WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer – Resources
Council:  17 December 2025
_______________________________________________________________________________
Subject: Review of West Dunbartonshire Council’s Capital Programme
1. PURPOSE
1.1 To provide Council with the outcome of a review of the Council’s capital
programme and present recommendations to reduce the capital
programme in response to concerns about financial sustainability.
2. RECOMMENDATIONS
2.1 It is recommended Members:
i) Approve the removal of the 7 projects listed in Exhibit 4a
of the report from the Council’s capital plan
ii) Approve reduced budget allocations to the 6 projects listed
in Exhibit 5a of the report.
iii) Approve reduced budget allocations to the 4 recurring
budget lines listed in Exhibit 6a of the report.
iv) Note these amendments will remove a total of £7.169m
capital expenditure from the Council’s long term capital
programme and generate an estimated £0.154m in revenue
savings in 2025/26.
v) Note these amendments will reduce the budget gap in
2026/27 by £0.248m, 2027/28 by £0.353m, 2028/29 by
£0.433m, 2029/30 by £0.441m and 2030/31 by £0.156m
3. BACKGROUND
3.1 On 5 March 2025, the Council agreed an updated Capital Plan with a
range of specific projects and also recurring projects for areas where it
is recognised there needs to be a degree of capital spend each year
(for example building upgrades, roads maintenance, vehicle
replacement etc).
3.2 The Capital Plan profiles capital expenditure over the life of the plan.
Exhibit 1 summarises that profiled expenditure over the period to
2033/34.
Exhibit 1 - Summary of Capital Expenditure as at March 2025 Budget Meeting (costs in £000)
Service No 25/26 26/27 27/28 28/29 29/30 30/31 31/32 32/33 33/34
Total
25/26-
33/34
Recurring 14 17,024 13,341 11,920 11,216 10,863 10,863 10,863 10,622 10,997 107,709
RES* 14 4,831 5,175 386 0 0 0 0 0 0 10,391
R&R* 13 8,584 14,503 4,123 0 0 0 0 0 0 27,210
ITEM 20

Page 2

R&N* 28 31,435 17,410 10,938 100 100 100 100 100 100 60,382
EDU* 5 12,343 2,854 100 100 107 0 0 0 0 15,504
P&T* 3 346 48 49 49 59 0 0 0 0 551
Total 77 74,562 53,331 27,516 11,465 11,129 10,963 10,963 10,722 11,097 221,748
*RES – Resources
*R&R – Regulatory & Regeneration
*R&N – Roads & Neighborhood
*EDU – Education
*P&T – People & Technology
3.3 The Council receives a general capital grant from the Scottish
Government each year (approximately £6m). Any spend above this
level, not funded from other grants, is funded through borrowing. Capital
spend funded from borrowing results in loan charges until the borrowing
is fully repaid. Exhibit 2 summarises how the capital expenditure in each
of the years between 2025/26 and 2033/34 is currently projected to be
financed.
Exhibit 2 - Financing the Capital Programme 2025/26-2033/34
Service 25/26 26/27 27/28 28/29 29/30 30/31 31/32 32/33 33/34
Total
25/26-
33/34
Borrowing 20,365 38,127 20,323 7,140 6,804 6,638 6,638 6,397 6,772 119,204
Ring Fenced
Capital Grant
21,887 8,345 2,299 0 0 0 0 0 0 32,531
General
Capital Grant
18,704 3,407 3,407 3,407 3,407 3,407 3,407 3,407 3,407 45,960
Matched
Funding
2,037 1,098 912 818 818 818 818 818 818 8,955
Other 11,569 2,354 575 100 100 100 100 100 100 15,098
Total 74,562 53,331 27,516 11,465 11,129 10,963 10,963 10,722 11,097 221,748
3.4 Exhibit 2 shows the Council’s current capital programme will require
£119.204m of prudential borrowing over the period 2025/26 to 2033/34
based on current projections. That represents 54% of the total planned
capital programme expenditure.
4. MAIN ISSUES
Financial Sustainability of the Capital Programme
4.1 The ongoing financial pressures continue to have a significant impact
on both the sustainability and delivery of the Council’s capital
programme.
Cost Escalation
4.2 Persistent inflationary trends across construction and related sectors
have driven up the cost of materials, labour, and specialist services.
Contractors and suppliers are increasingly incorporating risk premiums
to cover anticipated future price increases, particularly for projects with
extended delivery timelines. It is reasonable to assume that any
projects costed within the last 12–18 months may now require

Page 3

materially higher budgets than those currently reflected in the Capital
Plan.
Emerging Risks for 2025/26–2033/34
4.3 In addition to inflation several emerging factors will influence the cost of
the Capital programme over the medium term:
o Decarbonisation Requirements: increasing regulatory and policy
commitments to achieve net-zero emissions will require
investment in sustainable materials and technologies, often at a
premium cost.
o Interest Rate Volatility: higher borrowing costs could reduce the
Council’s capacity to finance large-scale projects without
impacting revenue budgets.
o Skills Shortages: labour market constraints in construction and
engineering sectors may lead to higher contractor rates and
longer project timelines.
o Technological Obsolescence: rapid changes in ICT and fleet
technology will necessitate more frequent upgrades, increasing
recurring capital demands.
Cost of Funding the Capital Programme
4.4 As shown in Exhibits 1 and 2, the revised Capital programme allocates
a total capital budget of £221.748m over the period 2025/26 to
2033/34. The programme continues to be funded through a
combination of borrowing, Scottish Government grants, and other
external sources:
o Borrowing: £119.204m (54% of total) will be financed through
borrowing, making the programme highly sensitive to interest
rate movements and debt servicing costs.
o General Capital Grant: £45.960m is expected from the Scottish
Government’s General Capital Grant.
o Ring-Fenced Grants: £32.531m linked to specific projects and
subject to strict eligibility criteria.
o Other Sources: Matched funding and other contributions total
approximately £24.053m, but these often require competitive
bidding and partnership arrangements.
Given the reliance on borrowing and the volatility of interest rates, the
financial sustainability of the programme remains a key concern.
Implications for Capital Plan Review
4.5 These financial and operational pressures highlight the need for a
comprehensive review of the capital programme to ensure investment
priorities remain deliverable within the Council’s financial capacity.
Impact of Interest Rate Movements and Cost Inflation

Page 4

4.6 It is widely recognised that interest rates have risen significantly
compared to previous projections, placing additional pressure on the
financial sustainability of the Capital Programme.
Public Works Loan Board (PWLB) borrowing rates currently sit at
approximately 4.5%, whereas in March 2022, when the Capital Plan
was last subject to a comprehensive review, long-term borrowing of up
to 10 years could be secured at around 2.3%.
To illustrate the impact, in 2022, a capital project costing £10m at an
interest rate of 2.3% repaid over 40 years would have resulted in a total
payback of £14.7m. At current PWLB rates of 4.5%, the payback rises
to £19.2m, an increase of £4.5m or 31%.
Impact of Capital Spend on Future Revenue Budgets
4.7 The repayment of borrowing used to fund capital projects creates a
long term revenue budget commitment over the lifespan of the asset.
Additional borrowing to fund higher-cost projects will increase the
Council’s overall debt position and result in substantial interest charges
and repayment of the loan principal.
4.8 The Council has a statutory obligation to balance its budgets. The
revenue budget continues to face significant pressure. Higher interest
rates have further compounded these challenges, meaning any new
capital investment will add additional strain to the loans charges
element of the revenue budget. Members should also note that, beyond
the increased cost of financing, completed assets often bring additional
ongoing revenue commitments for maintenance, lifecycle replacement,
and operational costs.
4.9 Decisions on future capital investment must focus on achieving best
value for money for the Council. This includes prioritising projects that
safeguard essential services, mitigate key risks, and align with statutory
and strategic objectives.
Approach to Review of the Capital Programme
4.10 This review of the Council’s capital programme builds on the review in
2022 where Council agreed to reduce the plan by £31.985m. It has
focused on non-recurring projects considered non-essential or
discretionary and annual recurring projects where the value remains
static year on year and could be reduced.
o
4.11 The capital programme was reviewed by a sub-group of the Strategic
Asset Management Group, chaired by the Chief Officer Resources.
Initial proposals and questions were issued to all Chief Officers
regarding projects allocated to their services and opportunities
provided to Chief Officers to provide detailed programmes in respect of
the recurring programmes.  Responses and feedback were considered
and informed the recommendations set out in this report.

Page 5

4.12 For each line in the Capital Programme, a recommended action has
been identified:
 Remove – cancel the project.
 Reduce – reduce the allocated budget over the life of the
programme.
 Keep – retain the project with no changes.
Financial Impact of Recommended Actions
4.13 If the recommendations in this report are fully accepted then:
o Removed Projects: Seven projects with a combined capital
budget of £0.408m in 2025/26 and additional allocations in
future years (2026/27–2029/30) of £2.104m, making an overall
reduction of £2.512m.
o Reduced Specific Projects: Six projects, with a combined capital
budget reduction of £1.511m in 2025/26 and additional
reductions in future years (2026/27–2029/30) totaling £0.388m,
giving an overall reduction of £1.899m
o Reduced Recurring Project: Four projects, with a combined
capital budget of £0.230m in 2025/26 and additional allocations
in future years (2026/27–2033/34) totaling £2.528m, giving an
overall reduction of £2.758m across the programme period.
These reductions reflect adjustments to recurring projects to
align with revised priorities and affordability constraints.
Following the latest review and re-profiling exercise for the 2025/26
capital programme, the combined effect of these changes will reduce
the overall capital programme by £7.169m across the period 2025/26 to
2033/34. This will deliver revenue savings in 2025/26 of £0.154m and
reduce future budget gaps by:
2026/27 – £0.248m
2027/28 - £0.353m
2028/29 - £0.433m
2029/30 - £0.441m
2030/31 – £0.156m
It will also generate further revenue savings beyond 2030/31 due to the
ongoing reductions in the recurring capital budgets and consequential
reductions in loan charges.  These have not been calculated at the
current time as the Council’s future budget estimates only extend to 5
years and loan charges estimates are reviewed on an annual basis.
These changes improve affordability and ensure that planned
expenditure is aligned with realistic delivery schedules and revised
priorities.
4.14 Exhibits 4a – 6c summarise the rationale for each project removed or
reduced and the capital and revenue impacts of the recommended
action.

Page 6

Exhibit 4a – Projects Recommended for Removal
Service Project Rationale
RES 7 New Sports Changing Facility
Dumbarton West
Minor spend to date and project has not
progressed for an extended period of time
due to site constraints.  The demand for a
facility in this location is currently unknown.
RR 1 Legal Case Management
System
Service has confirmed system is no longer
required.
RR 2 Installation of Solar PV at
Clydebank Leisure Centre
Project has not progressed for an extended
period.  If a future requirement is
recognised a capital bid can be submitted
to reflect estimated costs and a programme
of works.
RR 3 Leisure Energy projects - air
handling units, upgrade
lighting, circulating pumps, and
draught proofing
Project has not progressed for an extended
period.  Consideration will be given whether
this can sit within an existing revenue or
capital budget for service area or a capital
bid could be submitted once future costs
and programme are known.
RR11 Securing sites to make safe As reported to Infrastructure Regeneration
and Economic Development Committee on
21 May 2025 this project has been
completed.  The residual budget should
have been removed at that time however 
was carried forward in error.  This removal
corrects that error.
RN 17 Waste Transfer Station The project has not progressed and is
currently on hold. Some expenditure has
been incurred for work which will inform
and support the development of a future
project when it is resumed.
RN 22 Kilmaronock Cemetery
Extension
Excess budget with no spend allocated for
remainder of financial year.
Exhibit 4b – Reduction in Capital for Projects Recommended for Removal
Service Project Budget
2025/26
(£m)
Budget
2026/27
(£m)
Budget
2027/28
(£m)
Budget
2028/29
(£m)
Budget
2029/30
(£m)
Project
Life
(£m)
RES 7 New Sports
Changing
Facility
Dumbarton
West
0.340 0 0 0 0 0.340
RR 1 Legal Case
Management
System
0.033 0 0 0 0 0.033
RR 2 Installation of
Solar PV at
Clydebank
Leisure
Centre
0 0.057 0 0 0 0.057
RR 3 Leisure
Energy
projects 
0 0.226 0 0 0 0.226

Page 7

RR11 Securing sites
to make safe
0.030 0 0 0 0 0.030
RN 17 Waste
Transfer
Station
0 0 0 1.821 0 1.821
RN 22 Kilmaronock
Cemetery
Extension
0.005 0 0 0 0 0.005
Totals 0.408 0.283 0 1.821 0 2.512
Exhibit 4c – Revenue Savings for Projects Recommended for Removal
Service Project Budget
2025/26
(£m)
Budget
2026/27
(£m)
Budget
2027/28
(£m)
Budget
2028/29
(£m)
Budget
2029/30
(£m)
Total
Saving
(£m)
RES 7 New Sports
Changing
Facility
Dumbarton
West
0.024 0.023 0.023 0.023 0.022 0.115
RR 1 Legal Case
Management
System
0.003 0.003 0.003 0.003 0.002 0.014
RR 2 Installation of
Solar PV at
Clydebank
Leisure
Centre
0 0.005 0.005 0.005 0.004 0.019
RR 3 Leisure
Energy
projects
0 0.019 0.018 0.018 0.017 0.072
RR11 Securing
sites to make
safe
0.002 0.002 0.002 0.002 0.002 0.01
RN 17 Waste
Transfer
Station
0 0 0 0.127 0.127 0.254
RN 22 Kilmaronock
Cemetery
Extension
0.001 0.001 0.001 0.001 0.001 0.005
Totals 0.030 0.053 0.052 0.179 0.175 0.489
Exhibit 5a – Projects Recommended for Capital Budget Reduction
Service Project Rationale
RES 11 Finance
Ledger
System
Project reduced by £0.200m in line with anticipated
costs.
RN 9 A813 Road
Improvement
Phase 1
Footway upgrade including improvement to road
crossing and repositioning of street lights
programmed for February 2026. Future design works
for phase 2 have not commenced and a future capital
bid will be brought forward with detailed programme
and costs once known.
RN 12 River Leven
Flood
Budget reduced to £200k to complete the first phase
of works.  A future capital bid will be brought forward

Page 8

Prevention
Scheme
with detailed programme and costs for any project
identified from the feasibility study for possible future
phases.
RN 19 East End Park
Resurfacing
Budget reduced to reflect spend to date of £0.024m
plus an additional £0.010m for repair costs to
damaged pitch surface.
RN 23 Creation of 3
new all
weather
pitches.
Budget reduced by £0.799m due to the delivery of an
all weather pitch at Lachie Stewart Memorial Park not
being achieved. 
P&T 4 Development
of Workforce
Management
System
Budget reduced by £0.188m to reflect  amended
breakdown of spend profile provided by service
Exhibit 5b – Reduction in Capital for Projects Recommended for Reduction
Service Project Budget
2025/26
(£m)
Budget
2026/27
(£m)
Budget
2027/28
(£m)
Budget
2028/29
(£m)
Budget
2029/30
(£m)
Project
Life
(£m)
RES 11 Finance
Ledger
System
0 0.200 0 0 0 0.200
RN9 A813 Road
Improvement
Phase 1
0.121 0 0 0 0 0.121
RN12 River Leven
Flood
Prevention
Scheme
0.420 0 0 0 0 0.420
RN 19 East End
Park
Resurfacing
0.171 0 0 0 0 0.171
RN 23 Creation of 3
new all
weather
pitches
0.799 0 0 0 0 0.799
P&T 4 Development
of Workforce
Management
System
0 0.031 0.049 0.049 0.059 0.188
Total 1.511 0.231 0.049 0.049 0.059 1.899
Exhibit 5c – Revenue Implications of Projects Recommended for Reduction
Service Project Budget
2025/26
(£m)
Budget
2026/27
(£m)
Budget
2027/28
(£m)
Budget
2028/29
(£m)
Budget
2029/30
(£m)
Total
Saving
(£m)
RES 11 Finance
Ledger
System
0 0.017 0.016 0.016 0.016 0.065
RN9 A813 Road
Improvement
Phase 1
0.008 0.008 0.008 0.008 0 0.032

Page 9

RN12 River Leven
Flooding
Scheme
0.029 0.029 0.028 0.028 0.028 0.142
RN 19 East End
Park
Resurfacing
0.014 0.014 0.014 0.013 0.013 0.068
RN 23 Creation of 3
new all
weather
pitches
0.056 0.055 0.054 0.053 0.052 0.270
P&T 4 Development
of Workforce
Management
System
0 0.003 0.007 0.011 0.015 0.036
Total 0.107 0.126 0.127 0.129 0.124 0.613
Exhibit 6a – Recurring Projects Recommended for Reduction
Service Project Rationale
RR4 Regeneration/Local
Economic
Development
Several allocations have been removed as they were
aspirational, not legally committed, or better funded
through alternative sources such as the Levelling Up
Fund. Key strategic items like Dumbarton High Street
feasibility, Balloch Pierhead Masterplan, and long-
term staffing commitments remain in the plan to
support ongoing regeneration and planning priorities.
RN 13 Public non-adopted
paths and roads
Project reduced by 25%. No current detailed
programme of works.  Over the last three years the
budget has been underspent between £0.200m and
£0.400m each year. A potential risk for future increase
in insurance claims may occur.
HSCP 2 ICT Modernisation
HSCP
Project reduced by £0.050m in 2025/26 and £0.100m
per financial year from 2026/27 onwards. This reflects
spend profile provided by the service while leaving a
small residual balance to absorb any potential cost
increases. The budget line has been underspent year
on year. 
HSCP 3 Community Alarm
upgrade
Project reduced in future years 2027/28 – 2033/34 to
nil in line with programme provided by service.   
Exhibit 6b – Reduction in Capital for Recurring Projects Recommended for Reduction
Project 25/26
(£m)
26/27
(£m)
27/28
(£m)
28/29
(£m)
29/30
(£m)
30/31
(£m)
31/32
(£m)
32/33
(£m)
33/34
(£m)
Project
Life
(£m)
RR4
Regeneration/Local
Economic
Development
0.180 0.570 0.250 0.108 0.025 0.025 0.025 0.025 0.025 1.233
RN13 Public non-adopted
paths and roads
0 0.056 0.056 0.056 0.056 0.056 0.056 0.056 0.056 0.448
HSCP 2 ICT Modernisation
HSCP
0.050 0.100 0.100 0.100 0.100 0.100 0.100 0.100 0.100 0.850
HSCP 3 Community Alarm
upgrade
0 0 0.036 0.040 0.042 0 0 0.042 0.067 0.551
Total 0.230 0.726 0.442 0.304 0.223 0.181 0.181 0.223 0.248 2.758
Exhibit 6c – Revenue Implications of Recurring Projects Recommended for Reduction

Page 10

Service Project 25/26
(£m)
26/27
(£m)
27/28
(£m)
28/29
(£m)
29/30
(£m)
30/31
(£m)
31/32
(£m)
32/33
(£m)
33/34
(£m)
Total
Saving
(£m)
RR 4
Regeneration/Local
Economic
Development
0.013 0.053 0.07 0.078 0.079 0.081 0.083 0.085 0.086 0.628
RN 13 Public non-adopted
paths and roads
0.000 0.004 0.008 0.012 0.016 0.020 0.024 0.027 0.031 0.142
HSCP 2 ICT Modernisation
HSCP
0.004 0.012 0.021 0.029 0.037 0.045 0.054 0.062 0.07 0.334
HSCP 3 Community Alarm
upgrade
0 0 0.003 0.006 0.01 0.01 0.01 0.013 0.019 0.071
Total 0.017 0.069 0.174 0.125 0.142 0.156 0.171 0.187 0.206 1.175
Future Additions to the Capital Programme
4.15 Since December 2022, the Council has implemented a robust
assessment and risk prioritisation process for all future bids for
additions to the Capital Programme. This process is managed by the
Strategic Asset Management Group and includes input and
recommendations from the Chief Officer: Resources. 
4.16 Services submitting a request for a new capital project are required to
complete a detailed bid form, providing comprehensive information on
financial implications, alignment with the Council’s corporate objectives
and Strategic Plan, and any statutory or legal requirements.
Consideration is also given to service delivery impact, risk mitigation,
and potential financial benefits.
While services score their bids against these categories, all
submissions are subject to review by the Strategic Asset Management
Group to ensure consistency and fairness in the scoring process.
4.17 New capital bids can be considered throughout the year to address
emerging Council and service demands. These bids are assessed
through the established prioritisation process and, where appropriate,
are presented to Council and relevant committees via the regular
budgetary control reporting cycle.  This approach ensures flexibility to
respond to changing needs while maintaining strong governance,
transparency, and consistency in decision-making.
5. PEOPLE IMPLICATIONS
5.1 The reduction in the capital programme may have a direct impact on
staffing requirements.  As fewer projects progress, the demand for
project management and delivery resources will decrease. 
However, at this stage, until service areas review their capital
programme and other workstreams, the extent of these implications
cannot be definitive.
6. FINANCIAL AND PROCUREMENT IMPLICATIONS
6.1 Sets out the options to reduce the capital budget expenditure and
associated revenue impact.

Page 11

6.2 There are no procurement recommendations as a result of this report.
7. RISK ANALYSIS
7.1 Reductions in the Capital Programme, particularly in recurring service
budgets, may have a detrimental impact on service delivery and could
lead to an increase in complaints. In the current financial context, these
risks are heightened by several factors:
o Asset Deterioration: deferring or cancelling projects may
accelerate the decline of ageing infrastructure, resulting in
higher repair and maintenance costs and potential service
interruptions.
o Health and Safety Compliance: reduced investment could
compromise compliance with statutory obligations, increasing
the risk of incidents and associated liabilities.
o Impact on Strategic Objectives: scaling back projects may delay
progress on key priorities such as net-zero commitments, digital
transformation, and community regeneration.
o Operational Pressures: services may face increased operational
challenges if essential upgrades to ICT, fleet, or property assets
are postponed, affecting efficiency and resilience.
o Reputational Risk: service reductions or delays in planned
improvements could lead to negative public perception and
increased complaints, particularly where expectations have
already been set.
o Financial Consequences: short-term savings may result in long-
term cost escalation due to emergency repairs, higher borrowing
costs for future catch-up investment, and potential loss of
external funding tied to specific projects.
8. EQUALITIES IMPACT ASSESSMENT (EIA)
8.1 None of the proposed amendments to the capital programme are
anticipated to have a differential impact on individuals or groups with
protected characteristics under the Equality Act 2010.  As such, a
formal Equality Impact Assessment (EIA) is not considered necessary.
However, the Council will continue to monitor the implementation of
these changes to ensure that equality considerations remain fully
addressed.
9. CONSULTATION
9.1 The views of all Chief Officers have been requested on this report and
feedback incorporated herein.
10. STRATEGIC ASSESSMENT
10.1 In alignment with the West Dunbartonshire Council Strategic Plan
2022–2027, this report demonstrates that reviewing and reprioritising
the capital programme supports the delivery of key priorities:

Page 12

o Our Communities – Resilient and Thriving: By prioritising
essential infrastructure and assets, the review ensures that
services remain accessible, safe, and responsive to local needs,
promoting wellbeing and resilience across West Dunbartonshire.
o Our Economy – Strong and Flourishing: The revised programme
focuses on sustainable and financially viable investment,
supporting efficient use of resources and enabling projects that
contribute to economic growth and regeneration.
o Our Council – Inclusive and Adaptable: The review reflects the
Council’s commitment to sound financial governance and
transparent decision-making, ensuring that capital investment
remains adaptable to changing demands and fiscal realities.
Through this review, the Council reinforces its commitment to these
strategic priorities, ensuring that capital investment decisions deliver
long-term value, maintain essential services, and support the
achievement of the Strategic Plan objectives.
Laurence Slavin
Chief Officer – Resources
Date: 04 December 2025
Person to Contact: Laurence Slavin, Chief Officer - Resources
Email: Laurence.Slavin@west-dunbarton.gov.uk
Appendices: None
Background Papers:        Report by Chief Officer: Resources to Council 21
December 2022: Review of West Dunbartonshire
Council’s Capital Programme
Report by Chief Officer: Resources to Council 5 March 
2025: Capital Strategy 2025/25 to 2033/34
Wards Affected:               All