West Dunbartonshire Council Appendix 3
General Services Capital 2026/27
Changes to Capital Plan and Implications at P3
Project - RR 4 - Regeneration/Local Economic Development Initial End Date  Revised End Date Reprofiling Current Year  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  2034/35  2035/36  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
RR 4 Regeneration/Local Economic Development (unallocated) 15 0 0 0 475 475 475 475 475 475                       2,865
RR 4a Dumbarton Visitor Gateway/Arc of Attractions 100 100 50                          250 
Dumbarton Waterfront Walkway - consultancy & delivery 250 550                          800
Dumbarton High Street and Town Centre revitalisation 222 137 200                          559
RR 4b Alexandria - Alexander Street fees 101                          101 
Alexandria - Mitchell Way & Main Street improvements 800                          800 
Alexandria - Mitchell Way - gas pipe relocation 88                            88
RR 4e Balloch Pierhead Action Plan 311 83                          394                       
5,857
RR 4 Regeneration/Local Economic Development (unallocated) Revised 31/03/2027 31/03/2027 1,234 0 0 0 0 475 475 475 475 475 475                       2,850
RR 4a Dumbarton Visitor Gateway/Arc of Attractions Revised 20 100 80 50                          250 
Dumbarton Waterfront Walkway - consultancy & delivery Revised 10 240 550                          800
Dumbarton High Street and Town Centre revitalisation Revised 222 88 0                          310
RR 4b Alexandria - Alexander Street fees Revised 101 15                          116 
Alexandria - Mitchell Way & Main Street improvements Revised 800                          800 
Alexandria - Mitchell Way - gas pipe relocation Revised 88                            88
RR 4e Balloch Pierhead Action Plan Revised 50 344 249                          643                       
5,857
Explanation
Project - RR 6 - Place Based Investment Initial End Date  Revised End Date Reprofiling Current Year  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  2034/35  2035/36  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
RR 6 - Place Based Investment 675                          675 
Revised 31/03/2026 31/03/2028 210 465 210                          675
Explanation
Project - RR 14 - The Scottish Marine Technology Park Initial End Date  Revised End Date Reprofiling Current Year  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  2034/35  2035/36  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
RR 14 - The Scottish Marine Technology Park 4,299 0                       4,299 
Revised 31/03/2027 31/03/2028 1,500 2,799 1,500                       4,299
Explanation
Project - RR 15 - Clydebank Pride in Place Regeneration Plan Initial End Date  Revised End Date Reprofiling Current Year  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
RR15 - Clydebank Pride in Place Regeneration Plan 360                          360 
Revised 31/03/2026 31/03/2027 260 100 260                          360
Explanation
Project - EDUC 5 - Free School Meals Expansion Initial End Date  Revised End Date Reprofiling Current Year  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
EDUC 5 - Free School Meals Expansion 1,185                       1,185 
Revised 31/03/2027 31/03/2028 1,000 185 1,000                       1,185
Explanation
Delivery of projects re-profiled to allow sufficient time for project development and procurement with budgets updated to reflect updated cost estimates.Project development of the Alexandria Main Street/Mitchell Way improvements has taken longer than originally anticipated. Progress with the delivery of the walkway is slower than anticipated and
relies on cooperation with the landowners. Delivery of the Dumbarton Visitor Gateway/Arc of Attractions re-profiled to allow sufficient time for Council wide Tourism Strategy to be developed.Development of Balloch Pierhead project would be scheduled for 2027/28 and is subject to a future approval. This is a reallocation and re-profiling of the recurring
budget for Regeneration/Local Economic Development which is now being split out and monitored.
Place Based investment Programme funding (PBIP) is a non-competitive funding from the Scottish Government.Part of the funding is allocated to Alexandria Main Street/Mitchell Way project which is due to start on site in early 2027. Project development has taken longer than originally anticipated.
Regeneration Capital Grant Fund (RCGF) funding from the Scottish Government, for Malin to deliver remediation of the former Carless oil Terminal site.  This reprofiing alligns with the initial assumption made when the funding was awarded.
Financial Year 2026/27 is a project development year, and only  limited spend is expected on delivery. This is in line with the spend profile included in the Regeneration Plan and approved by the UK Government.  Reprofiling of the funding is acceptable under the funding terms & conditions and this alligns budget with the initial assumption made when
the funding was awarded.
This budget is proposed to be rephased to 2027/28. Planning permission has been secured and the project is progressing through detailed design, building warrant approvals and site investigations. Due to the complexity of delivering works within an operational school environment, including the need to minimise disruption to pupils and staff, the
construction programme and associated expenditure are now expected to fall predominantly within 2027/28. The rephasing aligns the budget with the revised delivery programme and anticipated expenditure profile.

Page 2

Official#
Project - HSCP 2 - ICT Modernisation HSCP Initial End Date  Revised End Date Reprofiling Current Year  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  2034/35  2035/36  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
HSCP 2 ICT Modernisation HSCP (unallocated) 72 0 0 0 0 90 87 80 90 90                          509
HSCP 2a Life Lens 13                            13
HSCP 2b Magic Notes 48                            48
HSCP 2c Staffing 45 46 48 49 50                          238
HSCP 2d ICT Device 5 5 5 5 5                            25
HSCP 2f Digital Inclusion (Prevention, Early Intervention, DCE) 10 10 10 10 10                            50
HSCP 2g Digital Telecare (AICO project, tec hub, new technology) 13 49 10                            72
HSCP 2h HSCP Systems/Applications (new applications, scripts, automation, data utilisation) 25 49 27 26 25                          152                       
1,107
HSCP 2 ICT Modernisation HSCP (unallocated) Revised 31/03/2027 31/03/2027 72 0 0 0 0 0 0 0 0 0 0                             -  
HSCP 2a Life Lens Revised 13                            13
HSCP 2b Magic Notes Revised 0                             -  
HSCP 2c Staffing Revised 45 46 48 49 50 52 53 55 56 58                          511
HSCP 2d ICT Device Revised 5 5 5 5 5 5 5 5 5 5                            50
HSCP 2f Digital Inclusion (Prevention, Early Intervention, DCE) Revised 10 10 10 10 10 10 10 10 10 10                          100
HSCP 2g Digital Telecare (AICO project, tec hub, new technology) Revised 13 15 15 15 14 14 14 5 14 14                          133
HSCP 2h HSCP Systems/Applications (new applications, scripts, automation, data utilisation) Revised 25 49 27 26 25 10 5 5 5 3                          180
HSCP 2i Granicus Blue Badge 13                            13
HSCP 2j Website Development 48 18 20 21                          107                       
1,107
Explanation
Project - HSCP 3 - Community Alarm upgrade Initial End Date  Revised End Date Reprofiling Current Year  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  2034/35  2035/36  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Community Alarm upgrade 55 4 0 0 42 42 0 0 0 0                          143 
Revised Community Alarm Upgrade 31/03/2031 31/03/2031 (4) 59 0 0 0 42 42 0 0 0 0                          143
Explanation
Project - P&T 1 - ICT Modernisation Initial End Date  Revised End Date Reprofiling Current Year  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  2034/35  2035/36  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
P&T 1 ICT Modernisation (unallocated) (153) 122 0 0 0 0 0 120 436 436                          961
P&T 1e Laptops for Corporate Employees 200 97 161 175 100 30 90 97                          950                       
1,911
P&T 1 ICT Modernisation (unallocated) Revised 31/03/2027 31/03/2027 (120) 0 122 0 0 0 0 0 0 436 436                          994
P&T 1e Laptops for Corporate Employees Revised 47 97 161 175 100 30 90 97                          797
P&T 1i Microsoft 365 Implementation Revised 120                          120                       
1,911
Explanation
Revised cost estimates for the Microsoft 365 programme reflect expanded scope to include CoPilot, increased Sharegate licensing requirements, and additional technical complexity and costs not fully anticipated in the original plan.
Additional budget is therefore required to ensure full delivery of the intended milestones. This is a reallocation and re-profiling of the recurring budget for ICT Modernisation which is now being split out and monitored.
Reprofiling is required due to ongoing work to roll out the digital strategy and a review of priorities. This is a reallocation and re-profiling of the recurring budget for ICT Modernisation HSCP which is now being split out and monitored.
Reprofiling is required to consolidate the 2026/27 budget with the small balancing budget from 2027/28.