Page 1
West Dunbartonshire Council Appendix 3 General Services Capital 2025/26 Reprofiling at Period 12 Service Project Approved Budget 2025/26 Actual to date 2025/26 Reprofiling Initial Completion Date Revised Completion Date Comment £'000 £'000 £'000 Resources RES 1 Valuation Joint Board - Requisition of ICT Equipment 4 4 (0) 31/03/2028 31/03/2028 Remaining budget to be carried forward to 26/27. Resources RES 2 Agresso Development 6 2 (4) 31/03/2026 31/03/2027 Ongoing support required for Agresso while replacement system in development. Resources RES 4 Community Success Capital Fund 21 0 (21) 31/03/2026 31/03/2027 No requests for funding have been received under the Community Success Capital Fund during the reporting period. Resources RES 5 Community Sports Success 9 9 35 31/03/2026 31/03/2027 Community Sports Success received a higher level of demand than anticipated during the 2025/26 financial year, with funding requests exceeding initial expectations. The Council will continue to work with community groups throughout 2026/27 to support ongoing delivery and manage future funding opportunities. Resources RES 7 New Sports Changing Facility Dumbarton West (Old OLSP site) 0 9 9 31/03/2026 31/03/2027 The New Sports Changing Facility at Dumbarton West (Old OLSP site) remains part of the Council’s investment in community sports infrastructure. Delivery is anticipated in 2026/27, with ongoing discussions to coordinate development alongside adjacent landowners. Resources RES 8 Building Upgrades and H&S - lifecycle & reactive building upgrades 2,536 3,061 525 31/03/2026 31/03/2027 Has reported an overspend in the period, primarily as a result of an accelerated programme of works across a number of operational properties. This approach has been taken to address priority compliance and condition issues at an earlier stage, reducing ongoing risk and future reactive pressures. The programme continues to be managed responsibly within the overall capital framework, with works prioritised in line with operational need and statutory requirements. Resources RES 10 Depot Rationalisation 500 273 (227) 31/03/2027 31/03/2027 Depot Rationalisation is progressing in line with an established programme of works, with completion anticipated in the 2026/27 financial year. The programme will deliver fit-for-purpose facilities that are compliant with current health and safety standards and support improved operational efficiency. Resources RES 11 Finance Ledger System 212 222 10 31/03/2027 31/03/2027 Additional cost of staff recharges due to pay award 25-26 Resources RES 12 Community Sports Facility at Millburn 20 16 (4) 31/03/2028 31/03/2028 The Community Sports Facility at Millburn is a community-led project being progressed by the Vale of Leven Community Sport Hub, with the Council’s contribution provided as match funding to support external funding bids. The Council will continue to assist the group as required, including supporting feasibility and development work as the project moves towards delivery. Resources RES 13 Holm Park Community Football Academy Accesibility Project 75 56 (19) 31/03/2026 31/03/2027 Holm Park Community Football Academy Accessibility Project is not expected to fully draw down the allocated budget within the current financial year. Final expenditure is subject to receipt of the outstanding invoice from the community group, which is anticipated in Quarter 2 of 2026/27. Resources RES 15 Design, Creation, Installation of Digital Content for Glencairn House 187 0 (187) 31/03/2026 31/03/2027 Design, Creation, Installation of Digital Content for Glencairn House is progressing in line with the approved programme, with completion anticipated in 2026/27. Full utilisation of the allocated budget is currently expected in line with project delivery. Regulatory and Regeneration RR 4 Regeneration/Local Economic Development 258 242 (15) 31/03/2026 31/03/2027 This budget includes a number of different budget lines/projects at different stages of development. 25/26 spend was lower than originally profied due to projects progressing slower than anticipated. Regulatory and Regeneration RR 5 Regeneration Fund 50 40 (10) 31/03/2028 31/03/2029 This budget includes a number of different budget lines/projects at different stages of development. 25/26 spend was a contribution to a construction of Dumbarton waterfront walkway which was lower than originally estimated. Regulatory and Regeneration RR 6 Place Based Investment 150 100 (50) 31/03/2026 31/03/2028 This is externally funded multi-year programme of works. 25/26 spend was lower than originally profied. Regulatory and Regeneration RR 7 Level Up Funding 4,379 4,860 481 31/03/2026 31/03/2028 This is externally funded multi-year programme of works. 25/26 spend was higher than originally profied. Regulatory and Regeneration RR 9 District Heating Network Expansion 201 (30) (231) 31/03/2028 31/03/2028 Underspend due to delay in programme of planned district heat network connections. Underspend to be carried forward to 26/27. Regulatory and Regeneration RR 10 Clyde Mission Catalyst Fund 625 766 141 31/03/2026 31/03/2028 External funding managed by the Council on behalf of the grantee. The final spend was higher than originally anticipated, however the overall budget amont remain the same. Regulatory and Regeneration RR 13 Pride in Place Impact Fund 0 0 0 31/03/2026 31/03/2028 External funding which wac received late in 2025/26 therefore no spend was achieved. To be carried forward, with spend anticipated in 26/27 & 27/28 Roads and Neighbourhood RN 1 Infrastructure - Roads 2,658 2,571 (87) 31/03/2026 31/03/2027 1 project slipped to 26/27 programme due to conflicting roadworks Roads and Neighbourhood RN 3 Street lighting and associated electrical infrastructure 100 102 2 31/03/2026 31/03/2027 Not sufficient to undertake a further replacement in 25/26 but will contribute to further replacements in 26/27 Roads and Neighbourhood RN 4 Flood Prevention 193 131 (62) 31/03/2026 31/03/2027 Feasibility and consultation undertaken which delayed design commencing Roads and Neighbourhood RN 5 Vehicle Replacement 5,358 4,036 (1,322) 31/03/2026 31/03/2027 Underspend due to lead times for delivery of vehicles, budget to be carried forward to 26/27. Roads and Neighbourhood RN 9 A813 Road Improvement Phase 1 201 8 (193) 31/03/2026 31/03/2027 Phase 1 footway improvements complete however funding required to complete remedial works and design to extend cycle lane. Roads and Neighbourhood RN 10 Traffic Signal Updates 14 0 (14) 31/03/2026 31/03/2027 Project wlil be delivered 26/27and this funding will part fund project that has external funding Roads and Neighbourhood RN 11 Gruggies Burn Flood Prevention 882 0 (882) 31/03/2028 31/03/2028 Further design underway following value enginnering, this budget will be utilised in 26/27 Roads and Neighbourhood RN 12 River Leven Flood Prevention Scheme 200 0 (200) 31/03/2026 31/03/2027 Detailed design will be completed 26/27 and presented for consideration as a capital bid Roads and Neighbourhood RN 13 Public non-adopted paths and roads 541 262 (278) 31/03/2026 31/03/2027 Design work and costings to be agreed with Roads for projects Roads and Neighbourhood RN 14 Cemetery Extension, North Dalnotter 250 188 (62) 31/03/2026 31/07/2026 Final drainage and landscaping work still to be completed Roads and Neighbourhood RN 16 Allotment Development 122 157 34 31/03/2026 30/06/2026 To be funded from Shared Prosperety Fund Roads and Neighbourhood RN 18 Play Area Upgrade Programme 376 444 67 31/03/2030 31/03/2030 Additional safety surfacing was required. Roads and Neighbourhood RN 20 Balloch Mountain Bike Track 15 4 (11) 31/03/2026 31/03/2027 Due to planning issues with National Park there is a requirement to re-design the track at another location within Balloch Park. This has led to delays in developing a tender package Roads and Neighbourhood RN 23 Creation of 3 new all weather pitches at Argyll Park, Lachie Stewart Memorial Park and Mountblow playing fields 50 2 (48) 31/03/2026 31/03/2027 Planning and contractural issues have resulted in delays to commencement of works Roads and Neighbourhood RN 24 Exxon City Deal 20,585 14,369 (6,216) 31/03/2028 31/03/2028 Project underway, spend not in line with projection due to delays to works on site and defect completion on Network Rail works Roads and Neighbourhood RN 25 Active Travel 942 427 (514) 31/03/2028 31/03/2028 Project externally funded and agreement made to deliver in 26/27 Roads and Neighbourhood RN 29 Roads Lining and Signing 150 83 (67) 31/03/2027 31/03/2027 Works ongoing to complete DPE lining as delay caused by weather Roads and Neighbourhood RN 30 Plant and Machinery Replacement 516 78 (438) 31/03/2026 31/03/2027 Longer lead time for delivery of machines than was expected Roads and Neighbourhood RN 32 People and Places - Transport Scotland 35 26 (9) 31/03/2026 31/03/2026 Works completed under budget. Can not be carried forward Roads and Neighbourhood RN 34 Nature Restoration Fund 185 81 (104) 31/03/2026 31/08/2026 Some seasonally dependant works still to be carried out. Education EDUC 1 AV Equipment - Education 96 113 17 31/03/2030 31/03/2030 Change in approach to replacement of items in 2025/26 due to staff shortage. Will be addressed in 2026/27 Education EDUC 3 Schools Estate Improvement Plan - next Phase - Faifley Campus 8,994 9,060 66 31/03/2027 31/03/2027 Overspend to be accelerated from FY26/27 - Demolition of Edinbarnet, Auchnacraig and EC still to be carried out Education EDUC 4 Schools Estate Improvement Plan 1,181 825 (356) 31/03/2026 31/03/2027 Programme of works to be confirmed
Page 2
Education EDUC 5 Free School Meals Expansion 51 57 6 31/03/2026 31/03/2028 Free School Meals Expansion relates to works required to support the delivery of statutory obligations, including necessary kitchen, dining and associated facility upgrades. Budget has been accelerated from 2026/27 to accommodate preparatory works, ensuring the programme is in place to meet implementation requirements. HSCP HSCP 1 Special Needs - Aids & Adaptations for HSCP clients 935 917 (18) 31/03/2026 31/03/2027 There is a slight underspend in this project for 2025/26 due to the nature of budget and fluidity of spend. This is a recurring budget and underspend requires to be carried forward due to likely demographic growth in client demand. HSCP HSCP 2 ICT Modernisation HSCP 114 42 (72) 31/03/2026 31/03/2027 Discussion around the website upgrade, which was planned for 2025/26, took longer than planned but the service are hoping to move forward early in the 2026/27 financial year. HSCP HSCP 3 Community Alarm upgrade 272 292 20 31/03/2026 31/03/2027 Overspend due to additional staff time of community alarm staff involved in the installation of alarms. People & Technology P&T 1 ICT Modernisation 578 731 153 31/03/2026 31/03/2027 Overspend ocurred due to timing of supplier invoices which resulted in two large device orders being paid from 25/26 budget instead of 26/27 as planned. Devices were ordered early to avoid device prices increase of over 20%. People & Technology P&T 2 ICT Security & DR 737 678 (59) 31/03/2026 31/03/2027 Underspend due to security hardware projects carrying forward into next budget year. People & Technology P&T 3 365 Implementation 226 202 (23) 31/03/2026 31/03/2027 Delays throughout the project year has resulted in phased work being carried forward into the 26/27 budget period. The remaining budget will be used as originally forecast. People & Technology P&T 4 Development of Workforce Management System 2 2 (0) 31/03/2027 31/03/2027 This is a 5 year rolling programme, project date extended to reflect this. People & Technology P&T 5 Data Strategy 27 0 (27) 31/03/2026 31/07/2026 Delayed start to discovery work to enable full engagement, project commencing in Q3 25/26 would have resulted in limited availability for services to participate resulting in a detrimental impact on the end strategy. (10,264)