WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Council – 26 August 2026
___________________________________________________________________ 
Subject:  Housing Revenue Account (HRA) Capital   
Budgetary Control Report to 30 June 26 (Period 3) 
1. Purpose 
1.1 This report provides an update on the HRA capital programme to 30 June
2026. 
2. Recommendations 
2.1 Members are asked to: 
i) note the current position of the 2026/27 HRA capital budgets and the 5-
year HRA capital plan. 
ii) note that project life performance will be monitored against a project life
estimate of £336.506m and a project life income estimate of £53.821m,
a borrowing requirement of £282.685m. 
iii) note that in year financial performance will be monitored against a
2026/27 capital expenditure budget of £58.434m and a 2026/27 capital
income budget of £13.064m, a one-year borrowing requirement of
£45.370m. 
iv) note that at this early stage all projects are on track regarding achieving
their planned completion dates and delivering within their project life
estimate. 
v) Note that there is an anticipated underspend of £2.340m against
2026/27 budgets reducing the forecast one-year borrowing requirement
to £43.030m.  
3. Background 
3.1 The Council approved the HRA Capital Plan for 2026/2027 to 2030/2031 on 4
March 2026. The approved plan estimated £63.285m of capital expenditure
and £16.901m of capital income in 2026/27, a one-year borrowing
requirement of £46.384m. The project life borrowing requirement was
£272.665m. 
3.2  Since March, budget adjustments have taken place to reflect up to date
information on progress delivering the plan, including the carry forward of over
/ underspends at the end of financial year 2025/26 and the incorporation of
the latest cost and income forecasts.  The adjustments result in revised capital
budgets as set out in Exhibit 1. The updated borrowing requirement for 26/27
of £45.370m is £2.340m less than advised in March 2026. The project life
ITEM 15

Page 2

Official
borrowing requirement increased to £282.398m because 2025/2026
underspends were brought forward into the revised capital plan. 
Exhibit 1: Revised HRA Capital Estimates 2026/2027 – 2030/2031 
2026/27
March 26 
(£m)
Project 
March 26 
(£m) 
2026/27
BCR03 
(£m)
Project 
BCR03 
(£m) 
2026/27
Change
(£m)
Project 
Change 
(£m
Other Capital   5.510 26.060  5.700 27.730 0.190 1.670
Component Replacement   14.600 73.000  14.600 80.083 0.000 7.083
Void Capital  5.400 27.000  5.400 26.514 0.000 -0.486
Structural & Environmental   3.400 18.600  4.521 21.890 1.121 3.290
Support Costs  3.400 17.000  3.400 17.000 0.000 0.000
More Homes    30.975 163.866  24.813 163.289 -6.162 -0.577
Total Expenditure  63.285 325.526  58.434 336.506 -4.851 10.980
Total Income   -16.901 -52.861  -13.064 -53.821 3.837 --0.960
Prudential Borrowing  46.384 272.665  45.370 282.685 -1.014 10.020 
4. Main Issues 
4.1 Progress against the 2026/27 capital plan is detailed in: 
Appendix 1 – HRA Capital Summary BCR03 
Appendix 2 – HRA Capital Detail BCR03 
4.2  The HRA capital summary report at Appendix 1 reports that: 
• There are fifteen capital projects where expenditure is tracked over the
multi-year life of the project and twenty-eight projects classified as rolling
programme projects / contingency / fees, that is programmes of work
where an annual estimate is set each year that takes account of demand,
cost, and affordability.
• At this early stage in the year, projected expenditure and projected income
are both in line with project life estimate. 
4.3  Appendix 2 shows all projects with their 2026/27 budget and their project life
estimate alongside the latest projections. The appendix reports: 
• 2026/27 projected spend of £55.894m, a £2.540m underspend against the
2026/27 expenditure budget.
• 2026/27 projected income of £13.151m, a £0.200m under-recovery
against the 2026/27 income budget.
• 2026/27 prudential borrowing forecast of £43.030m, £2.340m less than
budget. 
4.4 Commentary on the 2026/27 variances above £50,000 are set out in Exhibit 2
below.

Page 3

Official
Exhibit 2: Projected Over / Underspends 2026/27 as at BCR03 
Ref Project BCR03
Projection 
(£m) 
26/27
Budget
(£m) 
26/27
Variance
(£m)  Commentary
1 EESSH compliance
works
Expenditure
3.500 5.000 (1.500) Underspend reflects the
changing mix of the capital
programme with an increased
number of mixed tenure
blocks that require owner
consent before work can start.
This necessary process
delays project start. 
The underspend has been
reprofiled to a future year. 
2 Roofs
Expenditure
0.900 1.500 (0.600) Underspend reflects the
changing mix of the capital
programme with an increased
number of mixed tenure
blocks that require owner
consent before work can start.
This necessary process
delays project start. 
The underspend has been
reprofiled to a future year.  
3 Heating Works 
Expenditure 
1.600 2.400 (0.800) Underspend reflects a
reduced demand for
replacement heating systems. 
The underspend has been
reprofiled to a future year
pending a review of demand
across this programme. 
4 Void Capital 
Expenditure 
5.760 5.400 0.360 Overspend due to the high
number of void property
repairs being carried out by
the in-house team and
supporting contractors. 
The overspend has been
reprofiled to a future year 
5 Owner Recoveries
Income 
-0.300 -0.500 0.200 Under-recovery of income is
directly linked to the projected
underspend on the roofing
programme. 
The under-recovery has been
reprofiled to a future year 
4.5 Budget assumptions are required to forecast costs / income, especially where
projects span multi-year and project finances have yet to be finalised. It is
therefore likely that the projections will change during the year.

Page 4

Official 
5. Option Appraisal 
5.1 No option appraisal was required for this report. 
6. People Implications 
6.1 There are no people implications. 
7. Financial and Procurement Implications 
7.1 The report notes the projected in-year financial position for the HRA capital
plan. 
8. Risk Analysis 
8.1 The main risks are as follows: 
(a) The reported variances should be viewed in the knowledge that there
are several variable factors which could arise between now and 31
March which could affect the year end results for capital budgets. 
(b) To forecast for the full year costs budget assumptions have been
required. These assumptions continue to change regularly and therefore
it is likely the projected year end position will change from that reported. 
9. Equalities Impact Assessment (EIA) 
9.1 No equalities impact assessment was required in relation to this report. 
10. Environmental Sustainability 
10.1 No assessment of environmental sustainability was required in relation to this
report. 
11. Consultation 
11.1 All services involved in delivering the capital estimates have been consulted
during the compilation of this report. 
12. Strategic Assessment 
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council. 
________________
Laurence Slavin
Chief Officer – Resources
Date: 26 August 2026

Page 5

Official
Person to Contact: Jim McCarron 
Business Partner, Finance 07772 322055  
E-mail: james.mccarron@west-dunbarton.gov.uk 
Appendices: Appendix 1 -  HRA Capital Summary BCR03 
Appendix 2-  HRA Capital Details BCR03 