WEST DUNBARTONSHIRE COUNCIL 
Report by Chief Officer (Regulatory and Regeneration) 
Council: 29 April 2026 
Subject: Glasgow City Region City Deal – Update 
1. Purpose 
1.1 To provide an update on the Exxon Infrastructure Project, and to report
on matters being discussed by Glasgow City Region. 
2. Recommendations 
2.1 It is recommended that Council: 
i) Notes the update on the Exxon Infrastructure Project;
ii) Approves the request to remove the Eastern Access Road; and
iii) . iii) Notes the update and progress of the Glasgow City Region
programme.   
3. Background 
3.1 The Glasgow City Region City Deal Infrastructure programme equates to
£1.13bn of investment during period 2015-2035. Projects are progressing
and have reached various stages of development. 
4. Main Issues 
4.1 This report provides information on City Region progress and includes
the latest position on Exxon site infrastructure project development. 
Exxon Infrastructure Project 
4.2  The Exxon project is progressing well on site and remains on programme. 
The Western under-bridge was successfully completed during the December
2025 disruptive possession and is a key milestone for the delivery of the
project. 
4.3 As with any large scale construction project on a brown field site there have
been a number of challenges encountered during project delivery. While a
number of these are the subject of active discussions regarding responsibility,
it is now clear that there will be cost implications which have to be managed in
order to keep the project within the agreed budget. To address this the Project
Board have reviewed the project scope to identify any potential mitigation.
ITEM 8

Page 2

Official
4.4 Following review the Project Board recommend the removal of the Eastern 
Access Road from the current scope.  The total cost of this element is £1 million
and the removal of this element will keep the project within the agreed budget.
The construction of this element is programmed for commencement in May
2026 therefore if removed at this time there will be no adverse cost implication.  
The removal does not impact of the completion of the spine road and its ability
to operate as a relief road, however the eastern element of the site may be less
desirable for future development. 
4.5 In recent months, there have been a number of funding initiatives announced
by both UK and Scottish Governments aimed at growing the economy and jobs,
and the Exxon Project Board continue to explore these and other external 
funding opportunities to deliver this element of the project. Updates will be
provided to Council. 
Glasgow City Region - General Update 
4.6 A Glasgow City Region Cabinet Meeting was held on 17 March. Items on the
agenda included a report on Programme Management Office annual budget,
proposed changes to the Clyde Metro Case for Investment Governance
Arrangements, a report on Regional Empowerment, updates on the UK Shared
Prosperity Fund and Local Growth Fund, and a Glasgow City Region Quarterly
Performance Report. 
4.7 The Draft Programme Management Office budget noted overall increase of
£753,786 compared with 2025/26 which is attributed mostly to additional payroll
costs as well as increased marketing budget. The increase will be covered by
temporary loan interest earned on grant sums held by Glasgow City Council
and member recharges should remain unchanged in 2026/27. 
4.8 Updated governance arrangements for developing the Clyde Metro Case for
Investment were agreed by the Cabinet. Glasgow City Region Cabinet
becomes a Clyde Metro Project Sponsors, recognised as the ‘owners’ of the
Case For Investment document and will be expected to have a lead role in
supporting the local delivery of the Clyde Metro. The Chief Executives’ Group
will provide executive support by coordinating Member Authority input,
escalating unresolved issues, and ensuring each authority supplies the
necessary resources and the Programme Steering Group will expand to include
senior representatives from all eight Member Authorities. 
4.9 To date, SPT’s role has been to lead the delivery of the Clyde Metro Case For
Investment. Going forward, SPT will become the lead and accountable body
for the entire Case for Investment stage, taking responsibility for all
workstreams, programme management, staff, and procurement. This change
also means City Deal funding will flow directly to SPT. The aim is to strengthen
decision-making, manage dependencies, and keep the project on track for
Case For Investment completion in 2027.

Page 3

Official
4.10 An update was provided on the regional devolution process. Recent
announcements, including the First Minister’s commitment to new regional
legislation, and the UK Government’s shift to funding via Regional Economic
Partnerships - signal a strong move toward enhanced regional governance.
These developments support Glasgow City Region’s long-standing aim to
secure a more formalised, empowered regional role as well as securing fiscal
tools and flexibilities that would support long-term investment within the
region. 
4.11 The Cabinet approved establishment of a suite of workstreams covering key
policy areas (e.g., innovation, investment, infrastructure, planning, skills)
alongside two joint workstreams with Edinburgh City Region focusing on
governance and fiscal powers. These groups will over the next 12 months
develop detailed proposals on the powers, responsibilities and delivery
models Glasgow City Region seeks to secure through forthcoming legislation
and funding reforms. All partners will be invited to participate in the
workstreams, and further updates will be provided to the Cabinet. 
4.12  UK Shared Prosperity Fund Quarter 3 Update report noted the Quarter 3
spend. It also highlighted that the costs may now relate to activity that takes
place on or before the 30 September 2026 which is a 6-month extension to
the previous spend eligibility deadline 
4.13  An update on the on the new Local Growth Fund was provided, including budget
allocations, policy intentions, and the proposed methodology for distributing both
revenue and capital funding. Following the UK Government’s 2025 Spending
Review, Scotland will receive approximately £76 million per year from 2026/27 to
2028/29 to support regional economic growth. This replaces the UK Shared
Prosperity Fund There are four funding steams that make up the Local Growth
Fund: 
 Pride in Place Programme Phase 2
 Pride in Place Impact Fund 
 New Local Growth Fund 
 Growth Mission Fund 
4.14 Pride in Place Programme Phase 2, The Pride in Place Impact Fund and the
Growth Mission Fund were all confirmed on, or before, the UK Government
Autumn Budget Statement (26 November 2025) with the new Local Growth
Fund allocations announced on Thursday 8 January 2026. Allocations have
been determined at a Regional Economic Partnership level, rather than
individual Local Authority, with Glasgow City Region due to receive £60.9
million across the three-year funding period which amounts to 43.5% of the
overall Scottish new Local Growth Fund allocation. The allocations are noted
in the Table below.

Page 4

Official
2026/27 2027/28 2028/29 Total
Revenue £6,900,000 £6,700,000 £4,800,000 £18,400,00
Capital £15,800,000 £14,800,000 £11,900,000 £42,500,00
Total £22,700,000 £21,500,000 £16,700,000 £60,900,00 
4.15 The Local Growth Fund   has a different policy focus from previous funds,
emphasising economic growth through infrastructure, business support, and
skills development. It is not considered a successor to UK Shared Prosperity
Fund. However, due to widespread reliance on UK Shared Prosperity Fund
revenue for local authority services, the UK Government has agreed to a
transition year in 2026/27. 
4.16 The Cabinet approved that for 2026/27 FY only, revenue allocations will follow
the 2025/26 methodology (for UK Shared Prosperity Fund), enabling councils
to maintain continuity in business support and employability programmes.
West Dunbartonshire will receive £400,200, which is just over 5.80% of the
region’s £6.9m revenue budget for that year. This is a significant reduction in
comparison to the 2025/26 UK Shared Prosperity Fund revenue allocation
for West Dunbartonshire which was in the region of £1.2 million. 
4.17 Capital funding is expected to focus exclusively on regional-scale projects that
deliver meaningful economic outcomes 
 Increased development-ready land and sites
 Increased housing supply
 Improved utilities and energy upgrades
 Increased physical connectivity
 Increased digital connectivity 
4.18 The Glasgow City Region Programme Management Office will now work with
partners to prepare a “Credible Plan” which sets out proposed investments for
the full funding period. This plan will require approval by the Chief Executives’
Group and the Cabinet before submission to the UK Government. 
4.19 Glasgow City Region Quarterly Performance Report (Q3 2025/26) was
presented, including updates on the Regional Economic Strategy Action Plan; the
City Deal Programme; and the City Region Team workplan. The City Deal
Programme continues to perform strongly, 21 projects reporting Green status and
no projects in Red or Amber. Major construction activity is advancing across
multiple councils, including significant progress on Westerhill Development Road,
Bishopbriggs Town Centre, Balgray Station, Eurocentral Access, East Kilbride
Town Centre and the Exxon site. 
Formal approval of the Investment Zone Government 5-stage Gateway Process
was received on 23rd December 2025. Individual project Business Cases are now
being developed for approval by Glasgow City Region Chief Executives’ Group

Page 5

Official
5. People Implications 
5.1 There are several senior officers involved in the Glasgow City Region wider
programme as noted at City Region Update paper at Council on 26 August
2021. 
6. Financial Implications 
6.1 Spend to date on the Exxon Infrastructure Project for financial year 25/26 is
£14.3 million. Overall expenditure to date is £25.7 million. 
7. Risk Analysis 
7.1 There are several project risks associated with the development at the Exxon
project site, and these are contained within the project risk register and updated
by the Project Board on a regular basis. The Project Board is made up of senior
officers from all key services. 
8. Equalities Impact Assessment 
8.1 Previously completed. It is not considered that the proposed change to the
scope will have an impact on any matter addressed in an Equalities Impact
Assessment. 
9. Consultation 
9.1 Consultation with all key stakeholders is progressing as we continue to work as
part of the Glasgow City Region. 
10 Strategic Assessment 
10.1 At its meeting on 26 October 2022, the Council agreed that one of its main
strategic priorities for the Strategic Plan 2022 - 2027 is ‘A Strong local economy
and improved employment opportunities’. 
10.2 The proposals within this report are specifically designed to deliver on this
priority. 
Alan Douglas
Chief Officer: Regulatory and Regeneration
Date: 29th April 2026

Page 6

Official
Person to Contact: Alan Douglas
Alan.Douglas@west-dunbarton.gov.uk 
Appendix: None 
Background Papers: Glasgow City Region City Deal- Council 13 August 2014. “City
Deal Initiative” Clyde Valley Investment Fund-Council 30 April
2014 (Memorandum of Understanding). Clyde Valley
Community Planning Partnership – City Deal Initiative –
Council 28 August 2013. 
Wards Affected: All