Democracy Spraffa

Appendix 1 - Local Housing Strategy (Lhs) Annual Report 2024

Argyll and Bute Council · 21 November 2024
Back to Argyll and Bute Council — 21 November 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Argyll and Bute 
Local Housing Strategy
Annual Report 2024

Page 2

2 
CONTENTS 
Section              Page 
Introduction......................................................................................................  3  
Outcome ONE - Housing Supply and Place Making.........................................  9  
Outcome TWO – Energy Efficiency, Climate Change and Poverty....................  26     
Outcome THREE – Specialist Provision and Independent Living.......................  35  
Outcome FOUR – Housing Options, Information and Support............................  41 
Local Housing Strategy - Action Plan Progress...............................................  49 
Appendix 1 – Housing Emergency Action Plan.................................................  57

Page 3

3 
INTRODUCTION
Following publication of the Argyll & Bute Housing Need & Demand Assessment in 2021, the Council’s Local Housing Strategy (LHS)
was launched in April 2022, covering the planning period 2022/23 to 2026/27. The LHS sets out a detailed Action Plan which provides
the framework for reporting annual progress on the delivery of our strategic objectives and the new LHS Vision, which is: 
“Everyone in Argyll & Bute has access to a suitable, high quality home 
which is affordable and located within a vibrant, sustainable and connected community”  
A baseline summary of progress during the interim year 2023/24 is set out at the end of document which is structured around the
four LHS Outcomes: 
Outcome 1: Housing Supply and Place-making     
Outcome 2: House Condition, Energy Efficiency and Poverty                               
Outcome 3: Specialist Provision and Independent Living  
Outcome 4: Housing Options, Information and Support 
Table 1: Abbreviations frequently used in this document
ABC – Argyll & Bute Council NSSE – New Supply Shared Equity (Affordable housing model/initiative)
ACHA – Argyll Community Housing Association NRS – National Records of Scotland 
CHR – Common Housing Register (HOMEArgyll waiting list) OMSE – Open Market Shared Equity 
CPO – Compulsory Purchase Order PSHG – Private Sector Housing Grant
EESSH – Energy Efficiency Standard for Social Housing RGD – Rural Growth Deal
HNDA – Housing Need & Demand Assessment RPA – Resource Planning Assumption
HSCP – Health & Social Care Partnership RSL – Registered Social Landlord (Housing Association)
LA – Local Authority SHF – Strategic Housing Fund (Council)
LHS – Local Housing Strategy SHIP – Strategic Housing Investment Plan
LHEES – Local Heat and Energy Efficiency Strategy SoA – Scheme of Assistance 
LIFT – Low-cost Initiative for First Time Buyers WHHA – West Highland Housing Association

Page 4

4 
REFLECTION OF THE PAST YEAR
Over the last year there have been continual changes to the local and national housing markets, political environment, legislative
framework, and our economy which are impacting many of the services, residents, and businesses in Argyll and Bute. 
Significantly for housing delivery, there has been a notable cut from £713m to £595.5m (16%) to the Scottish Governments 2024/25
annual Affordable Housing Supply Programme budget to deliver affordable homes, with further cuts anticipated for 2025/26. This will
put additional pressures on Local Authorities and partners to meet their statutory duties and deliver the affordable housing required
to address the housing emergency being faced by many households across Scotland. 
The Scottish Housing Regulators analysis of Registered Social Landlords Audited Financial Statements for 2022/23 published in
March 2024, reports that the aggregate financial position of RSL’s is weaker that it has been for some time. Although RSL’s have
mitigated the difficult economic and operating conditions, many RSLs have reduced financial headroom and capacity to respond to
further challenges. The scale of the financial challenges faced by RSLs since March 2023 remains significant, reflecting the continuing
difficulties and volatility of current operating environment. There are increasing financial pressures on RSLs to address building safety,
decarbonisation, and investment in stock which reduces the financial capacity to respond to any arising unforeseen events and may
impact ability of RSLs to increase affordable housing stock to address Scotland's housing emergency. 
A study by Scottish Government on Housing Affordability was published in March 2024, which sought views from social and private
rental tenants on definitions of affordable housing. Unsurprisingly, the study concluded that many tenants are struggling with
affordability of housing costs and in most instances, sacrifices are being made to make ends meet. With recommendations that the
Scottish Government consider the findings and develop a ‘measure or definition of housing affordability’ that must: be clear, specific
and relative to tenant's everyday lives and finances; reflect the realities of the rental market; emphasise fairness and dignity for
tenants; consider what is realistic, affordable and allows for ‘future proofing’. 
In May 2024, we learned of the sudden passing of Councillor Robin Currie, Housing Spokesperson.                           
Robin was a Councillor for nearly 40 years and was a huge advocate for affordable housing in Argyll and Bute.  
We are proud of the housing legacy in Argyll and Bute that Robin so strongly contributed to and for the support from 
partners during this time. 
Picture 1: Robin Currie

Page 5

5 
HOUSING EMERGENCY 
In June 2023, Argyll and Bute Council was the first Local Authority in Scotland to declare a Housing Emergency, due to the significant
housing pressures that many of our residents are experiencing.  Since then, the Chartered Institute of Housing have declared a
Housing Emergency across Scotland together with other Local Authorities such as Edinburgh, Glasgow, Fife, South Lanarkshire, and
West Dunbartonshire.   
The Scottish Government initially declined to declare a national housing emergency in 2023, however in June 2024 they
acknowledged Scotland’s Housing Emergency. In response, a National Housing Emergency Action Plan for Scotland has been
developed in coalition with private, social, and third sector partners detailing steps for how the Scottish Government should tackle
the emergency.   
Argyll and Bute Response to Housing Emergency
In October 2023, the Council launched two surveys asking for views on housing from our communities and businesses. In total, the
Council received 688 responses to the community and 72 responses to the workforce survey. Most of the respondents (92%) felt
their communities were negatively impacted by the housing shortage. We were delighted that so many people took the time to respond
and provide us with details on local impacts and ideas to help tackle the housing shortage.   
A Housing Emergency Summit was held in November 2023, bringing together 90 partners from public, private, third and community
sectors who pledged their support to take decisive and bold action to address the housing emergency. Summit activity included
hosting pre-engagement workshops with stakeholders, the results from the community and business surveys, and extensive analysis
to evidence the extent and nature of the housing emergency in Argyll & Bute. Our priorities to address the housing emergency have
been grouped into four key themes: 
1. Enabling the delivery of more market homes in Argyll and Bute
2. Enabling the delivery of more affordable homes in Argyll and Bute
3. Enable the delivery of more homes for Argyll and Bute’s workforce
4. Make the best use of existing homes in Argyll and Bute 
The Housing Emergency Summit report outlines the outcomes achieved by the summit including the shortlisting and appraisal of
housing emergency responses and the collective partnership pledge to act on each response. The full outcome report can be
accessed here: Argyll and Bute Housing Emergency Summit Outcomes Report 2024

Page 6

6 
Council officers, working with the consultants engaged to facilitate the Housing Summit, have developed a final list of action points
under each housing emergency priority, which reflects the options appraisal and prioritisation carried out by the delegates attending
the Housing Emergency Summit.  The result is a Housing Summit Action Plan covering each housing emergency priority.  This will
allow delivery partners to set proposed timescales, specify activities and detail partner responsibilities to drive further action and
implementation. The collectively identified actions to tackle housing shortages will be programmed initially over a 5-year delivery
period and subject to regular review. The Action Plan was approved by the Council’s Environment, Development and Infrastructure
Committee in June 2024. The Housing Summit Action Plan is attached in Appendix 1. 
Moving forward, Council Officers are working on several new work streams to address the housing emergency and liaising closely
with partners on the Housing Emergency Action Programme to take forward the delivery of the identified priorities. 
An overview of action and regular updates on various workstreams are published on ‘Housing Emergency Webpage’ which can be
accessed here - Housing emergency | Argyll and Bute Council (argyll-bute.gov.uk)   
Island Housing Market Failure Report
A high-level market study exploring issues related to housing demand and delivery across the three main island Housing Market
Areas of Coll & Tiree; Mull & Iona; and Islay, Jura & Colonsay was undertaken in autumn 2023 to help inform the Rural Growth Deal
projects. This study built on existing knowledge, wider work, and research, to examine the housing markets in more detail with a
range of stakeholders, including in-depth one-to-one interviews. Unsurprisingly, the study evidenced that current housing market on
our Islands is unable to satisfy the local need and demand for affordable housing. Key issues reported:    
 Median house prices across each island HMA increased significantly over the 10-year period between 2012 and 2022;
 High proportion of housing stock on the islands is classified as ‘ineffective’;
 High demand for affordable housing of varying types and tenures;
 Long waiting lists and high demand for social/community/worker housing;
 Lack of available shared equity, mid-market rent or specialist housing stock to support different household choices and attract /
retain economically active people to live and work on the islands;
 No ‘private sector’ residential development sites across the island HMAs;
 Traditional private sector led model of housebuilding does not occur and no speculative housing development takes place on
the islands;
 Inability for people to access housing is limiting local economic development, business success, and the delivery of public
services – a significant constraint on island economic growth.

Page 7

7 
The supply of housing on our Islands, is constrained by several factors including the availability of land, contractor capacity and a
lack of competition among developers, but primarily high construction costs. The shortfall of housing has, over a prolonged period,
resulted in higher house prices and rental values, reducing overall affordability. 
The study confirms evident traces of market failure, and there is a clear rationale for public sector intervention. Public sector support,
in the form of funding and other initiatives to deliver a range of housing, would go some way towards addressing the housing market
failure. To enable the delivery of affordable housing solutions in response to high local demand, can achieve many positive outcomes
for island communities. Research by the Scottish Land Commission found that to deliver more homes and address areas of market
failure, it is necessary for the public sector to play a full role in shaping local housing markets and enabling new development. The
provision of affordable housing requires a mix of types of properties and tenures to support different household groups including
young people / first time buyers, those seeking family homes, and older people. By supporting the delivery of affordable housing in
remote and rural island communities, where there is more market failure than on the mainland, will improve access to housing, help
stem rural depopulation, and sustain island communities. 
The result of the study provides an overview of the evidence of housing market failure across the Islands and there are several
recommendations for the Council to consider, many of which have already been included in the Housing Emergency Action Plan.
More crucially the study reiterates the need for public sector support to address market failure in Argyll and Bute.  Direct public sector
intervention in the island housing market is key to local economic development and is required to address a range of economic, social,
and environmental challenges facing our island communities. Intervening in the market will help address: housing affordability, equal
access to housing, tackling fuel poverty, and supporting economic activity and public services.

Page 8

8 
The challenges faced by Rural Landlords: The case of Argyll and Bute
The Council sponsored research in 2023/24 to understand the ‘Challenges faced by Private Landlords’ in Argyll and Bute. This
research was undertaken in conjunction with Citizens Advice Bureau (CAB), Glasgow University and UK Collaborative Centre for
Housing Evidence (CaCHE) with purpose of gaining a better insight on the motivations and intentions of landlords across the area to
provide a clearer picture of the private rented sector in Argyll and Bute. The research built on previous study undertaken by CAB in
2022 which considered the challenges faced by ‘Private renters in rural and island communities’. 
The extensive research paper includes detail on the scale of challenges reported by private landlords such as a lack of tradespeople,
the legislative burden, difficulties in obtaining vacant possession, inflationary challenges, interest rate increases, the removal of
mortgage interest rate relief and other tax changes.  As a result of these challenges some landlords are choosing to leave the sector,
and whilst there are multifaceted reasons, there is an acute need to encourage landlords to remain and invest in the sector to ensure
there is choice of housing tenure across the area. 
There are several evidence-based recommendations that have been identified for partners to respond to the challenges reported by
landlords and to support the housing emergency by encouraging the retention of existing landlords. The Council will work with partners
to take these recommendations forward.  A copy of the report and summary are available here. 
MONITORING OF THE LOCAL HOUSING STRATEGY OUTCOMES 
The Local Housing Strategy (LHS) Action Plan at the end of document provides full details of progress for 2023/24 against the
baseline and previous year's figures. 
For reference, the LHS Action Plan has been interlinked to the Housing Emergency Action Plan available at Appendix 1.  The
Housing Emergency Action Plan will be fully integrated into the next Local Housing Strategy in 2027.

Page 9

9 
LHS OUTCOME ONE: HOUSING SUPPLY AND PLACE-MAKING 
LHS strategic aim one is: To facilitate access to sufficient, suitable and affordable housing across all tenures, and the
associated strategic objectives are to:

Page 10

10 
LHS OUTCOME ONE: HOUSING SYSTEM CONTEXT 
Argyll & Bute Council Tax Register recorded a total of 49,348 dwellings in April 2024, a slight increase of 377 properties on the 2023
total of 48,971. This includes all tenures of housing which are registered as domestic dwellings. 
There are approx. 8,086 HOMEArgyll properties, in addition Bield, Link, Key & Trust have social housing taking estimated total to
8,816 (18%) registered social housing properties across Argyll and Bute. Around 4,531 (9%) properties are privately rented. The
number of registered landlords has decreased from 5,697 in 2023. Whilst some landlords may have left the sector, there are various
reasons for reduction in numbers including cleansing of data records, removal of properties rented to family; backlog of applications
which may include renewals; and changes of tenure. 
TABLE 2: ALL PROPERTIES IN ARGYLL AND BUTE ON COUNCIL TAX REGISTER AS AT APRIL 2024
Council Tax records -       
1st April 2024 Bute Coll &
Tiree Cowal H&L I, J &C Kintyre Lorn  Mid
Argyll
Mull &
Iona Total
All properties  4,288 703 8,786 12,385 2,245 4,177 9,053 5,740 1,971 49,348 
Approx. 5,393, nearly 11%, of properties on the Council Tax register could be classed as “ineffective” which means they are not
being utilised as someone’s main residence. These comprise of long-term empty properties; empty & exempt* properties;
second/holiday homes and job related or purpose-built holiday homes. 
TABLE 3: INEFFECTIVE STOCK IN ARGYLL AND BUTE AS AT APRIL 2024
Council Tax – April 2024 
Properties NOT used as main residence 
Bute Coll &
Tiree Cowal H&L I, J &C Kintyre Lorn  Mid
Argyll
Mull &
Iona Total
Long-term empty 75 11 116 93 24 87 126 82 33 647
200% levy (empty homes) 95 13 143 108 72 95 121 107 50 804
Second/holiday homes 442 181 570 185 255 190 406 394 188 2,811
Job related or Purpose built holiday homes  7 2 149 5 0 6 24 22 3 218
Exempt* & Empty 138 21 166 215 29 121 119 81 23 913
Total 757 228 1144 606 380 499 796 686 297 5,393
% ineffective Stock in the Housing Market Area 18% 32% 13% 5% 17% 12% 9% 12% 15% 11%
*Exempt properties i.e. Deceased owner; Living/detained elsewhere; Empty under Statute; Under renovation; Held for demolition etc.

Page 11

11 
Second Homes data 
In Argyll and Bute 5.7% of properties are registered as second homes. The figures fluctuate between Housing Market Areas and as
are low as 1.49% in Helensburgh & Lomond but rise to 25.75% of registered properties in Coll & Tiree as shown in Table 4.  Within
HMA areas the second home figures for some settlements can be a lot higher. From 1st April 2024 Argyll and Bute Council in line
with many other Local Authorities in Scotland have doubled the Council Tax on Second Homes. The impact of the Council Tax
changes will be monitored but early indications show that the numbers of second homes has reduced by nearly 5% between April
2024 (2,811) and July 2024 (2,685). 
TABLE 4: SECOND HOMES IN ARGYLL AND BUTE APRIL 2024
Council Tax records -  
1st April 2024 Bute Coll &
Tiree Cowal H&L I, J &C Kintyre Lorn  Mid
Argyll
Mull &
Iona Total
Number second/holiday homes  442 181 570 185 255 190 406 394 188 2,811
% of stock second homes 10.31% 25.75% 6.49% 1.49% 11.36% 4.55% 4.48% 6.86% 9.54% 5.70%  
Short Term Lets 
There are 2,210 properties registered as self-catering lets (commercial) which are not included in Council Tax register figures above
as these are registered as businesses and subject to Rates.     
In addition, there are over 3,000 properties in Argyll and Bute which have applied for a short-term let licence. Due to the variation
of ways that short term let properties can be registered, some of these properties will be accounted for in Council Tax and Self-
Catering let figures. 
TABLE 5: SELF-CATERING LETS AND SHORT TERM LET LICENCE APPLICATION FIGURES MARCH 2024
Self Catering Lets & Short Term Let
Licences - March 2024 Bute Coll &
Tiree Cowal H&L I, J &C Kintyre Lorn  Mid
Argyll
Mull &
Iona Total
Self-Catering Lets (Rates – commercial) 103 85 314 192 250 133 541 267 325 2,210
Short Term Let Licence applications* 145 106 380 314 339 152 803 349 443 3,031 
* Information on the different type of licences and the public register is available here - Short Term Lets - Public Register | Argyll and
Bute Council (argyll-bute.gov.uk)

Page 12

12 
LHS OUTCOME ONE: DEMOGRAPHIC CHANGES 
Household projections – The National Records Scotland (NRS) estimated that between 2018 and 2028, the number of households
in Argyll and Bute was projected to decrease by 2% from 41,630 to 40,803. Whilst a decrease was expected, there was a slight
increase from 2018-2022; with only the most recent NRS Household estimates highlighting that between 2022 and 2023 there has
been a 0.1% reduction in households in Argyll and Bute.   
TABLE 6: NRS ARGYLL AND BUTE HOUSEHOLD ESTIMATES 2018 - 2023 
AREA 2018 2019 2020 2021 2022 2023 Change
2022-23
Argyll and Bute 41,630 41,789 41,839 42,384 42,664 42,610 -0.1%
Scotland   2,457,998 2,495,623  2,507,625  2,528,823  2,549,797  2,535,310 +0.8%           
Reference: statistics.gov.scot : Mid-Year Household Estimates 
Population Estimates - The NRS updated their mid-year population estimates in 2024 to take into account improvements in the
figures for international migration. 
TABLE 7: NRS MID-YEAR POPULATION ESTIMATES ARGYLL AND BUTE 2019-2022    
Year  Population Estimate - Argyll and Bute Population Estimate - Scotland
2019 85,870  5,414,400
2020 85,430  5,413,100
2021 86,220  5,418,400
2022 87,920  5,447,700 
Reference: NRS Population Estimates Time Series Data – July 2024 
As reported by the NRS in Household and Dwellings in Scotland 2023 report, there has been a bigger percentage increase in
households than in the population in each Council area over the last twenty years.

Page 13

13 
CHART 1: PERCENTAGE CHANGE OF HOUSEHOLDS AND POPULATION IN LAST 20 YEARS 
Source: NRS Mid-Year Population Estimates 
Ageing Population - The 2022 Scotland Census estimated population for Scotland to be 5,436,600m which was an increase of 2.7%
from 2011. The Census recorded the highest number of people in older age groups than ever before. With 1,091,000m people aged
over 65, compared to 832,300 people under the age of 15.  Compared to the 2011 census the: 
 0 to 14 year old population decreased by 21,800 (down 2.5%)
 15 to 64 year old population decreased by 37,700 (down 1.1%)
 65+ population increased by 200,700 (up 22.5%) 
The 2022 Census results report that Argyll and Bute have the highest older population rate across all 32 Local Authorities, with
27% adults aged 65 or over. The % in older age groups varies across Scotland's Council areas as shown in Figure 2.

Page 14

14 
CHART 2: THE POPULATION AGED 65 AND OVER AS A PROPORTION OF THE POPULATION IN 2022, FOR COUNCIL AREAS IN SCOTLAND 
Source: Scotland Census 2022 
Migration - NRS Migration Data from mid-2011 to mid-2021 has also been revised following 2022 Census and updated long-term
international migration data. The variances* from previous reporting in the LHS have been added to Table 8.
TABLE 8: NRS MIGRATION ESTIMATES 2020-MID 2022 
INDICATORS  2020*  2021 * 2022 
TOTAL IN-MIGRATION  (3,430)  (5,280) 
4,170 3,550 5,350
TOTAL OUT-MIGRATION  (3,530) (4,070)  3,730 3,440 4,160
TOTAL NET MIGRATION  (90)  (1,220) 
440  110 1,200

Page 15

15 
LHS OUTCOME ONE: HOUSING DEMAND 
HOMEArgyll Waiting List and Annual Lets     
There were 3,209 social housing applications across Argyll & Bute in April 2024, a slight decrease of 2% on the previous year of
3,289 signifying the continual demand for affordable social housing. 763 households were allocated permanent social rented
tenancies via HOMEArgyll (Argyll Community Housing Association, Dunbritton, Fyne Homes, & West Highland Housing Association)
in 2023/24, a decrease of 6% on the number of lets in 2022/23 (811) and below the annual 860 target. 
CHART 3: HOMEARGYLL WAITING LIST AND LETS    CHART 4: HOMEARGYLL LETS 2022/23 & 2023/24      
Based on the HOMEArgyll waiting list and annual lets, this equates to 4 applicants on the waiting list for each available let.  
Mid Market Rent - 658 households on the HOMEArgyll waiting list have expressed an interest in Mid-Market rental properties. A
significant increase of 43% from 374 households in April 2023. 
Shared Equity - The ‘New Supply Shared Equity Scheme (NSSE)’ aims to help households on low to moderate incomes to buy an
affordable new build home.  As at April 2024 there were 567 households interested in the NSSE scheme.   
Open Market Shared Equity (OMSE) - Helps people buy a home within certain price thresholds for sale on the open market including
the Low-cost Initiative for First Time Buyers (LIFT). 476 households on the social housing register expressed an interest in the LIFT.

Page 16

16 
LHS OUTCOME ONE: HOUSING TRANSACTIONS 
The local housing market has seen average house price sales steadily increasing over the last few years as detailed in table 6 below.   
The Registers of Scotland Annual Market report 2024 differs from previous years by using median figures as the main statistical base,
instead of average figures reported in previous years. This makes direct comparisons with previous year averages difficult, however
by looking at median figures over a 5-year period trends can still be identified. 2022/23 saw the biggest increase in recent time, with
the average sale price in Argyll and Bute exceeding the Scottish average for the first time since 2009/10, however in 2023/24, using
the median figures, the sale price in Argyll and Bute has fallen slightly below the Scottish average. The median trend shows an
increase over a 5-year period of 25% in sale prices in Argyll and Bute, higher than the national average of 22%. The volume of sales
during 2023/24 in Argyll and Bute also fell. 
Market Affordability - To meet the median house price in 2023/24, at the standard affordable ratio (3.5 x HOUSEHOLD income),
would require an annual income of £50,000. 
Based on average median house cost of £175,000. ONLY 33% of local households would be able to afford the median house price
in Argyll & Bute. Median household income is £35,114.  (Income Source: CACI, 2023)  
TABLE 9: AVERAGE & MEAN RESIDENTIAL PROPERTY PRICES, 2019/20 – 2023/24 (FINANCIAL YEARS DATA)
Average / MEAN
House Prices
2019/20 2020/21 2021/22 2022/23  2023/24 % change 22/23-23/24
Argyll &
Bute 
(All sales)
Average
Price £173,432 
(£145,650)
£184,316 
(£156,000) 
£194,918 
(£160,000)
£219,245 
(£180,000) 
n/a  
(£175,000)
-2.8%
(+25% over 5 years) Median
Price
Scotland 
(All sales)
Average
Price £182,075 
(£156,000)
£194,342 
(£167,000)
£202,024 
(£171,000
£216,337 
(£185,000) 
n/a 
£185,000
0%
(+22% over 5 years) Median
Price
Source: Registers of Scotland

Page 17

17 
As previously noted due to changes to the Registers of Scotland reporting the following tables have been updated from previous
years to highlight the median figures of house sales.   
TABLE 10: SALES ACTIVITY AND VALUE: ALL TRANSACTIONS AND NEW BUILD TRANSACTIONS, 2019/20 – 2023/24
ARGYLL & BUTE 2019-20 2020-21 2021-22 2022-23 2023-24
Volume of All Sales 1,900 1,835 2,047 1,835 1667
Value of All Sales (£m) £329 £334m £397m £405m £364m
Volume New Build Sales 118 85 60 84 72
Value New Build sales £30m £21m £15m £24m £21m
Average Price New Build sales £254,995 £237,995 £228,995 £296,286 £336,495
Source: Registers of Scotland   
TABLE 11: VOLUME OF RESIDENTIAL PROPERTY SALES BY FUNDING STATUS 2023-24
Volume of residential property
sales transactions by funding
status
Cash sale Sale with
mortgage
Total - cash sale and
sale with mortgage
Cash sales as
percentage of
total
Argyll and Bute
had the highest
proportion of
cash sales of all
local authority
areas in 2023-24
Argyll and Bute 947 720 1,667 56.8%
Scotland 34,062 59,367 93,429 36.5% 
Source: Registers of Scotland

Page 18

18 
LHS OUTCOME ONE: AFFORDABLE HOUSING SUPPLY 
The Strategic Housing Investment Plan Programme 2023/24  
The Strategic Housing Investment Plan (SHIP) sets out the new build affordable housing supply programme for Argyll and Bute. 
During 2023/24, our Registered Social Landlord (RSL) partners successfully completed 70 new affordable housing units across Argyll
and Bute.  This included 54 units for social rent, 11 properties for New Supply Shared Equity (NSSE) and 5 properties for Mid-Market
Rent.  Total investment in these SHIP completions was £15,122,019.  
Previous SHIP documents had programmed 178 completions for the year 2023/24 so while this number is lower, it can be explained
by delays encountered at various stages of the house building process in a number of larger proposed developments. Some delays
in delivery or ferry provision, for example, have necessitated finding alternative solutions which has delayed some developments.
However a number of live SHIP projects are currently progressing onsite for completion in 2024.  
There have been some notable changes in tenure provision within the SHIP programme. Rates of provision for specialist and amenity
housing have increased from 19% in 22/23 to 27% in 23/24. Also worthy of note are the 5 new builds let as Mid-Market Rent (MMR)
housing. Mid-market rent offers housing for rent at prices pitched between social rent levels and private rent levels. It appeals to
those who do not qualify for social housing, but who would struggle to meet market rent prices. 
This tenure was created by flipping some properties from NSSE, which were proving to be of limited demand. By switching to MMR,
the properties were swiftly allocated due to the level of demand for this particular tenure. In addition to the 5 MMR units let in 23/24,
a further 12 NSSE units completed in 22/23 were switched to MMR and similarly swiftly allocated.

Page 19

19 
Argyll & Bute Affordable Housing Completions 2023/24 
Dunbeg Phase3 - LINK Housing           
66 units completed in 2023/24              
HMA: Lorn             
Tenure: 50 x Social Rent, 11 New Supply Shared Equity and 5 Mid-Market Rent properties.
Provision: 51 x General Needs, 8 x Particular Needs, 7 x Amenity units   
Background: LINK have now completed over 300 new build properties at Dunbeg with further
proposals for Phase 4 and 5 in the planning stage.       
PICTURE 2: DUNBEG PHASE 3 (CREDIT: E MACDONALD)       
PICTURE 3: ETON AVENUE (CREDIT: ACHA)
Eton Avenue, Dunoon – Argyll Community Housing Association (ACHA)                    
4 units completed in 2023/24                                                                                       
HMA: Cowal                                                                                                                
Tenure: 4 x Social Rent                                                                                          
Provision: 4 x Particular Needs                                                                        
Background: The Eton Avenue project is a good practice example for the Strategic
Housing Investment Plan (SHIP) due to the demolition of old stock to regenerate the area
and high level of consultation and involvement with the proposed tenants on the design
and construction of the new properties to meet identified needs within households.  Working closely with Housing Occupational
Therapist, Architects, Housing Association staff, and Contractors ensured that the specific needs of families were embedded within
the design and specification for each house. 
The Council are working with ACHA and the tenants, to participate in HACT and Shelter Scotland Social Value Research for the Eton
Avenue development.  This valuable research will enable us to evidence the wider social and economic benefits to the delivery of
this particular need's development.

Page 20

20 
Local Development Plan and Housing Land Supply
Argyll and Bute Council’s Local Development Plan 2 (LDP2) was approved on the 28th February 2024. Regarding housing, it seeks
to help deliver new housing of the right type in the right places to meet the needs and aspirations of the wide variety of households
across Argyll and Bute. Part of this involves ensuring there is an adequate supply of land on which new housing can be developed. 
There have been some changes from previous LHS updates in how this topic is approached. Scottish Planning Policy (2014)
previously set out requirements on local planning authorities relating to housing land supply including the provision of a minimum 5-
year effective land supply at all times (an effective site being one where it could be demonstrated to be free of constraints within 5
years). Scottish Planning Policy was superseded by National Planning Framework 4 (NPF4) on 13 February 2023. 
NPF4 requires that Local Development Plans set out a Local Housing Land Requirement (LHLR) which is expected to exceed the
10-year Minimum All-Tenure Housing Land Requirement (MATHLR). The MATHLR for Argyll and Bute as set out within NPF4 is
2150 units and this has been translated within Local Development Plan 2 (LDP2) into a LHLR of 3000 homes for a 10-year period
commencing from 2020. 
NPF4 sets out that the Housing Land Audit will monitor the delivery of housing land. The publication of Scottish Government Guidance
relating to Housing Land Audits is anticipated during the 2023-24 auditing year and this will be used to help inform future audits. 
Delivery of Housing Land Against MATHLR and LHLR to Date
NPF4 sets out the MATHLR for Argyll and Bute is 2,150 units. The LHLR for the 10 period from 2020 as set out in LDP2 is 3,000
units. The total number of completions between 1/4/2020 and 31/3/2023 is 869 units. 
Taking into account completions since 2020 the total remaining number of units from the MATHLR is 1,281 and from the LHLR is
2,131. The 869 completions over the past 3 years represents 40% of the MATHLR and 29% of the LHLR.

Page 21

21 
Community Housing Network
In addition to the various Registered Social Landlord partners, the Council also supports and works with a range of community
organisations who have an interest in improving affordable housing. Regular meetings are held with a wide range of groups from
rural and island communities each with an expressed interest in affordable housing provision. The range of groups is diverse, and
levels of experience, knowledge and aspirations also vary, however the group is an excellent forum where ideas are shared and
learning, and partnership working can be evidenced. Examples of housing projects being delivered by community groups include: 
 Colonsay Community Development Company have been developing a 12-unit, mixed tenure development at Scalasaig,
comprising affordable rent, worker housing and self-build development plots. Due for handover in summer 2024.
 Isle of Gigha Heritage Trust are close to completion on 5 affordable units at Ardminish.
 Mull and Iona Community Trust are supporting the Council in developing worker accommodation in Tobermory. 
These developments are supported financially by the Council but in turn the Council are indebted to all of the community groups for
their tireless efforts in improving housing in Argyll and Bute. 
PICTURE 4: COLONSAY (COMMUNITY HOUSING TRUST)     PICTURE 5: GIGHA (THE ISLE OF GIGHA HERITAGE TRUST) 
“We hope that by offering more suitable housing, it will allow our residents to free up larger family homes and be able to
live on Gigha for longer.”  Isle of Gigha Heritage Trust

Page 22

22 
Local Place Plans
Local Place Plans are community led exercises which can highlight the various needs, challenges and aspirations within communities.
A Local Place Plan submitted to the Council will be assessed for inclusion in the next Local Development Plan (LDP3), giving
communities an opportunity to have their community concerns recognised within the development planning process. Many
communities have expressed an interest in developing Local Place Plans, and some are already engaged with the Council and have
raised housing concerns through the Community Housing Network. 
Self-Build Register
Self-build housing is where an individual (whether acting alone or with other individuals) commissions or is personally involved in the
design and construction of a dwelling that is intended to be the individual’s main residence. Plots of land are often advertised for sale
in Argyll and Bute that are suitable for developing a home within. 
It is a duty within the Planning Act for planning authorities to create and maintain a self-build register. Both the Council and LLTNP
are developing self-build registers to gather expressions of interest from people keen to develop their own housing project within
Argyll and Bute. Understanding the demand for self-provided housing is important for both evidence-gathering for plan-making and
decision-taking. This list will help a planning authority understand more about the demand for self-build plots across their area 
Currently the Council register is being finalised for sharing and there are no expressions of interest within the national park area in
Argyll and Bute. 
Loch Lomond and the Trossachs National Park
The National Park is a designated planning authority and has its own policies and procedures relating to housing. During 2023/24,
approval was given for 9 housing units within the Argyll and Bute area of the National Park. These were all developments within the
open market, and not affordable housing. None were on allocated sites. 
A Futures Group workshop was held in early 2024 to define the necessary interventions to increase affordable housing provision
within the National Park. The outcomes of the workshop are being used to refine and develop policies necessary to achieve this.

Page 23

23 
LHS OUTCOME ONE: INCREASING SUPPLY VIA OTHER INITIATIVES

Page 24

24 
LHS OUTCOME ONE: MAKING BEST USE EXISTING STOCK / EMPTY HOMES 
Bringing empty homes back into use, continues to be a key focus for the Council and partners. During 2023/24 the Empty Homes
Officer has assisted 28 owners, allowing 30 empty homes to be brought back into use. Advice and assistance were the main support
provided, with 7 owners supported to obtain a reduced VAT rate of 5% on eligible renovation works, and 1 owner received grant
funding to help bring the property back into use. These figures highlight the importance of providing support owners and reducing the
number of ineffective homes across the area. 
TABLE 12: PROPERTIES BACK INTO USE – HOUSING MARKET AREA  TABLE 13: LENGTH OF TIME PROPERTIES WERE EMPTY
2023-24 Properties back in use per HMA  2023-24 Properties back in use- 
length of time empty
Bute and Cowal 8  Less than a year 2
Helensburgh & Lomond 6  Between 1-2 years 8
Oban, Lorn & Isles 11  Between 2-5 years 9
Mid Argyll and Kintyre 5  Between 5-10 years 3
TOTAL 30  Longer than 10 years 8   
TOTAL 30 
Empty homes projects can have many positive impacts for the owners
but also, for the economy, the environment, the local community,
and services. Not only do projects make best use of existing stock and
address housing needs, they can also significantly improve the outlook for
the area. The pictures highlight the difference that can be made to the 
appearance of renovating a long-term empty property which has been
unoccupied since 2016.                                  
Picture 6 and 7: Gigha project before and during works

Page 25

25 
Health & Social Care Partnership (HSCP) - Empty Homes Project
The Empty Homes Officer for HSCP has been in post since September 2023. This is a two-year kick starter project which has been
funded by Shelter Empty Homes Partnership and HSCP. This project seeks to address the impact that the shortage of housing is
having on recruitment for HSCP. The project will enable property owners to bring their long-term empty property back into use as
affordable housing to be leased to new HSCP employees coming to Argyll and Bute, as well as making best use of existing assets. 
There are considerable challenges working with HSCP as this is a partnership of Council and NHS. The HSCP is a large organisation,
it has taken time to secure and build solid connections with the correct locality and facility managers.  Building a strategic approach
has been key to ensure information is filtered to new employees accordingly and encouraging employees to contact Empty Homes
Officer with their requirements of accommodation type.  There has been a lot of proactive work carried out to address the project
challenges, including: 
 Long term empty property owners contacted; 
 Second Home owners contacted in light of the double charge of Council Tax; 
 Contacting active Landlords advertising their properties; 
 Commercial Buildings investigated as possibilities of renovation;
 Survey attached to HSCP recruitment with Empty Homes Officer details. 
Despite the challenges, there have been early successes, and several projects identified between partners for HSCP staff: 
 Argyll Community Housing Association (ACHA) have identified a four-bedroom house in Connel. £200k Strategic Funding has been
approved to enable the refurbishment to become a House Multiple Occupancy for up to four HSCP staff;
 Two NHS Houses on the Island of Coll (2 and 4 bed) will be brought back into use for HSCP staff requiring accommodation on the island to
deliver essential health and social care services, this project is supported by £100k Strategic Funding; 
 There is outline proposals to convert an empty NHS Dental Surgery on Isle of Islay into short term accommodation for HSCP staff.  An
application for Strategic Funding is in progress.
 Supported a new landlord on Islay with the process of transferring from a second home to leasing the property to a Mental Health Nurse. 
 The Care Home Manger on Islay received support and housing advice on applying to Home Argyll which she successfully secured a new
property.  The manager was previously staying in short term accommodation. 
 New Landlords carrying out extensive refurbishment on a flat in Dunoon were supported with Empty Homes advice and landlord registration
process.  The property was successfully leased to a Mental Health Nurse. The Landlords are keen to continue in supporting the HSCP
Empty Homes project with future properties they purchase.

Page 26

26 
LHS OUTCOME TWO: ENERGY EFFICIENCY, CLIMATE CHANGE & POVERTY 
LHS strategic aim two is: To regenerate communities by improving the quality, condition and energy efficiency of housing and by
tackling poverty, including Fuel Poverty and Child Poverty, and ensuring that Housing contributes to addressing the wider Climate
Change agenda. The associated strategic objectives are:-

Page 27

27 
LHS OUTCOME TWO: HOUSING SYSTEM - ENERGY EFFICENCY & FUEL POVERTY INDICATORS 
Addressing the impacts of Child and Fuel Poverty are key areas of concern for partners and identified as a priority for the LHS. 
Improving the quality, condition, and energy efficiency of properties can have positive outcomes for the household in terms of reducing
poverty levels; the outlook of homes; energy costs; health and well-being; and contribute to the climate emergency by reducing use
of carbon. 
Child Poverty in Scotland remains relatively high despite policy interventions such as the Scottish Child Payment.  The most recent
Scottish Government 2021-23 child poverty statistics, estimate that 24% of children in Scotland are in relative poverty, which is almost
one in four children.  This compares to 21% of working-age adults and 15% of pensioners estimated to be living in relative poverty.
Research published by End Child Poverty in June 2024 estimate that in 2022/23 23.5% children in Argyll and Bute are living in poverty,
an increase of 2.8% from 21.7% in 2021/22. 
Through initiatives such as, income maximisation services, affordable housing supply and energy efficiency programmes, partners
are taking pro-active action to try to reduce levels of poverty across all cohorts. 
Fuel Poverty can be driven by many different factors, which can include age and types of buildings; income levels; health conditions;
limited choice of fuel types; high cost of heating properties and how energy is used in the home. For households in Argyll and Bute
this can be include living in rural areas and being off the gas grid - approx.53% of properties in Argyll and Bute are off gas grid.    
There is not a single measure that determines the energy efficiency of all dwellings and the level of fuel poverty being experienced
by households.  The Scottish Fuel Poverty Advisory Panel*, report that 31% of households in Scotland are currently living in fuel
poverty and 20% of households are living in extreme fuel poverty.  The estimated fuel poverty figures for Argyll and Bute 30% are
just below the Scottish average; however, those in extreme fuel poverty 25% is above the Scottish average. The figures for Argyll
and Bute will fluctuate dependent on the locality and could be much higher in rural/remote areas. 
*These are Scottish Government estimates for April to June 2024. They are based on the price cap of £1,690 under the updated TDCV’s  of 11,500 Kwh Gas
and 2,700 KWH electricity for the typical dual fuel household. They have been produced by uprating modelled fuel bills from the 2019 Scottish House
Condition Survey (SHCS) in line with the price cap under the EPG and accounting for the other support available to households.

Page 28

28 
Energy Performance Certificate (EPC)            CHART 5: ESTIMATED EPC RATINGS IN A&B 
An Energy Performance Certificate (EPC) provides information about how energy efficient a
building is, and provides information on measures, which could improve the energy efficiency of
the building. EPCs rate buildings on a scale from A to G, with A being the most efficient.                                                                                                                               
The Home Analytics database used below to report levels of ‘fuel poverty’ in Argyll and Bute is
derived from several trusted sources and therefore some of the data is extrapolated to determine
overall approximate numbers.   EPCs are the primary data source. As not all residential buildings
have an EPC, they have developed a series of models to predict values for properties with missing
data. Figures reported are estimated and subject to change. The figures are in line with the data
reported by The Scottish Fuel Poverty Advisory Panel. 
SOURCE: HOME ANALYTICS
TABLE 14: ARGYLL AND BUTE FUEL ESTIMATED POVERTY LEVELS – HOME ANALYTICS
A&B AVERAGE FUEL POVERTY PROBABILITY LEVELS 2024  Estimated % of Properties  
Fuel Poverty = Fuel bill > 10% income after housing costs  30% 
Extreme Fuel Poverty = Fuel bill > 20% income after housing costs  25% 
Excess cold = Risk property exacerbating health inequalities  9% 
(SOURCE: HOME ANALYTICS 2024) 
Heating Type in Argyll & Bute - The 2022 Census reported that 4% of households in Argyll & Bute had NO central heating system.
45% used form of gas as heating; 19% have electric heating source; 13% use oil heating; 6% have renewable energy source; nearly
4% have solid fuel, wood or biomass systems; less than 1% have district, communal or other heating source; and nearly 9%
households reporting they have two or more types of central heating.   
Ofgem - Energy Prices – Every 3 months, Ofgem review and set a level on how much an energy supplier can charge for each unit
of energy including the standing charge.  There has been a welcome reduction in energy bills over the last year. However, average
bills will increase by 10% in October 2024, and whilst this is estimated to be 6% cheaper compared to same period for last year, this
will put many households under pressure to heat their homes during the winter months.

Page 29

29 
LHS OUTCOME TWO: HOUSING SYSTEM - ENERGY EFFICIENCY & FUEL POVERTY 
Energy Efficiency Scotland: Area Based Scheme (EES: ABS) 2023/24
The Energy Efficiency Scotland programme allows homeowners and private rented tenants to access grant funding to help undertake
fabric improvements to properties that will help improve the fabric of building, reduce their energy bills, and reduce energy
consumption contributing to a reduction in climate change.    
Argyll and Bute Council was awarded funding of £1,979,827 for the year 2023/24 which has helped 236 households by installing 361
measures. We have received an in principle funding award of £1,979,827 for the 2024/25 Area Based Scheme (ABS 12).  The
Council’s Scheme Proposal has been submitted to the Scottish Government for approval and includes particular emphasis on
reducing high levels of fuel poverty associated with island and remote rural areas.  
Argyll Community Housing Association (ACHA) Warm Homes Project 2023/24
In conjunction with Argyll Community Housing Association (ACHA), Argyll and Bute Council completed a joint project of insulation in
Tarbert and Bute in June 2024 utilising funding of £633,000 received from the Scottish Government.  In this final tranche, which
concludes a four-year joint project to insulate privately owned and privately rented properties in mixed tenure blocks of flats, 39
properties benefited from insulation measures.   
Home Energy Scotland (HES)
Ensuring that households can access holistic energy efficiency advice is critical to address fuel and child poverty, and also to
encourage fabric improvements to make homes more energy efficient.  Home Energy Scotland are key partners for the Council in
delivery of Area Based Scheme, energy efficiency advice, and funding checks for local residents.  During 2023/23 they interacted
with 3,995 households compared to 4,266 in the same period last year. 
ALIenergy
ALIenergy works across Argyll and Bute to promote sustainable energy use and renewable energy generation, to address fuel poverty,
and reduce carbon emissions. During 2023/24 they received 1,262 enquiries (564 of which were returning customers), delivered
3,344 advice sessions, and 1,235 referrals were made to partners and/or funds. The Affordable Warmth Team secured £249,969 in
client gains from crisis intervention support through energy vouchers, alleviation of fuel debt, help with energy bills and white goods.
In addition to the support from Home Energy Scotland, these statistics demonstrate the demand for services which improve energy
efficiency and reduce fuel poverty.

Page 30

30 
Local Heat and Energy Efficiency Strategies (LHEES) 
The Heat in Buildings Strategy (2021) sets out the Scottish Government’s aims and objectives for achieving net
zero emissions within buildings in Scotland by 2045. Local authorities will develop a Local Heat and Energy
Efficiency Strategy (LHEES) to realise these aims and objectives. The LHEES will be a locally led, tailored
approach to transitioning to climate-friendly heating sources and ensuring local domestic and non-domestic
buildings are more energy-efficient. 
The Council and key stakeholders will take a strategic approach to shape heating transition, with the LHEES covering the authority’s
entire administrative area. Argyll and Bute’s LHEES will reflect the local context and will aim to identify the most suitable
decarbonisation and energy efficiency solution for the area. The strategy will be published towards the end of 2024 after a period of
public consultation and will: 
 Reflect local priorities, policies and strategies. 
 Identify any potential Heat Networks.
 Set out how each segment of the building stock needs to change to reach net zero and develop a variety of pathways to
decarbonise the building stock.
 Identify strategic heat decarbonisation zones.
 Sets out the principal measures for reducing building emissions within each zone. 
 Prioritise areas where heat decarbonisation action will be undertaken. 
 Provide a strategic plan which can be used to target government funding and private investment for heat decarbonisation and
energy efficiency investment.  
Accompanying the Strategy will be the Delivery Plan, which will clarify roles and responsibilities in achieving the objectives and
actions outlined in the strategy, as well as developing a mechanism to deliver activities. The first iteration of LHEES will largely be
focused on delivery within the scope of the current and near-future funding, regulatory and policy landscape. For example, we are
prioritising the delivery of programmes which we have resources to implement such as the Area Based Scheme while providing a
pathway to meeting medium to long-term targets and objectives outlined in the strategy.

Page 31

31 
LHS OUTCOME TWO: HOUSING SYSTEM CONTEXT – HOUSING IMPROVEMENT 
The Council’s Housing Improvement Officers work closely with private sector home owners and wider project teams to deliver housing
improvement works via Scheme of Assistance.  During 2023/24 Officers supported works to 50 properties in 8 tenements across
Argyll and Bute contributing £150,128 of Private Sector Housing grant funding to works.  
TABLE 15: PRIVATE SECTOR HOUSING GRANT – HOUSING REPAIR AND IMPROVEMENT GRANTS 2021/22 TO 2023/24
Home Repair & Improvement Works Supported via Council 
PRIVATE SECTOR HOUSING GRANT (PSHG) 2020/21 2021/22 2022/23 2023/24
Tenements Repaired 7 6 8 8
Individual Units Retained 43 19 22 50
Feasibility Grants 5 6 3  5
Amenity Grants 2 5 6  6
PSHG Investment (* excludes funding for private sector adaptations) £89,515 £48,614 £400,671 £150,128
The Housing Service also works closely with colleagues in Economic Development to support the delivery of the Conservation Area
Regeneration Schemes (CARS) and Town Heritage Initiative (THI) projects.  Funding of over £600k has been committed from PSHG
for projects in Lochgilphead, Dunoon, Rothesay and Helensburgh.   
TABLE 16: PSHG FUNDING FOR CARS / THI PROJECTS – 2022/23 - 2024/25                           
PSHG funding for CARS/THI projects 2023/24
Project PSHG Contribution Tenements No of Properties 
Lochgilphead £320,414 4 17
Dunoon £105,000 1 5
Rothesay £39,784 2 9
Helensburgh £172,900 5 18
Total committed £638,098 12 49

Page 32

32 
LHS OUTCOME TWO: POVERTY – MAXIMISING INCOME
The council and partners are working closely to support households affected by the cost-of-living crisis to help mitigate the impacts
and to sustain our communities be helping to increase income. 
A&BC Welfare Rights Service
The Council’s Welfare Rights Team aims to ensure that the residents of Argyll and Bute are not missing out on their entitlement to
both UK and Scottish Government administered benefits and other related help. They provide a free, confidential and impartial
benefits advice, information and appeal representation service. They are dedicated to helping clients who have money worries and
to providing advice and assistance on welfare benefits with a key focus on maximising client income and reducing poverty. 
During 2023/24 the team assisted residents to claim over £4.45m in additional
benefits. This “client gain” is not just a figure, the support provided by Welfare Rights
can make a significant impact on individual’s lives. For example, it may mean being
able to put heating on, keep a car running or replace a broken appliance. In 2023/24
the transfer of clients from legacy benefits to Universal Credit and from Personal
Independence Payment to Adult Disability Payment was ongoing and this has led to
increased demand for Welfare Rights assistance. This demand will continue going
forward as more clients are transferred over and as Social Security Scotland
continue with the roll out of further devolved Scottish benefits. It is anticipated the
number of people accessing the service will continue to increase due to energy costs
and the impact of the cost-of-living crisis on families and individuals.
CHART 6: WELFARE RIGHTS INCOME 202324/24 
In 2023-24, the team assisted with 460 enquiries about Attendance Allowance, which is a benefit for those over pension age, who
have personal care needs due to illness or disability. This high number of cases reflects the aging population in the area.  An
award could increase income by £68.10 or £101.75 per week with potential to increase other benefit income whilst promoting
independence and wellbeing. 
Not all cases have a recorded financial gain, over 290 cases were closed after “general advice provided” and 495 benefit checks
were carried out. Many of these client’s will have been signposted to claim benefits themselves. Others may be advised of no benefit
entitlement following a benefit check and be referred/signposted to food banks, energy advice/vouchers and other support
mechanisms available.

Page 33

33 
A&BC Welfare Rights Case Studies 
The work of the Council’s Welfare Rights Officers continues to make a real difference to their clients and these case studies highlight
the impact that their work makes to those accessing the service. Some of the Welfare Rights team are funded by MacMillian Cancer
Support, so they can provide an enhanced Welfare Rights Service for people affected by cancer. 
Case study 1
An elderly couple contacted the service requesting a benefit check after recently moving to the area. They were homeowners in
receipt of Attendance Allowance (AA) at the lower rate. We assisted each of them with a review of their AA as they met the qualifying
criteria. They were both awarded the higher rate increasing their weekly income by £67.30 per week. The couple had thought they
wouldn’t be entitled to any further benefits as they had some savings. However after completing a full benefit check it was clear the
couple were entitled to Pension Credit Guaranteed (PC), an application was made and they were awarded PC of £330.96 per week.
As well as the total ongoing increase of £398.26 to their weekly income the client also received backdated AA and Pension Credit
totaling £4779.12.  The award of PC meant were then entitled to full Council Tax Reduction taking their 10 monthly payments from
£202.56 to £54.64. Additional help and benefits are available if Pension Credit Guaranteed is awarded such as help with heating
costs, dental treatment, glasses, hospital travel fares and a free TV licence if you are over 75 which was the case with this couple. 
Case Study 2 
A client was referred to us by MacMillan Cancer Support. We assisted the client to apply for Adult Disability Payment and the Limited
Capability for work related activity component within her Universal Credit award. Due to the client’s terminal diagnosis these
applications were fast tracked and awarded with 2 weeks of applying increasing her total weekly income by £262.76. They also
submitted a MacMillan Grant application and a one off amount of £300 was received. 
“Through the work of A&BC Welfare Rights Service and Citizens Advice Bureau more than £6.133m of
additional benefit income has been secured for households across Argyll and Bute”

Page 34

34 
LHS OUTCOME TWO: POVERTY – MAXIMISING INCOME 
Citizens Advice Bureau (CAB)
The Argyll and Bute CAB also provides a debt and welfare rights service on behalf of the Council.   During 2023/24 they secured
over £1.675m for clients. 
Flexible Food & Fuel Fund
Funded by the Scottish Government, the project enables the Council’s Welfare Benefit team to work with third sector partners
including Bute Advice Centre, ALIenergy and foodbanks, to support people who are struggling for money to cover food and fuel costs.
The Fund provides a one-off cash payment to families on low incomes to help with food and fuel. Claimants are offered a second
cash payment if they have engaged with support agencies in financial management. Over 95% of people receiving the first grant
payment engage, get the support they need and receive a second payment.  With an average financial gain of £1,525 per household. 
Scottish Welfare Fund –Community Care and Crisis Grants
The Scottish Welfare Fund is there to provide a safety net to vulnerable people on low incomes through the provision of Community
Care and Crisis Grants. These are available for residents of Argyll and Bute on a low income, to help with daily living expenses such
as food and bills, fuel or heating costs, emergency travel expenses, and for anyone fleeing domestic violence or facing exceptional
pressures caused by loss of income or employment.  During 2023/24 – 767 Crisis grants were awarded with total value of £79,731
and 370 Community Care Grants with total value of £509,437.    
Community Care Grants are provided to help a qualifying individual to establish or maintain a settled home.  They can also be used
to support families facing exceptional pressure. A qualifying individual is someone who, without assistance may be in prison, hospital,
a residential care establishment or other institution; or homeless or otherwise living an unsettled life.   
Crisis Grants can be awarded in a crisis to meet expenses that have arisen as a result of an emergency or disaster in order to avoid
an immediate threat to health or safety of an individual or family.

Page 35

35 
LHS OUTCOME THREE: SPECIALIST PROVISION AND INDEPENDENT LIVING 
LHS strategic aim three is: To enable people to live well, with dignity and independently for as long as possible. The
associated strategic objectives are:

Page 36

36 
LHS OUTCOME THREE: SPECIALIST PROVISION & PARTICULAR NEEDS: CONTEXTUAL INDICATORS 
In 2023/24, the HOMEArgyll partnership of local housing associations rehoused 101 households in specialist accommodation,
amounting to just over 13% of the total HOMEArgyll lets that year. An increase of 22 compared to 79 in 2022/23.  This included:  
 47 lets - Amenity Housing 
 41 lets - Sheltered Housing 
 11 lets - Wheelchair Accessible Housing
  2 lets -  Supported Accommodation  
In addition, the national specialist associations operating in Argyll & Bute, such as Link and Trust, accommodated over 36
households and individuals in housing for particular needs. 
The demand for specialist provision and accommodation for particular needs is evidenced by households on the HOMEArgyll list
who require distinct property types.  As at April 2024 over 26%* of those on the list required some form of specialist housing
including: wheelchair suitable housing; housing with support; amenity/elderly housing; and sheltered housing. 
Further analysis of the HOMEArgyll list highlights several key indicators for the requirement of particular housing and support
services to meet varying needs.   
 37% state their medical condition is affected by current housing circumstances
 34% of primary household members declared some form of disability
 12% require support or assistance living in their home
 6% have severe health issues
 5% need to move home to access specialist support services 
 9% of primary applicants are aged 65-74
 6% primary applicants are aged 75 or over (with 11 applicants aged 90+) 
* Applicants can select multiple housing options including General Needs/ Mainstream housing, therefore there may be a small element of double counting
across the figures if applicants have selected more than one housing option.

Page 37

37 
LHS OUTCOME THREE - HEALTH & SOCIAL CARE 
The LHS vision and outcomes support the overarching objectives of both the HSCP Strategic Plan and the Argyll and Bute Outcome
Improvement Plan, as well as helping to address the national housing, health and well-being outcomes for Scotland. The housing
sector has an important and direct contribution to make to these national health and well-being outcomes as well as the local service
priorities identified in the HSCP Strategic Plan.  
Partnership working and investment will help to increase the provision of affordable housing and aids and adaptations across all
tenures; improve the condition and energy efficiency performance of homes; and deliver support, advice and assistance on a range
of housing options, as well as tackling poverty, improving health and well-being, and generating additional income / benefits for
vulnerable households.  
The Argyll & Bute Housing Contribution Statement was published in 2022, following a comprehensive revision for inclusion in the
Health Social Care Partnership’s (HSCP) Joint Strategic Plan for 2022/25. Work has started on preparation for updating the Housing
Contribution Statement for the next Joint Strategic Plan due in 2025.  As part of this process, Housing Services have been working
closely with HSCP/NHS partners on development of the Joint Strategic Needs Assessment during 2023/24.   
Shaping Places - Place and Wellbeing Assessment Report
The recommendations from the Improvement Service ‘Place and Wellbeing Assessment’ review of the Argyll and Bute HSCP Joint
Strategic Plan and Joint Commissioning Strategy will be taken into account during development of the next Plan. These include: 
 Strengthen the role of prevention, specifically opportunities to link with Council plans for housing developments and employability
initiatives; 
 Include more detail on housing needs to support workforce development and sustainability;
 Include reference to the benefits of sharing data relevant to housing and links with Council housing plans, including locations of
new developments, mix, density and tenure of housing;
 Include more emphasis in the plans on the role of housing in the prevention of poverty, particularly in relation to child poverty and
links to mental health;
 Investigate how the proposed statutory duty for preventing homelessness is to be included and identify how it can link up with
duties for other statutory organisations;
 Include references within the plans to good housing models that promote wellbeing and the benefits to preventative healthcare.

Page 38

38 
Equipment & Adaptations - Scheme of Assistance 
The provision of equipment and adaptations are an essential component of an integrated health & social care service to support
individuals to live in their own homes as independently for as long as possible.  The type of adaptations that can be undertaken to
properties varies from minor to major and can include items such as: installation of safety rails; non-slip/tactile surfaces; alterations
to doors, electrics, or plumbing; external paths, steps, paving; door access; stair lifts/hoists; and accessible showers/baths. This helps
facilitate improved quality of life and can have positive impacts on mental health and well-being, as well as being a cost effective
model of housing intervention. 
The Scottish Government published revised guidance for the provision of equipment and adaptations in March 2022.  The key
principles and aims of the new guidance, which includes, among others: Early intervention with full exploration of rehousing
opportunities; Better planning for the delivery of barrier-free housing and an inclusive design / living approach; and Equity in the
system, applying a “tenure neutral”” approach (as far as practicable).  Our Scheme of Assistance has been reviewed during 2023/24
reflecting the new guidance to facilitate improvements for those who require home adaptations to live as independently as possible.
This is due to go to Council later in 2024 for approval.    
Private Adaptations
During 2023/24 the Council’s Scheme of Assistance supported 70 private owners to undertake adaptations to their homes with
support of £440k Private Sector Housing Grant (PSHG).  Care & Repair supported 69 private owners with the adaptation process. 
RSL Adaptations
Our Registered Social Landlord partners undertook approx. 352 adaptations to 235 of their properties in 2023/24 with around £633k
of Stage 3 grant funding from Scottish Government to support independent living.   
Housing for Older People in Scotland 
As detailed in Outcome 1, Argyll and Bute has an ageing population which will impact on our housing need and provision.   A summary
briefing from the UK Collaborative Centre for Housing Evidence published in May 2024, highlights housing for older people as a key
priority area for the housing sector alongside health and social care. The report acknowledges the extra challenges for rural areas
where the ageing demographic is increasing at higher rates and the crucial role of the planning system, and cross-tenure intervention
plays to address. Practical recommendations include; a new housing strategy for older people; renewed focus on housing need and
demand to integrate the housing requirements of an ageing population; and linking age-appropriate housing to a preventative
approach with health and social care partners, including a tenure-neutral, adequately funded adaptations system.

Page 39

39 
LHS OUTCOME THREE: GYPSY/TRAVELLERS 
The two official Gypsy/Traveller sites in Argyll and Bute at Duncholgan, Lochgilphead and Bayview, Ledaig that are owned and
managed by ACHA, who are the only Registered Social Landlord in Scotland operating sites; whilst the Council have the strategic
obligation to take into account the Housing Needs and Demands of Gypsy/Travellers. 
 Dunchologan – There are 7 pitches on the site.  At the end of financial year 2023/24 all 7 pitches were occupied.  
 Bayview –There are 4 pitches on the site.  At the end of 2023/24 all 4 pitches were occupied.    
Gypsy/ Traveller Site Improvement Works
There are significant improvement works required to both sites. ACHA engaged Architects who have worked with the community to
develop design proposals for improving the accommodation, facilities, and layouts of both the sites. Due to the substantial investment
that will be required to take forward the finalised design plans, we are continuing to engage with ACHA, partners and the Scottish
Government in relation to when the next round of the Gypsy/Traveller Accommodation Fund will be available. At this time, it is
anticipated that there will not be a further round of funding until at least 2025. ACHA will continue to engage with the community and
keep them updated with a view to applying for funding at earliest opportunity to enable the longer-term improvement works required
to sites to be taken forward.  
Gypsy/Traveller Working Group - The Gypsy/Traveller Working Group (GTWG), which was established in 2022, has continued to
bring together key partners to collectively engage with the community and work with them to deliver community priorities and
improvements.  The core membership includes representation from the key strategic partners involved in delivering accommodation,
health, education, advocacy, and community safety, as well as community representation, which is central to the effectiveness of the
group. There have been several guest speakers over the year raising awareness of local services such as the Poverty Alliance. 
MECOPP (Minority Ethnic Carers of People Project) - continue to support Gypsy/Traveller community in Argyll and Bute and help
facilitate on-going engagement. This dedicated resource has helped to encourage and improve partnership working and participation
in the Working Group. 
LACER Funding -The Housing Services secured £10k LACER funding for the Gypsy/Traveller community. MECOPP are working
with Bute Advice to ensure that the community are able to access funding support they may be entitled to and are helping break
down any barriers that the community are experiencing in being able to access support.

Page 40

40 
LHS OUTCOME THREE - EQUALITIES MONITORING 
The Housing Service ensure that all households approaching the Council for housing advice are treated fairly, with dignity and respect.
We have implemented an enhanced equalities monitoring & evaluation framework for our key functions. 
As well as a full Equalities and Socio-Economic Impact Assessment, the Council has carried out impact assessments for the LHS in
respect of Human Rights, Children’s Rights and Wellbeing, Island and Rural Communities, as well as a Health Impact Assessment.
A copy of these is available on the council website: localhousingstrategy@argyll-bute.gov.uk  
Our statistics are regularly analysed to identify any emerging trends, where these are identified then service improvements will be
brought in to ensure that households are provided with the service that meets their needs and that equalities and human rights
legislation requirements are being met. 
There will be positive impacts on service users through this additional analysis as it will help Housing Services better understand the
needs of households. Equalities data monitoring is reported annually to Housing Management Team, the Strategic Housing Forum
partnership, the Scottish Government, and Scottish Housing Regulator.  
For example, in relation to Homelessness Equalities Monitoring, the Housing Services produce a quarterly report on the following
information:- 
 The number of males presenting as homeless
 The number of females presenting as homeless
 The number of households with children presenting as homeless
 The ethnic origin of all households presenting as homeless
 The number of households presenting as homeless as a result of domestic abuse
 The number of households who stated that they slept rough the night before making a homeless application
 The number of households who stated that they slept rough within three months of making a homeless application
 All households who identified that they had at least one support need when they made a homeless application

Page 41

41 
LHS OUTCOME FOUR: HOUSING OPTIONS, INFORMATION & SUPPORT 
The LHS strategic aim four is: To provide effective and timeous information, advice and support to help
persons in housing need to make informed choices and decisions on the range of Housing Options
available. The associated strategic objectives are to:-

Page 42

42 
LHS OUTCOME FOUR: HOMELESSNESS CONTEXT 
Many households are threatened with or facing homelessness.  Shelter Scotland now estimate that every 16 minutes a household
becomes homeless in Scotland.    
The Argyll and Bute Homeless Service staff provide vital support, information and advice to households who have nowhere to live,
are worried about losing their home, or need advice on their housing options. Our priority is to try and help people stay in their home,
and where this is not practically possible staff will assist households to find alternative accommodation including provision of
temporary accommodation when required. 
During 2023/24 the Housing Service received 492 homeless applications in Argyll and Bute which is a slight reduction from 512
applications in the previous financial year.                          
Homelessness can affect everyone and the type of households requiring assistance during 2023/24 varied. Table 17 shows
breakdown of household types. Presentations from single households account for 65% of cases and 23% of homeless presentations
last year involved children. 
The main reasons for presenting as Homeless in 2023/24 were due to ‘Non-violent dispute in household/relationship breakdown
(28%)’ or being ‘asked to leave current accommodation (18%)’. However there has been an increase in households presenting due
to overcrowding (48% increase), compared to 2022/23. Table 20 records the reasons for homelessness over the last four years. 
As at the end of March 2024, there were 125 households in temporary accommodation, including 27 households with children. Whilst
the average time for homeless applicants to be rehoused has reduced, on average it still takes 31 weeks to be offered permanent
accommodation.  These statistics highlight the urgent need for more affordable housing across the area.

Page 43

43 
TABLE 17: HOMELESS PRESENTATIONS BY HOUSEHOLD TYPE 2019/20 TO 2023/24
Homeless Presentations by Household Type 2019/20 2020/21 2021/22 2022/23 2023/24
Single Person 295 257 253 303 322
Single Parent 77 104 66 98 88
Couple 34 31 37 57 34
Couple with Children 22 16 32 45 35
Other  2 6 1 9 13
Other with Children 4 1 9 0 0
All 434 415 398 512 492 
TABLE 18: HOMELESS PRESENTATIONS BY AREA 2022/23 & 2023/24
Homeless Presentations by Area 2022/23
and 2023/24
Number Number
2022/23 2023/24
Bute 37 41
Coll & Tiree 1 1
Cowal 114 105
Helensburgh & Lomond 121 87
Islay, Jura & Colonsay 25 15
Kintyre 25 47
Lorn  116 121
Mid-Argyll 70 72
Mull & Iona 1 3
Out with the area 2 0
TOTAL 512 492 
TABLE 19: AVERAGE TIME FOR HOMELESS CASE TO BE REHOUSED
Homeless Case Durations 21/22 22/23 23/24
Average time to discharge duty (weeks) 38 33 31

Page 44

44 
TABLE 20: REASONS FOR PRESENTING AS HOMELESS 2019/20 TO 2023/24
REASONS FOR PRESENTING AS HOMELESS 2019/20 2020/21 2021/22 2022/23 2023/24
Termination of tenancy / mortgage due to rent arrears / default on payments 25 7 9 12 11
Other action by landlord resulting in the termination of the tenancy 51 32 50 73 60
Applicant terminated secure accommodation 8 3 2 6 8
Loss of service / tied accommodation 13 19 14 22 25
Discharge from prison / hospital / care / other institution 19 15 12 15 13
Emergency (fire, flood, storm, closing order from Environmental Health etc.) 2 3 0 1 3
Forced division and sale of matrimonial home 2 6 1 4 1
Other reason for loss of accommodation 31 26 16 41 29
Dispute within household: violent or abusive 33 35 25 28 32
Dispute within household / relationship breakdown: non-violent 110 115 105 150 139
Fleeing non-domestic violence 13 11 10 17 18
Harassment 5 13 7 12 10
Overcrowding 18 19 18 21 31
Asked to leave 78 83 107 87 88
Other reason for leaving accommodation / household 26 28 22 23 24
All 434 415 398 512 492
TABLE 21: NUMBER  HOMELESS CASES WAITING FOR PERMANENT HOUSING AS AT JUNE 2024
Total Number of Statutory Homeless Cases Waiting for Permanent Housing as at June 2024
68% of statutory homeless
households are waiting for a one
bedroom property 
44% of statutory homeless
households waiting for a one
bedroom property in 
Lomond or Lorn
Area 1 bed 2 bed 3 bed 4 bed Total
Bute  1  1 0   0  2
Cowal  26  7 4   1  38
Kintyre  11  5 1   0  17
Lomond  54  16 10   5  85
Lorn 42  8 3   0  53
Mid Argyll  15  5 1   3  24
TOTAL    149  42 19   9 219

Page 45

45 
LHS OUTCOME FOUR: HOUSING OPTIONS, INFORMATION & SUPPORT 
Homeless Prevention and Advice – Prevent 1
All local authorities have a statutory duty under the Housing (Scotland) Act 2001 to provide advice and assistance on housing
options to try and prevent and alleviate homelessness. 
The Housing Service had 1,135 ‘Prevention and Advice’ cases in 2023/24 which increased slightly from 1,123 in 2022/23. The majority
were in relation to households seeking advice in respect of ‘General Housing Advice (410).  Of the 1,135 cases, only 235 went on to
make a homeless application which is the lowest since peak of 409 cases in 2017/18, this highlights the pro-active approach to
homeless prevention and the importance of households receiving appropriate advice and assistance at an early stage. 
Rapid Rehousing Transition Plan (RRTP) / Housing First
RRTP funding was made available for a five year period (2019 to 2024) and has been extended for a further year to 31/03/25. The
main projects funded in 2023/24 include:  
Rent Arrears Prevention Funding – assists households who are at risk of homelessness due to rent arrears. Payments are made
direct to the landlord to prevent eviction action. Signposting to appropriate support services and Welfare Rights Team is offered to
enable the household to sustain their tenancy. £92,886 has assisted 85 households to remain in their tenancies during the period
01/04/2023 to 31/03/2024.  
Mental Health Addictions Practitioner - is engaging with Housing First cases and some of our more complex cases across the
local authority area.  
Decoration Project – many homeless households are on low incomes and often cannot afford to decorate their properties or bring
them up to a standard where they take ownership of their house, see it as their home and therefore a greater chance of sustaining
their tenancy. £3,829 has been paid during the period 01/04/2023 to 31/03/2024.   
Housing First – is delivered within the overall RRTP and aims to give the most chaotic and vulnerable homeless households housing.
Appropriate support is provided to ensure tenancy sustainment and achieve positive outcomes.

Page 46

46 
There are currently 12 Housing First cases. Of these, 8 have live housing association tenancies: 2 in Oban, 3 in Helensburgh, 2 in
Campbeltown and 1 in Cowal.  £23,516 has been paid during the period 1st April 2023 to 31st March 2024, to provide white goods
and furnishings to Housing First tenants.  
Flexible Emergency Fund – provides monies to contracted housing support providers to assist households at the point of crisis. 
£1,000 has been paid during the period 1st April 2023 to 31st March 2024.  
Starter Packs – provides funding to local organisations that supply household starter packs to people presenting as homeless. The
packs contain various essential items e.g. bedding, kettles, cutlery, crockery and toiletries. £5,000 has been paid during the period
1st April 2023 to 31st March 2024.  
TABLE 22: RAPID REHOUSING TRANSITION PLAN 2019 -2024 SPEND TO DATE (1ST APRIL 2019 TO 31ST MARCH 2024)
Rapid Rehousing
Transition Plan 
2019 -2024 spend to date
Spend No of Households
Assisted
Rent Arrears Prevention £368,528 296
Mental Health Addictions
Practitioner
£80,124  
Decoration Project £80,573 110
Housing First £29,719 11
Flexible Emergency Fund £21,500  
Starter Packs £5,000   
Total  £585,444 417

Page 47

47 
Section 11 Notices
The Homelessness etc (Scotland) Act 2003 places an obligation on social and private landlords, as well as creditors to inform the
local authority where they plan to evict a tenant by raising proceedings for possession of the property or serve certain notices relating
to the standard security.  The key purpose of Section 11 Notice is to give local authorities advance notification of households who
may be at risk of homelessness so they can engage with the household to try and prevent them from becoming homeless. The
number of Section 11 Notices received by Housing Service since 2020/21, has fluctuated and will be impacted by the temporary ban
on evictions imposed by Scottish Government which ended in March 2023 (exceptions in place for serious anti-social behaviour and
domestic abuse).  There has been significant increase in number Section 11 Notices being received during 2023/24 which is being
monitored, with homeless staff continuing to pro-actively engage with households affected. 
TABLE 23: SECTION 11 NOTICES RECEIVED SINCE 2020/21 
Section 11 Notices
Received  Total
Source of Referral 
Private
Landlord RSL
Creditors –
including Bank or
Building Society
2020/21 3 3    
2021/22 46 4 16 26
2022/23 21 4 5 12
2023/24  151 12 87 52   
Homelessness Prevention – Housing (Scotland) Bill
The new Housing (Scotland) Bill, legislation was published in March 2024 and focuses on several topics that affect homelessness. 
The Bill includes a new ‘ask and act’ duty for a range of public bodies requiring them to ask about a person's housing situation and
take specific actions to reduce the risk of homelessness, this will include health and social care, Police, children’s services, social
landlords, and the criminal justice sector. The Bill sets out a framework for the new homelessness prevention duty with further details
to be introduced in secondary legislation or regulations/guidance following further consultation and scrutiny by the Sottish Parliament. 
The Housing Service works closely with partners and will continue to engage as the new Bill and associated policy develops to ensure
that a co-ordinated approach to implementation of duties between partners is achieved.

Page 48

48 
LHS OUTCOME FOUR: HOUSING SUPPORT 
Tenancy Support
The Council’s Housing Service is committed to preventing homelessness and helping people to stay in their own homes. 
Housing support helps vulnerable people or those at risk of losing their homes, with support tailored to meet the specific needs of the
individual. The Housing Support Service aims to: assist people to sustain their tenancies and prevent homelessness; support
homeless clients to prepare for the allocation of a permanent home; provide quality services and work with internal and external
partners to ensure Best Value; and promote independent living. 
Due to the high demand for support, the ‘Prioritisation of Need Framework’ is used to prioritise those who are homeless or threatened
with homelessness for support.    During 2023/24 there were 299 new referrals received and 248 were onward referrals.  The 51
cases who were not referred included cases where the person referred did not wish an onward referral, chose to use drop in service,
returned home or did not respond to telephone calls/email/letter and also included in this figure. There were 18 referrals who could
not be taken on for support due to hours being at capacity due to being Priority 4 and/or other support services in place for example
Social Work.    
At the end of March 2024 there were 187 households in receipt of tenancy support, 38 (20%) households were statutory homeless.
There were 288 departures from support during 2023/24 - 224 (78%) were planned departures and 64 unplanned departures.    
Domestic Abuse / Women’s Aid 
Argyll and Bute Council are one of over 400 Organisations who have signed up to the ‘Make a Stand pledge’ which was developed
by the Chartered Institute of Housing in partnership with Women’s Aid and the Domestic Abuse Housing Alliance. The pledge was
created to encourage housing organisations to make a commitment to support people experiencing domestic abuse. 
The Council’s Housing staff work closely with Women’s Aid who are the lead organisation in Scotland working towards the prevention
of domestic abuse. Women’s Aid play a vital role coordinating, influencing and campaigning for effective responses to domestic
abuse and supporting those subjected to domestic abuse. During 2023/24 Women’s Aid received 30 referrals for support in Argyll
and Bute. This is significant reduction on 171 referrals received last year.

Page 49

49 
LOCAL HOUSING STRATEGY PROGRESS 2023/24
The annual progress in 2023/24 against each of the four outcomes has been collated in Action Plan table below.  Reference to the
links to Housing Emergency Plan at Appendix 1 has been added to each of the indicators. 
TABLE 24:  PROGRESS MADE AGAINST KEY ACTIONS AND OUTPUT TARGETS IN 2023/24 
LHS OUTCOME ONE – HOUSING SUPPLY AND PLACEMAKING PROGRESS 2023/24 
RELEVANT INDICATORS
BASELINE
HISTORIC
TREND
2023/24
ANNUAL
&    
5-YEAR
TARGET
ASSESSMENT / COMMENT ON
PROGRESS
1.1 Number of new house building completions (all tenure) 2020/21: 228
2021/22: 275
2022/23: 340 144 
290 per
annum
(1,450)
National Register Scotland new
build sales figures + SHIP figures Links to HE Action 1.1, 1.2, 1.5, 1.6, 2.1, 2.3
1.2 Number of new private market homes completed 2020/21: 172
2021/22: 156
2022/23: 152
74 
75 per
annum
(375)
National Register Scotland new
build sales figures  Links to HE Actions 1.1; 1.4; 1.6; 1.7
1.3
Number of new affordable RSL homes completed.
Baseline/ Historic Trend data from Scottish Government Housing
Statistics & Planning estimates; “2021/22” figure sourced from
Council Planning records & SHIP monitoring data 
2020/21: 56
2021/22: 119 (146
ABC HousingStats) 
2022/23: 180
70  215 per
annum 
(1,075) 
39% of previous year figure and is
short of the ambitious 215 target. 
(Council / SHIP figures vary due to
differences in reporting systems)  
Links to HE Action 2.1, 2.4, 2.6, 2.9
1.4
Total Investment in completed SHIP projects (value of
projects completed in year NOT actual spend in that year for
ongoing work) 
*2021/22 - (+c.£24m for  Dunbeg units)
2020/21:
£6.767m
2021/22:
£4.522m 
2022/23:
£6.173m
£15.122m
Maximise
RPA, SHF, &
RSL funding
above
baseline
£1,150,707 Eton Avenue
£13,971,312 Dunbeg. Figures from
SHF applications and HARP.
Dunbeg is a pro-rata cost based on
overall package for 300 homes.   
Links to HE Action 2.4, 2.9

Page 50

50 
1.5 
5 year effective housing land supply (unit capacity) /
Local Housing Land Requirement (LHLR) 
2021: 2,889 
2022: 2,684
2023: 2,591
3,010  4372 
(10 year
target)
LDP2 identifies a LHLR of 3000
units between 2020 and 2030, this
number being reduced by an agreed
percentage to account for years
already elapsed. Thus the figure
shown is the remained of the 10
year LHLR, supplemented by
approved and expected windfall
sites. 
Additional capacity also available
within National Park area of Argyll &
Bute which is currently under review
due to NPF4. 
Links to HE Action Plan 1.2, 1.5, 1.8, 2.2, 2.4, 2.5,
3.5, 4.9
1.6 
Number of alternative/intermediate tenure homes
completed via the SHIP (% of total completions) 
2020/21:4 (8%)
2021/22: 2 (1%)
2022/23: 24
(13%)
16 
(23%)
(10-15% of
total 
completion
s)
Target met with 11 New Supply
Shared Equity (NSSE) and 5 Mid-
Market Rent properties developed 
Links to HE Action Plan 2.4, 2.8, 2.9, 3.1, 3.3, 3.4
1.7
Number of households housed through Common
Housing Register (CHR) / RSL tenancies created 
2020/21: 631
2021/22: 733
2022/23: 811
(951)
763  860 per
annum 
(4,300)
LINK, & TRUST RSL Lets would
raise total to 850 last year which is
just below target. (Trust-15, Link-
72) Links to HE Action Plan 2.9, 4.4
1.8 
Nos. of empty homes brought back into use  (all cases
involving Empty Homes Officer) 
2020/21: 29
2021/22: 38
2022/23: 41
31
(+ 2
HSCP
Project)   
30 per
annum
(150) 
In addition to the cases where the
Empty Homes officer has supported
owners to bring properties back into
use, the HSCP Empty Homes
Project Officer has also worked with
private owners to bring 2 empty
homes into use for workers. 
Links to HE Action Plan 1.6, 2.4, 4.1 4.2, 4.10

Page 51

51 
LHS OUTCOME TWO – ENERGY EFFICENCY, CLIMATE CHANGE AND POVERTY PROGRESS 2023/24 
RELEVANT INDICATORS
BASELINE
HISTORIC
TREND
2023/24
ANNUAL
&    5
YEAR
TARGET 
ASSESSMENT / COMMENT ON
PROGRESS
2.1 
Number of properties improved with energy efficiency
measures & total grant investment via the Energy
Efficiency Scotland: Area Based Scheme  (operates on
July-June timeframe) 
2020/21: 237 &
£1.496m
2021/22: 105 &
£560,511
2022/23: 288 &
£2.312m
236 &
£1.775m 
280 homes
pa
(1,400
homes
& at least
£4.875m)
Works to 236 properties with 361
measures installed to value of
£1,775,533
2.2 
Nos of households receiving advice & assistance on
house condition/ energy improvement and/or home
safety works
*Home Energy Scotland (HES) data 
2020/21: 2,901 
2021/22: 2,120 
2022/23: 2,554 
2,245
referrals 
2,000
cases
completed
pa
(10,000
closed by
2027)
HES – 3,955 household interactions;
2,245 referrals to range of
schemes/partners; 578 Warmer
Homes measures installed;
In addition, ALIenergy – 1,262
clients registered in year.
Links to HE Action 4.6
2.3 Annual Household Income Generated by Council’s
Welfare Rights Service
2020/21:
£3.364m
2021/22:
£2.736m
2022/23: £4.3m
£4.458m £2.75m
(£13.75m)
Effective support services continued
to be delivered; resulting in
successful generation of
income/benefits for vulnerable
households, which was 62% more
than target of £2.75m. 
In addition, CAB secured £1.675m
for clients
2.4
Progress on approving & implementing the Scheme of
Assistance (SoA),  incorporating strategy for homes
failing Below Tolerable Standard (BTS)  & policy on
Compulsory Purchase Orders (CPOs)
Previous SoA
approved 2016
Review started 
New SoA
drafted 
SoA to be
approved &
implemented 
New Scheme of Assistance
incorporating policy on CPO and
BTS reviewed with a view to
implementing revised update in
2024.
2.5 % of RSL properties achieving Energy Efficiency
Standard for Social Housing (EESSH1) compliance
2020/21: 88%
2021/22: 87.6%
2022/23: 92.4% 
87.8% 
Compliance
by 2032 for
EESSH2
target.
Average for ACHA, DHA, FH,
WHHA, Trust & Link); no return for
Bield, Key, Cairn or Blackwood)
Figures revised by RSL when EPC obtained

Page 52

52 
2.6 Nos of private properties improved with PSHG aid, or
assistance from ABC Housing Improvement Officers
2020/21:43 -
£89,515
2021/22: 19 -
£48,614
2022/23: 22 -
£400,671
50
Properties 
£150,128
(400
properties
& grant
spend of
£2m)
8 tenements received repair and
improvement grants totalling
£150,128 & 50 individual homes
received repair & improvement
works
LHS OUTCOME THREE: SPECIALIST PROVISION AND INDEPENDENT LIVING PROGRESS 2023/24
RELEVANT INDICATORS
BASELINE
HISTORIC
TREND
2023/24
ANNUAL
&    5
YEAR
TARGET 
ASSESSMENT / COMMENT ON
PROGRESS
3.1 
Housing Contribution Statement (HCS) revised &
approved for inclusion in HSCP Strategic Plan; Housing
OT post established as permanent and Action Plan
reviewed and agreed. 
2020/21: OT post
piloted
2021/22: OT post
made permanent
2022/23: Revised
HCS 
HCS/OT
Action Plan
fully
delivered
by 2027
Housing OT established joint area
partnership groups with RSLs;
implemented review of waiting lists;
improved assessment procedures &
data collation/case monitoring; early
engagement in new build design and
allocations for SHIP projects. Links to HE Action 4.2
3.2
Number of RSL and Private Homes adapted with grant
assistance; and Total grant (all tenures)  2020/21: 309
£1.15m
2021/22: 319
£1.146m
2022/23: 305
£925k
302
homes &
£1m+ 
c 350 pa 
(1,750 with
£5.5m
grant by
2027)
Scottish Government enabled 352
adaptations in 235 RSL properties
with £632,510* Stage 3 grant
funding. *Excludes funds not yet
drawn down. The Council’s PSHG
supported adaptations to 67
properties with £370,815 Grant.  Links to HE Action 4.6
3.3 Nos of telecare unit installations & total clients in receipt
of Technology Enabled Care (TEC) service at year end.
2021/22:
1,774 installs &
1,994 clients as
of March 2022
2022/23: 
2,056 clients
Installs: n/a
2,074
clients &
2248
installs 
By 2027,
4,500
clients to
have 5,700
installs;
and over
2,000
active
clients.
During 2023/24 the TEC team
supported 2,074 clients with
installation of 2,248 installs to assist
them to remain safely and
independently at home

Page 53

53 
3.4 
Nos & % of specialist subsidised new builds completed
via SHIP 
2020/21: 1
2021/22: 22
2022/23: 36
19 
(27%) 
5% of SHIP
new builds
are
wheelchair
units & 5%
are other
specialist 
Increase in number of specialist new
build homes delivered. 27% of
annual SHIP total, including 12
wheelchair adapted units (17%) and
7 amenity/older person units (10%).   Links to HE Action 4.6
3.5 Improvements to official Gypsy/Traveller sites &
satisfaction levels
2020/21: 
No survey 
2021/22: No
survey 
2022/23: 75%
43%
100%
satisfaction 
7 out 11 residents. The GTWG
continues to engage with partners
and community to address current
site conditions and to identify funding
to take improvements forward. 
3.6
Enhanced Equalities monitoring & evaluation framework
established and annual reports produced  2020/21: HNDA
published
Data and
indicators
reviewed 
Annual
Report for
all Housing
functions 
Range of LHS Impact Assessments
published online. Enhanced 
Equalities homelessness reporting
implemented 2022/23. 
LHS OUTCOME FOUR: HOUSING OPTIONS, INFORMATION & SUPPORT PROGRESS 2023/24
RELEVANT INDICATORS
BASELINE
HISTORIC
TREND
2023/24
ANNUAL
&   5
YEAR
TARGET 
ASSESSMENT / COMMENT ON
PROGRESS
4.1
Protocols for persons leaving an institutional setting
including hospital discharge, looked-after children,
armed forces, prison, or evictions 
Looked after
Children
Protocols in
place; Armed
Services
Covenant.
Existing
protocols
for
Looked
After
Children. 
Protocols
drafted &
consultation
carried out
by 2023.
Protocols
agreed & in
place by
2024 
Review / work on protocols for
hospital discharge, those leaving
care setting, and evictions.           
14 Homeless cases due to
“Discharge from prison / hospital /
care / other institution”; there was 1
homeless application from leaving
looked after care setting directly and
6 cases where had been “Previously
Looked After by LA within last 5
years”

Page 54

54 
4.2
Housing sector enables an effective response to
meeting the needs of those experiencing domestic
abuse
2020/21: 128
CHR applicants
35 Homeless
cases 
2021/22: 100
CHR applicants
25 Homeless
cases
2022/23: 104
CHR
28 Homeless
CHR 61 
32
Homeless
cases 
Homeless
& CHR
applicants
due to
Domestic
Abuse
reduced
below
baseline.
The number of Common Housing
Register (CHR) applicants “being
abused by someone in household”
has reduced. However, Homeless
cases due to domestic abuse have
increased on previous year’s figure.
4.3 Rural Housing First Initiative in Argyll and Bute –
number of tenancies created
Protocols agreed
with RSLs
2021/22 = 1
2022/23 = 6
7 new
tenancies
10
tenancies
pa (50 by
2027)
The initiative was developed in
2021/22. 7 Housing First tenancies
have been created in 2023/24 
4.4
Rough Sleeping presenting as Homeless
(based on HL1 statistics: as reported at Homeless case
interviews)
2020/21: 6% slept
rough night before
& 10% within
previous 3 months
2021/22: 4% slept
rough night before
& 7%  within 3
months
2022/23: 5% slept
rough night before
& 7% within 3
months
7% slept
rough
night
before & 
11%
within 3
months 
Incidence
reduced
below
baseline/
Scottish
Average
Based on information provided by
households presenting as homeless,
7% of homeless cases slept rough
the night before presenting (33 out
of 492); while 56 slept rough within 3
months previously (11% of total
cases      
4.5
HL1 presentations from Prison securing positive
housing outcomes (supporting Community Justice
agenda)
2020/21 – 2 of 4
closed cases
(50%)
2021/22 – 12 of
16 closed cases
(81%)
2022/23: 5 of 11
closed cases
(45%)
3 of 5
cases 
Levels
sustained
at or above
baseline
i.e. >50%
3 out 5 cases closed moved to RSL
tenancy, which is above the
baseline of 50%
4.6
% of Housing Support services departures (clients
leaving support) which are planned departures per
annum
2020/21: 70%
2021/22: 76%
2022/23: 65%
78% 
80% 
224 of 288 closed cases were
planned departures which just below
baseline.

Page 55

55 
4.7
Nos of households supported via Housing First with
support of dedicated Mental Health /Addictions Housing
Practitioner.
New Initiative
2021/22- Post
established – 25 
2022/23: 56 
55
referrals 
50
assessments
to be
completed
55 referrals have been made for
support, exceeding the baseline
4.8 Temporary Accommodation provision with protocols to
address emergency needs
2021: 108 units 
2022: 121 units
2023: 122 units
123  
100%
applicants 
in need
receive
suitable
offer of T.A.
Core provision of 123 units
(including serviced accommodation)
as of March 2024.
4.9
Level of Homeless presentations and average time to
rehouse homeless applicants in an RSL property. 
2020/21: 416
applicants; 39
weeks 
2021/22: 398
applicants; 34
weeks 
2022/23: 512
applicants; 33
weeks 
492
applications
&
31 Weeks 
Cases at or
below
baseline
(416). 26
weeks on
average to
rehouse in
RSL sector
Homeless applicants reduced
slightly on previous year 
Average time to rehouse homeless
cases is 31 weeks which is below
previous year, but still 6 weeks
longer than target of 26 weeks.
Links to HE Action 2.9
4.10 Develop a Housing Communication Plan and social
media strategy
Enhanced
Housing Options
module
established
Complete Plan to be
implemente
d in 2023 
Communication Plan approved April
2024.

Page 56

56 
Appendix 1 – Housing Emergency Action Plan 
As detailed in the Housing Emergency Section, in collaboration with strategic partners, a Housing Emergency Action was developed
following pre-engagement activities and option appraisal sessions held as part of the Housing Summit. Whilst an appendix to the
current LHS Action Plan these actions have been interlinked and will be incorporated into the next LHS. 
Housing Emergency Priority 1: Enable the Delivery of More Market Homes in Argyll & Bute 
Action Point  Progress 
Priority
Year 
1-5 
Lead
Partners  Delivery Partners
1.1 Implement a more flexible
approach to infrastructure, roads
and design requirements on
development sites.
New Roads Guideline / Almost complete  Yr 1 A&BC 
Links to LHS outcome 1.1, 1.2,
1.3
1.2 Increase capacity within Council
services key to housing
development including Planning,
Roads and Building Standards. 
DM has increased capacity over recent months. 
New roads staff in place.  Building Standards Fees
increase over a 3 year period will improve
resources. Monitoring performance.  Scottish Govt.
Resourcing Planning System Review is currently
underway. Project officer to support Housing Group
& improved internal communications has been
agreed and recruited.
Yr 1 /
monitor
A&BC Scottish
Government
Links to LHS outcome 1.1, 1.5
1.3 Dramatically increase the number
of college places for construction
skills development in Argyll &
Bute.
Need to establish baseline, existing numbers,
evidencing the need, scoping of options/
identification of target or direction.
1-3Yrs A&BC   UHI / Construction
Industry /
Developers /
Colleges / A&BC
Education

Page 57

57 
1.4 Create an empowered
Construction Forum bringing
together all planning consultees
to speed up decision making. 
Current communication channels exists between all
statutory consultees & Key Agencies involved in
the planning process both at Planning application
stage, and during LDP production.  Increased
resources (see 1.2) will assist communication. 
Monitor improvement and evaluate in year 3.  
Yr 3. A&BC 
Links to LHS Outcome 1.2
1.5 Develop funding and risk sharing
models to enable infrastructure
investment in housing sites.
The Council is working with Scottish Futures Trust
(SFT) and HubNorth who are already looking at
this issue. 
Ongoing A&BC Scottish Futures
Trust, HubNorth
Links to LHS Outcome 1.1, 1.5
1.6 Repurpose vacant
spaces/derelict buildings to
deliver homes for sale or rent
(see 4.2)
An additional Empty Homes Officer appointed with
HSCP.
NDR & Development and Economic Growth Teams
developing repurposing with NDR.  
Yr1 A&BC Private landowners
Links to LHS Outcome 1.1, 1.2,
1.8
1.7 Use rural housing burdens and
RGD/Partnership Support for
Regeneration Funding (PSRF)
enabling developers to offer
principal homes at a fixed price
Rural Growth Deal Pilot will explore this delivery
model.  Outline Business Case already submitted. 
A&BC acts as developer in the pilot which will then
be reviewed. A&BC seek to influence More Homes
for review of PSRF 
Yr3 ABC SG / UK
Government / SFT
Links to LHS Outcome 1.2
1.8 Create supplementary planning
guidance to bring forward sites
for speculative building that are
not a housing allocation in the
current LDP, making it easier for
developers to take forward
Feb 2024 LDP2 adoption allows consideration of
development on a wider geographical area than
previously. LDP3 work / OSDF / HSDF will seek to
identify new development land. 
Yr 1 (re
LDP2) &
Yr3
ABC 
Links to LHS Outcome 1.5

Page 58

58 
Housing Emergency Priority 2: Enable the Delivery of More Affordable Homes in Argyll & Bute 
Action Point  Activity
Priority
Year 
1-5 
Lead
Partners  Delivery Partners
2.1 Consider the use of standard
housing design types to speed up
procurement planning approvals
and building warrant approvals.
Primary beneficiary RSLs.  RSLs should decide if
they want it and take the lead with ABC being the
supporting partner.  Raise at Strategic Housing
Forum.
Yr 2/3 ABC
Housing
Forum  /
RSLs
RSLs / A&BC
Links to LHS Outcome 1.1, 1.2, 1.3
2.2 Create a ring fenced
infrastructure fund for Argyll &
Bute similar to the Highland
Council model
Highland Council model was a loan as part of their
Rural Growth Deal.
Alternatives:
HIF applications scheduled for several projects.
Issue of RPA flexibility raised with SG & Housing
Minister.
Council funding strategic Masterplanning will
facilitate planned future investment in strategic
infrastructure.  (see 1.8).
Ongoing. A&BC Scottish
Government
Links to LHS Outcome 1.5
2.3 Improve infrastructure planning
across agencies 
Seek to influence improvements.  Liaison activity
already happens prior to LDP production and
National Infrastructure Plan but doesn’t result in
appropriate investment.  Priority action.  
Ongoing COSLA /
A&BC
Scottish
Government
Link to LHS Outcome 1.1
2.4 Freedom to use Scottish
Government housing funding
more flexibly and as an allocation
with local administrative control
Raised with More Homes division and Housing
Minister  
Seek to influence change.
Ongoing A&BC /
CPP 
Scottish
Government / RSLs
/ Community
Housing Trusts
Links to LHS Outcome 1.3, 1.4.
1.5, 1.6, 1.8

Page 59

59 
2.5 Use Rural Housing Body status to
enable land assembly, master
planning and infrastructure
investment 
The following are proposed as more deliverable
actions:
A&BC have achieved Rural Housing Body Status,
will implement to secure primary occupancy and
potentially affordability in a variety of ways,
guidance will be developed to support this.
Land assembly and Masterplanning will be
considered through OSDF / HSDF and LDP3.  (see
1.8)
See 2.2 & 2.3 for infrastructure investment.
1/5yrs ABC 
Links to LHS Outcome 1.5
2.6 Develop planning policies which
tackle the housing crisis e.g.
exception policies, Affordable
Housing Policy contributions,
rural burdens
Currently reviewing and developing new
approaches to planning policy including: primary
occupancy restriction, planning control for short
term lets, include key worker definition in affordable
housing, construction worker housing strategies,
seasonal worker accommodation. 
1-3yrs A&BC 
Links to LHS Outcome 1.3
2.7 Create funding mechanisms for
Community Housing Trusts to
finance feasibility studies,
professional fees and approval
process
Need to explore sustainable model for Community
Housing Trusts & clarity of roles.
Ongoing CPP /
Scottish
Governm
ent
HiREP / HIE /
Community Housing
Trusts
2.8 Evidence the demand for
intermediate housing to enable
an RSL development pipeline and
deliver more MMR and low-cost
homes for sale 
Have engaged with LAR to explore delivery of mid-
market rent.  
Evidence exists within the HNDA.  Will seek to
review understanding of that evidence at Housing
Forum, with a view to improving dissemination.    
A&BC /
Housing
Forum 
Links to LHS Outcome 1.6
2.9 ACHA to develop a minimum of
300 new build homes of mixed
tenure and a minimum of 50 buy
backs by 2029 
1-5Yrs ACHA 
Links to LHS Outcome 1.3, 1.4,
1.6, 1.7, 2.9

Page 60

60 
Housing Emergency Priority 3: Enable the Delivery of More Homes for Argyll & Bute's Workforce 
Action Point  Activity
Priority
Year 
1-5
Lead
Partners  Delivery Partners
3.1 Deliver seasonal and temporary
workforce accommodation using
short term occupancy
agreements
Working with MICHT to deliver worker
accommodation on Mull.  (HubNorth & SFT
involved).  HIE have expressed interest in
contributing to this work.  Temp construction
worker accommodation also needs to be tackled. 
SSEN and Cruachan Conditions Example.  SG and
HIREP looking at the issue. 
Yr 1 &
ongoing. ABC for
Tobermory
proposal.  
CPP re
wider
issue.
MICHT / UK
Government &
Scottish
Government
through Rural
Growth Deal),
HiREP / HIE. Links to LHS Outcome 1.6
3.2 Develop a strategic approach to
evidencing the need for workforce
housing in the public sector
Already a lot of evidence/ HNDA / Consultants
Reports / MICHT survey / CPP survey.  HSCP
Empty Homes officer.    
CPP may be able to instigate a more formal route
for monitoring live demand and consideration to a
more collaborative approach such as sharing
accommodation. 
ABC  
CPP
Public sector
agencies.
3.3 Deliver emergency workforce
housing options including the use
of modular, temporary and tiny
homes   
Rural Growth Deal worker housing project on Mull.
HIREP work on worker housing.
Housing Strategy conditions for major projects
such as SSEN Sub-stations and Cruachan.  Will
incorporate in Planning Policy.
Yr 2-3 ABC  
CPP
SSEN / HiREP / HIE
/ DRAX
Links to LHS Outcome 1.6
3.4 Deliver a Mid-Market Rent
workforce housing programme 
LINK 18 units at Dunbeg.  
LAR exploring opportunities without Govt Finance.  
RSLs  
LAR 
Links to LHS Outcome 1.6

Page 61

61 
3.5 Identify public sector land and
buildings which could provide
workforce housing via
repurposing and change of use.
ABC property is mapped.   CPP 
Links to LHS Outcome  1.5 
3.6 Use the Partnership Support for
Regeneration Fund to enable
private sector workforce housing
models
Initial analysis suggested this would not prove
attractive to developers in rural ABC.  Will seek to
influence SG / More Homes Division to review this
Fund (see 1.7) 
Ongoing. ABC  
3.7 Assess the potential to
reintroduce the Rural Home
Ownership Grant model for
working households in
partnership with Community
Housing Trusts    
Community
Housing
Trusts 
Housing Emergency Priority 4: Make the Best Use of Existing Homes in Argyll & Bute 
Action Point  Activity
Priority
Year 
1-5 
Lead
Partners  Delivery Partners
4.1 Further reform CPO processes to
tackle abandoned homes more
effectively 
Empty Homes Officers have delivered empty
property back in to use via CPO before, currently
exploring on one property to see if interest from
developer / purchaser.
Not clear what reforms are needed if any.  Input to
SG consultation.
Low ABC Scottish
Government 
Links to LHS Outcome 1.8
4.2 Create a multi-agency team
enabling mixed tenure
refurbishment and regeneration
projects  (see 1.6) 
Council NDR Team developing NDR relief scheme
for empty property back in to use.
Council ‘Conservation Area Regeneration
Schemes (CARS)’ schemes.  Private Sector
Housing Grant funding to support this.
Ongoing. ABC

Page 62

62 
Links to LHS Outcome 3.1 Council APAG group for dangerous property.
Work in Helensburgh Clyde Street with ACHA.
4.3 Develop a housing model that
offers apprenticeships with
tenancies to keep young people
in Argyll & Bute
Home Argyll can discuss if they would want to
implement a local lettings policy connected to
apprenticeship.
Yr2 HOME
Argyll
Construction
Industry
4.4 Create more choice and flexibility
within the Home Argyll policy to
address identified housing
pressures
Home Argyll partners amended lettings policy to
allow prioritization of identified pressures.
Yr1 HOME
Argyll
Partnership 
Links to LHS Outcome 1.7
4.5 Increase the number of Empty
Homes Officers with more
flexibility to assemble funding
New Empty Homes officer employed in partnership
with HSCP.
Yr1 ABC/
HSCP 
Links to LHS Outcome 1.8
4.6 Develop a better range of
housing options for older people
to encourage movement in
existing housing stock
Incorporate into the LHS Action Programme and
develop from there.
Yr 2-3 ABC  
CPP 
Links to LHS Outcomes 2.2,
3.2, 3.4
4.7 Introduce STL control areas in
pressured housing market areas
Now short term let license applications have been
received.  We can explore process of consulting on
and establishing planning control areas.  
Yrs1-2 ABC  
4.8 Double the Council Tax on
Second Homes
This was implemented on the 1st of April 2024.
Have bid for additional officer resource to help
support transition from second homes to long term
rental.  
ABC  
4.9 Map public sector land and
buildings which could provide
Duplicates 3.5   CPP

Page 63

63 
affordable housing via
repurposing and change of use 
Links to LHS outcome 1.5
4.10 Extend the use of rural housing
burdens across Housing Market
Areas to maintain primary
occupancy and/or affordability
Rural Housing Authority Status Achieved.  
Models to utilize this being developed.  
Yrs 1-2 ABC 
Links to LHS Outcome 1.8