WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer, Housing
Council: 4 March 2026
Subject: Housing Revenue Account (HRA), Housing Capital
Investment Programme, Revenue Budget, and Rent
Levels for 2026/27
1. Purpose
1.1 To seek Council approval of the proposed Housing Capital Investment
Programme 2026-2031 and the HRA revenue budget for 2026/27 and to agree
the level of weekly rent increase for 2026/27.
2. Recommendations
2.1 It is recommended that Council:
i) Notes the progress made in delivering the HRA Capital Investment
Programme for 2025/26 as detailed in appendix 1.
ii) Approves the HRA Capital Investment Plan 2026/27 – 2030/31 as detailed
in Appendix 2.
iii) Approves the HRA revenue budget for 2026/27 as detailed in Appendix 3
and Appendix 4.
iv) Approves a 6.7% weekly house rent increase for 2026/27: an average
increase of £6.88 per week on a 52-week basis, inclusive of the Gypsy
Traveller site at Dennystoun Forge.
v) Approves an initial 6.7% lock up and garage site rent increase for 2026/27:
an increase to lock-up rents of £0.44 per week to £6.96 per week on a 52-
week basis.
vi) Approves a 6.7% rent increase for properties that the HRA rents for
homeless temporary accommodation and this increase will be reflected in
temporary accommodation charges from 1st April 2026.
vii) Notes the outcome of the tenant consultation process as detailed in
Appendix 5 of this report.
viii) Notes that the HRA prudential reserve target for 2026/27 is £1.222m (2% of
gross expenditure) 
ITEM 9

Page 2

3. Background
3.1 West Dunbartonshire Council (the Council) is the landlord for 10,547 homes as
at the 31st March 2026 located in communities across West Dunbartonshire.
Council housing costs must be self-financing from house rents and other
income. This includes any investment in improving homes or increasing the
number of homes. In delivering this landlord role, the Council strives to provide
excellent quality, affordable, safe, secure, and warm housing that is fundamental
to the health and well-being of individuals and families, the sustainability of local
communities and the success of the local economy.
3.2 The Council has a legal requirement under the Housing (Scotland) Act 2001 to
consult council tenants and give consideration to their views before considering
any proposed rent increase. Approval of this report will demonstrate this
obligation has been fulfilled. Full details of the consultative exercise are included
in appendix 5 of this report.
3.3 The recommended rent increase for 2026/27 will contribute towards the funding
of the HRA Capital Housing Investment Programme and fund increased HRA
revenue costs which will allow for:
 Continued investment in tenant priorities through the Housing Capital
Investment Programme.
 Investment in improving homes including energy efficiency measures that
help alleviate fuel poverty.
 Investment in measures to meet compliance with the proposed Social
Housing Net Zero Standard which will help reduce council home carbon
emissions.
3.4 In considering the structure of the budget, consideration has been given to
increasing revenue, reducing costs, and identifying ways to mitigate the impact of
high interest rates and increased employment costs. The service has focused on:
 Improving void performance and increasing the desirability of council
housing stock.
 Strategic asset management of our council homes.
 Improving housing management.
 Strengthening cost control over revenue expenditure, including recruitment,
overtime, property, and responsive repair costs.
 Value for money, including an ongoing review of charges to the HRA
account.
 Stringent application of the rechargeable repairs policy.
 Reducing costs associated with the housing repairs service and void
houses.
 Reviewing the expenditure across revenue and capital budgets to ensure all

Page 3

spend of a capital nature (spend that enhances and improves a capital
asset) is charged to the HRA capital account.
3.5 The following factors have been considered when preparing the 2026/27 HRA
estimates:
 Inflation has been applied to relevant revenue budget lines.
 Provision made for a 3.5% pay award.
 Provision made for higher employer pension costs.
 A 4% turnover allowance has been applied to the employee cost budget.
 Debt interest rates have been assumed in line with projected council
borrowing costs.
4. Main Issues
4.1 HRA Capital Investment Programme
HRA Capital Investment Programme 2025/26
4.1.1 On 5 March 2025, Council approved a five-year HRA capital programme
for capital works over the period 2025/26 - 2029/30. On 20 August 2025,
the Housing and Communities committee was advised that the 2025/26
HRA capital programme had been reprofiled with a revised net borrowing
estimate of £49.257m in 2026/26. Progress delivering the 2025/26
programme is shown in Appendix 1.
4.1.2 The Better Homes element of the Housing Capital Investment Programme
invests in improving existing housing stock is projecting a £9.827m
underspend in 2025/26. Council has been advised of progress delivering
this programme during 2025/26.
4.1.3 The More Homes element of the Housing Capital Investment Programme
invests in provision of new homes, regeneration activities, and buyback
acquisitions is forecasting a £4.339m overspend against budget. A
significant positive factor in this overspend is the accelerated spending to
deliver much needed new homes at greater pace in Bonhill and Queen
Mary Avenue.
4.1.4 It is forecast that HRA capital resources will be £4.989m more than budget,
as set out in appendix 1 of this report.
HRA Capital Investment Programme 2026/27 – 2030/31
4.1.5 The HRA Capital Investment Programme has been developed using data from
current stock condition surveys and a bi-annual stock assessment exercise. The
main drivers for the programme are for the Council to deliver on the key
objectives of the Council’s Better Homes Strategic Housing Asset Management
Strategy and to ensure the Council complies with its health and safety
responsibilities. In addition to investment in the core stock, the investment
programme includes the Council’s ambitious ongoing new house build

Page 4

programme More Homes West Dunbartonshire.
4.1.6 The Investment Programme is consistent with evidenced tenant priorities which
were reinforced through the findings of the 2024 tenant satisfaction survey that
highlighted the top two spending priorities for tenants are:
 A responsive and high-quality repair and maintenance service; and
 Building new Council homes.
4.1.7 Due to the long-term nature of HRA capital investment, there is an ongoing
need for assurance that investments are affordable in the longer-term taking
account of estimated inflation, cost pressures, potential savings, and projected
changes to future interest rates. Current financial modelling work identifies short
term cost pressures across capital financing costs; however, capital financing
costs are projected to stabilise as CPI inflation reduces to target levels and
public sector borrowing rates reduce.
4.1.8 The HRA capital investment plan addresses the long term need to improve
existing housing stock and provide new homes that meet the needs and
aspirations of current and future tenants. This report outlines proposals for
investment in housing-led regeneration and renewal to meet this need.
4.1.9 Through the HRA Capital Investment Programme, investment of £261m is
planned over the next five years. This will enhance and improve the Council’s
housing stock, contribute to the wider transformation of West Dunbartonshire,
and be central to improving West Dunbartonshire’s economic and social
wellbeing.
4.1.10The housing supply and regeneration programme element of the HRA
Capital Investment Programme, ‘More Homes West Dunbartonshire,’ will
see investment of £100m over the next five years, partially funded by a
projected minimum £41m of Scottish Government grant funding from the

Page 5

Affordable Housing Supply Programme. Therefore, for new builds and
acquisitions, there is a net HRA capital cost of £59m over the next five
years. The borrowing cost of financing new builds is spread over 60 years.
4.1.11The More Homes West Dunbartonshire programme contributes towards the
Council’s commitment for 2,500 new homes over the period 2022 – 2032.
Quarterly updates on progress, including changes in programme, will continue to
be reported to the Housing and Communities Committee.
4.1.12The Better Homes programme that invests in improving the quality of existing
houses has been reviewed and rolled forward a year to 2030/31. The proposed
plan delivers £162m of investment over the next 5 years, with a forecast £3m of
capital income recovered from owners participating in capital investment
programmes. The Better Homes programme therefore has a net HRA capital
cost of £159m over the next five years.
4.1.13The updated HRA capital programme is shown in Appendix 2 and summarised
as follows.
Financial Year Expenditure
£m
Income
£m
Net
£m
2026/2027 63.685 (16,901) 46.384
2027/2028 60.200 (6.801) 53.399
2028/2029 44.550 (5,701) 38.849
2029/2030 47.650 (8.561) 39.089
2030/2031 45.650 (5.981) 39.669
Five Year Total 261.335 (43.945) 217.390
4.1.14The planned investment will deliver against the ongoing commitment to
improve housing for tenants and future tenants of Council homes and will
support the delivery of wider Strategic Plan and Local Housing Strategy
priorities, including:
 Providing a pipeline of construction work with opportunities for job
creation, community benefits, training, and benefits to the local supply
chain and the potential to lever in significant external investment.
 Providing a catalyst for engagement with local communities in the
development and delivery of these ambitious plans through strong
tenant participation mechanisms.
 Ensuring design and specification maximises opportunities to future
proof homes including use of modern technology to improve the health
and wellbeing of tenants, the quality of housing, and helping improve
the quality of people’s lives.
 Contributing to the Council’s place making agenda, providing a
framework for improving the quality of the places where people live and
supporting tenants to be actively involved in shaping change, impacting
positively on the attractiveness of West Dunbartonshire as a place to

Page 6

live and encouraging economic investment.
 Improving the quality and appearance of neighborhoods and deliver a
consistent and cost-effective approach to the maintenance and
management of areas.
 Contributing to the achievement of climate change ambitions and the
Council’s Climate Change Strategy and addressing fuel poverty using
the highest standards of energy efficiency practices in new build
construction and retrofit technologies.
4.2 HRA Financial Plan
4.2.1 The HRA requires a balanced budget which means budgeted rental income
is sufficient to cover all anticipated revenue costs for operating and
maintaining HRA properties including the borrowing costs associated with
capital investment.
4.2.2 The HRA’s financial environment continues to be challenging due to high
inflation, public sector pay pressures, and high borrowing costs. There has
been an increased call on HRA reserves over the past few years, with HRA
reserves reducing from a balance of £2.635m on March 23 to a forecast HRA
reserve balance of £1.691m on March 26.
4.2.3 HRA financial plans have been reviewed and updated for the period 2026/27
to 2030/31 to take account of planned capital investment, projected
borrowing costs, and estimated changes to revenue costs and income.
4.2.4 The plan assumes an easing in inflationary pressures with CPI returning and
remaining at the 2% Bank of England target during financial year 2026/27. It
also assumes public sector pay pressures ease, however the recent increase to
employer national insurance, the ongoing review of employer pension
contribution rates, and the recent levels of public sector pay awards highlight
the challenges in forecasting pay pressures.
4.2.5 One of the key financial challenges facing the HRA over the next five years is
the increase in debt servicing costs because of the significant increase in HRA
debt and associated borrowing costs. The assumption is the HRA will incur
increasing debt servicing costs.
4.2.6 In considering debt affordability, our HRA financial plans look at debt servicing
costs as a percentage of gross expenditure. This is an indicator of the stress that
borrowing places on the remainder of the HRA revenue budget. When the
decision was taken to retain all the housing stock in West Dunbartonshire the
investment requirement needed to achieve the Scottish Housing Quality
Standard, coupled with the historic HRA debt structure, recommended that the
“debt affordability” percentage in West Dunbartonshire ideally does not exceed
50% in the medium to long term, and that the HRA should aim to have a surplus
to generate CFCR (Capital Funded from Current Revenue) or a break-even
revenue position.

Page 7

4.2.7 The annual debt / expenditure percentages under the most recent HRA financial
model update highlight that debt servicing costs continue to put a strain on the
HRA revenue account and future rent increases. Debt affordability percentages
are modelled to be around 50% of gross expenditure over the next few years. In
addition, current financial plans require above inflation rent increases to fund
HRA revenue and debt servicing costs. Officers will aim to minimise borrowing
costs through proactive treasury management. Furthermore, officers will target
efficiency and cost reductions across HRA revenue and capital expenditure lines
to ensure that future rent rises are kept as low as possible whilst delivering a
balanced HRA budget. However, there may be a requirement to further review
the scope and scale of the HRA capital and revenue programmes if the level of
financial pressure faced by the HRA cannot be reduced.
4.3 HRA Revenue Estimates and Rent Levels
4.3.1 The revenue estimates for 2025/26 are attached in summary form in Appendix 3
with a more detailed analysis explaining budget movements provided in
Appendix 4. The estimates show an increase in expenditure of £4.099m in
2026/27.
4.3.2 The Council is required to consider the level of weekly rent increase for the
budget year 2026/27 and agree an appropriate rent that meets estimated HRA
revenue costs as identified in Appendix 3.
4.3.3 In determining the level of weekly rent increase, consideration needs to be given
to changing service demands and cost pressures as well as the requirements for
investment as highlighted in the Housing Asset Management Strategy. The
Council also needs robust financial planning and management to ensure it
delivers on its investment commitments.
4.3.4 The required weekly rent increase contained within the attached HRA estimate is
6.70% (based on housing stock and occupancy levels), an average increase of
£6.88 per week on a 52-week basis (£7.61 per week on a 47-week basis)
4.3.5 It is also recommended the Council increase rents at the Gypsy Travellers site at
Dennystoun Forge, lock ups, garage sites and homeless temporary
accommodation by 6.7%. There is an ongoing review of lock ups and garage
sites that may include future rent remodelling which, if approved, would be
introduced during 2026/27.
4.4 Tenant Consultation 
4.4.1 The Council has a statutory duty to consult tenants before increasing rents. The
formal consultation was launched at a public meeting on 30 October 20205
where draft HRA spending plans for 2026/27 were presented. Information was
also posted on the Council’s website at the same time. The consultation
consisted of four rent increase options as follows: -
Option 1: 6.7% rent increase (average weekly increase of £6.84)
This option will mean:
• Maintaining all current services that tenants receive

Page 8

• Delivering our New Build housing programme
• Delivering our Capital Investment programme to improve existing Council homes
• A Tenant Priority Budget of £200k for tenant led improvements
Option 2: 6.95% rent increase (average weekly increase of £7.09)
This option will mean the same as Option 1 plus:
• Additional expenditure of £140k to re-instate open space maintenance to 2024/25 funding levels
Option 3: 7.2% rent increase (average weekly increase of £7.35)
This option will mean the same as Option 1 plus:
• An additional £3.6m of Capital Investment during 2026/27 expanding the Buy Back Scheme to
deliver twenty-four additional Council homes for rent
Option 4: 7.45% rent increase (average weekly increase of £7.60)
This option will mean the same as Option 1 plus:
• Additional expenditure of £140k to re-instate open space maintenance to 2024/25 funding levels
• An additional £3.6m Capital Investment during 2026/27 expanding the Buy Back Scheme to     
deliver twenty-four additional Council homes for rent.
4.4.2 The formal consultation was open to all tenants and those residing in homeless
temporary accommodation. A wide range of accessible consultation methods
were chosen to gather the views of as many tenants as possible. Information
was provided in a clear and understandable way with staff across Housing
Services promoting the survey and explaining the options to tenants.
4.4.3 A total of 1,246 completed responses were received – a response rate of 12%.
Responses indicated a 66% preference for the 6.7% rent increase option, with
34% of respondents supporting the other options highlighted below: -.
Option 1 (6.7% increase) got 825 votes = 66.2%
Option 2 (6.95% increase) got 174 votes = 14%
Option 3 (7.2% increase) got 116 votes = 9.3%
Option 4 (7.45% increase) got 131 votes = 10.5%
4.5 Reserves
4.5.1 HRA reserves were £0.611m on the 31 March 2025, The HRA is forecasting an
in-year surplus of £1.080m that will see HRA reserves increase to £1.691m on
31 March 2026.

Page 9

4.5.2 Council policy is to target a HRA prudential reserve of 2% of gross HRA
expenditure. Based upon the recommended budget for 2026/27, this
equates to a prudential reserve target of £1.218m (previously £1.162m).
The increase in the prudential reserve target is therefore £0.056m for
2026/27.
4.5.3 In terms of the forward HRA reserve strategy, the aim is to maintain HRA
reserves at circa £1.7m over the short term (above the prudential target)
whilst balancing the need to keep rent rises as low as possible. The aim is
to provide additional financial headroom so that the HRA can more
effectively deal with unforeseen financial pressures.
4.5.4 Future HRA financial planning will aim to maintain HRA reserves at or
above prudential levels with a medium-term goal for the HRA to generate
annual revenue surpluses that can be used to finance capital expenditure,
CFCR contributions, and reduce HRA capital debt and associated debt
servicing costs.
5 People Implications
5.1 There are no people implications.
6 Financial and Procurement Implications
6.1 The financial implications are detailed within the report and appendices. The cost
to notify tenants of the rent increase is absorbed within existing budgets.
6.2 All procurement activity conducted by the Council, more than £50,000, is subject
to a contract strategy. The Corporate Procurement Unit Contract develops
strategies for the HRA Capital Investment Programme in consultation with
housing officers. The contract strategies will include but is not limited to; contract
scope, service forward plan, the market, procurement model and routes –
including existing delivery vehicles, roles and responsibilities, risks, issues and
opportunities and on-going contract management. Opportunities to maximise the
positive social, economic, and environmental impact for the Council through the
relevant procurement processes will be developed in line with procurement policy.
6.3 An affordability analysis undertaken prior to the commencement of the Council’s
2026/27 rent consultation determined Council WDC rents are on average £77 (42%)
less than Market Rents with all properties comfortably below the equivalent average
market rent. In addition, all households on minimum income can afford Council rents
assuming the standard 35% rent to income ratio. Using equivalized income
measures, all tenant household types spend under 35% of their income on rent, in
some cases as little as 14%. Single adults on Universal Credit are the only group
exceeding 30%.
7 Risk Analysis
7.1 The key driver for determining rents for Council properties is the HRA
investment plan. Failure to set rents consistent with the delivery of this
plan will potentially result in insufficient funding being available to meet

Page 10

the aspirations highlighted above.
7.2 Officers have made assumptions in relation to performance around
the repairs budget, rent recovery and void levels when setting this
budget. Performance against these key areas will continue to be
closely monitored during 2026/27 and members advised of any
significant variations that impact materially on HRA financial
performance.
7.3 In terms of the capital programme, the main financial risk relates to whether
inflation increases costs, resulting in cost increases and upward pressure on
budgets.
7.4 Ongoing budgetary control processes will monitor the above issues,
and any issues will be reported to future council meetings for
consideration.
8 Environmental Sustainability
8.1 Our current and future approach to strategic housing asset
management will continue to prioritise a ‘zero carbon’ approach to
decision making and deliverability, The proposed investment plan
aligns with the aims of the Housing Asset Management Strategy and
the Council’s Climate Change Strategy.
9 Equalities Impact Assessment (EIA)
9.1 An initial assessment has been completed for the Housing Capital 
Investment Programme 2026-31. This showed that a full assessment
was not required as the programme was a refresh of the previous
programme with spend reprofiled to ensure delivery and as such,
there are no significant changes.
10 Consultation
10.1 The Council has a statutory requirement to conduct a rent consultation exercise.
Appendix 5 details the results of the consultation exercise.
10.2 A HRA budget scrutiny group (Joint Rent Group) is now well-
established, involving tenant representatives. This group meet with
officers and the Convenor bi-monthly and examines the HRA to ensure
increased transparency and to respond to tenant enquiries about the
value for money offered to tenants.
11 Strategic Assessment
11.1 The proposals contained in this report directly address all the Council’s
strategic priorities. The investment in and provision of attractive affordable
housing will also indirectly support the objective of economic growth and
employability through supporting employment and improving place

Page 11

attractiveness.
11.2 Proper budgetary control and sound financial practice are cornerstones of
good governance and support Council and officers to pursue the five
strategic priorities of the Council’s Strategic Plan. This report forms part of
the financial governance of the Council.
Peter Barry
Chief Officer - Housing
4 March 2026
Person to Contact: Jim McCarron – Finance Business Partner
16 Church Street, Dumbarton, G82 1QL
e-mail:  james.mccarron@west-dunbarton.gov.uk
John Kerr – Housing Development and Homelessness
Manager
E-mail: john.kerr@west-dunbarton.gov.uk
Appendices: Appendix 1: HRA Capital Projects Forecast
Outturn and Slippage 2025/26
Appendix 2: HRA Capital Investment Plan
2026/27 – 2030/31
Appendix 3: HRA Draft Revenue Estimate
2026/27 Summary
Appendix 4: HRA Draft Revenue Estimate
2026/27 Explanation of Movements
Appendix 5: Consultation Summary  
Background Papers: EIA screening
Wards Affected All

Page 12