Item 14 - General Services Capital Budgetary Control Report 2025-26 to 31 March 2026 (Draft Outturn)

West Dunbartonshire Council · 17 June 2026
Back to West Dunbartonshire Council — 17 June 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Council: 17 June 2026
_________________________________________________________________ 
Subject: General Services Capital Budgetary Control Report 2025/26 to
31 March 2026 (Draft Outturn). 
1. Purpose 
1.1 This report provides the draft outturn on the General Services capital financial
performance to 31 March 2026. 
2. Recommendations 
2.1 Members are asked to: 
a) Note the draft outturn of the 2025/26 General Services capital budget. 
b) Note the recurring budget underspend and 8 completed projects detailed
in Appendix 2. 
c) Note the reprofiling of the budgets of 50 projects in Appendix 3 of
(£10.264m) over the project life. 
3. Background 
3.1 On 5 March 2025 the Council approved the updated General Services Capital
Plan for 2025/2026 to 2034/35. The three years from 2025/26 to 2027/28
were approved in detail with the remaining years being indicative. The budget
agreed was £73.780m for 2025/26 and £307.818m for the project life budget. 
4. Main Issues 
4.1 Exhibit 1 sets out the revised capital budget at period 10 as reported to
Council on 25 March 2026. 
Exhibit 1: Revised Capital Budget as at 31 January 2026. 
2025/26
(£m)
Project Life
(£m)
Capital Budget Agreed 5 March 2025 73.780 307.818
Updates reported to Council on 27 August, 29
October, 17 December and 25 March plus
adjustments for year-end carried forward balances
8.045 28.708
Reprofiling reported to Council on 27 August, 29
October and 17 December
(22.607) 0
Revised Capital Budget as at Period 10 59.218 336.526 
4.2  Progress against the 2025/26 capital plan is detailed in:
ITEM 14

Page 2

Appendix 1 – Project Life Summary by Chief Officer 
Appendix 2 – Completed Projects at Period 12 
Appendix 3 – Reprofiling for Noting 
Appendix 4 – All Approved Projects 
4.3 The overall programme summary report at Appendix 1 shows a reduction
in project life budget of £4.158m. This is due to completed projects being
removed from the capital plan. Note Appendix 1 is constructed assuming
all changes in this report are approved. 
4.4 Appendix 2 highlights 8 projects completed at period 12 and 1 underspend
on a recurring budget. 
4.5  Appendix 3 highlights 50 projects where the expenditure requires to be
reprofiled across the project life but there is no need for additional budget.
This reprofiling will be reflected in the P3 budgetary control report going to
council in August. 
4.6  Exhibit 2 sets out the revised capital budget at period 12 assuming approval
by Council of all recommendations contained within this report. 
Exhibit 2: Revised Capital Budget 
2025/26
(£m)
Project Life
(£m)
Capital Budget as at 31 January 2026 59.218 336.526
Saving (RN 14) – RN 5 Vehicle Replacement
(Para 4.8)
0 0.300
Increased budget – RN 11 Gruggies Burn Flood
Prevention (Para 4.8)
0 3.460
New Funding – RN 39 Milton Park MUGA (Para
4.8)
0.109 0.109
Additional budget – RN 5 Vehicle Replacement
(Para 4.8)
0.255 0.255
Proposed revised Capital Budget as at Period
12
59.582 340.650
Recurring budget underspend (Appendix 2) (0.053) (0.053)
Projects completed at P12 (Appendix 2) (1.382) (5.855)
Overspends in year (Para 4.9) 1.750 1.750
Reprofiling over project life (Appendix 3) (10.264) 0
Proposed revised Capital Budget as at Period
12 subject to Council Approval
49.633 336.492 
4.7 Appendix 4 shows all projects with approved in year and project life budgets
as well as anticipated expenditure. It highlights that the 2025/26 budget is
£59.582m, final spend at 31 March was £50.061m resulting in an in year
variance of (£9.483m). 
4.8  Other minor changes to the capital plan included in the summarised plan in
appendix 4 are:

Page 3

• Saving RN 14 approved at council on 4 March 2026 for an additional
£0.300m for replacement of hire vehicles added to the Vehicle
Replacement budget (RN 5). 
• Increased budget of £3.460m for Gruggies Burn Flood Prevention (RN 11)
agreed at council on 25 March 2026. 
• New funding for Milton Park MUGA (RN 39) of £0.109m in 2025/26. 
• Additional budget of £0.255m in Vehicle Replacement (RN 5) for the
purchase of Education mini buses funded by revenue agreed at council on
18 June 2025. 
4.9  The final position resulted in an overspend in RES 9 Direct Project Support of
£1.750m. These are internal project support costs from services for the
execution and implementation of the capital plan throughout the year. Finance
have committed to conducting a review of direct project support costs during
26/27 and this will be reported back to council through the normal capital
budgetary control report process. 
5. Option Appraisal 
5.1 No option appraisal was required for this report. 
6. People Implications 
6.1 There are no people implications. 
7. Financial and Procurement Implications 
7.1 The report notes the projected financial position for capital budgets. 
8. Risk Analysis 
8.1  The main risks are as follows: 
(a) As a consequence of current market conditions, inflation is high and interest
rates continue to be volatile. To forecast for the full capital plan costs budget
assumptions have been required. These assumptions continue to change
regularly and therefore it is likely the projected capital plan budgetary position
will change from that reported. 
9. Equalities Impact Assessment (EIA) 
9.1 No equalities impact assessment was required in relation to this report. 
10. Environmental Sustainability 
10.1 No assessment of environmental sustainability was required in relation to this
report.

Page 4

11. Consultation 
11.1 All services involved in delivering the capital budgets have been consulted in
the compilation of this report. 
12. Strategic Assessment 
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council. 
______________
Laurence Slavin
Chief Officer – Resources
Date: 1 June 2026 
Person to Contact:  Lynsey Dickson, Finance Business Partner  
Council Offices, Church Street, Dumbarton   
E-mail: lynsey.dickson@west-dunbarton.gov.uk 
Appendices:  Appendix 1 – Project Life Summary by Chief Officer
Appendix 2 – Completed Projects at Period 12 
Appendix 3 – Reprofiling for Noting
Appendix 4 – All Approved Projects 
Background Papers:    General Services Capital Plan Update - Council 6 March
2024
General Services Capital Plan Update - Council 5 March
2025
Capital Budgetary Control Report (P3) – Council 27
August 2025
Review of Hybrid Meetings of Council and Committees –
Council 27 August 2025
Capital Budgetary Control Report (P5) – Council 29
October 2025
Capital Budgetary Control Report (P7) – Council 17
December 2025
Review of West Dunbartonshire Councils Capital
Programme – Council 17 December 2025
Gruggies Burn Flood Alleviation Scheme – Council 17
December 2025
Financial Update – Council 17 December 2025
General Services Budget Setting – 4 March 2026
Capital Budgetary Control Report (P10) – Council 25
March 2026 
Wards Affected:  All Wards