WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Council – 17 June 2026 
___________________________________________________________________ 
Subject:       Housing Revenue Account
Capital Outturn for Financial Year 2025/2026 
1. Purpose 
1.1 The purpose of this report is to advise members of the Housing Revenue
Account (HRA) capital outturn position for 2025/2026. 
2. Recommendations 
2.1 Council is asked to: 
i) Note the outturn position against the 2025/26 HRA capital plan   
3. Background 
3.1 The Council approved the HRA Capital Plan for 2025/26 to 2029/30 on 5
March 2025. The HRA capital plan approved £70.590m of capital expenditure
and £15.324m of capital income in 2025/26, creating a borrowing requirement
of £55.266m. 
3.2  At its meeting on the 27 August 2025, the Housing and Communities
Committee agreed budget adjustments that revised the 2025/26 capital
expenditure budget to £55.547m and the capital income budget to £6.290m,
an updated one-year borrowing requirement of £49.257m. Committee also
approved a revised project life budget of £264.933m. A summary of the
outturn against the revised capital budgets is set out in Exhibit 1. 
Exhibit 1: HRA Capital Outturn 2025/26 
Actual 
(£m)
2025/26 
Budget
(£m)
Variance 
(£m) 
Project Life
Budget
(£m)
Other Capital   5.919 7.433 (1.514)  26.267
Component Replacement   13.592 20.881 (7.289)  93.567
Void  5.744 5.258 0.486  19.873
Structural & Environmental   1.693 3.762 (2.069)  17.320
Support Costs  2.918 3.100 (0.182)  17.155
More Homes   19.894 15.113 4.781  171.129
Total Expenditure  49.760 55.547 (5.787)  345.311
Total Income   (12.396) (6.290) (6.016)  (80.378)
Net Capital Expenditure   37.364 49.257 (11.893)  264.933 
ITEM 16

Page 2

4. Main Issues 
4.1 Progress against the 2025/26 HRA capital plan is detailed in Appendix 1. 
4.2 Commentary on the variances above £50,000 are set out in Exhibit 2 below. 
Exhibit 2: Project Over / Underspends 2025/2026 
Ref Project
Actual 
(£m) 
25/26
Budget
(£m) 
25/26
Variance
(£m)  Commentary
1 Capitalised Minor Works 3.273 3.715 (0.442) Underspend due to reduced
contractor spend.
2 Better Homes Priority
Projects 
0.033 0.275 (0.242) Underspend based on timing
of programme. 
3 Environmental Sensors 1.191 2.000 (0.809) Underspend due to challenges
getting access to properties. 
4 Targeted SHQS
/EESSH compliance
works
3.712 6.628 (2.916) Underspend reflects the
changing mix of the capital
programme with an increased
number of mixed tenure
blocks that require owner
consent before work can start.
This necessary process
delays project start. 
5 External Component
Renewal - Roofs
1.187 2.550 (1.363) Underspend reflects the
changing mix of the capital
programme with an increased
number of mixed tenure
blocks that require owner
consent before work can start.
This necessary process
delays project start.  
6 Doors/Window
Component Renewals
4.215 4.985 (0.770) Underspend is due to
challenges getting access to
property. Install team to
continue programmed
addresses and revisit no
accesses to use materials
already supplied. 
7 External Stores /
Garages / Bin Stores
0.000 0.048 (0.048) Works funded from the
capitalised minor works
budget. 
8 Secure entry component
renewals
0.000 0.100 (0.100) Works funded from the
capitalised minor works
budget. 
9 Statutory / Compliance
Works
0.095 0.594 (0.499) Health and safety works
funded from the capitalised
minor works budget.

Page 3

Ref Project
Actual 
(£m) 
25/26
Budget
(£m) 
25/26
Variance
(£m)  Commentary
10 Heating Improvement
Works 
1.646 2.268 (0.622) Overspend due to reduced
demand for replacement
heating systems 
11 Energy Improvements /
Efficiency Works
0.000 0.058 (0.058) Works funded from the
capitalised minor works
budget. 
12 Kitchen Upgrade 2.022 2.850 (0.828) Underspend as team re-
assess and pre-inspect to
ensure a focus on necessary
renewals led by condition.  
13 Bathroom & Shower
Replacement
0.715 0.800 (0.085) Underspend as team re-
assess and pre-inspect to
ensure a focus on necessary
renewals led by condition. 
14 Void House
Programme
5.744 5.258 0.486 Overspend due to mix of work
requiring contactors in addition
to in-house team. 
15 Defective structures
/component renewals
0.170 0.800 (0.630) Underspend as future blocks
are pre-inspected for condition
and re-prioritisation for
completion if necessary. 
16 Environmental Renewal
- Paths & Environment
1.078 1.000 0.078 Overspend due to mix of work
requiring contactors in addition
to in-house team. 
17 Multi Storey Flat
Strategy
0.158 1.720 (1.562) Underspend based on timing
of programme. 
18 Buy Backs 3.528 4.380 (0.852) Underspend due to lower
purchase price of acquired
properties 
19 Demolition Programme 0.232 0.140 0.092 Overspend based on timing of
programme. 
20 Clydebank East 0.601 0.250 0.351 Overspend due to retentions
being accrued into current
financial year.  
21 Pappert 1.012 0.730 0.282 Overspend due to retentions
being accrued into current
financial year. 
22 Mount Pleasant 0.464 0.382 0.082 Overspend due to retentions
being accrued into current
financial year. 
23 Gilmour Avenue  0.326 0.264 0.062 Overspend due to contractor
liquidation and the need to
procure a replacement
contractor.

Page 4

Ref Project
Actual 
(£m) 
25/26
Budget
(£m) 
25/26
Variance
(£m)  Commentary
24 Willox Park Phase1 3.465 2.980 0.485 Overspend due to retentions
being accrued into current
financial year. 
25 Bank Street 1.657 1.500 0.157 Overspend based on timing of
programme.  
26 Bonhill Gap Sites 5.112 1.600 3.512 Overspend based on timing of
programme. 
27 West Thomson Street  0.462 0.375 0.087 Overspend based on timing of
programme. 
28 Silverton 0.007 0.100 (0.093) Underspend based on timing
of programme. 
29 Queen Mary Avenue 2.429 0.800 1.629 Overspend based on timing of
programme. 
30 Dennystoun Forge  0.000 0.400 (0.400) Underspend based on timing
of programme. 
31 Ottawa Crescent  0.413 0.250 0.163 Overspend based on timing of
programme. 
32 Future New Build &
Related Regeneration
Projects 
0.000 0.550 (0.550) Underspend based on timing
of programme. 
33 Fees, Contingency  0.017 0.150 (0.133) Underspend based on timing
of programme. 
34 Scottish Govt Buyback
Grant Income 
(1.326) (0.550) (0.776) Over-recovery based on the
distribution of Scottish
Government acquisition
funding. 
35 7 – 9 Gilmour Avenue
Grant Income  
0.000 (0.120 (0.120)  Under-recovery due to
ongoing negotiations with
Scottish Government over
additional funding  
36 Willox Park Phase 2 
Grant Income 
(0.127) 0.000 (0.127) Over-recovery based on the 
on timing of programme. 
37 Bank Street
Grant Income 
(1.049) (1.500) 0.451 Under-recovery based on the 
on timing of programme. 
38 Bonhill Gap Sites 
Grant Income 
(3.360) (1.600) (1.760) Over-recovery based on the 
on timing of programme. 
39 West Thomson Street
Grant Income 
(0.518) (0.375) (0.143) Over-recovery based on the 
on timing of programme. 
40 Queen Mary Avenue  (1.649) 0.000 (1.649) Over-recovery based on the 
on timing of programme.

Page 5

Ref Project
Actual 
(£m) 
25/26
Budget
(£m) 
25/26
Variance
(£m)  Commentary
41 Ottawa Crescent
Grant Income 
(0.379) 0.000 (0.379) Over-recovery based on the 
on timing of programme. 
42 Future new build sites &
regeneration projects
Grant Income 
0.000 (0.060) 0.060 Funding released to support
accelerated projects 
43 Owner Recoveries  (1.613) (1.500) (0.113) Over-recovery based on
higher than anticipated
invoicing of owners
participating in capital
projects.   
44 Other Grant Income  (2.196) (0.406) (1.790) Additional funding secured to
support capital investment
including more than £1m for
cladding remediation works
and circa £800,000 to support
the acquisition and
refurbishment of properties
allocated to the resettlement
service. 
5. Option Appraisal 
5.1 No option appraisal was required for this report. 
6. People Implications 
6.1 There are no people implications. 
7. Financial and Procurement Implications 
7.1 The report notes the outturn position for the HRA capital plan. 
8. Risk Analysis 
8.1      This is an outturn report therefore there are no risk implications. 
9. Equalities Impact Assessment (EIA) 
9.1 No equalities impact assessment was required in relation to this report. 
10. Environmental Sustainability 
10.1 No assessment of environmental sustainability was required in relation to this
report.

Page 6

11. Consultation 
11.1 All services involved in delivering the capital estimates have been consulted
during the compilation of this report. 
12. Strategic Assessment 
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council. 
________________
Laurence Slavin
Chief Officer – Resources
Date: 17 June 2026 
Person to Contact: Jim McCarron 
Business Partner, Finance 07772 322055  
E-mail: james.mccarron@west-dunbarton.gov.uk 
Appendices: Appendix 1 -  HRA Capital Detail Final Outturn   
Background Papers: 
Housing Revenue Account (HRA) Capital Investment Programme, Revenue
Budget, and Rent Levels for 2025/26 - Council 5 March 2025. 
Wards Affected           All Wards