project delivered within amended timescales.
Early Years Early Learning and Childcare Funding
Early learning and childcare funding awarded to West Dunbartonshire Council to facilitate the expansion in entitlement to
funded ELCC to 1140 hours from August 2020.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Provision of Capital Funding from Scottish Government to implement free school meal initiative.
Mitigating Action
None available at this time.
Mitigating Action
None required at this time
Anticipated Outcome
Project delivered to required specification
Free School Meals
Provision of Capital Funding from Scottish Government to implement free school meal initiative.
Schools Estate Improvement Plan - next Phase - Faifley Campus
Improvement of Schools Estate.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The next phase of the Schools Estate Improvement Plan involves the development of a new Campus provision in the Faifley area. WDC has been successful in securing
funding from the Scottish Government Learning Estate Improvement Programme. SFT confirmed the indicative funding allocation for this project at £18.416m on the 4
May 2021, this will be received as a revenue stream over the 25 years of the Scottish Government financial support (subject to the Council adhering to the funding
criteria). Site Options Appraisal has taken place and Members approved the recommendation to proceed with the new Faifley Campus on the St Joseph's site at
Education Committee on 9th June 2021.  Planning permission has been agreed and Stage 1 Building Warrant approved.  Remaining budget will be reprofiled into
2024/25.
Main Issues / Reason for Variance
Works progressing in line with programme - unspent budget will be reprofiled into 2024/25
Mitigating Action
None at this time
Anticipated Outcome
Project delivered within budget and to required specification
Anticipated Outcome
Increase the Chromebook ratio for most disadvantaged children.
Schools Estate Improvement Plan
Improvement of Schools Estate.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Delay in identifying appropriate cohort for project delivery. Current challenge is finding a suitable and available location.
Mitigating Action
None required at this time.
Digital Inclusion
Increase the ratio of chrome book devices for most disadvantaged children and families and support for families with remote
access.

Page 21

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 12
Budget Forecast
Spend
£000 £000 % £000 £000 %
Electronic Insurance System
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
67
Project Life Financials 845 960 114% 960 115 14%
Current Year Financials 845 960 114% 960 115 14%
Project Description
Project Manager Julie Slavin
Chief Officer Beth Culshaw
Project Lifecycle 31-Mar-24 31-Mar-24
68
Project Life Financials 584 40 7% 584 0 0%
Current Year Financials 584 40 7% 40 (543) -93%
Project Description
Project Manager Alastair Handley
Chief Officer Beth Culshaw
Project Lifecycle 31-Mar-24 31-Mar-24
69
Project Life Financials 308 27 9% 308 0 0%
Current Year Financials 308 27 9% 27 (281) -91%
Project Description
Project Manager Julie Slavin
Chief Officer Beth Culshaw
Project Lifecycle 31-Mar-24 31-Mar-24
70
Project Life Financials 19 3 14% 19 0 0%
Current Year Financials 19 3 14% 3 (17) -86%
Project Description
Project Manager Julie Slavin
Chief Officer Beth Culshaw
Project Lifecycle 31-Mar-24 31-Mar-24
71
Project Life Financials 892 962 108% 962 69 8%
Current Year Financials 892 962 108% 962 69 8%
Project Description
Project Manager James Gallacher
Chief Officer Victoria Rogers
Project Lifecycle 31-Mar-24 31-Mar-24
Anticipated Outcome
projects delivered.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Device replacement project completed.
Mitigating Action
none required
Mitigating Action
None available at this time
Anticipated Outcome
Renovation of Unit 11 Leven side Business Court
ICT Modernisation
This budget is to facilitate ICT infrastructure and modernise working practices.
Criminal Justice Adaptations
Renovation of Unit 11 Levenside Business Court.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works Complete
Main Issues / Reason for Variance
While there has been some movement on the project to date, progress is slow.  Procuring equipment that is fully compatible with the platform is the priority to enable
WDHSCP to best support the digital rollout, however delays from Scotland Excel has required an alternative procurement solution to be identified for a smaller scale
initial purchase.  The contract for the Digital ARC has been awarded and a test unit and access to the demo platform has been received with a plan to on-board
partnerships to the live platform in Spring 2024, while the process to formalise arrangements with East Dunbartonshire Council for the ARC cover for the calls is ongoing
with the cost for the call handling service still to be confirmed. Remaining budget will be reprofiled into 2024/25.
Mitigating Action
Officers will continue to progress the project as quickly as possible but is complex and dependent on 3rd parties and equipment being compliant with the platform
Anticipated Outcome
Community Alarm Upgrade
Anticipated Outcome
Upgrade and enhance digital systems within HSCP
Community Alarm upgrade
To upgrade Community Alarm
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
A HSCP Digital Strategy 2024-2027 is in development. The strategy will have an internal focus, identifying areas where the HSCP would need to progress to support
digital transformation and improve the digital maturity of the partnership. The strategy will focus on areas where structures are in place to support change, where focus will
be required and setting the stage for opportunities to move forward. As well as digital technologies, the strategy will focus on staff skills and digital inclusion within our
communities, and support digital change projects over the duration of the strategy. A draft version of the strategy is out for comment, and has been submitted to the
Senior Management Team, with a view to a final version being submitted to HSCP Board for approval on 25th June.  Remaining budget  will be reprofiled into 2024/25 for
progressing planned works
Mitigating Action
None available at this time as project spend will be dependent upon the digital strategy being approved by the HSCP Board
Mitigating Action
None available at this time
Anticipated Outcome
Provision of adaptations and equipment to HSCP clients as anticipated.
HSCP ICT Upgrade of systems
Review/replace the current case management systems.
Aids & Adaptations - Special Needs Adaptations & Equipment
Reactive budget to provide adaptations and equipment for HSCP clients.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
There is likely to be a small underspend in the current year due to the implementation of the new system, however this will require to be carried forward to 2024/25 in light
of anticipated equip cost increases and as activity levels increase back to normal levels.

Page 22

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 12
Budget Forecast
Spend
£000 £000 % £000 £000 %
Electronic Insurance System
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
72
Project Life Financials 50 50 100% 50 0 0%
Current Year Financials 10 0 0% 0 (10) -100%
Project Description
Project Manager James Gallacher
Chief Officer Victoria Rogers
Project Lifecycle 31-Oct-22 31-Mar-24
73
Project Life Financials 873 873 100% 873 0 0%
Current Year Financials 873 735 84% 735 (138) -16%
Project Description
Project Manager James Gallacher
Chief Officer Victoria Rogers
Project Lifecycle 31-Mar-24 31-Mar-24
74
Project Life Financials 898 418 47% 898 0 0%
Current Year Financials 185 100 54% 100 (85) -46%
Project Description
Project Manager James Gallacher
Chief Officer Victoria Rogers
Project Lifecycle 30-Sep-23 30-Sep-23
Anticipated Outcome
365 Implementation
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Delay to Sharepoint implementation project. External resourcing requirements less than expected and small underspend being carried into 2024/25..
Mitigating Action
none required
Mitigating Action
none required
Anticipated Outcome
ICT Security & DR
365 Implementation
Project services to delivery Microsoft 365 Implementation including 3rd party supplier, training, technical consultancy etc.
ICT Security & DR
The project is for the enhancement of security systems, server replacement and the update of corporate applications to
ensure compliance with 15/16 PSN requirements, to enhance the disaster recovery capabilities of WDC.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Various projects in progress and orders raised for Cyber Security technology, Citrix replacement devices, SAN storage, server hardware, system security remediation and
upgrades - remaining budget will be reprofiled into 2024/25. 
Main Issues / Reason for Variance
Project Complete
Mitigating Action
None available at this time.
Anticipated Outcome
projects delivered on time.
Internet of Things Asset Tracking
Asset Tracking.
Planned End Date Forecast End Date

Page 23

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 12
Budget Forecast
Spend
£000 £000 % £000 £000 %
Electronic Insurance System
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
75
Project Life Financials 1,586 1,586 100% 1,586 0 0%
Current Year Financials 1,586 3,895 246% 3,895 2,309 146%
Project Description
Project Manager N/A
Chief Officer N/A
Project Lifecycle 31-Mar-24 31-Mar-24
Mitigating Action
None required.
Anticipated Outcome
Direct project support costs allocated as appropriate.
Direct Project Support
Business support cost such as reallocation of architects and project support at year end.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Salary Capitalisation in 2023/2024.

Page 24

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 12
Budget Spend at
31/3/24
£000 £000 % £000 £000 %
1
Project Life Financials 25 25 100% 25 0 1%
Current Year Financials 2 2 100% 2 0 0%
Project Description
Project Manager Russell Hewton
Chief Officer Russell Hewton
Project Lifecycle 31-Mar-23 31-Mar-24
2
Project Life Financials 20 10 50% 20 0 0%
Current Year Financials 10 10 99% 10 (0) -1%
Project Description
Project Manager Karen Shannon
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-24 31-Mar-24
Main Issues / Reason for Variance
The module is live
Mitigating Action
None required at this time.
Anticipated Outcome
Upgraded version with PCI compliant telephone payment system.
None available at this time.
Anticipated Outcome
Requisition of ICT Equipment.
Payment Card Industry Data Security Standard (PCIDSS)
Module would ensure that WDC were compliant with the current requirements of PCIDSS for card payments without the
need for numerous costly workarounds
Planned End Date Forecast End Date
Requisition ICT Equipment.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Replacement of laptops, monitors and other ICT equipment.
Mitigating Action
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
Valuation Joint Board - Requisition of ICT Equipment

Page 25

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 12
Budget Spend at
31/3/24
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
Valuation Joint Board - Requisition of ICT Equipment3
Project Life Financials 750 250 33% 750 0 0%
Current Year Financials 0 0 0% 0 0 0%
Project Description
Project Manager Adrian Gray
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-26 31-Mar-26
Anticipated Outcome
Project will be delivered on time and on budget
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The budget has been spent. Spend is transferred at year end as part of the year end process
Mitigating Action
None required at this time.
Cost of Living
To support Council and community organisations with capital costs for cost of living initiatives.

Page 26

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 12
Budget Spend at
31/3/24
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
Valuation Joint Board - Requisition of ICT Equipment

Page 27

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 12
Budget Spend at
31/3/24
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
Valuation Joint Board - Requisition of ICT Equipment4
Project Life Financials 46 41 88% 46 0 0%
Current Year Financials 7 0 0% 0 (7) -100%
Project Description
Project Manager Alan Douglas
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
Mitigating Action
None required at this time.
Anticipated Outcome
Solicitor support for Capital Projects.
Solicitor Project Support for Capital Projects
Solicitor costs to directly support capital projects
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Trainee solicitor now in place.

Page 28

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 12
Budget Spend at
31/3/24
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
Valuation Joint Board - Requisition of ICT Equipment5
Project Life Financials 450 193 43% 193 (258) -57%
Current Year Financials 0 0 0% 0 0 0%
Project Description
Project Manager Rachel Moir
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
Anticipated Outcome
Credit note received and project closed
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This project has been completed.
Mitigating Action
This project has been completed.
Zero Carbon
Zero Carbon

Page 29

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 12
Budget Spend at
31/3/24
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
Valuation Joint Board - Requisition of ICT Equipment

Page 30

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 12
Budget Spend at
31/3/24
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
Valuation Joint Board - Requisition of ICT Equipment6
Project Life Financials 326 326 100% 326 (0) 0%
Current Year Financials 116 20 18% 20 (95) -82%
Project Description
Project Manager Emma Eremin
Chief Officer Amanda Graham
Project Lifecycle 31-Mar-24 31-Mar-25
7
Project Life Financials 906 906 100% 906 0 0%
Current Year Financials 6 5 83% 5 (1) -17%
Project Description
Project Manager Elaine Troup
Chief Officer Amanda Graham
Project Lifecycle 31-Mar-24 31-Mar-24
Main Issues / Reason for Variance
Project complete.
Mitigating Action
Project complete
Anticipated Outcome
Project complete
Invest in "Your Community Initiative"
Capital budget to support the roll out of Your Community,  an initiative designed to achieve coordinated service delivery in
response to community need. This is complimented by community capacity building, empowering WD citizens to do more
for their own communities (leading to less reliance on council).  Also included is the implementation of participatory
budgeting to support and build capacity in communities.
Planned End Date Forecast End Date
Mitigating Action
Non required
Anticipated Outcome
Projects delivered on budget
Transformation of Infrastructure Libraries and Museums
To improve performance and efficiency of Council's Libraries and Cultural Services.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Library colocations of Dalmuir and Balloch being fitted out by Asset Management.  Awaiting outcome for Duntocher and Parkhall libraries.  Remaining Libraries capital to
be spent in 24/25 once colocation plans completed.

Page 31

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 12
Budget Spend at
31/3/24
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
Valuation Joint Board - Requisition of ICT Equipment

Page 32

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 12
Budget Spend at
31/3/24
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
Valuation Joint Board - Requisition of ICT Equipment8
Project Life Financials 220 220 100% 220 0 0%
Current Year Financials 8 7 87% 7 (1) -13%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 03-Apr-21 31-Mar-24
Main Issues / Reason for Variance
Project works complete.  Retentions to be paid.
Mitigating Action
None required at this time.
Anticipated Outcome
New all weather tennis courts.
Sports Facilities Upgrades - Argyll Park - Construction of 3 All Weather Tennis Courts
Project is part of wider investment in sporting facilities and is dependent on match funding from Sports Scotland. Agreement
in principle to wider WDC strategic priorities.
Planned End Date Forecast End Date

Page 33

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 12
Budget Spend at
31/3/24
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
Valuation Joint Board - Requisition of ICT Equipment9
Project Life Financials 25 25 100% 25 0 0%
Current Year Financials 6 6 100% 6 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
10
Project Life Financials 574 519 90% 574 0 0%
Current Year Financials 430 519 121% 519 89 21%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Main Issues / Reason for Variance
Projects identified with a number commenced. Budget will be reprofiled into 2024/25 and claimed back from the Scottish Government.
Mitigating Action
None required at this time.
Anticipated Outcome
completion of project on time.
Anticipated Outcome
Large bins provided for high traffic areas
Nature Restoration Fund
Nature resource for Faifley Community
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project complete.
Mitigating Action
None required at this time.
Large bins for high traffic areas (pilot)
Supply and install extra large litter bins as a pilot project within hotspot problem areas.

Page 34

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 12
Budget Spend at
31/3/24
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
Valuation Joint Board - Requisition of ICT Equipment11
Project Life Financials 237 237 100% 237 0 0%
Current Year Financials 237 237 100% 237 0 0%
Project Description
Project Manager Raymond Walsh/ Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Main Issues / Reason for Variance
Works completed.
Mitigating Action
None required at this time.
Anticipated Outcome
Project complete within budget.
Flood Risk Management
Enhancement of drainage infrastructure to ensure compliance with Flood Risk Management Act 2009.
Planned End Date Forecast End Date

Page 35

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 12
Budget Spend at
31/3/24
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
Valuation Joint Board - Requisition of ICT Equipment12
Project Life Financials 84 70 84% 84 0 0%
Current Year Financials 84 70 84% 70 (14) -16%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Anticipated Outcome
Intention is to complete works within budget.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Lighting works completed - final invoices to be received and processed.
Mitigating Action
None available at this time.
Street lighting and associated electrical infrastructure
00 January 1900

Page 36

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 12
Budget Spend at
31/3/24
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
Valuation Joint Board - Requisition of ICT Equipment

Page 37

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 12
Budget Spend at
31/3/24
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
Valuation Joint Board - Requisition of ICT Equipment13
Project Life Financials 958 958 100% 958 0 0%
Current Year Financials 878 837 95% 837 (42) -5%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
14
Project Life Financials 169 71 42% 169 0 0%
Current Year Financials 9 0 0% 0 (9) -100%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
Anticipated Outcome
Project delivered within  budget.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works complete awaiting final invoice
Mitigating Action
None Required.
Replacement of compactors at Dalmoak civic amenity site
The purchase of 2 compactors for the Council civic amenity site at Dalmoak.
Mitigating Action
None required.
Anticipated Outcome
Improvement to pavements.
Pavement improvements
Various pavement improvement projects.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Footway resurfacing works completed final invoices to be received & processed.

Page 38

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 12
Budget Spend at
31/3/24
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
Valuation Joint Board - Requisition of ICT Equipment15
Project Life Financials 20 0 0% 20 0 0%
Current Year Financials 20 0 0% 0 (20) -100%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
16
Project Life Financials 44 44 100% 44 0 0%
Current Year Financials 59 44 75% 44 (15) -25%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Mitigating Action
None Required.
Anticipated Outcome
Whitecrook Tennis Court Up-grade
Whitecrook Tennis Court Up-grade
Whitecrook Tennis Court Up-grade
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project Complete
Mitigating Action
None Required.
Anticipated Outcome
Project delivered within  budget.
River bank erosion repair - Levenhowe
River bank erosion repair in the Levenhowe area
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works complete awaiting final invoice

Page 39

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 12
Budget Spend at
31/3/24
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
Valuation Joint Board - Requisition of ICT Equipment

Page 40

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 12
Budget Spend at
31/3/24
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
Valuation Joint Board - Requisition of ICT Equipment17
Project Life Financials 151 151 100% 151 0 0%
Current Year Financials 200 151 75% 151 (49) -25%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 30-Nov-23 30-Nov-23
Mitigating Action
None available at this time
Anticipated Outcome
Deliver project outcomes within agreed budget
Dalmonach Steps upgrade
Upgrading steps at Dalmonach to make them more accessible
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project complete.

Page 41

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 12
Budget Spend at
31/3/24
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
Valuation Joint Board - Requisition of ICT Equipment

Page 42

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 12
Budget Spend at
31/3/24
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
Valuation Joint Board - Requisition of ICT Equipment

Page 43

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 12
Budget Spend at
31/3/24
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
Valuation Joint Board - Requisition of ICT Equipment18
Project Life Financials 291 42 14% 291 0 0%
Current Year Financials 46 0 0% 0 (46) -100%
Project Description
Project Manager Arun Menon
Chief Officer Victoria Rogers
Project Lifecycle 31-Mar-30 31-Mar-30
Main Issues / Reason for Variance
Project complete.
Mitigating Action
none required
Anticipated Outcome
Development of Workforce Management System
Development of Workforce Management System
Project to develop the Workforce Management System.
Planned End Date Forecast End Date

Page 44

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 12
Budget Spend at
31/3/24
£000 £000 % £000 £000 %
31 March 2024
Budget Details
Project Life Financials
Spend at 31 March 2024 Variance
Valuation Joint Board - Requisition of ICT Equipment

Page 45

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RESOURCES
PERIOD END DATE
PERIOD 12
Budget Forecast Spend
£000 £000 % £000 £000 %
1
Project Life Financials (3,473) 1,372 -39% (3,473) 0 0%
Current Year Financials (2,115) 1,272 -60% 1,272 3,387 -160%
Project Description
Project Lifecycle 31-Mar-24 31-Mar-24
2
Project Life Financials (73,090) (49,208) 67% (81,658) (8,568) 12%
Current Year Financials (7,453) (14,786) 198% (14,786) (7,333) 98%
Project Description
Project Lifecycle 31-Mar-30 31-Mar-30
3
Project Life Financials (56,921) (13,645) 24% (51,914) 5,007 -9%
Current Year Financials (16,027) (9,140) 57% (9,140) 6,887 -43%
Project Description
Project Lifecycle 31-Mar-26 31-Mar-26
4
Project Life Financials (9,604) (5,363) 56% (9,604) 0 0%
Current Year Financials (5,315) (2,754) 52% (2,754) 2,561 -48%
Project Description
Project Lifecycle 31-Mar-24 31-Mar-24
Anticipated Outcome
Match funding received.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Application of resources is dependent on capital project progressing in year as planned.
Mitigating Action
None required.
Mitigating Action
None required.
Anticipated Outcome
Application of resources as appropriate.
Match Funding / Other Grants and Contributions
Match Funding / Other Grants and Contributions
Ring Fenced Government Grant Funding
This is ring fenced grant funding which is primarily anticipated to be received from the Scottish Government and
relates to Cycling, Walking, Safer Streets, Regeneration Placed Based Investment Programme, Early Years,
Gruggies Burn Flood works, Early Years funding, City Deal and Town Centre Fund.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Application of resources applied to capital project  as planned.
Main Issues / Reason for Variance
General services capital grant received.
Mitigating Action
None required at this time
Anticipated Outcome
General services capital grant received.
Application of resources held on balance sheet as at 31 March 2024 as appropriate.
General Services Capital Grant
This is a general grant received from the Scottish Government in relation to General Services capital spend
Planned End Date Forecast End Date
Mitigating Action
None required at this time.
Anticipated Outcome
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Application of resources applied to relevant capital projects.
Spend to Date Forecast Variance
Resources Carried Forward
These are resources that have been received in previous years relating to Turnberry Homes, Town Centre Fund
Grant, Digital Inclusion, Clydebank Can on the Canal, Internet of Things Asset Tracking, Renew Playparks,
Knowes Nature Reserve, Flood Prevention, District Heating Electric Vehicle Infrastructure and Auld Street Bond.
31 March 2024
Budget Details
Project Life Financials

Page 46

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RESOURCES
PERIOD END DATE
PERIOD 12
Budget Forecast Spend
£000 £000 % £000 £000 %
Spend to Date Forecast Variance
Resources Carried Forward
31 March 2024
Budget Details
Project Life Financials
5
Project Life Financials (88,219) (20,450) 23% (91,238) (3,019) 3%
Current Year Financials (62,794) (5,481) 9% (5,481) 57,313 -91%
Project Description
Project Lifecycle 31-Mar-26 31-Mar-26
Mitigating Action
None available at this time.
Anticipated Outcome
Prudential borrowing was less than anticipated.
Prudential Borrowing
Prudential borrowing is long term borrowing from financial institutions that has been approved for the purposes of
funding capital expenditure
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Prudential borrowing is impacted by programme delivery therefore mitigating action is detailed in the red and amber analysis.