Item 11 Addendum - Construction Cost Update - Gruggies Burn Flood Alleviation Scheme

West Dunbartonshire Council · 25 March 2026
Back to West Dunbartonshire Council — 25 March 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

WEST DUNBARTONSHIRE COUNCIL 
Report by Chief Officer – Roads & Neighbourhood
West Dunbartonshire Council – 25 March 2026 
Subject: Addendum to Item 11 - General Services Capital Budgetary Control
Report 2025-26 to 31 January 2026 (Period 10) 
Construction Cost Update - Gruggies Burn Flood Alleviation
Scheme 
1. Purpose 
1.1 The purpose of this addendum is to update members on the increase of
construction costs since December 2025 to deliver the Gruggies Burn
Flood Alleviation Scheme and to request approval to finalise and sign the
construction contract to deliver Option 1 – Full Scheme Delivery. 
2. Recommendations 
2.1 It is recommended that Council: 
i) Note that, following receipt of all project costs, the construction cost
for the Gruggies Burn Flood Alleviation Scheme has increased by
£3.46m since council approval in December 2025.  This increases
the council’s capital contribution by £0.692m with an annual revenue
implication of £0.032m. 
ii) Approve that the capital plan budget details for RN11 Gruggies
Burn Flood Alleviation Scheme are updated to reflect the
increase in capital costs to construct Option 1 – Full Scheme
Delivery. 
iii) Authorise the Chief Officer Regulatory and Regeneration to
conclude negotiations in relation to the finalisation and signing of
the construction contract to deliver Option 1 - Full Scheme
Delivery. 
3. Summary 
3.1 At the 17 December 2025 Council meeting elected members considered the
following 4 options to deliver the Gruggies Flood Alleviation Scheme: 
 Option 1 – Full Scheme Delivery
 Option 2 – Delivery of Inlet and Diversion Culvert 
 Option 3 – Delivery of Coastal Defences and Flood Gates
 Option 4 – Do Nothing 
3.2 The costs following detailed design considered in December 2025 were as
ITEM 11
Addendum

Page 2

follows: 
December 2025 Option 1 Option 2 Option 3 Option 4
Total £44.7m £39.2m £14.7m £1.98m
West Dunbartonshire
Council Contribution
(20%)
£8.94m £7.84m £2.94m  £1.98m
Scottish Government
Contribution (80%) £35.76m £31.36m £11.76m  N/A 
3.3 Council approved the progressing of Option 1 – Full Scheme Delivery. 
3.4 Officers have progressed with the contract preparation for Option 1 to meet
the deadline set to access Scottish Government funding.  Should the 31
March 2026 deadline not be met the opportunity to access Scottish
Government funding of 80% of project costs is no longer available. 
3.5 The project costs included all anticipated major utility service diversions and
construction work being undertaken by Network Rail however these have
increased through confirmation with the key stakeholders.  Final costs have
been received which have increased the construction cost of Option 1 to
£48.16m. 
3.6 The updated construction costs to deliver the 3 options are set out in the
table below: 
Construction Costs (Capital)
March 2026
Option 1 Option 2 Option 3
£m £m £m
Total 48.160 42.560 14.700
West Dunbartonshire Council
Contribution (20%) 9.632 8.532 2.940
Scottish Government
Contribution (80%) 38.528 34.028 11.760 
3.7 The total revenue implications for the council are set out below: 
WDC REVENUE PER ANNUM Option 1 Option 2 Option 3
£m £m £m
Principal Repayment 0.241 0.213 0.074
Interest on Principal 0.210 0.186 0.063
Total 0.451 0.399 0.137    
WDC REVENUE 40 YEARS Option 1 Option 2 Option 3
£m £m £m
Principal Repayment 9.632 8.532 2.940
Interest on Principal 8.400 7.440 2.520
Revenue in 2025/26 0.000 0.000 0.000
Total 18.032 15.972 5.460

Page 3

3.8 The additional capital impact of the construction cost increase since
December 2025 is as follows: 
INCREASE IN CAPITAL  Option 1 Option 2 Option 3
£m £m £m
Total 3.460 3.460 0.000
West Dunbartonshire Council
Contribution (20%) 0.692 0.692 0.000
Scottish Government
Contribution (80%) 2.768 2.768 0.000 
3.9 The additional revenue impact of the construction cost increase since
December 2025 is as follows: 
WDC REVENUE PER ANNUM Option 1 Option 2 Option 3
£m £m £m
Principal Repayment 0.017 0.017 0.000
Interest on Repayment 0.015 0.015 0.000
Total 0.032 0.032 0.000    
WDC REVENUE 40 YEARS Option 1 Option 2 Option 3
£m £m £m
Principal Repayment 0.692 0.692 0.000
Interest on Repayment 0.600 0.600 0.000
Revenue in 2025/26 0.000 0.000 0.000
Total 1.292 1.292 0.000 
Chief Officer: Gail Macfarlane 
Service Area:  Roads and Neighbourhood 
Date:   20 March 2026 
Person to Contact:   Liam Greene  
Roads and Transportation Manager  
Email: liam.greene@west-dunbarton.gov.uk 
Wards Affected: Dumbarton and Leven Wards