WEST DUNBARTONSHIRE COUNCIL 
Report by Planning, Building Standards and Environmental Health Manager 
Planning Committee: 20th September 2023 
DC23/083/FUL: Residential development of 27 affordable housing units
comprising; 10 townhouses, 8 cottage flats (including 2 
wheelchair accessible cottage flats); and 9 flats with associated
landscaping, amenity space and parking on the former site of 
Faifley Bowling Club, Abbeylands Road, Clydebank by Knowes
Housing Association 
1. REASON FOR REPORT 
1.1 The planning application raises issues that in the opinion of the appointed
officer merits the determination of the application by Committee. Under the
terms of the approved Scheme of Delegation, it therefore requires to be
determined by the Planning Committee. 
2. RECOMMENDATION 
2.1 Grant planning permission subject to the conditions set out in Section 9
below. 
3. DEVELOPMENT DETAILS 
3.1 The application site extends to 1.03ha and is located to the south of Abbeylands
Road in Clydebank. The site, which was formerly in use as Faifley Bowling
Club, is comprised of two bowling greens, a pavilion building and a tennis court.
The bowling club closed in 2012 due to low usage. 
3.2     There is a significant gradient across the site, which has three distinct levels.
From the northern boundary situated at street level, an embankment drops
approximately 3m southwards to the upper level which includes the pavilion,
with the bowling greens situated on a mid-level approximately 2.3m below. The
site drops a further 3.8m towards the southern boundary. With Abbeylands
Road rising in height as it moves west to east, the level changes between the
road and the site also increase, with the largest changes outlined above located
at the eastern end of the site. There is a total level change of approximately
5.3m at the western end of the site. The former bowling greens and tennis court
are separated by embankments and hedges, with access via staircases on the
eastern and western sides of the pavilion building. Retaining walls are evident
to the west of the staircase and to the south of the pavilion. A variety of trees
are located along the site boundaries, which are enclosed by perimeter fencing.
A sewer line is located along the west boundary.

Page 2

3.3 The site is situated within a well-established residential area and bounded by
Abbeylands Road to the north, which connects with a variety of secondary
roads in the wider residential area. Two storey terraced housing is located along
the northern and southern side of the road, with Faifley Knowes Woodlands to
the south. 
3.4 Planning permission is sought for the development of 27 no. affordable housing
units and associated landscaping, amenity space and parking. The
development comprises six blocks of two or three storeys and a range of
dwelling types and sizes as detailed below:  
• 4 no. x  2 bed terraced houses
• 3 no. x 4 bed spilt level townhouses 
• 3 no. x 3 bed spilt level townhouses  
• 2 no. x 1 bed cottage flats
• 2 no. x 2 bed cottage flats
• 4 no. x 3 bed cottage flats
• 6 no. x 1 bed flats within a  flatted block  
• 3 no. x 2 bed flats within a flatted block 
3.5 The redevelopment of the site will include the demolition of the single storey
pavilion building that formed a part of the former bowling club and is located in
the north east part of the site. A community garden / growing space is proposed
as part of the development where the pavilion is currently located.   
3.6 The development is comprised of eight house types across two and three storey
blocks. External materials for the buildings include a light buff multi brick, light
buff soldier course, with light coloured fibre cement panels around some of the
aluminium windows. Light coloured Juliet aluminium balconies are proposed on
all upper floors, with concrete tiles and PV panels on the pitched roofs (the
flatted block has a mono pitched roof). The townhouses will feature in curtilage
driveways, with the remaining properties served by off street parking areas on
the southern side of the service road. A single vehicular access is proposed
within the northwest corner of the site. A SuDS pond is proposed within the
south eastern extent of the site. 
3.7 The proposed development has been developed in accordance with the
principles of Housing for Varying Needs. In addition to two wheelchair
accessible properties within Blocks 3 and 4, the proposal includes barrier free
access to all houses and surrounding environment, sufficient space around
internal and common doors to facilitate easy access for residents and visitors
in wheelchairs and those who may use other mobility aids. All ground floor units
are also capable of future adaptations. 
3.8 The proposal features a variety of open and amenity green space. This is
principally comprised of community gardens, allotments and a play area within
the north east part of the site, along with several shared open spaces and
extensive areas of informal amenity space within the southern and western
boundaries.

Page 3

3.9 With respect to soft landscaping, it is proposed to plant 43 new trees, along with
native woodland planting within the northern and eastern boundaries of the
community space and significant areas of wildflower meadow planting across
the site. 
3.10 In support of the proposal, the applicant has submitted a range of supporting
documentation and information, including a Design and Access Statement,
Tree Report, Site Investigation Report, Preliminary Ecological Appraisal, Water
Vole Survey, Flood Risk Assessment and drainage details. 
4. CONSULTATIONS
4.1 West Dunbartonshire Council Roads Service have no objection to the proposal
in respect of roads and parking together with flooding matters. 
4.2 West Dunbartonshire Council Environmental Health Service have no objection   
subject to conditions relating to unexpected contamination, soils, construction               
hours, delivery times, dust control and piling methods 
4.3 West Dunbartonshire Council Biodiversity Officer has no objections but has
requested that further information is provided, specifically a Biodiversity
Enhancement Plan, Landscape Plan and a refreshed Water Vole Survey. 
4.4 West Dunbartonshire Council Greenspace has no objections but requested
further information on the management and maintenance of the proposal. 
4.5 SportScotland, Scottish Water and West of Scotland Archaeological Service
have no objections to the proposed development. 
5. REPRESENTATIONS 
5.1 Six representations were received, with five objecting to the proposal and one
supporting it. The detail of each submitted representation is available in the
electronic planning file for the application and available for public viewing. The
points raised in objection can, however, be summarised as follows: 
• Concerns that the height and type of housing proposed is significantly
higher than the surrounding homes. 
• Concern that the proposal would increase on street parking along
Abbeylands Road and thereby exacerbate an existing issue whereby
cars are sometimes unable to pass.  
• Would pose a safety risk as more parked cars on Abbeylands Road
increases the likelihood of emergency vehicles being unable to pass. 
• Concern about impacts on local deer and other wildlife on or around
the site. 
• Concern that noise, dust and debris arising from the construction phase
will have negative effects on amenity.
• Loss of privacy. 
• Light disturbance from headlights to property located directly across
from the proposed access to the site.

Page 4

• Reduction in property value.
• Loss of view. 
5.2     The points raised in support of the proposal were that Faifley is small and more            
social housing is needed. 
5.3 The matters raised above are considered and addressed in Section 7 below. 
6. ASSESSMENT AGAINST THE DEVELOPMENT PLAN 
National Planning Policy 4
6.1 National Planning Framework 4 (NPF4) was adopted by the Scottish Ministers
on 13th of February 2023 and now forms part of the Development Plan.  
6.2 Policy 1 relates to tackling the climate and nature crises and states that when
considering all development proposals significant weight will be given to the
global climate and nature crises. Policy 2 also relates to the climate in the form
of climate mitigation and adaptation and states development proposals will be
sited and designed to minimise lifecycle greenhouse gas emissions as far as
possible and development proposals will be sited and designed to adapt to
current and future risks from climate change. 
6.3 Policy 3 seeks to protect biodiversity and deliver positive effects from
development. It requires that local development will include appropriate
measures to conserve, restore and enhance biodiversity. It is noted that
measures should be proportionate to the nature and scale of development. 
6.4 Policy 6 aims to protect and expand forests, woodland and trees. It advises that
proposals will not be supported where they result in the loss of ancient
woodlands, ancient and veteran trees, or individual trees of high biodiversity
value. Where woodland is removed, compensatory planting is expected to be
delivered. 
6.5 Policy 9 relates to brownfield, vacant and derelict land and empty buildings,
with development proposals for the reuse of vacant land being supported,
taking into account their suitability for conversion to other uses. 
6.6 Policy 12 relates to waste and advises that development proposals, including
residential, will set out how much waste the proposal is expected to generate
and how it will be managed. 
6.7 Policy 13 supports proposals to improve, enhance or provide active travel
infrastructure, public transport infrastructure or multi-modal hubs. This includes
proposals for electric vehicle charging infrastructure. 
6.8 Development proposals will be designed to improve the quality of an area
whether in urban or rural locations and regardless of scale, as per Policy 14.
Policy 15 relates to local living and 20 minute neighbourhoods. Development
proposals will contribute to local living including, where relevant, 20 minute
neighbourhoods. Consideration will be given to existing settlement pattern, and

Page 5

the level and quality of interconnectivity of the proposed development with the
surrounding area, including local access to affordable and accessible housing
options, ability to age in place and housing diversity. 
6.9 Policy 16 relates to quality homes. Part (c) supports proposals for new homes
that improve affordability and choice. This includes a range of size of homes.
Part (e) supports proposals for new homes where they make provision for
affordable homes to meet an identified need. Part (f) states that development
proposals for new homes on land not allocated for housing in the LDP will only
be supported in limited circumstances where: the proposal is supported by an
agreed timescale for build-out; the proposal is otherwise consistent with the
plan spatial strategy and other relevant policies including local living and 20
minute neighbourhoods; and the proposal is for the delivery of less than 50
affordable homes as part of a local authority supported affordable housing plan. 
6.10 Under part (f) of Policy 19, proposals for buildings that will be occupied by
people will be supported where they are designed to promote sustainable
temperature management, for example by prioritising natural or passive
solutions such as siting, orientation, and materials. 
6.11 Green infrastructure is considered through Policy 20. Proposals that result in
fragmentation or net loss of existing green infrastructure will only be supported
where it can be demonstrated that the proposal would not result in or
exacerbate a deficit in green infrastructure provision, and the overall integrity of
the network will be maintained. 
6.12 Policy 21 relates to play, recreation and sport. It advises that development
proposals which result in the loss of outdoor sports facilities will only be
supported in certain circumstances, including where it can be demonstrated
that there is a clear excess of provision to meet current and anticipated demand
in the area, and that the site would be developed without detriment to the overall
quality of provision.    
6.13 Policy 22 - Flood risk and water management states that proposals will: not
increase the risk of surface water flooding to others, or itself be at risk; manage
all rain and surface water through sustainable urban drainage systems (SUDS),
and seek to minimise the area of impermeable surface. Policy 23 does not
support proposals which are likely to raise unacceptable noise issues. Policy
24 supports proposals that incorporate appropriate, universal, and future-
proofed digital infrastructure. 
6.14 The proposed development is supported by NPF4 and is assessed fully in
Section 7 below. 
West Dunbartonshire Adopted Local Plan 2010 
6.15 Policy UR1 encourages the redevelopment and re-use of underused, vacant
and/or derelict land and buildings for appropriate uses, such as housing. Policy
RD1 gives preference to residential development on brownfield sites within the
urban area rather than on greenfield land.

Page 6

6.16 Policy H4 sets out standards expected of residential development, requiring
high quality design in the range of house types and sizes and in terms of form,
layout and materials. Policy H5 safeguards and where possible enhances the
character and amenity of existing residential area. Policy GD1 seeks to ensure
that all new development is of a high quality of design and respects the
character and amenity of the area. 
6.17 Policy R1 relates to the retention of existing open space. It includes a
presumption against development which adversely affects the use, character
or amenity of areas of functional and valued open space, or which are capable
of being brought into functional use to meet an identified need. Developments
on existing open space will be considered against the existing or potential future
use, quality, function and value of the open space and the sufficiency of
provision of the facility type in the local area. Developments on existing sports
pitches are only supported where a variety of circumstances are met. 
6.18 Policy R2 specifies the open space provision required for all developments.
Assessment of open space requirements has been undertaken against the
more updated “Green Network and Green Infrastructure Guidance (2022)” in
Section 7 below. Policy GN1 promotes and protects the Green Network. 
6.19 Policy T1 and T4 requires sites to be integrated with sustainable travel. Policy
E1 relates to the Council’s Biodiversity duty and Policy E5 requires new
development proposals to consider impacts on trees and incorporate suitable
tree planting. Policies F1 and F2 aim to ensure that new development is not at
risk from, and does not increase the risk of flooding, and has suitable SUDS
drainage infrastructure. Policy DC7 supports the inclusion of on-site micro-
renewable technologies. 
6.20 The proposal complies with the policies of the adopted local plan and is
assessed fully in Section 7 below. 
7. ASSESSMENT AGAINST MATERIAL CONSIDERATIONS 
West Dunbartonshire Local Development Plan (LDP2) Proposed Plan
7.1 On 15 March 2023, the Planning Committee took a decision that the Council
would not adopt Local Development Plan 2. The Proposed Local Development
Plan 2 (LDP2), incorporating the recommended modifications of the
Examination Report received on 22 April 2020, which were accepted by the
Planning Committee of 19 August 2020, remains the Council’s most up to date
spatial strategy and is therefore afforded significant weight in the assessment
and determination of planning applications, subject to compatibility with NPF4.
The Scottish Ministers’ Direction relating to the adoption of LDP2, dated 18
December 2020, is also a material consideration. 
7.2 Policy CP1 seeks to ensure that housing is of a high quality, adaptable and is
designed to be suitable for a mix of occupants. It indicates that all new
development will be expected to contribute towards creating successful places
by having regard to the six qualities of a successful place (distinctive,
adaptable, resource efficient, easy to get to/move around, safe and pleasant,

Page 7

and welcoming). Policy CP2 requires the integration and consideration of green
infrastructure from the outset of the design process through to its maintenance
and stewardship of the resource. Policy CP4 relates to enhancing the quality of
design through the Council’s Place and Design Panel. 
7.3 Policy H2 supports new housing development on sites in Schedules 2 and 3.
This site is included on Schedule 3. Policy H4 of the LPD2 relates to residential
amenity. The policy states that the Council will protect, preserve and enhance
the residential character and amenity of existing residential areas at all times. 
7.4 Policy GI1 relates to open space and outdoor sports facilities. It notes that
playing fields and sports pitches should not be developed upon except where;
the proposed development is ancillary to the principal use of the site as a 
playing field or involves a minor part of the playing field which would not affect             
its use and potential for sport and training; or a new or upgraded playing field 
of comparable or greater benefit for sport is provided in a location which is 
convenient for its users and which maintains or improves the overall playing               
field capacity in the area. 
7.5 Policies GI2 and GI4 relate to green infrastructure. Policy GI2 requires new
development to meet with the open space standards set out within the policy.
It is noted that the policy sets a higher open space standard to that of the
adopted Local Plan. Policy ENV1 requires that all new development should
enhance biodiversity as part of the green network, in accordance with Policy
CP2 and the above supplementary guidance.   
7.6 Policy CON1 requires that significant travel generating uses are designed to
encourage sustainable transport. Policy CON3 encourages improvements to
core paths and the development of new core paths and Policy CON4 sets out
a need for all developments to install sufficient broadband provisions. 
7.7 Policy ENV8 requires developments to address air quality, lighting and noise
as part of the planning process, whilst policy ENV9 requires all potentially
contaminated sites to be remediated where necessary to ensure that the site is
suitable for the intended use. 
7.8 Policies ENV1, ENV4, and ENV6 are all similar to the ecology, tree, water
environment and flooding policies of the adopted Local Plan. Policy CP2
requires the integration and consideration of green infrastructure from the
outset of the design process through to its maintenance and stewardship of the
resource. 
7.9 RE4 encourages micro-generation and heat recovery technologies within or
associated with individual properties and Policy RE5 relates to low and zero
carbon buildings and states that new buildings should conform to the
sustainability standards. 
7.10 It is considered that the application proposal being assessed complies with the
relevant policies above as set out in the assessment below.

Page 8

Creating Places Planning Guidance and Green Network and Green
Infrastructure Planning Guidance
7.11 The Creating Places Guidance – November 2022 seeks to achieve high quality
development with a design led approach based on a thorough appraisal of the
site and an analysis of its context, and sets out that this is expected for all
development proposals. The proposal has been informed by a comprehensive
pre-application as encouraged by the guidance and has been considered by
the Place and Design Panel. This has resulted in a development proposal that
achieves a high quality design that responds to the local context and accords
with the approach set out in the Guidance. 
7.12 The Green Network and Green Infrastructure Guidance - November 2022
seeks to ensure that the proposal also integrates landscaping and green
infrastructure as part of the setting of the new development and open space
created. This will include a focus on biodiversity enhancement and also the
creation of a community growing space. The on-site provision follows the
Guidance in respect of residential development proposals. The open space also
integrates with the wider green network adjacent, inclusive of pathway
connections. The proposal accords with the approach set out in the Guidance. 
Principle of Development
7.13 The proposed development is situated on a vacant brownfield site. As such, it
is supported by Policy 16 of NPF4, which promotes the sustainable re-use of
brownfield land. It is further supported by Policy UR1 of the Local Plan which
aims to redevelop underused and vacant land, and Policy RD1 which gives
preference to residential development on brownfield sites within the urban area.   
7.14 Policy H2 supports the development of sites identified in Schedule 3, with Policy
16 also supporting proposals for new homes on land allocated for housing. The
proposal is supported by both policies as the site is identified in the proposed
LDP2 as a residential development opportunity for affordable housing on
Schedule 3 ref: H2(63). 
7.15  Although the application site is no longer in active use as a bowling club, its last
use was as an outdoor sports facility. Within the adopted Local Plan, the site is
identified as an area of open space on the Proposals Map. Policy 21 of NPF4
sets out strict criteria in respect of considering whether a proposal which would
result in the loss of an outdoor sports facility could be supported. This includes
situations where there is a clear excess of provision to meet current and
anticipated demand in the area, and that the site would be developed without
detriment to the overall quality of provision. Policy R1 of the adopted Local Plan
takes a similar position. As such, the loss of this use requires to be assessed.
Whilst identified as open space in the adopted Local Plan, the site comprised a
local sporting facility rather than recreational open space. In the proposed Local
Development Plan 2, the site is identified as a residential development
opportunity. In identifying the site as a development opportunity it is therefore
clear that the site is considered to no longer function as open space. This,
together with the extensive open space available within the adjacent Faifley
Knowes and the contribution this area makes to the wider green network means
that it can be concluded that there is sufficient provision of open space within

Page 9

the locality. Notwithstanding this, the proposal provides a variety of open and
amenity green space. This is principally comprised of community gardens,
allotments and a play area within the north east part of the site, along with
several shared open spaces and extensive areas of informal amenity space
within the southern and western boundaries. 
7.16 Turning to the use of the site as an outdoor sporting facility, it is understood that
the bowling club closed in 2012 due to low usage and, having become disused,
was subsequently identified as a housing site in the proposed LDP2. The
assessment of the loss of the outdoor sporting facility, which requires to balance
the conflicting positions of the adopted and proposed Development Plans, is
informed by a consultation response from SportsScotland. SportScotland have
considered the proposal in the context of Policy 21 of NPF4, noting the closure
of the bowling club was due to dwindling membership. They have in turn
consulted with Bowls Scotland who raised no concerns. The response goes on
to advise there is currently good capacity for new members in the four nearest
alternative blowing clubs, which are less than two miles from the Faifley Bowling
Club site and accordingly it is considered that the site could be developed
without detriment to the overall quality of provision in the local area. In light of
this, SportScotland raise no objection. It can therefore be concluded that there
is satisfactory provision of bowling facilities within the locality and the
development of the site would not be to the detriment of overall provision. The
proposal therefore does not conflict with Policy 21 of NPF4 and Policy R1 of the
adopted Local Plan in this respect.   
7.17 Whilst Policy GI1 of the proposed Local Development Plan 2 takes a stronger
position in respect of the loss of such facilities, the site is identified as a
residential development opportunity within the same plan and therefore no
further assessment against Policy GI1 is required. 
7.18 The principle of development for housing on the site is therefore established
and considered to be fully compatible with the surrounding locality.   
Site Layout, Design and Appearance
7.19 New residential layouts require to be well designed, take cognisance of the
setting into which they are introduced and provide a high quality environment
of well-designed buildings in a setting of gardens and open space whilst
recognising the impact on existing neighbouring properties. The surrounding
locality is largely based on a low density approach, with two storey terraced
housing located to the east and west of the site on the southern side of
Abbeylands Road, and along the northern side of the road. Flatted blocks are
located further west along Abbeylands Road. The proposed development
follows the overall theme and pattern of development in the locality whilst
providing a wider range of housing sizes and it is considered that the density of
development is compatible with the character and amenity of the wider adjacent
residential areas. The proposal makes provision for varying housing needs, with
two wheelchair accessible properties within Blocks 3 and 4, barrier free access
to all houses and surrounding environment, sufficient space around internal and
common doors to facilitate easy access for residents and visitors in wheelchairs

Page 10

and those who may use other mobility aids. All ground floor units are also
capable for future adaptations. 
7.20 The proposed layout and design of the site responds to the difference in levels
between the site, Abbeylands Road and the existing housing along it. In order
to create a development which provides continuity with the existing
arrangement, a mix of two and three storey buildings are proposed. When
viewed in the context of the disparity in levels, this mix broadly mimics the height
of the existing housing along the road. While one of the objections raised
concern that the housing is significantly higher than the existing two storey
terraced housing, it is noted that the proposed townhouses are split level, with
the northern elevation facing the road being two storey and only the southern
elevation being 3 storey. In addition to the scale of the buildings, a number of
design features have been used to ensure that the townhouses relate positively
to the existing position. These features include the use of contemporary style
dormers on the northern elevation to give the appearance of a more domestic
two storey arrangement, and the stepped roof pattern which reflects the levels
changes along the road. The townhouses, in conjunction with the proposed
community gardens to the east also create an active frontage onto Abbeylands
Road. The layout, along with the use of active gables, ensures that the
development is outward looking and that all open and amenity spaces are
overlooked. The provision of low level walls around the private rear gardens of
the townhouses, cottage flats and terraced housing also increases community
interaction and encourages observation and ownership of the shared spaces.
Within the lower level, the three storey flatted block forms an anchor and
creates an opening for public space and the route to Faifley Knowes woodland. 
7.21 The mix of two and three storey blocks and house types will assist in creating
visual interest within the development. While elevations share a material and
proportional language, there is variety within this to add further diversity to the
development. Visual interest is further enhanced by the use of a stepped roof
arrangement that reflects the sloping nature of Abbeylands Road. The
proposed layout has made the most of the site layout and levels and its
topographical character and what is proposed successfully integrates into the
wider residential area. The built ratio of each plot accords with the requirements
of the Council’s Creating Places Guidance (2022) and this ensures a suitable
level of garden ground and associated private amenity space is provided for
new residents. 
7.22 Turning to the proposed materials, the new buildings will be finished externally
in facing brick and a concrete tile roof. Samples have not been provided in
advance of the determination of the application. In the absence of material
samples, the final choice of external materials can be addressed by condition,
and the condition will require a quality clay brick to be proposed. This will ensure
consistency with the established approach taken on other sites where the use
of high quality materials has been proposed to ensure the best possible
development. 
7.23 The proposed houses will also feature solar panels incorporated into the roof
covers and this ensures the incorporation of zero carbon generating

Page 11

technologies into the development which in turn reduces greenhouse gas
emissions and responds to the climate emergency. 
7.24 Overall, it is considered that the proposal will create a well-designed and
integrated development which will address the six qualities of successful places
by having a distinctive identity, forming safe streets, having quality green
infrastructure, using high quality materials and being sustainable, all complying
with policies GD1, DS1 and CP1 of the adopted and proposed Plans alongside
the Creating Places Guidance (2022). 
Residential Amenity
7.25 Whilst a number of objections raised concerns about impacts on residential
amenity, it is considered that the proposal would have no significant effects in
this respect. The layout, scale and massing proposed relative to the proximity
of existing housing raises no concerns with respect to privacy, overshadowing
or overbearing effects. While noting the specific concern raised about the
impacts that vehicles entering and exiting the access road would have on the
amenity of the existing properties opposite, this is a common arrangement
within a residential area. While the development will undoubtedly bring
additional activity to the area, the occupation of new dwellings is not expected
to cause any noise or activity beyond that typically found in a residential area.
Although it is accepted that any construction site will produce an element of
short term noise and disruption, the Council’s Environmental Health Service
highlight the requirement to require that the construction of the development is
undertaken in a way that ensures that adjacent residential amenity is not
adversely affected and this can be addressed by condition. 
Trees, open space and landscaping 
7.26 The last use of the site for outdoor sports and the open space designation in
the adopted Local Development Plan are addressed in paragraphs 7.15 - 7.17
above. A variety of trees exist within the site and, as noted in the Tree Report
submitted with the application, it is acknowledged that none of these are
protected, ancient or veteran or trees. The function of many of these trees was
to provide part of the landscape setting of the Bowling Club. Some of the trees
are in poor condition and the correct course of action is removal regardless of
any development proposals. It is also desirable to remove Ash trees due to the
threat of dieback. It is accepted that other trees are removed to accommodate
the development. Due to the presence of trees either on or in close proximity to
the developable areas of the site, it is proposed to remove 21 trees.
Compensatory planting is proposed at a ratio of 2:1, with 43 new trees with 12-
14cm girth to be planted. In addition, native woodland planting is proposed
along the northern and eastern boundaries of the community space. An
indicative list of tree species have been identified. The Council’s Biodiversity
Officer has requested that a detailed Soft Landscaping Plan be provided to
ensure appropriate mitigation for the proposed tree loss, which can be
addressed through condition. 
7.27 With respect to open space provision within the new development, the proposal
provides a hierarchy of spaces. This is comprised of community gardens, a play
area and allotments on a graded area of open space within the north east of

Page 12

the site. It is noted that the proposal sets out an indicative design for the
community spaces, with the final design, management and maintenance to be
developed through community consultation during the construction phase. As
this approach will ensure that the community spaces reflect and meet the needs
of the local community, it is supported and can be secured through condition.
Two further areas of open space are provided between the blocks of cottage
flats and between the terraced housing and the flatted block. In addition, two
areas of formal amenity space are located adjacent to the eastern elevation of
the flatted block, with the SuDS area and extensive areas within the southern
and western boundaries providing further informal amenity space. In total, the
proposal provides in excess of 5300sqm of open space within the site boundary
comprising a variety of forms which is significantly more than the 1620sqm
required for this scale of development by Policy GI2 of the proposed LDP2 and
importantly goes someway in compensating for the loss of open space
associated with the bowling club. It is noted that the open space areas are well
connected by pedestrian paths, one of which also links to the Faifley Knowes
Woodland open space to the south.   
7.28 The landscaping strategy includes a variety of plants, flowers and trees to
encourage wildlife and biodiversity to the site, along with a management and
maintenance plan. While this is acceptable in principle, it is noted that the
species identified are indicative. In light of this, the Council’s Biodiversity Officer
has requested a detailed soft landscaping plan be provided. Variety is also
proposed to the hard landscaped areas through a mix of materials. As noted
above, new tree planting is proposed throughout the development. The overall
approach to open space provision and planting is considered appropriate and
the request for a detailed soft landscaping plan can be addressed by condition.             
7.29 Overall, the quality and range of open spaces will likely all contribute to the
overall success of the transformation of the now vacant site. The approach to
and provision of open space within the development also presents no conflicts
with the Council’s  Green Network and Green Infrastructure Guidance which
seeks to ensure that development proposals positively contribute to the
provision and enhancement of open spaces and the wider green network. 
Traffic, parking and road safety
7.30 A number of objections raised concerns that the proposal would result in
increased parking along Abbeylands Road, with knock on adverse effects for
resident’s safety and emergency vehicle access. Parking provision is provided
on a 115% basis, i.e. 31 parking spaces for 27 dwellings, and the Councils
Roads Service is happy with this arrangement. The Roads Service also raised
no concerns with respect to parking on Abbeylands Road. In light of this, it is
considered that the proposal would not adversely affect the existing parking
situation along Abbeylands Road. With respect to the type of parking to be
provided, Blocks 1 and 2 have in curtilage parking, with the rest of the
residential units provided for by on street parking along the southern side of the
street serving the development. Each wheelchair unit has its own designated
parking space an appropriate distance from the property. Cycle parking is also
proposed.

Page 13

7.31 In terms of pedestrian movements, the proposed layout provides varied means
of moving through the site, with a primary pedestrian route along the street
pavement serving the development, a secondary pedestrian route from
Abbeylands Road through the community space and shared open space with
onward access to the Knowes woodland, and a wandering route which includes
the community spaces, play area, two greenspaces and the Suds area within
the eastern extent of the site. A public pavement is located along the southern
side of Abbeylands Road, which connects east and west to surrounding areas.   
Transport, connectivity and permeability
7.32 The wider area is well served by public transport, with bus stops on Milldam
Road and Hardgate roundabout, which are a 5min and 10min walk respectively
from the proposed development site, providing services to local destinations
and Glasgow. The Hardgate Local Centre is also within a 10min walk. It is
therefore concluded that the development is provided in an appropriate location
within an established settlement accessible by means other than the private
car. It is considered appropriate for a travel information pack which encourages
reduced dependency on the private car by highlighting the location of local
amenities, public transport services and active travel routes to be provided to
the residents of the new dwellings. This can be addressed by condition. 
Flooding and drainage
7.33 With respect to flooding and drainage, the applicant has submitted a flood risk
assessment in support of the application. The application is below the threshold
for SEPA to be consulted and accordingly the assessment is guided by the
advice of the Council’s Roads Service who have advised that there is no flood
risk to the development or resulting from the development. The drainage
strategy submitted with the application comprises separate storm and foul water
sewer runs located with the new road carriageway. Foul water from the
development will be collected via a new foul water sewer and discharged to the
existing foul sewer local adjacent to the site’s western boundary. Surface water
run-off from the new development will be collected and treated via an end of
line SuDS basin located within the south east extent of the site. While the
proposed drainage arrangements are acceptable in principle, further detailed
information on the methodology and calculations, together with surface flow
pathways, is required to confirm acceptability. This matter can be addressed
through condition.   
Ecology
7.34 The preliminary ecological appraisal submitted with the application found that
the habitats on the site were of low ecological importance overall. Suitability for
nesting birds was found, with a number of measures to avoid and mitigate any
impacts identified. While the appraisal found some suitability for water vole, a
follow up survey found no evidence of water vole presence. The Council’s
Biodiversity Officer has, however, requested that the water vole survey be
refreshed as evidence of water vole presence has since be found in close
proximity to the site. While the preliminary appraisal found that the clubhouse
building had moderate bat roost suitability, two follow up bat activity surveys
found that no bats were using potential roost features. Specific methods for the
demolition of the building were identified. Habitats suitable for badgers were

Page 14

found and a pre-commencement badger survey was recommended. Finally,
actions for the removal and management of invasive non-native species and
fox occurring within the site were identified, and a number of biodiversity
mitigation or enhancement measures suggested. The Council’s Biodiversity
Officer has no objection to the Preliminary Ecological Appraisal, but requests
that a Biodiversity Enhancement Plan be provided. The recommendations of
the preliminary appraisal and the bat activity surveys, including further surveys,
can be addressed through condition. 
Cultural Heritage
7.35 West of Scotland Archaeological Service (WOSAS) advises that no
archaeological features are identified within the site and previous development
will likely have removed any potential for significant sub-surface archaeology.
Archaeological work is not identified as being required.  The potential impact
on the setting of the Antonine Wall is also noted, but this is some 570 metres
from the site and WOSAS consider that the new buildings will be viewed in the
context of the wider urban area. No concerns therefore arise. 
Waste Provision
7.36 The houses and cottage flats have in curtilage bin stores, with the flatted block
having its own designated communal bin store. 
Other Technical matters 
7.37 With respect to the re-use of a brownfield site, a Site Investigation Report, which
includes remedial measures for contaminated land, is acceptable to the
Council’s Environmental Health Service. In further considering the consultation
response from Environmental Health, this does not highlight any concerns over
and above the standard need for conditions to address unexpected land
contamination, validation of soils, construction operating hours, delivery vehicle
times, dust control, and piling method statement, all of which can be addressed
through condition. Scottish Water have raised no objection. It is noted that there
is currently capacity in the Burnocks Water Treatment Works and the Dalmuir
PFI Waste Water Treatment works. 
Other Matters raised in representations
7.38 With respect to other issues raised in the objections and not already assessed
above, it was highlighted that the proposal would result in a loss of view and
loss of property value. It is noted that both these issues are not material
planning considerations and do not therefore form part of this assessment.   
Pre-application Consultation and Place and Design Panel 
7.39 The applicant and their project team engaged in a pre-application framework
process with West Dunbartonshire Council Planning Service between October
2022 and February 2023. Four meetings were held in which comments were
made by the Planning Service which are reflected in the submitted design. The
design proposal was also reviewed by the Council’s Place and Design Panel in
November 2022. The panel commended the provision of a mix of housing
typologies within the proposal, noting that this would support a sustainable
proposal. It was further acknowledged that the proposal responded to adjacent
housing. The significant area of community open space provision, as well as

Page 15

provide a route through the site connecting Abbeylands Road into Faifley
Knowes, was welcomed with the Panel highlighting how the design could
further evolve by exploring how building design and massing could aid in
signalling a hierarchy of spaces and route to Faifley Knowes. The Panel also
encouraged further consideration of how the impact on the vehicle
infrastructure could be reduced and pedestrian movement prioritised. The
comments of the panel were taken into account in concluding the final design.   
8. CONCLUSION
8.1 The proposed redevelopment of this former bowling club and green for 27
affordable residential units of 1, 2, 3 and 4 bedroom accommodation is
welcomed. The site is within an existing residential area and, subject to the
appropriate use of conditions, the proposed development is acceptable. The
layout and design of the development has been developed to ensure that it
integrates with the existing residential form as well as creating a high quality
development which enhances the local residential area as well as
improvements to the footpath and greenspace networks. The development will
provide high quality housing with good connections to the surrounding area and
wider green network. The provision of a community garden and enhanced open
space will not only benefit this development but the wider area. 
8.2 The proposal will result in a high quality residential development that presents
no conflict with the policy requirements of NPF4, the adopted Local Plan and
the proposed Local Development Plan.
9. CONDITIONS 
1. Prior to the commencement of development on site, exact details, specifications
and samples of all proposed external materials to be used for the houses within
the development site shall be submitted to and approved in writing by the
Planning Authority. For the avoidance of doubt, all facing bricks to be used shall
be good quality clay bricks. Thereafter, unless otherwise agreed in writing with
the Planning Authority, the development shall be completed in strict accordance
with the approved material details and palette. 
2. Further to Condition 1 above, prior to the approved brickwork associated with
any house being constructed or installed on site, a sample panel of this
brickwork shall be constructed on site in order for it and the associated mortar
to be reviewed, inspected and approved in writing by the Planning Authority.
Thereafter, unless otherwise agreed in writing with the Planning Authority, the
development shall be completed in strict accordance with the approved brick
details. 
3. That prior to the commencement of works on site full details of the timescale
for the phasing of the development shall be submitted to and approved in writing
by the Planning Authority. Works shall then proceed as approved unless an
alternative timescale is first agreed in writing by the Planning Authority.

Page 16

4. Prior to the commencement of development on site, full details of all hard
surfaces shall be submitted for the further written approval of the Planning
Authority. The development shall thereafter be proceed in accordance with the
approved details. 
5. Prior to the commencement of development on site, a detailed soft landscaping
plan shall be submitted to and approved in writing by the Planning Authority.
Thereafter, unless otherwise agreed in writing with the Planning Authority, the
development shall be completed in strict accordance with the approved plan. 
6. Prior to the commencement of development on site, a Biodiversity
Enhancement Plan setting out how the proposal enhances biodiversity beyond
the current baseline, together with the implementation on site, shall be
submitted to and approved in writing by the Planning Authority. All measures
shall then be implemented as approved. Thereafter, unless otherwise agreed
in writing with the Planning Authority, the development shall be completed in
accordance with the approved plan. 
7. The approved hard and soft landscaping and all associated approved planting
details shall be implemented within a timescale to be agreed with the Planning
Authority prior to the commencement of works on site. 
8. That any trees, shrubs or areas of grass which die, are removed, damaged or
become diseased within five years of completion of the landscaping shall be
replaced within the following year with others of a similar size and species. 
9. Full details of the form, management, operation and timescale for completion
on site of the community allotments, community gardens and play space or any
alternative form of community space developed following the results of a
community consultation shall be submitted to and approved by the Planning
Authority prior to the occupation of the first dwellinghouse hereby permitted.
Management and operation shall then be undertaken in accordance with the
approved details at all times thereafter. 
10. In addition to the water survey submitted with the application, a follow up water
vole survey shall be undertaken and submitted to and approved in writing by
the Planning Authority. All recommendations shall then be implemented as
approved. 
11. All recommendations within the Preliminary Ecological Appraisal dated 18th
May 2023, the Bat Activity Surveys dated July 20223, shall be implemented.
This shall include all required further survey work identified as being required
for badgers.  This further survey work undertaken shall be submitted to and
approved in writing by the Planning Authority prior to the commencement of
any works on site and implemented as approved. 
12. Prior to the commencement of development on site, details of the design and
location of cycle storage shall be submitted for the further written approval of
the Planning Authority and the development shall thereafter be completed in
accordance with the approved details prior to the occupation of any housing

Page 17

unit within the development, unless otherwise agreed in writing with the
Planning Authority. 
13. That prior to each house hereby permitted being occupied, all new roads and
footways leading to it shall be surfaced to a sealed base course. 
14. That within 4 weeks of the last of the houses hereby permitted being completed,
all roads and footways within the application site shall be completed to a final
wearing course. 
15. That prior to the occupation of any house, the off-street parking provision shall
be completed and be available for use by residents of the associated house.
The off-street parking provision shall be then remain unobstructed and available
for use by residents of the associated house at all times thereafter. 
16. All on street parking and visitor parking spaces shall be formed
commensurately with the development of the houses that they serve. 
17. That prior to the commencement of works on site, full details of the proposed
drainage regime inclusive of calculations and overland flow details shall be
submitted to and approved in writing by the Planning Authority. The drainage
regime shall then be implemented and maintained thereafter. For the avoidance
of doubt, the drainage regime shall be implemented commensurately with the
construction of the houses it serves. 
18. That all surface water shall be intercepted within the site both during
construction and on completion of the development and full details of measures
to ensure that surface water run-off is contained within the site shall be
submitted to and approved in writing to the Planning Authority prior to the
commencement of any works on site. The measures shall be implemented and
maintained as approved. 
19. No site clearance works shall be undertaken during the bird nesting season
March to September inclusive unless first agreed in writing by the Planning
Authority. For the avoidance of doubt, any such agreement will require a full
nesting bird survey prior to the commencement of works on site, the
methodology and findings of which shall be submitted to and approved by the
Planning Authority and shall be implemented as approved. 
20. Prior to the commencement of development on site, details of the location and
design of electric charging points/units and associated infrastructure and
ducting to serve the development shall be submitted to and approved in writing
by the Planning Authority. The approved car charging points/units/ducting and
associated infrastructure shall thereafter be installed in accordance with the
approved details at a timescale agreed by the Planning Authority and
maintained at all times thereafter. 
21. Prior to the occupation of the first house within the site, the developer shall
install the necessary infrastructure to enable the full development and all
associated properties to be connected to the existing fibre optic network, where

Page 18

available in West Dunbartonshire, and in accordance with the relevant
telecommunications provider’s standards. 
22. Prior to the commencement of works on site, details of any street furniture
inclusive of grit bins and telecommunications cabinets shall be submitted to and
approved in writing by the Planning Authority. Development shall then proceed
as approved.   
23. No house shall be occupied until the contents of a Travel Information Pack
which encourages reduced dependency on the private car by highlighting the
location of local amenities, public transport services and active travel routes is
submitted to and approved in writing by the Planning Authority. Thereafter, on
the occupation of each dwelling, the approved Travel Information Pack shall be
provided to new residents. 
24. Prior to the commencement of any works on site, full details of the incorporation
of photovoltaic panels shall be submitted to and approved in writing by the
Planning Authority. Thereafter the development shall be undertaken in
accordance with the approved details. 
25. The presence of any previously unexpected contamination that becomes
evident during the development of the site shall be reported to the Planning
Authority in writing within one week, and work on the site shall cease. At this
stage, if requested by the Planning Authority, an appropriate investigation and
risk assessment shall be undertaken and a remediation scheme shall be
submitted to and approved by the Planning Authority prior to the
recommencement of site works. The approved details shall be implemented as
approved. 
26. If there is a requirement to either re-use site won material or to import material
then the assessment criteria and sampling frequency that would adequately
demonstrate its suitability for use shall be submitted to and approved by the
Planning Authority prior to any material being re-used or imported. In addition
to this and in accordance with BS3882:2015 and BS8601:2013, material to be
used in the top 300mm shall also be free from metals, plastic, wood, glass,
tarmac, paper and odours. 
On completion of the works and at a time and/or phasing agreed by the
Planning Authority, the developer shall submit a validation report containing
details of the source of the material and associated test results to demonstrate
its suitability for use. 
27. During the period of construction, all works and ancillary operations which are
audible at the site boundary (or at such other place(s) as may first be agreed in
writing with the Planning Authority), shall be carried out between the following
hours unless otherwise approved in writing by the Planning Authority:
• Mondays to Fridays: 0800 – 1800
• Saturdays: 0800 – 1300
• Sundays and public holidays: No Working

Page 19

28. Unless otherwise approved in writing by the Planning Authority, no
development shall commence on site until such time as a scheme for the control
and mitigation of dust has been submitted to and approved in writing by this
Authority. The scheme shall identify likely sources of dust arising from the
development or its construction, and shall identify measures to prevent or limit
the occurrence and impact of such dust. The approved scheme shall thereafter
be implemented fully prior to any of the identified dust generating activities
commencing on site and shall be maintained thereafter, unless otherwise
approved by this Authority. 
29. No commercial vehicle making deliveries to or collecting material from the
development during construction shall enter or leave the site before 0800 or
after 1800. 
30. No piling works shall be carried out until a method statement has been
submitted to and approved in writing by the Planning Authority. This statement
shall include an assessment of the impact of the piling on surrounding
properties, taking into account the guidance contained in BS 6472: 1984
‘Evaluation of Human Response to Vibration in Buildings’. It shall detail any
procedures which are proposed to minimise the impact of noise and vibration
on the occupants of surrounding properties. This statement shall be prepared
by a suitably qualified person, and the piling works shall thereafter be carried
out in accordance with the approved method statement. 
Pamela Clifford 
Planning, Building Standards and Environmental Health Manager 
Date: 20th September 2023 
Person to Contact: Pamela Clifford Planning,  Building Standards and
Environmental Health Manager 
Pamela.Clifford@west-dunbarton.gov.uk 
James McColl, Development Management Team
Leader
james.mccoll@west-dunbarton.gov.uk 
Appendix: Location Plan   
Background Papers: 1.  Application forms and plans 
2.  Consultation responses 
3.  Representations

Page 20

4.  National Planning Framework 4 
5.  West Dunbartonshire Local Plan 2010 
6.  Proposed West Dunbartonshire Local
Development Plan 2 2020, as amended 
7. ‘Green Network and Green Infrastructure’
Planning Guidance (2022) 
8. Creating Places Planning Guidance (2022) 
Wards affected: Ward  4 - Kilpatrick