WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer – Housing 
West Dunbartonshire Council 25 March 2026
Subject:Crescent Court Lift; Information and Timeline
1 Purpose
The purpose of this report is to provide Council with the information on events,
timeline, challenges and learning in relation to the breakdown of the Crescent
Court lift.
2 Recommendations
2.1 It is recommended that Council note the contents of this paper.
3 Background
3.1 The Council is responsible for the maintenance of approximately 80 lifts. Many
of these are in multistorey buildings owned or factored by the Council’s
Housing Department.
3.2 These blocks each contain two lifts.  The most common structure, including at
Crescent Court, is that one lift services all odd number floors and the other
services all even floors.
3.3 The Council committed to substantial investment in renewal of lift equipment
in the latter part of the 2000’s and these lifts and some of their core
components are now approaching end of life. Ad-hoc repairs, renewals and
replacement of components have taken place in the intervening years but the
average age of much of the infrastructure is towards the end of its operational
life.
3.4 On 4 August 2025 the Council’s lift maintenance contractor KONE, was called
to attend the even lift at Crescent Court as the lift was operating but making
excessive noise. The lift was put out of service and investigations were
undertaken. It was determined the gearbox was failing and required it to be
disassembled for further investigations to occur.  It became apparent the lift
would be out of service for an extended period of time given the failure of such
a major component of the infrastructure, its age, and the ‘sealed’ nature of the
gearbox.
3.5 By the end of August, following investigation and discussion with the
contractor, it was agreed the most effective solution was to commission the
manufacture of a new gearbox to replace the failed unit.  Although repairing
the existing gearbox remained a theoretical option, it would have required
additional time for removal, inspection, and assessment, with no guarantee a
ITEM 14

Page 2

repair would be viable. Given the urgency of reinstating the lift and the
likelihood the cost and timescale would be comparable to installing a new unit,
the decision was taken to proceed with full replacement. A new gearbox was
also expected to provide greater long-term reliability.
4 Main Issues
4.1 The instruction was received by KONE who provided terms and conditions
for the supply of the new component and once agreed by the Craft
Supervisor, they started on preparatory works. The first part was weighing
the existing lift car in order to determine the exact specifications and
capabilities required of a new gearbox.
4.2 Following this process, and with the manufacturing requirements set, the
invoice for the first portion of the works was provided to the Council.
However, the officer who was the primary contact for KONE and who had
instructed the works had now left the Council.
4.3 While the maintenance and repair works undertaken by the contractor
under the terms of their contract was invoiced in arrears, the manufacture
of the new components required payment in advance of manufacture.
4.4      An invoice was sent to the Council’s Craft Supervisor’s email address after
he left the organisation, the invoice was not known about by any other
officer in the Council, and the delay was not picked up by another Council
officer. 
4.5     This communication breakdown caused the only major avoidable delay of
the project. The timeline for delivery of a new gearbox was estimated at
around 12 weeks and so no action was taken by any remaining officer of
the Council as it was wrongly assumed the order was in progress. With two
key posts responsible for the oversight of this contract vacant, no Council
officer was aware that there was any problem. The only Officer aware that
there was an invoice that required payment in advance had left the
organisation and KONE took no action to make any other Council Officer
aware of any issue.
4.6  KONE made us aware of an issue with invoicing in the last week in October,
following contact from WDC requesting an update on the progress of the
project.
4.7      KONE were tasked with immediately restarting works and reviewing
timelines for production and installation. Unfortunately, it became apparent
the initial 12 week timeline, was also impacted by the Christmas period
shutdowns creating logistical challenges which would further delay
completion of the project.

Page 3

4.8 New timelines were produced in the second and third week of December
2025 following an update from KONE’s supplier on the shipping date of
component parts. This final timeline proved to be accurate and the works
were completed on 13 February 2026.
4.9 The only significant avoidable delay resulted from inadequate contract
management and insufficient Council staffing to oversee and track the project
as set out in paragraph 4.4 above. By August 2025, the senior Coordinator
post had been vacant for over 18 months, and the subsequent departure of
the relevant officer left no dedicated staff to manage the work, increasing the
risk of service failures. Both roles were filled in early January 2026. While staff
turnover cannot be prevented, stronger arrangements for continuity and
handover have been put in place to avoid similar issues in future.
4.10 Although the gearbox could have failed at any point, the age of the equipment
was a significant factor in both the failure itself and the Council’s limited ability
to restore the lift quickly. While the Housing service aims to renew assets only
when necessary, the critical role of lifts and the lengthy timescales involved in
replacing major components have prompted a full review of lift condition
across the high-rise stock. This review will inform a planned investment in lift
cars and other essential equipment to improve reliability and reduce the risk of
prolonged unplanned outages in future.
4.11 Whilst not a contributor to any of the delays in this instance, the lift protocol
document, (the inter-departmental action plan to follow in case of failure of a
lift) has been reviewed which updates roles/duty holders and recirculated in
various forums over and above those who are responsible for undertaking
tasks on this document.
4.12 While this failure was unforeseen and the contract should have been
managed better, the issue has served to highlight the wider issues associated
with lift infrastructure at high rise flats owned or operated by West
Dunbartonshire Council’s Building Services/Housing teams.
Efforts have been made to avoid, reduce or mitigate any future events with
faster reactions, better forward planning and maintaining appropriate
resources and continuity to deal with issues as they arise.
5. Options Appraisal
5.1 There are no options to present in relation to this paper.
6. People Implications
6.1 There are no people implications to present in relation to this paper, other
than the staffing issues already mentioned and resolved.
7. Financial and Procurement Implications
7.1 There are financial and procurement implications related to the ongoing
maintenance and continued renewal of the lift infrastructure, however these
are not the subject of this paper.

Page 4

8. Risk Analysis
8.1 While the age of the lift infrastructure presents ongoing service risks, these
matters fall out with the scope of this paper.
9. Equalities Impact Assessment (EIA)
9.1 While there are equalities issues related to the function of lift infrastructure,
these matters fall out with the scope of this paper.
10. Environmental Sustainability
10.1 There are sustainability implications to present in relation to this paper.
11. Consultation
11.1 There are no consultation requirements in relation to this paper.
12. Strategic Assessment
12.1 There is no strategic assessment to be made in relation to this paper.
Chief Officer: Peter Barry
Service Area: Housing
Date: 06 March 2026
_____________________________________________________________
Person to Contact: Craig Wilson
Building Services Manager
craig.wilson@west-dunbarton.gov.uk
Appendix: 1. Timeline of Events
Background Papers: None
Wards Affected: All