ARGYLL AND BUTE COUNCIL  COUNCIL 
ROAD AND 
INFRASTRUCTURE SERVICES  26 SEPTEMBER 2024 
REST AND BE THANKFUL UPDATE 
1.0 INTRODUCTION 
1.1 At Full Council on 29 June 2023, a report was considered following the
announcement from Transport Scotland regarding the preferred option for the
long-term solution to address the challenges at the A83 Rest and Be
Thankful. The report can be found here: REST AND BE THANKFUL UPDATE
JUNE 2023.pdf (argyll-bute.gov.uk) 
1.2 The preferred option (Brown) is for a debris flow shelter along the line of the
existing Trunk Road with a construction time of approximately three to four years
following improvements to the Old Military Road.  This is considered the most
deliverable option by Transport Scotland. 
1.3 This report provides an update on the Scottish Government’s announcement
on the long term solution for the Rest and Be Thankful.   
2.0 RECOMMENDATIONS 
2.1 It is recommended that Members consider the updates provided in this report. 
3.0 DETAIL 
3.1 At its meeting on 29 June, Council agreed the following motion:
1.     request that the Leader of the Council writes to the newly appointed
Minister for Transport, Fiona Hyslop MSP, to highlight our communities’
concerns and their need for urgency in progressing the permanent
solution for the Rest;  
2.     seek reassurance from the Minister and her officials at Transport
Scotland on a range of points including clear timescales; measures to
mitigate against delay; contingency plans for maintaining access in the
event of a major incident during construction; and confirmation that the
A82 upgrade will progress as planned;

Page 2

3.     ask the Minister to convene an urgent meeting of the A83 Taskforce given
the commitment made at the last meeting in Arrochar, in the context of
this recent announcement and the questions that remain within the
community and local industry;  
4.     call upon the Minister to ensure that the Scottish Government, Transport
Scotland and any other relevant agency will prepare and share a robust
communications strategy which will reinforce the vital message at a
national level that Argyll and Bute is open for business;  
5.     reiterate this Council’s longstanding position that urgent completion of the
permanent solution is of the utmost importance in order that Argyll and
Bute’s current and future opportunities for population and economic
growth are not compromised; and  
6.     request officers to respond to the Scottish Government’s recent
announcement on the basis of paragraphs 1 to 5, above.  
3.2 On the basis of the Council decision, a letter was sent to the Minister from the
Council Leader and also to Transport Scotland from officers in July 2023.
Whilst acknowledgements were received there were no substantive replies to
the correspondence.
3.3 A meeting of the A83 Taskforce was held on 24 January 2024, the minutes of
which and are available on the Transport Scotland website at the following
link: A83 Taskforce - Meeting Minutes - 24 January 2024 | Transport Scotland 
3.4 Transport Scotland held public engagement events on the long-term solution
at the A83 Rest and Be Thankful between 18 to 21 March 2024 at four venues
across Argyll and Bute. These events provided local communities and road
users with the opportunity to meet the designers, as well as view and
comment on the design development and the progress towards delivering the
medium-term improvements along the Old Military Road (OMR). In addition to
the public engagement events, a virtual exhibition was also available on the
Transport Scotland website.
3.5  On 27 March, Transport Scotland were invited to a Members Seminar
regarding the Rest and Be Thankful. Transport Scotland officials along with
their technical advisors and the project’s Contract Manager, AtkinsRealis
WSP Joint Venture (AWJV), provided an update on the progress of the project
covering both the medium term and long term solutions including an overview
of the feedback received to date from the recent and previous public
exhibitions/events. The presentation slides from this seminar are available to
view on the Elected Members Hub. 
3.6  A further meeting of the A83 Taskforce was held on 22 May 2024, the minutes
of which and are available on the Transport Scotland website at the following
link: A83 Taskforce - Meeting Minutes - 22 May 2024 | Transport Scotland

Page 3

3.7 A briefing session was provided for the Policy Lead for Roads, Transport and
Amenity on Thursday 29 August by  Transport Scotland’s project team and
their consultants. The purpose of this briefing was to provide an updated
position regarding progress and timescales, where known, for both the
medium and long term works.
3.8 At the briefing it was confirmed that further upgrades to the Old Military Road
(OMR) are being progressed. These works will provide two way traffic along
the OMR other that at the northwest end of the OMR where the road climbs
up to the car park. This section is expected to continue to be operated under
traffic management including a convoy system due to the gradient and
alignment. However, the maximum waiting time will reduce due to the upgrade
to 2 way traffic for much of the length of the OMR.
3.9 During construction of the debris flow shelter it is anticipated that all traffic will
be diverted onto the OMR due to the complexity of the construction
requirements. Whilst traffic is expected to be diverted onto the OMR for a
significant period (years rather than months) to allow construction the actual
duration will not be firmed up until a contractor is in place and programmes,
method statements etc are completed. Transport Scotland confirmed that
significant work had been carried out to ensure that a positive message of
Argyll being open for business is conveyed by the media when traffic uses the
OMR.
3.10 The Policy Lead enquired regarding the forest route on the western side of
Glen Crow being upgraded as an alternative route during the construction of
the permanent works. Transport Scotland confirmed that this route had been
considered. However, due the gradients and the susceptibility of landslide
above and below the forest route, the route is not considered feasible to be
progressed.  Alternatively the OMR is being upgraded as detailed above to
minimise delays in travel time and keep Argyll and Bute open for business.
Next Steps
3.11 The following bullet points summarise the next steps in so far as they are
known:
• Upgrades for the OMR continue, the realignment of the southern section of
the OMR having been recently completed.
• Detailed design continues for the permanent solution.
• Ground Investigation (GI) works to commence from the end of September
2024 for approximately 16 weeks. These works will involve large drilling
rigs positioned on the existing A83. The A83 will be managed under traffic
signals during these works. The GI works being an essential element of
the design process.

Page 4

• Draft Road Orders due by the end of 2024. These Draft Orders will form
part of a consultation process regarding the alignment of the proposed
works including connecting into the local road network (B828).
3.12 Further updates on this project as it progresses will be provided to future
Council meetings. 
4.0 CONCLUSION 
4.1 This report provides an update on the Scottish Government’s announcement
on the long term solution for the Rest and Be Thankful.  The preferred option
(Brown) is for a debris flow shelter along the line of the existing Trunk Road with
a construction time of three to four years following improvements to the Old
Military Road.   
5.0 IMPLICATIONS 
5.1 Policy – in line with the Council’s policy positon in respect of the A83 Rest and
Be Thankful which is seeking a long term permanent solution. 
5.2 Financial – funding for the project to be met by Scottish Government. 
5.3 Legal – limited for the Council relating to side road orders and tie-ins to the
B828 to Lochgoilhead.   
5.4 HR – none known. 
5.5  Fairer Scotland Duty: none known. 
5.5.1   Equalities – none known. 
5.5.2   Socio-economic Duty – none known. 
5.5.3 Islands – forms part of a lifeline route to islands and remote rural mainland
locations. 
5.6 Climate Change – due regard will be given to climate change with a view to
minimising any climate change impact and these will be considered as and
when they arise.   
5.7  Risk – ongoing connectivity challenges for Argyll and Bute until a permanent
sustainable solution is completed. 
5.8  Customer Service – none known. 
5.9 The Rights of the Child (UNCRC) – none known.

Page 5

Executive Director with responsibility for Roads and Infrastructure Services,
Kirsty Flanagan 
Policy Lead for Roads, Transport and Amenity Services: Councillor John Armour 
August 2024                     
For further information contact: 
Jim Smith, Head of Roads and Infrastructure Services 
Jim.Smith@argyll-bute.gov.uk