ITEM 6e - APPENDIX 2 
CONDITIONS
1. No individuals shall reside in the tourist accommodation for more than 28
consecutive days or for more than 60 days in the calendar year.  To this effect,
a permanent log book shall be kept of all visitors who stay at the tourist
accommodation for the lifetime of the development. This shall note the names
and addresses of all visitors. The log book shall be made available for the
inspection of the Council as Planning Authority, if requested. 
2. The occupation of each of the three lodges forming the tourist accommodation
hereby permitted shall not exceed four people at any one time, with a maximum
occupancy of the site as a whole not exceeding 12 people at any one time 
3. The approved parking arrangement shall be formed and available prior to the
lodges hereby approved being first brought into use. The spaces and access
arrangements shall thereafter be kept available for the lifetime of the
development. 
4. The approved arrangements shall be implemented prior to the lodges hereby
approved being brought into use. The drainage arrangements shall thereafter
be maintained for the lifetime of the development.  For the avoidance of doubt,
the arrangement will incorporate sustainable drainage arrangements (SuDS). 
5. Prior to the lodges hereby approved being first brought into use, the lodges
operator shall submit a Management Plan to the Planning Authority for their
written approval. The Management Plan shall include details of day to day site
management and maintenance and how potential noise and guest behaviour
issues are to be dealt with, should they arise. Thereafter, the site will operate
in accordance with the approved Management Plan for the lifetime of the
development unless otherwise agreed by the Planning Authority. 
6. Prior to the commencement of works, full details of both hard and soft
landscaping works shall be submitted to and approved in writing by the
Planning Authority. Where appropriate, these details shall include proposed
finished and existing grounds levels and contours, hard surfacing materials and
lighting. Thereafter, the approved details shall be fully implemented in
accordance with the approved details prior to the lodges being brought into use,
unless otherwise agreed by the Planning Authority.  Any trees, shrubs, or
hedges planted in accordance with this condition which are removed, die,
become severely damaged or become seriously diseased within five years if
planting shall be replaced within the next planting season by trees, shrubs or
hedging plants of similar size and species to those originally required to be
planted.

Page 2

7. The 1.6m high wall to the north of the gable end of unit 1 and the 1.1m high wall
along the front edge of the former water tank shall be finished in timber cladding
to match that across the wider site. 
8. Prior to the commencement of development on site, the finishing materials to
be used shall be submitted to the Planning Authority for written approval.
Thereafter, the approved materials shall be implemented as approved.   
9. If there is a requirement to either re-use site one material or to import material
then the assessment criteria and sampling frequency that would adequately
demonstrate its suitability for use shall be submitted to and approved by the
Planning Authority prior to any material being used. In addition to this and in
accordance with BS3882:2015 and Bs8601:2013 material to be used in the top
300mm shall also be free from metals, plastic, wood, glass, tarmac and odours. 
10. On completion of the works and at a time and/or phasing agreed by the
Planning Authority, the developer shall submit a verification report containing
details of the source of the material and appropriate test results to demonstrate
its suitability for use. 
11. The presence of any previously unexpected contamination that becomes
evident during the development of the site shall be reported to the Planning
Authority in writing within one week, and work on the site shall cease. At this
stage, if requested by the Planning Authority an appropriate investigation and
risk assessment shall be undertaken and a remediation scheme shall be
submitted to and approved by the Planning Authority prior to the
recommencement of works. The approved details shall be implemented as
approved.