ARGYLL AND BUTE COUNCIL  COUNCIL
DEVELOPMENT AND ECONOMIC
GROWTH 
21 NOVEMBER 2024 
STRATEGIC HOUSING INVESTMENT PLAN (SHIP) 2025/26 - 2029/30 
1.0 EXECUTIVE SUMMARY 
1.1 This report details the proposed annual Strategic Housing Investment Plan which will cover
the period 2025/26 - 2029/30 and summarises the proposals for the revised SHIP, in line with
statutory requirements and the latest guidance.   
1.2 The SHIP document required to be submitted to the Scottish Government on 25th October
2024.  The Strategic Housing Investment Plan, as attached at Appendix 1, was submitted to
comply with that deadline on the basis of it being subject to ratification by the Council at their
meeting on 21st November 2024.   
1.3 The Scottish Government have not yet agreed the Resource Planning Allocation (RPA) for
future years of the SHIP programme. The Council has been advised of an assumed RPA for
the years 2025/26 to 2027/28 of 80%/, 60% and 40%* of current year RPA levels based on
programme management advice from the Scottish Government. It is important to note that
the figures for 2025/26 to 2027/2028 are not a formal definitive allocation and no indication
has been provided at all for later years: 
Year 2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 Total
RPA £14.002 £11.201* £8.401* £5.600* TBC TBC £39.205 
1.4 In 2023/24, the SHIP delivered 70 new affordable homes. In addition 14 properties were
bought from the open market by RSL’s to be brought into the affordable housing stock. This
SHIP identifies potential for 72 units to be delivered in 2024/25 and over 1000 additional
homes to be completed or approved in subsequent years. 
1.5 As well as addressing unmet local need and contributing to national targets, the proposed
programme will: 
• generate additional investment in the local economy, support additional jobs including
new apprenticeships in the construction sector and associated labour market; 
• stimulate community regeneration and sustainability; 
• help to attract and retain residents and employees for local businesses; 
• encourage movement within, and more effective operation of, the local housing system; 
• also contribute to improving general health and well-being; 
• generate additional Council tax revenue.

Page 2

RECOMMENDATIONS  
It is recommended that the Council consider and approve the SHIP 2025/26 – 2029/30 which
will then be submitted to the Scottish Government as the Council’s approved SHIP document.

Page 3

ARGYLL AND BUTE COUNCIL  COUNCIL
DEVELOPMENT AND ECONOMIC
GROWTH 
21 NOVEMBER 2024 
STRATEGIC HOUSING INVESTMENT PLAN (SHIP) 2025/26 - 2029/30 
2.0 INTRODUCTION 
2.1 The core purpose of the SHIP is to set out strategic investment priorities for affordable
housing over a five year period to achieve the outcomes set out in the Local Housing Strategy. 
2.2  The SHIP document required to be submitted to the Scottish Government on 25th October
2024.  The Strategic Housing Investment Plan, as attached at Appendix 1, was submitted to
comply with that deadline on the basis of it being subject to ratification by the Council at their
meeting on 21st November 2024.   
2.3  The SHIP remains a continuous, iterative process: individual projects are subject to a variety
of factors which can lead to slippage or revision; and the overall programme requires constant
monitoring.   Formal updates are now required on an annual basis. 
2.4 The revised SHIP has potential for delivery of 72 units in 2024/25, and over 1000 new
affordable homes in subsequent years. 
3.0 RECOMMENDATIONS  
3.1 It is recommended that the Council consider and approve the SHIP 2025/26 – 2029/30 which
will then be submitted to the Scottish Government as the Council’s approved SHIP document. 
4.0 DETAIL 
4.1 From 2017, the Scottish Government, COSLA and Association of Local Authority Chief
Housing Officers (ALACHO) agreed that SHIPs would revert to being submitted on an
annual basis. In June 2024 revised guidance was issued to assist local authorities prepare
their SHIPs, with a requirement to submit to Scottish Government by October 2024.  The
SHIP was submitted noting that the document would be submitted for approval to Full
Council in November 2024.   
4.2 The Local Housing Strategy (LHS) sets out the strategic policy approach of the council and
its partners to delivering high quality housing and related services across all tenures to
meet identified need in the area. SHIPs are directly informed by the LHS and its policies
and are developed in consultation with key stakeholders. Therefore, the SHIP is operational
in nature and not considered as a policy document.

Page 4

4.3 The core purpose of the SHIP remains to set out strategic investment priorities for
affordable housing over a five year period to achieve the outcomes contained in the LHS.
The plan reinforces the council as the strategic housing authority; the importance of the
outcomes and targets set out in the LHS; and informs Scottish Government investment
decisions. 
4.4 The SHIP should therefore:- 
• Set out investment priorities for affordable housing;
• Demonstrate how these will be delivered;
• Identify the resources required to deliver these priorities;
• Enable the involvement of key partners.   
The SHIP should contain a succinct narrative in PDF form, submitted as a supporting
document to the SHIP in the Housing and Regeneration Programme (HARP) system, which
explains the context to the SHIP including: 
➢ A statement on alignment with the LHS demonstrating that priorities identified in the
SHIP are consistent with what the local authority outlined in its LHS (and any
subsequent updates) and how the SHIP priorities will contribute to delivery of LHS
Outcomes; 
➢ A summary of the methodology used to prioritise projects; 
➢ Details of how the local authority has responded to and resolved development
constraints on projects prior to the site start date; 
➢ Details on how the local authority’s own resources and other funding are supporting
the delivery of affordable housing in its area; 
➢ Details of progress towards the delivery of its Affordable Housing Supply Programme
across all tenures by completions; 
➢ Details of affordable housing projects for Gypsy/Travellers; 
➢ Details of Housing Infrastructure Fund projects where these are linked to affordable
housing delivery; 
➢ Details of local plans to support the delivery of wheelchair accessible housing within
its area;  
➢ A statement that strategic housing priorities are aligned and are consistent with
Rapid Rehousing Transition Plan priorities;  
➢ Details of affordable housing projects that are aligned with the local authority’s Child
Poverty Action Report;  
➢ Details that duties under the Islands (Scotland) Act have been followed by the local
authority if appropriate; 
➢ Details of any empty homes services and actions to bring homes back into use; 
➢ Details of how Council Tax on Second and Empty Homes has been used to assist
affordable housing;  
➢ Details of how Developer Contributions have been used to assist affordable housing;   
➢ The type and level of consultation undertaken with RSLs, communities, developers
and other stakeholders in developing the SHIP and how this has helped with the
development of strategic investment priorities.   
4.5  Key Aspects of the SHIP Guidance Issued in June 2024 
4.5.1  The most recent guidance includes an emphasis on ensuring any specific requirements and
actions for delivery of key worker housing are included in the SHIP.

Page 5

4.5.2  The guidance makes reference to the Affordable Rural Homes for Key Workers Fund which
was announced in April 2023. Council officers are in discussion with the Scottish
Government over several housing projects which they consider may be eligible for the
Fund. 
4.5.3  The guidance also requires details on how the SHIP supports and enables the local
authority to deliver duties required under the Islands Act. 
4.5.4  The guidance continues to include an enhanced emphasis on the delivery of wheelchair
accessible housing in support of action 62 of the Fairer Scotland for Disabled People Action
Plan.   
4.5.5  The latest guidance continues to emphasise the specific linkages between the SHIP
process and the duty on local authorities to produce Rapid Rehousing Transition Plans,
essentially ensuring that the delivery of the SHIP will have direct impact on homelessness
in the local authority area. 
4.5.6 The latest guidance also includes reference to the fact that any capital works to the official
Gypsy Traveller sites in Argyll should be included in the document. Subsequent to the
guidance being issued the Scottish Government has now confirmed that Capital Projects in
relation to the sites can now be included in the SHIP tables. 
4.6 Resource Planning Assumptions (RPAs) 
4.6.1   The Scottish Government have not yet agreed the Resource Planning Allocation (RPA) for
future years of the SHIP programme. The Council has been advised of an assumed RPA for
the years 2025/26 to 2027/28 of 80%, 60% and 40%* of current year RPA levels based on
programme management advice from the Scottish Government. It is important to note that
the figures for 2025/26 to 2027/2028 are not a formal definitive allocation and no indication
has been provided at all for later years: 
Year 2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 Total
RPA £14.002 £11.201* £8.401* £5.600* TBC TBC £39.205 
4.6.2 It should be noted that this is potential investment for Argyll and Bute, dependent on actual
need and deliverability of suitable projects. While obviously very welcome, this level of funding
will also present real challenges for the Council and its partners. This would be subject to
sufficient complementary funding being available from the Council and RSLs themselves to
support the programme; and the capacity of the constrained local construction industry to gear
up to such an enhanced level of productivity. Officers will continue to explore with Scottish
Government and through COSLA, areas of flexibility in uses of the RPA which will help us to
maximise its utilisation. 
4.7 Additional funding is required to complement the Scottish Government investment, and in
Argyll and Bute this includes a contribution from the Council’s Strategic Housing Fund (SHF)
as well as Housing Association investment drawn from private sector borrowing. The council’s
SHF is primarily based on the revenue raised from reduced tax discounts on holiday and
second homes. The SHIP sets out plans to fully utilise the SHF over 5 years to support the

Page 6

affordable housing development programme, including empty homes grants and loans. The
projected income to the SHF over the next 3 years is approximately £2m per annum. 
4.8 Consultation and Collaboration 
4.8.1 The preparation of the SHIP is intended to be viewed as a corporate activity with close
working relationships fostered across housing, planning, economic development and other
internal services. It is also crucial that the SHIP process is based on collaboration between
the Council, RSLs, communities, developers, the Scottish Government and other
stakeholders such as the Health and Social Care Partnership; and that the SHIP document
should provide a detailed narrative about how consultation and collaboration has been
undertaken with all stakeholders. In Argyll and Bute, while the Council remains the strategic
authority with overall responsibility for the plan, local RSLs and developers are engaged
formally and informally throughout the process, and do lead on delivering most of the
individual projects. Regular review meetings are held with SHIP officers from the Council,
RSLs, and the Scottish Government, and all proposals and decisions are considered by the
overarching, multi-agency Strategic Housing Forum. Updates are also being tabled at local
area community planning groups; and at the level of specific projects, sites and settlements,
a range of community representatives and individual residents are routinely engaged and
consulted. In recent years, a number of local community councils and development trusts
have pro-actively engaged in the SHIP process, undertaking localised Housing Need and
Demand Assessments (HNDAs), with Council support, to feed into the process and
contributing to discussions on the project proposals. Additional engagement has been
promoted across the local business sector. 
4.9 A primary focus for the new SHIP has been continued engagement with the Health and
Social Care Partnership (HSCP) to ensure adequate specialist provision is included in the
new build programme. The HSCP’s new 3 year strategic plan was launched in 2022 and
incorporates a Housing Contribution Statement (HCS) outlining the essential role housing
plays in supporting and maintaining independence, health and well-being of residents. The
current LHS consolidates the partnership working with the HSCP and sets out a high-level
outcome which is: 
“To enable people with particular needs to live independently in their own homes
and to remain in their communities” 
The post of dedicated Housing Occupational Therapist which was established in October
2018 to co-ordinate and promote these needs through the SHIP group, was made
permanent in 2021. 
4.10 Housing Infrastructure Fund (HIF) 
4.10.1 The Scottish Government introduced a Housing Infrastructure Fund in 2016 to support
housing development through dedicated loans and grants. The HIF will prioritise sites which
are of strategic importance and cannot proceed or have stalled due to exceptional
infrastructure works. The Council secured a £2.1 million HIF grant to address the costs of
upgrade works at Kirk Road/Lorn Road.  This work is now complete and has enabled
delivery of the 300 unit affordable housing development at Dunbeg, which remains a high
strategic priority for the Council and its partners. The SHIP annual update contains
proposals for 4 further HIF projects in Argyll.

Page 7

4.11 Other Affordable Housing Provided Without Affordable Housing Supply Programme
(AHSP) Assistance 
4.11.1 SHIPs should contain details of all proposed affordable housing projects within the local
authority area including those which will be provided without AHSP support. This could
include off the shelf purchases, buybacks of ex-council/RSL stock, projects where councils
have exclusively used their own resources, pension funds or other sources of funding,
including Scottish Government non-AHSP funds to develop housing. 
4.11.2 The Council will continue to explore these and all other appropriate options to increase the
supply of affordable housing. The Council agreed an Open Market Purchase Statement
with the Scottish Government in January 2022. In June 2023 the Council launched a buy
back initiative in partnership with the local RSLs. 
4.11.3 SHF has contributed to 3 Rural and Islands Housing Fund projects in Argyll during 2023/24
–the development of 9 affordable houses on Colonsay and the development of 5 affordable
houses on Gigha and a project to upgrade infrastructure on the island of Ulva. The
Community Housing Network Group continues to meet on a quarterly basis in order to
support community groups to take forward housing projects which meet identified need. 
4.11.4 The potential impact of the Rural Growth Deal (RGD) for Argyll and Bute will be significant,
and the SHIP and the housing sector in general can contribute to this strategic agenda. 
4.12 Current Progress: Outputs 2023/2024 
4.12.1 Table 1 details the affordable housing delivered by the SHIP in 2023/24. 
TABLE 1:  SHIP New Build Homes by HMA & Project, 2023/24
Project address Developer Units
Dunbeg Phase 3 LINK 66
Eton Avenue, Dunoon ACHA 4
Argyll & Bute 2023/24 Total Completions  70 
4.13 The Revised SHIP Programme 
The current year, 2024/25, is covered by a Strategic Local Programme Agreement while the
new SHIP is intended to commence from 2025/26. The following tables summarise all
proposals at the time of writing, including those projects which were completed in the first
quarters of this year and for which funding has already been drawn down. It should be
noted that the status of many future projects, particularly in the later years, remains
provisional and purely indicative at this stage; some may not proceed within the timescale.
However there is also scope for additional proposals to be brought forward or included in
earlier years. 
TABLE 2: SHIP Projects Completions/Anticipated Completions in 2024/25

Page 8

Project address Developer Units
Anticipated
/Completion
Date
Jeannie Deans, Helensburgh Dunbritton HA 12 June 2024
Lochgilphead Baddens, Riverside Drive Fyne Homes  6 Nov 2024
Wilkie Houses, Rothesay Fyne Homes 8 March 2025
Imeraval Phase 4 Islay WHHA 20 July 2024
Port Appin Phase 1 WHHA 6 August 2024
Buyback Acquisitions  ACHA 20 March 2025
Buyback Acquisitions Fyne Homes 1 March 2025
Argyll & Bute 2024/25 Total Completions (est.) 73 March 2025

Page 9

TABLE 3: SHIP Core Programme - Potential Completions by March 2030 
Project Address Developer Units Anticipated Completion
Bowmore Phase 4 ACHA 17 Year 1 (25/26)
Dalintober ACHA 32 Year 1 (25/26)
East Clyde Street ACHA 14 Year 1 (25/26)
Various Acquistions ACHA 50 Year 1/5 (25/30)
Carsaig (Tayvallich) ACHA 2 Year 2 (26/27)
Inveraray ACHA 20 Year 2 (26/27)
Glen Machrie Phase 1  ACHA 30 Year 2 (26/27)
Tarbert Police Station  ACHA 1 Year 2 (26/27)
Tighcargaman, Port Ellen ACHA 60 Year 2 (26/27)
Tiree ACHA 10 Year 2 (26/27)
Duncholgan Gypsy/Travellers Site ACHA 7 Year 2 (26/27)
Bay View Gypsy Travellers Site ACHA 4 Year 2 (26/27)
Alexander Street, Phase 1 ACHA 35 Year 3 (27/28)
Tarbert Phase 1 ACHA 20 Year 3 (27/28)
Alexander Street, Phase 2 ACHA 35 Year 4 (28/29)
Tarbert Phase 2 ACHA 10 Year 4 (28/29)
Dunoon ACHA 16 Year 5 (29/30)
Grant Street, Helensburgh DUNBRITTON HA 14 Year 1 (25/26)
Cardross DUNBRITTON HA 30 Year 1 (25/26)
18th Tee, Helensburgh Golf Club DUNBRITTON HA 16 Year 3 (27/28)
Helensburgh Golf Club DUNBRITTON HA 45 Year 4 (28/29)
Succoth Phase 2, Arrochar DUNBRITTON HA 12 Year 5 (29/30)
Ballochgoy FYNE HOMES  8 Year 1 (25/26)
Inveraray Phase 1 FYNE HOMES  16 Year 1 (25/26)
Baddens Phase 10 FYNE HOMES  14 Year 2 (26/27)
Rothesay Academy Phase 1 FYNE HOMES  30 Year 3 (27/28)
Lochgilphead Phase 6 - LDP2 Site FYNE HOMES  55 Year 3 (27/28)
Inveraray Phase 2 FYNE HOMES  10 Year 4 (28/29)
Rothesay Academy Phase 2 FYNE HOMES  35 Year 5 (29/30)
Tighnabruaich Phase 2 FYNE HOMES  10 Year 5 (29/30)
Luss LINK GROUP 8 Year 4 (28/29)
Dunbeg phase 4 LINK GROUP 349 Year 5 (29/30)
Imeraval Ph 5 WHHA 20 Year 1 (25/26)
Colonsay WHHA 5 Year 1 (25/26)
Dalmally Ph 1 WHHA 8 Year 1 (25/26)
Shillinghill Ph 3 WHHA 10 Year 1 (25/26)
Port Appin Ph 2 WHHA 6 Year 2 (26/27)
Baliscate, Tobermory WHHA 12 Year 2 (26/27)
Port Charlotte Ph 2 WHHA 17 Year 2 (26/27)
Campbell St WHHA 4 Year 2 (26/27)
Lochawe Phase Ph 1 WHHA 16 Year 3 (27/28)
Salen, Isle of Mull WHHA 8 Year 4 (28/29)
Craignure WHHA 12 Year 4 (28/29)

Page 10

Dalmally ph2 WHHA 6 Year 5 (29/30)
WHHA – Old Hospital Site Ph 1 WHHA 25 Year 5 (29/30)
WHHA - Bunessan Ph 2 WHHA 6 Year 5 (29/30)  
1170 
1 NB. Timescales are indicative and subject to change; and will be monitored on a regular basis.
Some projects could also revise their final number of units. 
4.14 Alternative sites are also being considered either to replace or enhance some of the sites
listed in above tables. The Council also continues to provide support for communities
considering the use of the Government’s Rural and Island Housing Funds and other
resources to deliver affordable housing out with the core AHSP development programme.
The table below provides details of these projects. 
TABLE 4: Community Housing Projects 
COMMUNITY
GROUP PROJECT AREA NOTES ON PROJECT STAGE TOTAL UNITS 
(if relevant)
Colonsay
Community
Development
Scalasaig, Isle of
Colonsay
Houses scheduled for final completion in Autumn
2024. Allocation in progress
9 + 3 self build
plots
Luing Community Isle of Luing
Detailed housing proposals prepared and to be
submitted in Local Place Plan. Community
Council engaging with second home owners
encouraging them to sell or rent their properties –
one home already transferred to rental market.
Actively looking at open market acquisition.
12
Mull and Iona
Community Trust
Worker
Accommodation
House purchased with rural housing burden for
key worker on the island 1
Worker
Accommodation
Tobermory
Supporting A & B Council in the provision of
worker accommodation in Tobermory. Works
onsite.
12
Fishnish affordable
housing
Deep peat at potential Salen site made this
project financially unfeasible. 3
South West Mull
and Iona
Development
Ardmeanach View
Bunessan
Working with WHHA towards demonstrating
Feasibility 6
Bunessan Village Exploring feasibility of site, funding for site
purchase 5 or 6
Hebridean Trust Tiree Council funding to support bringing two
properties back into use. 2
Tiree Community
Development  Tiree RIHF monies in place, site investigations are
ongoing.  12
Isle of Gigha
Heritage Trust Ardminish  Units due for completion autumn 2024 5

Page 11

Coll Community
Housing Group Arinagour
This group have engaged with the Council
Housing Service regarding the provision of
affordable housing. Land has been offered for
this purpose. 
North West Mull  Isle of Ulva Post Construction Management / Infrastructure
Upgrade   
Tayvallich
Initiative
Tayvallich  
Progressing with application for rural housing
body status. Draft approval in place pending
clarification from Scottish Ministers. 
Community consultation on housing needs has
been carried out 
Archie's Land,
Tayvallich 
Procurement process agreed with developer
CHT and a tender for an architect has been
released.  
10 
4.15 Impact Assessments 
In preparing the SHIP, as in all aspects of housing policy and planning, the Council has
taken account of the housing needs of all the communities we serve, and continues to
address equalities issues and adhere to principles of diversity and inclusion. In addition to
the robust baseline evidence of specialist accommodation and support needs across the
range of equalities client groups contained in the HNDA, the Council is proactively pursuing
engagement with the Health and Social Care Partnership to inform the SHIP programme.
An overarching equality impact assessment will be completed for the LHS and this will
inform our assessment of the impact of the SHIP, and how the strategic aims are embodied
in the housing priorities of the programme. Housing Services will also consider
requirements for Health Inequalities Impact Assessments, Child Rights and Wellbeing
Impact Assessments or other potential policy implications. However, as the responsible
authority for the purposes of the relevant 2005 Act, the Council has determined that a
Strategic Environmental Assessment (SEA) is not required for the LHS or SHIP. 
5.0 CONCLUSION 
5.1 The Scottish Government will review the SHIP submitted by the Council in line with the
process agreed jointly with COSLA. Their appraisal will therefore take account of the following:   
• the extent to which the SHIP delivers LHS Outcomes; 
• the extent to which it is feasible to deliver; 
• the local authority’s contribution to the delivery of the programme, both in terms of its
facilitation role and in terms of maximisation of resources;
• evidence that the Council is supporting the efficient delivery of the SHIP;
• evidence of stakeholders’ involvement in developing the SHIP and in the
implementation of proposals; and 
• the extent to which it takes account of equality issues.   
6.0 IMPLICATIONS

Page 12

6.1  Policy - Proposals are consistent with current Council policy, including the revised policy in
respect of the use of Strategic Housing Fund monies. The SHIP supports the Local Housing
Strategy vision and outcomes which are directly aligned with the overarching objectives of
the Outcome Improvement Plan, in particular Outcome 2 – we have infrastructure that
supports sustainable growth. 
6.2  Financial - The proposals are based on the Resource Planning Assumptions provided by
the Scottish Government; the Strategic Housing Fund and RSL private finance. There will
be an ongoing requirement to retain and target SHF resources to support the proposed
programme. 
6.3  Legal - The submission of the SHIP will meet our statutory duties, and following its
approval, Strategic Local Programme Agreements will be concluded between the Council
and Scottish Government. 
6.4  HR – None.   
6.5  Equalities (Fairer Scotland Duty) - The proposals are consistent with aims and objectives
set out in the local housing strategy, which is subject to an EQIA. 
6.5.1  Equalities – protected characteristics - There are targets set within the SHIP to deliver
housing which meet the needs of specialist groups. 
6.5.2  Socio-economic Duty - The delivery of affordable housing across Argyll and Bute facilitates
socio-economic opportunities for all. The SHIP links with the Child Poverty Strategy. 
6.5.3  Islands - The Housing Needs and Demand Assessment process takes full account of
housing need on the islands. New build developments on the islands are included in each
of the SHIP tables. 
6.6 Climate Change – new housing in the right location helps reduce carbon outputs when
delivered using renewable energy and other measures. Making best use of existing stock
by delivering energy efficiency measures helps towards achieving climate change targets.
6.7 Risk – there is a risk of depopulation, damage to the economy a risk to delivering essential
services in the local authority area if partners cannot effectively fund and deliver affordable
housing to meet need and demand. 
6.8  Customer Service – none. 
6.9 The Rights of the Child (UNCRC) – the delivery of more housing will enable more children
to have a safe secure environment. The Strategic Housing Investment Plan also has clear
links to the Child Poverty Strategy.   
Kirsty Flanagan, Executive Director with Responsibility for Development and Economic Growth

Page 13

Councillor Jim Lynch, Policy Lead for Economic Development, Islands, Rural Communities and
Housing 
November 2024 
For further information contact: 
Fergus Murray, Head of Development and Economic Growth   
fergus.murray@argyll-bute.gov.uk 
Matt Mulderrig, Development Policy and Housing Manager
matt.mulderrig@argyll-bute.gov.uk 
Douglas Whyte, Team Lead – Housing Strategy
douglas.whyte@argyll-bute.gov.uk 
APPENDICES 
Appendix 1 – SHIP