WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2025/26
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Actual Spend Use of EMR
Variance after
the use of
EMR
£000 £000 £000 £000 %
Audit 291 195 0 (96) 0% 
Service Description
Main Issues / Reason for Variance
Revenues & Benefits 2,424 3,019 427 167 7% 
Service Description
Main Issues / Reason for Variance
Cost of Collection of Council Tax (1,072) (905) 0 167 0% 
Service Description
Main Issues / Reason for Variance
Corporate Assets (2,050) (980) 204 866 -42% 
Service Description
Main Issues / Reason for Variance
Democratic and Registration Service 1,609 1,556 0 (53) 0% 
Service Description
Main Issues / Reason for Variance
Environmental Health 575 458 0 (117) 0% 
Service Description
Main Issues / Reason for Variance
This service provides asset and estate management
£250k adverse variance due to asset rationalisation, with property disposals that were previously
rental‑income‑generating now contributing capital receipts to the wider budget position.
The variance also now reflects £262k of Storm Eowyn damage, which cannot be absorbed within the
remaining repairs and maintenance budget due to the scale of the works.
An ongoing cost pressure of £50k has been introduced for future years due to higher property
valuation costs. Employee turnover savings are mitigating the rise in Property costs linked to last
year’s increases. The remaining overspend (£304K) relates to an under recovery of rental income. A
full review of rentals will be carried out 26/27.
The main reason for the variance is due to current levels of vacancies (£77k) and additional income
generated for environmental health services provided (£38k). The remaining variance (£2k) is due to
small variance across the service.
The service provided by this area deal with benefits, council tax and debt recovery.
The primary contributing factor is £146k relating to the Scottish Welfare Fund (SWF), which is offset
by RSG income. The majority of the variance arises from deferred income recognised within service,
as the associated commitments will not be fulfilled until FY27.
This service collects Council tax from local residents. The services also provides support and advice
to those residents regarding council tax.
The £332k FY26 bad debt provision for Council Tax has been reallocated to the service, with the
overall impact partially mitigated by the increase in statutory additions.
31 March 2026
Budget Details
Resources
Internal audit of council services.
Favourable variance arising from underspend in staffing costs due to vacant posts.
Variance Analysis
RAG Status
Regulatory and Regeneration
This services deals with the administration functions and Democratic Services within the Authority.
The main reasons for the variance is the current level of vacancies within the service (£45k). The
remaining variance (£8k) is due to various small variances across the service area.
The 3 Groups within this service (Food and Business Group, Environmental Pollution Group and
Community Health Protection Group) are responsible for all aspects of Environmental Health work.

Page 2

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2025/26
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Actual Spend Use of EMR
Variance after
the use of
EMR
£000 £000 £000 £000 %
31 March 2026
Budget Details
Variance Analysis
RAG Status
Licensing (221) (275) 0 (54) 0% 
Service Description
Main Issues / Reason for Variance
Planning 557 505 218 (270) 39% 
Service Description
Main Issues / Reason for Variance
This Service provides Building & Planning services.
The variance is mainly  due to additional income of (£144k) generated from planning applications,
and building warrants, lower employee costs than anticipated due to delays and difficulties filling
vacancies within the service (£44k). Payments to Other Bodies were (£88k) lower due to  payments
to Glasgow City Region external partners being less that expected. The remaining £6k is due to small
variances within the service.
This service provides all licensing on behalf of the Council.
The variance is mainly due to receipt of adianta income (£54k), mainly for taxi licences.

Page 3

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2025/26
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Actual Spend Use of EMR
Variance after
the use of
EMR
£000 £000 £000 £000 %
31 March 2026
Budget Details
Variance Analysis
RAG Status
Strategic People and Change 1,863 1,806 2 (58) 0% 
Service Description
Main Issues / Reason for Variance
Information Services 5,093 4,908 0 (185) 0% 
Service Description
Main Issues / Reason for Variance
Central Administration Support 2,602 2,502 0 (100) 0% 
Service Description
Main Issues / Reason for Variance
Libraries 1,833 1,757 0 (76) 0% 
Service Description
Main Issues / Reason for Variance
Arts and Heritage 306 192 0 (114) -37% 
Service Description
Main Issues / Reason for Variance
Catering Services 5,077 5,557 11 468 9% 
Service Description
Main Issues / Reason for Variance
Facilities Assistants 2,665 2,474 0 (191) -7% 
Service Description
Main Issues / Reason for Variance
This service provides the provision & protection of Arts & Heritage
There is a favourable variance against employee costs as a result of vacancies.
There is a small favourable variance against employee costs (£33k) and electricity/gas (£24k) with
the balance from additional income.
This service provides Facility Assistants throughout WDC buildings.
There is a favourable variance against employee costs as a result of vacancies.
This service area provides general ICT support to the Council and also supports transformational
change and modernisation of working practices through technology.
The favourable position reflects several factors: £57k of reduced expenditure on printer lease costs
following the transition to a new supplier; £26k lower printing and copy costs across WDC; £27k
favourable variance on ISDN transition costs; £54k favourable variance on computer software costs
driven by the M365 licence renewal; and £21k of increased budgeted recharges for computer
software to other services.
Citizens, Culture and Facilities
Catering Services across WDC
Although there is a small favourable variance against employee costs (£30k) as a result of vacancies
this has been offset by adverse variances against kitchen equipment repairs/purchases (£118k) and,
particularly, against income. The income budget was overstated and includes £350k which was also
shown within General Revenue Grant income. This was highlighted as a 2026/27 budget pressure in
the June 2025 Finance Update to Council.
Employee turnover was ahead of budget together with an uplift in recharges
This service includes the provision of Library, Culture and Museums within West Dunbartonshire
People & Technology
This service area provides strategic and operational HR advice, H&S advice and guidance (including
fire safety) and strateigc and operational risk management.
The variance was primarily driven by reduced Occupational Health expenditure of £39k, with £29k
relating to the 2025/26 burden being overstated due to the inclusion of VAT. In addition, £8k of
training costs have been carried forward to FY27 with the remaining balance across variance lines -
employee costs, events, supplies and lower Paye settlement agreement (PSA).
This services deals with administration functions within the Authority.

Page 4

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2025/26
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Actual Spend Use of EMR
Variance after
the use of
EMR
£000 £000 £000 £000 %
31 March 2026
Budget Details
Variance Analysis
RAG Status
Primary Schools 35,041 35,101 0 60 0% 
Service Description
Main Issues / Reason for Variance
Secondary Schools 35,876 35,913 124 (87) 0% 
Service Description
Main Issues / Reason for Variance
Specialist Educational Provision 23,471 23,724 35 218 1% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
The reason for the adverse variance is an overspend on employee costs - mainly APT&C following
the recent job evaluation of grade 3 and 4 staff (£320k inc. backdating to August 2024 plus £12k for
non-achievement of turnover ) - and an overspend on transport (£567k). Payments for teachers to
cover absences (£21k) were also greater than budgeted.  Whilst the purchase of 6 additional buses
has reduced the number of taxi contracts the payback period for the one-off cost of £255k , charged
directly to the taxi budget within the service , was always projected to be more than one year.The use
of taxis will remain essential for some children given their individual needs (£136k). As a result of the
additional buses and a reduction in other internal users the recharge from Transport Services is
anticipated to be higher (£169k).These overspends are partly offset by a projected underspend on
out of authority placements (£575k) and increase staff recharges to grants and other service areas
(£129k).
Steps have been taken to reduce taxi expenditure further, with discussions ongoing with external
providers about transport of children attending those facilities. We have however taken on additional
runs required for both Riverside School and St. Mary's Duntocher, which have increased our costs. 
Discussions are ongoing with Transport Services about internal recharges, due to the reduction in
other services making use of Internal Transport
adverse variance
This service area includes all Primary Schools.
Recharges for upkeep of grounds and refuse collection were greater than budgeted resulting in an
overspend (£76k) and teacher costs were £711k overbudget as a result of payments to cover teacher
absences .In addition, supplies & services, mainly classroom materials, were over budget
(£65k).These overspends are offset by a number of underspends - gas/electricity (£273k), clothing
grants (£55k), non-teacher vacancies (£117k). Finally, there was additional income from recharges to
Early Years for shared campus property costs (£187k) and additional grant and commercial income
from early start clubs (£155k)
This service area includes all Secondary Schools.
Teacher cover costs, mainly cover, are greater than anticipated (£324k) and recharges for upkeep of
grounds were greater than budgeted resulting in an overspend (£30k). There are however a number
of underspends - gas/electricity/NDR (£79k) , lower EMA payments (£35k) , clothing grants (£45k)
and exam fees (£16k) ,and lower transport costs (especially on both SPT bus contracts and reduced
taxi usage, £132k).In addition there was greater school meal income (£123k) and favourable
variances on some miscellaneous income budgets (£10k).
This service area covers all ASN Services.
Education , Learning and Attainment

Page 5

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2025/26
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Actual Spend Use of EMR
Variance after
the use of
EMR
£000 £000 £000 £000 %
31 March 2026
Budget Details
Variance Analysis
RAG Status
Early Education 19,346 19,729 0 383 2% 
Service Description
Main Issues / Reason for Variance
The reason for the adverse variance is an overspend on employee costs (£313k) due to the Grade 3
and 4 job evaluation and the non-achievement of the turnover target. In addition, payments to private
providers are greater than budget following the sharp increase in the number of eligible 2 year olds in
these nurseries (£83k) and the net position from cross boundary charging is adverse (£30k). An
underspend against childminding (£30k) and income from pre-entitlement hours (£13k) has reduced
the overall adverse variance.
This services area includes all Early Years establishments within West Dunbartonshire.

Page 6

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2025/26
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Actual Spend Use of EMR
Variance after
the use of
EMR
£000 £000 £000 £000 %
31 March 2026
Budget Details
Variance Analysis
RAG Status
PPP 18,373 18,145 0 (228) 0% 
Service Description
Main Issues / Reason for Variance
Education Development 2,539 2,398 70 (211) 3% 
Service Description
Main Issues / Reason for Variance
Transport, Fleet & Maintenance
Services (99) 2,261 0 99 -100% 
Service Description
Main Issues / Reason for Variance
Roads Services 2,329 2,261 150 (218) -9% 
Service Description
Main Issues / Reason for Variance
Outdoor Services 300 241 0 (59) 0% 
Service Description
Main Issues / Reason for Variance
Crematorium (1,072) (843) 0 229 -21% 
Service Description
This service covers the outdoor sporting facilities provided by WDC and public conveniences
The variance is mainly due to property costs (£79k) which is due to utiltiy costs being less than
budgeted. The remaining balance of is due to small variances across the Service.
This service provides crematorium services within the Council area
This service relates to Roads operations, design, structures, street lighting, road safety and school
crossing patrols
Employee costs are underspent by £419k due to current levels of vacancies. Property has overspend
by £46k mainly due to additional rates payments. Transport and plant overspent by £178k due to the
current vehicles on hire to ensure that planned works are undertaken and supplies and services
overspent by £290k mainly due to materials required to undertake planned works. Payments to other
bodies are underspent by £49k due to lower than anticipated payments to Greenspace which is due
to level of works carried out for them. Income has over recovered by £264k due to additional
unplanned works which were undertaken on behalf of other Services,.
Transport services across WDC.
Transport Services is operated on behalf of services across the Council. An under recovery on
income is anticipated as while the service fully allocates all costs out to appropriate services there is
currently a mis-alignment between the expenditure and income budgets. A cost pressure was agreed
at Council 17 December to rectify this from 2026/27 budget.
This service includes spend in areas such as technician service, language programmes and senior
phase programme.
The favourable variance is due to underspends on employee costs
Roads and Neighbourhood
This service area includes Vale of Leven, Clydebank High and St Peter the Apostle High Schools
and St Eunan's Primary School. The costs charged to this service are Property costs and the Unitary
charge.
The favourable variance is due to underspends on gas/electricity and a reduction in our estimate for
banked hours payment to BAM

Page 7

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2025/26
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Actual Spend Use of EMR
Variance after
the use of
EMR
£000 £000 £000 £000 %
31 March 2026
Budget Details
Variance Analysis
RAG Status
Main Issues / Reason for Variance
Employee costs are overspent by £32k due to overtime and non achievement of turnover savings.
Property costs are showing a favourable variance of £43k due to utility costs being lower than
anticipated.  Income from cremations is £231k less than budgeted partly due to a new crematorium
recently opened in East Dunbartonshire and the remainder due to number of cremations undertaken.
This budget is uncontrollable and changes throughout. The remaining balance of £9k is due to a
small variance within supplies and services.

Page 8

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2025/26
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Actual Spend Use of EMR
Variance after
the use of
EMR
£000 £000 £000 £000 %
31 March 2026
Budget Details
Variance Analysis
RAG Status
Waste Services 10,074 9,888 0 (186) -2% 
Service Description
Main Issues / Reason for Variance
Working 4 U 2,039 1,957 181 (263) -13% 
Service Description
Main Issues / Reason for Variance
Provision of Working 4U Service.
The underspend  is mainly due to employee costs as a result of achieving savings of £206,500 within
the current financial year and in year vacancies. The service received additional in year funding,
which was maximised resulting in further savings.
Waste Collection and Refuse disposal services
Employee costs overspent by £159k mainly due to turnover not being met. Supplies and services are
underspent £246k mainly due a reduction in the costs for tonnage in relation to waste collection.
Additional income of £92k was received manly due to brown bin waste permits. The remaining £8k
variance is due to small variances throughout the service.

Page 9

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2025/26
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Actual Spend Use of EMR
Variance after
the use of
EMR
£000 £000 £000 £000 %
31 March 2026
Budget Details
Variance Analysis
RAG Status
Homelessness Services 837 737 0 (100) 0% 
Service Description
Main Issues / Reason for Variance
Resettlement Services 0 (964) 0 (964) 0% 
Service Description
Main Issues / Reason for Variance
Sundry Services 6,768 7,468 1,184 (460) -7% 
Service Description
Main Issues / Reason for Variance
Loan Charges 16,708 11,657 0 (5,051) -30% 
Service Description
Main Issues / Reason for Variance
Resettlement service aims to support refugees in establishing a safe, stable and independent life
within the local community
Receipt of resettlement grant with costs incurred within other service areas.  The income has not
been reallocated as it all sits within the General Fund.
Interest and other charges on council borrowing
Loan charges are showing a £5.029m favourable variance against budget as a result of the Council’s
Finance Team, in conjunction with our Treasury Advisers (MUFG), identifying an opportunity to
terminate £33.1m of long-term fixed rate loans in return for a discounted repayment amount resulting
in a £3.4m benefit to the General Fund.  The four loans were due to mature between 2064 and 2078.
The remaining favourable variance is a result a statutory accounting adjustment to loan charges.
Miscellaneous
This service area budgets for non departmental specific costs such as pensions costs, external
grants, external audit fees and insurance costs. The service heading also holds a number of general
savings options which have still to be fully allocated e.g. procurement targets.
The main reason for this favourable variance is due to a number of underspends across the service.
An underspend on employee costs of £183k mainly due to the underspend on unfunded pension
costs and the apprenticeship levy, an underspend on empty property costs £405k and the remainder
across various other budget lines . This is offset by the increase in the provision for legal fees £450k
and procurement savings not being achieved £435k.
Other
Housing and Employability
This service seeks to prevent homelessness occurring across the authority and improves access to
support services
The service has efficiently managed its operational and commissioned budgets to delver a range of
underspends. In addition, the service has generated additional housing benefit income because
there has been an increase in the number of temporary flats.

Page 10

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2025/26
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Actual Spend Use of EMR
Variance after
the use of
EMR
£000 £000 £000 £000 %
31 March 2026
Budget Details
Variance Analysis
RAG Status
Suspense transfer to Reserves 0 (3,212) (3,212) 0 0% 
Service Description
Main Issues / Reason for Variance
Transfer to reserves re SPFO reduction 4,294 (408) (4,702) 0 0% 
Service Description
Main Issues / Reason for Variance
Revenue Support Grant (175,591) (176,208) 0 (617) 0% 
Service Description
Main Issues / Reason for Variance
Non GAE Allocation (8,453) (7,701) 0 752 -9% 
Service Description
Main Issues / Reason for Variance
Central Government Funding (1,672) (2,347) (675) (675) 40% 
Service Description
Main Issues / Reason for Variance
The main reason for this favourable variance is due to additional money received for expenditure
already built into the budget.
This represents the funding from Scottish Government
Release of suspense balances to Earmarked Reserves
A review of the Council’s suspense accounts has identified material sums sitting in suspense
accounts which have accumulated over a number of years which can be released back to earmarked
reserves as agreed in the October finance update.
Balance of in year SPFO saving
Balance of SPFO in year saving to be transferred to earmarked reserves to smooth the budget gap in
future years.
This budget reflects funding received from Central Government
The UK Government provided funding to the council to support local recycling services.  The actual
amount received was greater than originally anticipated. The additional amount (£0.675m) will be
earmarked to deliver future recycling initiatives.
Following a recent review, there is a reduction in the recharge of central support services to non GAE
services.
This budget represents the recharge of central support services to non GAE services ie HRA and
capital