WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer (Regeneration and Regulatory)
Council: 28 August 2024
Subject: Glasgow City Region City Deal - Update
1. Purpose
1.1 To note the progress with the implementation of the Exxon Infrastructure
Project and approve a Change Control Request, and to provide an
update on Glasgow City Region City Deal Programme.
2. Recommendations
2.1 It is recommended that Council:
i) Notes the update on the Exxon Infrastructure Project;
ii) Approves a Change Control Request to vary the construction
programme dates be submitted to Glasgow City Region for approval;
and
iii) Notes the progress of the Glasgow City Region programme
3. Background
3.1 The Glasgow City Region City Deal Infrastructure programme equates to
£1.13bn of investment during period 2015-2035. Projects are progressing
and have reached various stages from Strategic, Outline and Full Business
Case stages of approval.
3.2 At the meeting of Council on 20 December 2023, Council agreed to
delegate authority to the Chief Officer – Regulatory and Regeneration to
agree the construction agreements with Balfour Beatty Civil Engineering Ltd
and Network Rail and such ancillary agreements as may be required to
deliver the works, all in line with the approved budget.
4. Main Issues
4.1 This report provides information on City Region progress, and includes an
update on the Exxon site infrastructure project development.
Exxon Infrastructure Project
4.2 It was previously reported to Council that the Esso remediation works were to
be completed by the first week of June. Since then the Regulators have
asked Esso to undertake additional remediation at the quay, which has
added a few weeks to their programme. These delays, which have been
ITEM 8

Page 2

outside the Council’s control, have had an impact on the commencement of
the main infrastructure programme. The additional remediation work is
anticipated to be completed by early August, with a period of environmental
reporting to follow. The estimated land transfer of the formal Esso site is now
mid-September 2024. 
4.3 All other required land acquisitions and temporary access agreements have
now been agreed in principal.  The main construction contract will be signed
when these are concluded and the land from Esso is transferred to the
Council. Balfour Beatty will need up to 8 weeks after receiving the contract to
mobilise for site start, meaning that commencement of construction will be in
mid-November. Some early enabling works on land outwith Esso’s current
ownership, site clearance and archaeological surveys, are expected to begin
in September. 
4.4 With a site start in November 2024, project completion would be expected in
July 2027, however we are discussing with Balfour Beatty an earlier phased
handover of part of the site in late 2026, should this be required. 
4.5 The changes to the dates of the construction programme will require a
Change Control Request to be approved by Glasgow City Region following
August’s Council meeting. 
City Region Update 
4.6 A Glasgow City Region Cabinet Meeting was held on 11 June. Cabinet
agreed that the recommendation to UK Government be that the sectoral
focus of the Glasgow City Region Investment Zone is Advanced
Manufacturing and Precision Engineering. The Investment Zone will bring
£160m of investment into the City Region through a combination of capital
funding and tax relief over 10 years from 2025.This decision on sectoral
focus is favourable to West Dunbartonshire as the only Stage 2 bid that was
submitted from the Council area was an Advanced Manufacturing Maritime
development. Prior to the report to Cabinet, the Stage 2 bids had been
evaluated by the City Region Programme Management Office, the
Intelligence Hub and a Strategic Assessment Panel to determine the
preferred sectoral focus. The bids have also been ranked according to
compliance with the objectives of the Investment Zone. The ranking has not
yet been made public and is expected to be disclosed following agreement
with the UK Government. With a new UK Government in place, there have
been some inevitable prolonged timescales for decision-making, however we
are being advised by UK Government civil servants that the direction of
Investment Zone is not expected to change. 
4.7 As previously reported to the Council there is approximately £120m of
funding being made available across the Region due to the reprogramming of
City Deal, and specifically the transferring of responsibilities of the Glasgow
Airport Rail Link to Clyde Metro. Half of the funding is proposed to be spent
on helping meet inflation costs for existing City Deal projects, including the
Exxon Infrastructure Project. UK Government had previously requested that
the remaining £60m be spent on a new project that must demonstrate a

Page 3

significant impact across the City Region, and should be led by one Member
Authority. Four expressions of interest were submitted in May, including two
that the Council supported as a potential beneficiary. These were River Clyde
flood measures and the development of small-scale new commercial and
industrial premises across the Region.  The decision on the successful bid(s)
will require input from both Scottish and the new UK Government. In the
meantime a working group has been set up by the City Region Programme
Management Office to develop the proposal on commercial and industrial
premises. 
4.8 A commercial approach to Electric Vehicle Charging Infrastructure (EVCI)
has been agreed by all City Region Member Authorities and the intention is to
seek an external partner to deliver the required infrastructure. This was
agreed at IRED Committee in May 2024. The funding application for this year
has been agreed by all parties and submitted to Transport Scotland. 
Exploratory works associated with the EVCI project are currently ongoing.
Based upon the current estimate, it is projected that an agreement with a
Charge Point Operator would commence in May/June 2025. In the interim the
Glasgow Ciity Region collaboration intend to use EV Infrastructure Fund to
meet the costs of consultancy support. 
4.9 A senior officers’ working group for Clyde Metro has been established for
Glasgow City Region Member Authorities and the Council is represented on
that group. Early engagement has been undertaken with each local authority
to review the case for investment for Clyde Metro. A Case for Change and an
Initial Option Development programme is underway to develop a vision, the
objectives, and network options. 
4.10 The Clyde Bridge is nearing completion, and Renfrewshire Council has been
in touch to discuss joint publicity. 
4.11 The next Cabinet meeting is on 8 August, and a verbal update from Cabinet
can be given at Council. 
5 People Implications 
5.1 There are a number of senior officers involved in the Glasgow City
Region wider programme as identified at City Region Update paper at
Council on 26 August 2021. 
6. Financial Implications 
6.1  Spend this financial year to date on the Exxon project is £1,460,824 
Overall spend is £ 8,240,350. 
7. Risk Analysis 
7.1 There are a number of project risks associated with the development at
the Exxon project site and these are contained within the project risk
register and updated by the Project Board on a regular basis. The Project
Board is made up of senior officers from all key services.

Page 4

8. Equalities Impact Assessment 
8.1 Previously completed. 
9. Consultation 
9.1 Consultation with all key stakeholders is progressing as we continue
to work as part of the Glasgow City Region. 
10 Strategic Assessment 
10.1 At its meeting on 26 October 2022, the Council agreed that one of its
main strategic priorities for the Strategic Plan 2022 - 2027 is ‘A Strong
local economy and improved employment opportunities’ 
10.2 The proposals within this report are specifically designed to deliver on
this priority. 
Alan Douglas
Chief Officer: Regulation and Regeneration
Date: 13 March 2024 
Person to Contact: Gillian McNamara 
gillian.mcnamara@west-dunbarton.gov.uk 
Appendix: None   
Background Papers: UK Shared Prosperity Fund Report to Housing and
Communities Committee 22 August 2022                                          
Glasgow City Region City Deal- Council 13 August 2014.                                          
“City Deal Initiative” Clyde Valley Investment Fund-
Council 30 April 2014 (Memorandum of Understanding).                                          
Clyde Valley Community Planning Partnership – City Deal
Initiative – Council 28 August 2013.   
Wards Affected: All