WEST DUNBARTONSHIRE COUNCIL 
Report by Chief Officer Roads and Neighbourhood
West Dunbartonshire Council – 17 December 2025 
Subject: Gruggies Burn Flood Alleviation Scheme 
1. Purpose 
1.1 The purpose of this report is to update members on the progress
delivering the Gruggies Burn Flood Alleviation Scheme, advise of
associated costs and confirm the Scottish Government funding position. 
2. Recommendations 
2.1 It is recommended that Council: 
i) Note that, following development of the detailed design, the costs of
the Gruggies Burn Scheme have significantly increased since
scheme conception in 2016. 
ii) Approve option 3 to construct coastal defences and flood gate as
set out in paragraphs 4.27 to 4.32. This requires a total West
Dunbartonshire capital investment of £2.94m which translates to
a revenue impact of £0.137m per annum for a 40-year period to
repay the loan and the incurred interest. 
iii) Note the funding milestone of 31 March 2026 for construction
tender award. 
iv) Note that, should Option 2 or Option 3 be approved for delivery,
the Council will liaise with the Scottish Government to confirm
funding will be awarded for part implementation in advance of
contract award.  If the Scottish Government do not confirm
positively a further report will be brought to Council. 
v) Authorise the Chief Officer Regulatory and Regeneration to
conclude negotiations in relation to the finalisation and signing of
the construction contract. 
vi) Grant delegated authority to Chief Officer Roads and
Neighbourhood and Chief Officer Regulatory and Regeneration,
in consultation with the Procurement Manager, to award any
procurement and contract awards related to Gruggies Burn Flood
Alleviation Scheme using appropriate procurement routes. 
ITEM 14 
(Revised Version)
Page 259

Page 2

3. Background 
3.1 The Flood Risk Management (Scotland) Act 2009 established a modern
framework for managing flood risk across Scotland. It aims to reduce the
harmful effects of flooding on people, property and the environment through
sustainable and coordinated planning. 
3.2 The Flood Risk Management Act established three 6 year cycles of actions
with the Scottish Government committing £420m of funding for schemes
identified in Cycle 1. 42 schemes were identified across Scotland through this
process with funding to be provided over a 10 year period.   
3.3 West Dunbartonshire Council’s (the Council) Gruggies Burn Flood
Alleviation project was one of the Cycle 1 schemes identified and
prioritised through this process. 
3.4 The Flood Risk Plan for Dumbarton was originally completed in 2012. One of
the flood actions highlighted in that report was the development of a flood
alleviation scheme for the Gruggies Burn. 
3.5 The Gruggies Burn is an open watercourse approximately 1 mile long from
the meeting of the Garshake and Overtoun Burns to the outfall on the estuary
of the Clyde. It has steep fast moving culverted sections with 4 road crossings
and 1 footpath crossing, with a tidally influenced outfall. Due to this the burn
has two main historic flood paths – Fluvial (Watercourse) and Tidal. 
3.6 Fluvial flooding occurs from the burn overspilling in periods of heavy rainfall
but also overflowing in constrained culvert sections from Castlegreen Street to
Glasgow Road. This can result in flooding of a number of properties in the
Dumbarton East Area, including Castlegreen Street, Glasgow Road,
Buchanan Street and the surrounding area. 
3.7 Tidal flooding occurs from backwater effects from the Clyde during high tide or
storm surge combined with a strong southwestern wind. This reduces
discharge capacity and results in back up in the burn and overflowing
upstream. 
3.8 There are records of flooding from the burn causing minor temporary flooding
going back to the 1950s including a few events recorded in the 1990s, with
increasing reports in the 2000s. Since the late 2000s there has been an
increase in precipitation levels which has resulted in more fluvial flooding from
the burn, with reports of at least 1 flood event annually since 2002, the most
significant being in 2007.   
3.9 There are limited reports of significant impacts from tidal flooding alone, with
most instances short lived and quickly dissipating as tide levels reduce. 
3.10 Large scale flooding events occur during high tide or storm surge events
combined with periods of heavy rainfall. This was last experienced in October
2023 with flooding to properties, businesses and significant disruption to the
transport network. 
Page 260

Page 3

3.11 The initial scheme was developed and submitted to the Scottish Government
for prioritisation and funding as part of the Cycle 1 funding. The scheme costs
were expected to be £20m. At that stage however only high-level assessment
and design had been undertaken. 
3.12 All projects identified through this process were awarded grant funding of
80% of the scheme costs with the remaining 20% to be funded by the
Local Authority. 
3.13 The Gruggies Burn Flood Alleviation Scheme was awarded grant funding of
£16m by the Scottish Government in 2016 as a Cycle 1 Scheme. A breakdown
of the initial project costs and funding is shown below. 
Initial Project Funding £(m)
Total Original Scheme Costs 20
West Dunbartonshire Council Funding (20%) 4
Scottish Government Funding (80%) 16 
3.14 A large portion of Cycle 1 schemes in other councils as well as the
Gruggies Burn Scheme reported significantly increased costs from their
initial design. Consequently, the total funding available for all the Cycle 1
schemes was insufficient. The Scottish Government instructed a pause on
all scheme progression in 2019 until funding levels could be reviewed and
agreed. 
3.15 Although progress was initially paused, in September 2021 the IRED
Committee approved that Council capital funds be made available to
continue to progress the detailed design of the scheme whilst awaiting a
decision at national level.  This has been progressed since that approval
was granted. 
3.16 The Scottish Government, after review, allowed projects to progress in
2022 however to ensure that Cycle 1 could be concluded placed several
conditions on the projects identified. 
3.17 As a result, all local authorities wishing to progress their projects had to: 
1. Confirm their intention to undertake the works by October 2023.
2. Undertake all public consultation and notify the project by March 2024
3. Complete all design works and have the contract awarded by March
2026. 
Any local authority who fails to achieve any of the above targets would not
be funded for the schemes identified.  
Page 261

Page 4

4. Main Issues 
4.1 Committee approved our intention to progress the project in September
2021 and the Council undertook the required design and consultation
works which allowed for the project to be notified to meet the deadline of
31st March 2024. 
4.2 The Council also progressed the final detailed design to allow us to
meet the final deadline of 31st March 2026 for tender award. 
4.3 All design work has been delivered through the SCAPE Civil
Engineering Framework by Balfour Beatty. Through undertaking the
design works the Council have been able to regularly review costs and
ensure ability for appointment of the construction contract in time to
meet the required deadline. 
4.4 Like many other projects identified in Cycle 1, the original estimated
costs were based on a high-level assessment of the potential works
involved. As detailed designs have progressed, the construction
elements of the project have been assessed in more detail, and with
more accurate estimates of the expected cost determined. 
4.5 In addition to more clarity on the scale of works involved there has been
a significant increase in construction costs including the impact of
inflation. Additionally, the Scottish Environment Protection Agency now
require schemes to factor in a 40% adjustment for the effects of climate
change which has resulted in increased capacity requirements within
the scheme.   
4.6 The full project will include several key elements: 
1. Installation of 4m wide diversion culvert from Strowans Well Road to
outfall at Hunter Burn into the River Clyde
2. Construction of a new inlet structure to slow down the water and divert
the water from the Gruggies Burn into the diversion culvert
3. Construction of new coastal defence walls
4. Coastal embankments
5. Flood gate 
4.7 The cost to deliver the full scheme and all benefits is now estimated to
be £44.7m. In addition to the construction costs this includes all
preliminary site investigation and design works, all anticipated major
utility service diversions and various ancillary works to facilitate the
delivery of the project. 
4.8 Although costs have increased significantly, the Council has been
working with the designers to minimise construction costs. Through a
value engineering exercise, which has included the implementation of
an innovative hybrid high grade PVC/Concrete culvert approach,
savings have been made.
Page 262

Page 5

4.9 The Council will continue to explore any cost saving opportunities
throughout the project stages. 
4.10 The Scottish Government have been kept updated throughout the
design process on the projected costs and the Council have been
seeking assurances that the funding levels provided will remain at 80%
of the overall costs at final tender stage rather than the original £20m
estimate. 
4.11 A letter provided by the Scottish Government on 5th November 2025
confirmed the agreed position is that the grant will be fixed at 80% of
costs when the scheme costs are confirmed after tender stage. 
4.12 The letter does highlight that, as the grant will be fixed at the final tender
stage, should any additional costs exceed this value no additional grant
is payable. A level of bias has been included in the predicted figures
and tender process to accommodate a level of unforeseen risk. 
4.13 As funding levels could not be confirmed and the potential increased
costs to the Council were not clear, a phased construction approach
was incorporated into the design so consideration could be given to
partial installation should funding levels require. 
4.14 Through this approach 4 options have been developed for members to
consider. 
• Option 1 – Full Scheme Delivery
• Option 2 – Delivery of Inlet and Diversion Culvert 
• Option 3 – Delivery of Coastal Defences and Flood Gates
• Option 4 – Do Nothing 
4.15 When considering the four options set out below Council should be
mindful of the need to balance affordability and the delivery of flood
prevention.  The Council has one of the highest ratios of financing costs
to net revenue of all 32 Scottish councils and material increases to the
capital programme will have a consequential impact on the Council’s
revenue budget gap in future years due to the loan charges associated
with any borrowing.  Option 1 would be broadly equivalent to a 1.0%
increase in Council Tax. This is summarised in the Financial and
Procurement Implications of this report at paragraph 6.1. 
Option 1 – Full Scheme Delivery 
4.16 Option 1 is the full delivery of the scheme and will ensure the
anticipated overall benefits for local residents are achieved, however
with the requirement for 20% contribution of funding it requires the
largest capital investment from the Council. 
4.17 This would require a total capital investment of £8.94m from the
Council, which is an additional £4.94m on the original value.
Page 263

Page 6

4.18 Full scheme delivery provides the biggest reduction in flood risk to the
area and delivers on the information provided to elected members and
residents throughout the consultation process. 
4.19 A cost benefit analysis for the full scheme highlights that 631 properties
will benefit from reduced flood risk against fluvial (river) and pluvial
(surface water) events. The whole life benefit cost for the full delivery of
the project would be £70m. Overall the project provides a cost benefit
ratio of 1.64. For a scheme to be considered to deliver a benefit a cost
benefit ratio should be in excess of 1.0.  
4.20 Option 1 – Full Scheme Capital Costs Summary 
£(m)
West Dunbartonshire Council Funding (20%) 8.94
Scottish Government Funding (80%) 35.76
Total Scheme Costs 44.70 
Option 2 – New Inlet and Diversion Culvert 
4.21 The primary benefit of the scheme comes from the construction of the
culvert and weir as the primary source of flooding is identified as
watercourse and surface water flood risk. Option 2 allows for the
delivery of the main benefits of the scheme but reduces the expected
Council contribution. 
4.22 This approach also ensures the Council maximises the opportunity for
the local area from the available Scottish Government funding whilst
leaving the smallest elements with the lower overall benefit to be
delivered at a later stage should additional funding become available. 
4.23 Of the two partial delivery options the construction of the culvert and
weir provides the highest reduction in flood risk and addresses the most
frequent flood issues in the Dumbarton area. 
4.24 If progressing with this option, the Council would likely receive limited
public negativity as it delivers the main objectives of the scheme and
leaves the potential for the coastal elements to be delivered at a later
date. 
4.25 This option only reduces the number of properties benefiting by 5 to 626
properties. However, it should be noted these properties would only be
protected against fluvial risk.  305 of the properties in the area would still
be at risk of tidal flooding when tide levels are high. The whole life cost
benefit for this option is £44m and the cost benefit ratio is 1.18.   
Page 264

Page 7

4.26 Option 2 – Construction of Culvert and Inlet Capital Cost Summary 
£(m)
West Dunbartonshire Council Funding (20%) 7.84
Scottish Government Funding (80%) 31.36
Total Culvert Scheme Costs 39.20 
Option 3 – Construction of Coastal Defences and Flood Gate Only 
4.27 Coastal flooding in this area only occurs in periods of high tide when
water levels in the burn are increased due to the volume of rainfall. In
these circumstances although a proportion of properties are at risk of
flooding, water levels can quickly dissipate as the tide level reduces. 
4.28 This option provides the lowest overall benefit to the area.  Full
confirmation of Scottish Government funding is required in advance of
the contract award for a phased implementation. 
4.29 It is likely that progressing with this option alone may receive public
criticism as it would fail to deliver on a significant portion of the
scheme’s aims and objectives. As any Scottish Government funding in
future years is likely to be focused on Cycle 2 delivery it is unlikely this
scheme would receive further funding. 
4.30 The delivery of option 3 will provide a benefit to 310 properties in total
with this risk being restricted to tidal flooding only. There would be no
benefit or protection provided for flooding resulting from heavy rain or
capacity issues within the Gruggies Burn. 
4.31 The cost benefit ratio is the highest at 2.05 due to the significant
reduction in overall costs and has a whole life cost benefit of £26m. 
4.32 Option 3 – Construction of Coastal Defences  Capital Cost Summary 
£(m)
West Dunbartonshire Council Funding (20%) 2.94
Scottish Government Funding (80%) 11.76
Total Original Scheme Costs 14.70    
Option 4 - Do Nothing 
4.33 Given the significant increase in the capital cost of the project since its
inception and the consequential increase in the revenue costs (for
example option 1 creating a revenue pressure of £0.419m per annum
due to loan charges) the Council could decide not to proceed with the
project.  
Page 265

Page 8

4.34 Under the terms of the Flood Risk Management Act (Scotland) the
Council has various responsibilities in relation to mapping, evaluating,
and maintaining our watercourses as well as developing flood risk
management plans for the area. 
4.35 The purpose of the Flood Risk Management Plan is to evaluate the
current flood risk and identify potential interventions which could be
introduced to reduce flood risk for that area. 
4.36 Any cancellation of the project would require all capital expenditure
incurred to date to be transferred to the revenue budget as there is no
capital asset being created. The costs incurred to date are £1.98m
which would need to be funded from Council reserves. 
4.37 All consultations and notifications undertaken throughout the
development of the scheme have set out the full delivery of the scheme.
It is anticipated that the cancellation of the scheme would result in
reputational damage to the Council. 
4.38 Option 4 – Do Nothing Revenue Cost Summary 
£(m)
West Dunbartonshire Council Funding (100%) 1.98
Total Costs Incurred to Date 1.98 
4.39 Overall Option Summary 
Initial
Estimate
Option
1
Option
2
Option
3
Option
4
Total  £20m £44.7m £39.2m £14.7m £1.98m
West
Dunbartonshire
Council
Contribution (20%)
£4.0m £8.94m £7.84m £2.94m  £1.98m
Scottish
Government
Contribution (80%)
£16.0m £35.76m £31.36m £11.76m  N/A
Whole Life Cost
Benefit  £70m £44m £26m N/A
Cost Benefit Ratio  1.64 1.18 2.05 N/A
Properties
Protected 370 631 626 310 N/A 
The initial estimate was based on full delivery of the scheme in 2016.  
Page 266

Page 9

5. People Implications 
5.1   There are no people implications associated with this proposal. 
6. Financial and Procurement Implications 
6.1  Taking account of the contributions anticipated from the Scottish
Government the capital cost increase to the Council for full project
delivery is £4.94m additional to the £4m in the original project scope. The
borrowing requirement of £8.94m has an estimated revenue implication of
£7.79m which will be spread over the life of the loan (at approximately
£0.419m per annum – this estimate is based on a 40 year loan at 4.25% -
this in indicative as the actual amount will depend on the interest rate
when the borrowing occurs).  The full costs to the Council of each of the
four options is set out in the tables below   
CAPITAL
Option 1
£m
Option 2
£m
Option 3
£m
Option 4
£m
WDC Contribution 8.94 7.84 2.94 N/A
SG Contribution 35.76 31.26 11.76 N/A
Total 44.70 39.10 14.70 N/A     
WDC REVENUE PER
ANNUM
Option 1
£m
Option 2
£m
Option 3
£m
Option 4
£m
Principal Repayment 0.224 0.196 0.074 N/A
Interest on Principal 0.195 0.171 0.063 N/A
Total 0.419 0.367 0.137 N/A     
WDC REVENUE 40
YEARS
Option
£m
Option 2
£m
Option 3
£m
Option 4
£m
Principal Repayment 8.94 7.84 2.94 N/A
Interest on Principal 7.79 6.83 2.53 N/A
Revenue in 25/26 0 0 0 1.98
Total 16.73 14.67 5.47 1.98     
DIFFERENCE
BETWEEN OPTION 1
AND OTHER OPTIONS
Option 1
£m
Option 2
£m
Option 3
£m
Option 4
£m
Per Annum 0 -0.052 -0.282 N/A
40 Years 0 -2.059 -11.264 -14.749  
6.2 All options will also require legal and procurement support to ensure the
construction tender is awarded by 31 March 2026.  
Page 267

Page 10

7. Risk Analysis 
7.1  There is a risk with any project of the size and complexity of increased
construction costs due to unforeseen difficulties. Any delay to construction
commencing may also increase costs due to rising material costs, however an
element of risk has been built into the current costs. 
7.2 Mitigation measures and value engineering of design options was undertaken
before costs were refined, therefore reducing some risks related to cost
increases. 
7.3 The funding supplied by Scottish Government in fixed at 80% of the final tender
package. If final costs are higher (for example through compensation events or
contract variations) no additional funding is payable. Any additional costs will
need to be funded directly by the Council. 
7.4 The Scottish Government have advised that they are currently considering
whether new affordability measures are necessary to bring the overall
programme of Cycle 1 flood schemes within the available funding envelope.
However, the only measure in place at this time is the 31 March 2026
milestone for any remaining schemes. 
8. Equalities Impact Assessment (EIA) 
8.1  A completed EIA was undertaken as part of the Detailed Design process and
there have been no material changes in terms of impact on people with protected
characteristics since. 
9. Consultation 
9.1 The detail contained within this report was considered by the Strategic Asset
Management Group which is attended by representatives of all service areas. 
10. Strategic Assessment 
10.1  This report reflects the 2022 – 2027 Strategic Plan and in particular the  
following Strategic Priorities: 
•  Our resources are used in an environmentally sustainable way 
•  Our Council is adaptable and focused on delivering best value for our
residents 
Chief Officer: Gail Macfarlane 
Service Area:  Roads and Neighbourhood 
Date:   10 December 2025 
Person to Contact:   Liam Greene  
Roads and Transportation Manager  
Email: liam.greene@west-dunbarton.gov.uk 
Page 268

Page 11

Background Papers: IRED 15 September 2021 
Gruggies Burn Flood Prevention Scheme Update 
IRED 2 November 2022
Flood Prevention Schemes - Levenhowe, River Leven
and Gruggies Burn. 
Wards Affected: Dumbarton and Leven Wards