WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer – Regulatory and Regeneration
Planning Committee: 15th November 2023
_____________________________________________________________
Subject: Developer contributions
1. Purpose
1.1 To update the Committee of the current balance of the developer
contribution account.
2. Recommendations
2.1 It is recommended that the Committee note the current balance of the
developer contribution account and the funding from the account that is
already allocated.
3. Background
3.1 The Council’s Local Development Plan and Planning Guidance sets out
standards for the provision of new open space and other green
infrastructure within new developments. For new residential development
the option exists, in prescribed circumstances, for a financial contribution to
be made towards open space, or other green network, provision/
enhancement in an off-site location rather than providing on site.
3.2 Developer contributions can also be received for other reasons such as for
off-site car parking provision or sustainable access measures.
4. Main Issues
4.1 At its meeting of 8 June 2022, the Planning Committee approved
documents relating to the procedures for managing developer contributions
and the allocation of developer contributions towards green network and
green infrastructure projects. A correction is required to the allocations
document as it refers to any contribution received from April 2022 being
required to be spent within 5 years from the date the contribution is
received, after which the contribution will be returned to the developer. This
should refer to 10 years as per the approved Green Network and Green
Infrastructure Planning Guidance document.
ITEM 6

Page 2

Status of developer contributions at 31 March 2023
4.2 In financial year 2022/23 no contributions were received into the Developer
Contribution account, although £11,646.28 interest was credited. One
payment of £7500 was made from the account towards the cost of a
feasibility study for sustainable travel improvements to the Golden Jubilee
Hospital. As at 31 March 2023 there was £591,691.20 in the Developer
Contribution account. However, a significant amount of this is already
allocated to projects. £234,962 will soon to be transferred for projects
already delivered, and £263,500 will be held until identified projects are
delivered:
• £192,500 towards sustainable access improvements to the Golden
Jubilee Hospital – still to be delivered.
• £52,902 towards Dalmuir Square – delivered
• £50,000 towards Dumbarton waterfront – delivered
• £50,000 towards Christie Park, Alexandria - delivered
• £40,000 towards Loch Lomond Rugby Club improvements – still to be
delivered
• £33,255 towards play area at Crown Avenue, Clydebank – delivered
• £25,000 towards Faifley Knowes - delivered
• £23,805 towards play area at Kyle Terrace, Dumbarton – delivered
• £20,000 towards Dalmonach Steps – currently being delivered
• £11,000 towards parking improvements in Dumbarton town centre –
still to be delivered
4.3 Taking the above committed or delivered projects into account, there is
therefore an unallocated balance of £93,229.20 within the Developer
Contributions account. The Planning Service will work with Greenspace
and other relevant services to identify suitable projects in line with the
allocations procedure. The Planning Service will also work with the
Communities team to support the participatory budgeting process and any
eligible green network/green infrastructure projects that may come through
that process.
5. People Implications
5.1 There are no direct people implications associated with this report.
6. Financial and Procurement Implications
6.1 The procedures and allocation document approved at the 8 June 2022
Planning Committee, and updated via this report, ensure that developer
contributions received are managed, reported and spent in an orderly and
transparent manner. Local government procurement rules will be followed
for any projects being delivered by the Council using developer
contributions funds.

Page 3

7. Risk Analysis
7.1 There are no risks associated with this report.
8. Equalities Impact Assessment (EIA)
8.1 No Equalities Impact Assessment is required with this report as no new
policy is being introduced or changed.
9. Consultation
9.1 No consultation is required in relation to this matter. The views of
Greenspace, Finance and Legal Services have been sought in the
preparation of this report.
10. Strategic Assessment
10.1 The use of developer contributions to develop and enhance green
infrastructure is considered to support the strategic priority of Our
Environment – A Greener Future.
Pamela Clifford
Planning, Building Standards and Environmental Health Manager
Date: 15th November 2023
_________________________________________________________________
Person to Contact: Pamela Clifford, Planning, Building Standards and
Environmental Health Manager
pamela.clifford@west-dunbarton.gov.uk
Alan Williamson, Development Planning & Place Team
Leader
alan.williamson@west-dunbarton.gov.uk
Appendix: None
Background Papers: West Dunbartonshire Local Development Plan (2020,
as modified)
Green Network and Green Infrastructure
Supplementary Guidance (2022)
Report to Planning Committee, 8 June 2022

Page 4

Procedure for monitoring, requesting and allocating
developer contributions (2022)
Allocation of green network developer contributions
(2022)
Wards Affected: All