WEST DUNBARTONSHIRE COUNCIL 
Report by Planning, Building Standards and Environmental Health Manager 
Planning Committee:  20th September 2023
_____________________________________________________________ 
DC23/098/FUL: New build education and community campus
comprising new early years, primary schools,
Additional Support Needs unit, library and community
facilities together with associated parking, sports
facilities and landscaping at St Joseph’s Primary
School, Faifley Road, Clydebank, by West
Dunbartonshire Council 
1. REASON FOR REPORT 
1.1  The application proposal comprises a major development as defined by 
the Town and Country Planning (Hierarchy of Developments) (Scotland)
Regulations 2009. Under the terms of the approved Scheme of
Delegation, it therefore requires to be determined by the Planning
Committee. 
2.        RECOMMENDATIONS 
2.1 Grant planning permission subject to the further conditions detailed in
Section 9 below. 
3.  DEVELOPMENT DETAILS 
3.1     The application site comprises St Joseph’s RC Primary School and
associated grounds, and is located in Faifley Rd, Faifley. The site is on
the opposite side of the road from St Joseph’s Roman Catholic Church
and east of the Faifley Knowes. It occupies an area of approximately
21,891sqm in the shape of a diamond. The north-eastern perimeter of
the site faces onto Faifley Rd at Lawmuir Cres, with  three vehicular
access points providing access to the current school’s car parks and
grounds. To the north of the site lies the former janitor’s house once
associated with the school, beyond which there is an area of open space
bounded from the north by Faifley Rd which curves and continues west
at this point. The north-western perimeter is alongside the area of
greenspace which continues in the southern direction along Abbeylands
Rd to join Knowes Woodlands. The south-western boundary is along the
edge of the residential area formed of Langfaulds Cres and Hart St, while
the south-eastern perimeter meets with the rear gardens of the
residential properties at Quarryknow and Abercorn Streets. In addition
to the existing school building, the site has a number of hardstanding
areas including parking and a play areas around the school building.  The
site is relatively level with its elevation increasing slightly towards its rear

Page 2

at the southern corner of the plot. An established group of trees along
the south eastern perimeter facing onto the rear curtilages of the
properties in Quarryknow and Abercorn Streets can be found.
Otherwise, the remainder of the site is grassed. 
3.2 The proposal is for a new educational and community campus on the
current St Joseph’s site which will replace the current buildings and will
co-locate St Joseph's RC Primary, Edinbarnet Primary and Lennox Early
Years, Auchnacraig Early Years together with community facilities to
replace the Skypoint Centre and a new library. 
3.3 The current school buildings at St Joseph’s and Edinbarnet require to be
renewed due to their condition and will be replaced with new accessible
campus  that is designed to deliver the Curriculum for Excellence. The
Skypoint Centre, also located in Faifley, which provides local community
services, is under-utilised, and has reached the end of its serviceable
lifespan. The new facility will be a significant investment by the Council
in the area and will provide a service hub for the local community. The
proposed new campus will be  designed and built   to  passivhaus  design
standards. This will  significantly reduce ongoing maintenance and
running costs of the existing separate facilities and it will provide a
response to the Scottish Government’s Climate Change Bill to target net-
zero carbon emissions by cutting greenhouse gas emissions against the
2045 target set by the government. 
3.4 The various facilities would be contained within a single new building to
be constructed to the south west of the existing school building. The
footprint of the new building, predominantly L-shaped, would measure
approximately 3,321sqm. It will be three storeys in height at the highest
point which will allow for greater outdoor space for play and learning and
the intended community facilities. A new temporary area of hardstanding
will be built in the east of the site; as the project progresses through its
phases, an all-weather sports pitch measuring 1,962sqm and an
adjacent multi-use sports pitch (MUGA) measuring 318.5sqm
playground area will be constructed  during the latter phases of the
development . The building design is contemporary and features
pronounced massing, spread over three levels overall across the north-
western half of the complex, and a single level across the south-eastern
half. When viewed from the west and the east, the massing and the
shape of the building is softened by the stepped roof level arrangement.
Quality materials have been proposed with natural facing brick and
sinusoidal metal cladding, perforate aluminium panels and flat metal
cladding, as well as  aluminium curtain walling and aluminium glazed
windows and glazed and solid doors.   
3.5 The campus will provide a progression of learning up through the
building and provide a number of community facilities. In terms of the
specific layout, the following will be found within the proposal:

Page 3

 Ground floor: Community facilities space (incl. meeting room),
school and community library, school office, conference and
multipurpose rooms, dining space with the associate kitchen
facilities and various stores to serve to campus, an assembly
hall/gymnasium with the associated changing and storage facilities,
school teaching and nurture rooms. Moreover, the south-eastern
wing of this floor will feature the Early Learning Centre to consist of,
staff room and associated storage rooms, dedicated playrooms for
the 0-2, 2-3 and 3-5yrs age groups and the associated dining and
food preparation area, toilet and boot room as well as guest and
quiet rooms.
 First floor: Primary 1 and 2-3 Learning Zones with the associated
Music Room and stores and external terrace and internal flexible
teaching spaces,  ERS training suites, meeting rooms, ASN teaching
spaces with a kitchenette and a dining space and the associated
changing facilities and cloak rooms with bathrooms. 
 Second floor: Primary 4-7 Learning Zones with the associated
facilities and stores and external terrace and internal flexible
teaching spaces, nurture rooms and a conference/multipurpose
office, ASN teaching spaces with a kitchenette and a dining space
and the associated changing facilities and cloak rooms with
bathrooms, and staff rooms with a shared kitchen and workbases
and dedicated toilets. 
3.6 The new build  will be delivered in distinct Phases as a “tandem-build”
with  the existing St Joseph’s school buildings remaining  operational
during the Phase 1 works. Solid Hoarding delineation will be introduced
to live school boundary with fencing to alternative perimeters. Separate
vehicular and pedestrian access/egress points will be introduced to
ensure the school and  construction site can operate independently. To
protect the site throughout the build, it will be monitored remotely through
newly introduced security CCTV, including outwith live operational hours
of the site. The phasing submitted with the application suggests that,
subject to the necessary permissions, the project is scheduled to
commence in November 2023 with an outline duration of 27 months. 
3.7 Once the new building is completed and occupied, the existing school
building will be demolished and parking provision and a drop-off area for
the site will be constructed in its place, with access from Faifley Rd. The
car park will contain  95 parking spaces and  six disabled parking spaces
with the associated footway access will be built. Twelve  of the spaces
will provide electric vehicle (EV) charging facilities, with another  38
spaces having capacity for future conversion to accommodate additional
EV parking requirement. 
3.8 Spaces for outdoor learning, socialising and physical activity are
proposed and would be located to the rear of the newly built campus,
overlooking the rear curtilages of the residential area south of the site.
The area would include natural play and interactive equipment, a
playground over an area of hard surfacing to feature painted on play area

Page 4

markings, and the separated area closest to the rear elevation of the
campus with sections dedicated for the particular age groups (0 -5yrs)
and external dining areas with seating. 
3.9 In support of the proposal the applicant has submitted a range of
supporting documentation and information including a series of Ground
Investigation reports and Remediation Strategy, Air Quality Impact
Assessment, GPR and Topographical Statement, Proposed Phasing
and Phasing Narrative documents, Transport Statement and Travel Plan
Framework, Design and Access Statement, Landscape Design and
Access Statement, Pre-application Consultation Report, Proposed
Floodlighting, Ecological Constraints and Preliminary Roost
Assessment, Development Drainage Impact Assessment, Tree Survey,
Bat Survey, solar/overshadowing assessment and Noise Impact
Assessment ..  
4.  CONSULTATIONS 
4.1 West Dunbartonshire Council Roads Service has no objection in respect
of roads and parking matters, together with flooding. 
4.2 West Dunbartonshire Council Environmental Health Service has no
objection subject to conditions relating to noise, delivery times, hours of
work during construction, piling method statement provision,
contaminated land remediation works implementation and unexpected
contamination, validation of soils, dust control and control of light from
outdoor facilities. 
4.3 Scottish Water has no objection to the proposed development. 
4.4  West of Scotland Archaeological Service has no objection to the
proposal subject to a condition regarding the implementation of a
programme of archaeological works. 
4.5 Glasgow Airport has no objection to the proposal subject to conditions
relating to a Bird Hazard Management Plan and soft landscaping in
relation to bird hazards. 
4.6  West Dunbartonshire Council Biodiversity Officer has no objection.
Points relating to the  ecology report and further bat surveys, biodiversity
enhancements and landscaping proposals can be addressed by
conditions. 
4.7 West Dunbartonshire Council Greenspace has  no objection but points
relating to the size of the community allotment area, the location of the
sports pitches and planting proposals are highlighted and are addressed
in Section 7 of the report.

Page 5

5.  REPRESENTATIONS 
5.1  No representations have been received. 
6.  ASSESSMENT AGAINST THE DEVELOPMENT PLAN 
6.1   National Planning Policy 4 
National Planning Framework 4 (NPF4) was adopted by the Scottish
Ministers on 13th of February 2023 and now forms part of the
Development Plan. 
6.2  Policy 1 relates to tackling the climate and nature crises and states that
when considering all development proposals significant weight will be
given to the global climate and nature crises. Policy 2 also relates to the
climate in the form of climate mitigation and adaptation and states
development proposals will be sited and designed to minimise lifecycle
greenhouse gas emissions as far as possible and development
proposals will be sited and designed to adapt to current and future risks
from climate change. 
6.3  As a part of the site would be brownfield following demolition of the
existing primary school , Policy 9 – Brownfield, vacant and derelict land
and empty buildings applies. Development proposals that will result in
the sustainable reuse of brownfield land including vacant and derelict
land and buildings, whether permanent or temporary, will be supported. 
6.4 Policy 13 supports proposals to improve, enhance or provide active
travel infrastructure, public transport infrastructure or multi-modal hubs.
This includes proposals for electric vehicle charging infrastructure. 
6.5  Development proposals will be designed to improve the quality of an
area whether in urban or rural locations and regardless of scale as per
Policy 14. Policy 15 relates to local living and 20 minute neighbourhoods.
Development proposal will contribute to local living including, where
relevant, 20 minute neighbourhoods. Consideration will be given to
existing settlement pattern, and the level and quality of interconnectivity
of the proposed development with the surrounding area, including local
access to affordable and accessible housing options, ability to age in
place and housing diversity. 
6.6   Under part (f) of Policy 19 proposals for buildings that will be occupied
by people will be supported where they are designed to promote
sustainable temperature management, for example by prioritising
natural or passive solutions such as siting, orientation, and materials. 
6.7 Green infrastructure is considered through Policy 20. Proposals that
result in fragmentation or net loss of existing green infrastructure will only
be supported where it can be demonstrated that the proposal would not
result in or exacerbate a deficit in green infrastructure provision, and the
overall integrity of the network will be maintained.

Page 6

6.8 Policy 22 Flood risk and water management states that proposals will :
not increase the risk of surface water flooding to others, or itself be at
risk; manage all rain and surface water through sustainable urban
drainage systems (SUDS), and seek to minimise the area of
impermeable surface. Policy 23 does not support proposals which are
likely to raise unacceptable noise issues. Policy 24 supports proposals
that incorporate appropriate, universal, and future-proofed digital
infrastructure. 
6.9 The proposal is considered to be in accordance with these policies as
discussed in Section 7 below. 
West Dunbartonshire Local Plan 2010
6.10   Policy PS1 supports the continued use of the site as a public service.
This policy also seeks to protect amenity of surrounding
neighbourhoods. Policy GD1 outlines the need for all new development
to be of a high design quality. Policy H5 safeguards and where possible
enhances the character and amenity of existing residential area. Policy
T1 and T4 requires sites to be integrated with sustainable travel. Policy
E1 relates to the Councils Biodiversity duty and Policy E5 requires new
development proposals to consider impacts on trees and incorporate
suitable tree planting. Policies F1 and F2 aim to ensure that new
development is not at risk from, and does not increase the risk of
flooding, and has suitable SUDS drainage infrastructure. Policy DC7
supports the inclusion of on-site micro-renewable technologies. 
6.11 The proposal is considered to be in accordance with these policies as
discussed in Section 7 below. 
7. ASSESSMENT AGAINST MATERIAL CONSIDERATIONS 
West Dunbartonshire Local Development Plan (LDP2) Proposed Plan
7.1 On 15th March 2023, the Planning Committee took a decision that the
Council would not adopt Local Development Plan 2. The Proposed Local
Development Plan 2 (LDP2), incorporating the recommended
modifications of the Examination Report received on 22 April 2020,
which were accepted by the Planning Committee of 19 August 2020,
remains the Council’s most up to date spatial strategy and is therefore
afforded significant weight in the assessment and determination of
planning applications, subject to compatibility with NPF4. The Scottish
Ministers’ Direction relating to the adoption of LDP2, dated 18 December
2020, is also a material consideration. 
7.2     The site is also identified in this plan as being within an existing
neighbourhood where policy H4 seeks to protect residential areas from
any development which would adversely affect its amenity. Policies CP1,
CP2 and CP4 are all related to enhancing the quality of design and
improving green infrastructure across West Dunbartonshire. Policy
CON1 requires proposals to be in accordance with designing streets

Page 7

guidance and promotes sustainable forms of transportation and active
travel. Policy ENV8 requires developments to address air quality, lighting
and noise as part of the planning process, whilst policy ENV9 requires
all potentially contaminated sites to be remediated where necessary to
ensure that the site is suitable for the intended use. 
7.3 RE4 encourages micro-generation and heat recovery technologies
within or associated with individual properties and Policy RE5 relates to
low and zero carbon buildings and states that new buildings should
conform to the sustainability standards. Policies ENV1, ENV4, and
ENV6 are all similar to the ecology and tree, water environment and
flooding policies of the adopted Local Plan 
7.4 The proposal is considered to be in accordance with all of the above 
policies for the reasons discussed below. 
Creating Places Guidance and Green Network and Green Infrastructure
Guidance
7.5 The Creating Places  Guidance – November 2022 seeks to achieve high
quality development with a design led approach based on a thorough
appraisal of the site and an analysis of its context, and sets out that this
is expected for all development proposals. The proposal has been
informed by a comprehensive pre-application as encourage by the
guidance and has been considered by the Place and Design Panel. This
has resulted in a development proposal that achieves a high quality
design that responds to the local context and accords with the approach
set out in the Guidance. 
7.6 The Green Network and Green Infrastructure  Guidance - November
2022 seeks to ensure that landscaping and green infrastructure is
integrated into the proposal as part of the setting and curtilage of the
new building. This will include a focus on biodiversity enhancement and
also the creation of a community growing space. The proposal accords
with the approach set out in the Guidance. 
Principle of Development
7.7 The site is currently occupied and is situated within a well-established
predominantly residential area. The adopted Local Plan specifically
supports the continued use of the site as a public service. The
sustainable re-use of brownfield land and previously developed sites is
supported through Policy 9 of NPF4. It is acknowledged that the site is
currently occupied and the existing buildings are in use as a school. It is
therefore not currently vacant or derelict, nor are the existing buildings
disused. With the site being re-developed on a tandem build basis, on
the completion and occupation of the new building, the existing building
will be vacated. The existing building will at that point become redundant
and be demolished to allow the second phase of the development to
commence. The re-use of the previously developed site overall is
supported.  Whilst Policy 12 sets a clear preference for the re-use of the
existing buildings, it is accepted that the existing building on site are in

Page 8

poor condition and have become life expired, as have the
buildings/facilities on other sites in Faifley  that the new facility will
replace. 
7.8 The site has been used as a primary school for many years. The
proposal would result in the continuation of this educational use and
would replace the existing building and facilities , with high quality
modern educational facilities. The proposal involves the co-location of
Edinbarnet Primary School , St Joseph’s RC Primary School , Education
Resource Centre (currently located at Edinbarnet), Early Learning and
Childcare Centre  Provision (Auchnacraig/Lennox), Additional Support
Needs  Facility (currently at St Joseph’s RC Primary School), along with
creation of a  new Community Library and a community space, leading
to a more efficient grouping of these facilities within the community.
Whilst the site currently contains only a single school, it is considered
that the site is large enough to accommodate all of these uses and that
the principle of redeveloping the site as a new educational campus is
acceptable. 
7.9 As such, the principle of the development of the site for new school and
community complex is supported on this site by planning policy.   
Site Layout, Design and Appearance
7.10  The building is sensitively located within the site so as not to over
dominate surrounding residential streets and the Faifley Road
thoroughfare. To the north end of the site, a new school frontage and
public zone faces towards the centre Faifley Road and would provide a
welcoming arrival point via the proposed entrance plaza. Another
potential entry point for pedestrians may be formed at the north-western
part of the plot from Faifley Knowes. Convenient and accessible parking
and drop-off provision is provided at this location; separation of
staff/visitor parking along with EV charging facilities is provided within
the site. Access to the playground for school and the campus building
itself will be via the main gate and the aforementioned plaza to Faifley
Road. It is considered that this will reactivate this important part of
Faifley, adding a focal point to this part of Faifley Road. Towards the
north-east of the site would be a new fenced all-weather sports and
MUGA pitches with proposed community allotment separating the
former from the street level. This would create a strong boundary and
screening from the residential properties beyond. In the south-eastern
corner of the site, closest to Hart St, a forest school with a habitat zone
and associated trail would be formed to provide areas for forest school
type outdoor activities. Overall, it is considered that the proposed layout
is well considered and sensitive to surrounding uses. Spaces for outdoor
learning, socialising and physical activity including the variety of sports
pitches, open and informal areas, natural play equipment, seating and
community allotment space to grow fruit and vegetables are to be
provided and will create a stimulating variety of settings with differing
characters which is supported.

Page 9

7.11 The building is of a striking and contemporary design and  provides a
landmark feature in this part of Faifley. It utilises a limited palette of high
quality, durable and robust materials; it is a refined and appropriate form
within its context. The  proposed materials  have been inspired by the
Cochno Stone  which  is a large cup and ring marked rock at Auchnacrig
Faifley  The proposed clay brick  has a very natural look with the use of
earthy tones.  This will  result in is a bold statement building that rises
three storeys thus providing prominence in the local community.  It is of
a  greater  height  than that of the existing school building, which is
reflective of the intended amalgamation of schools and learning centres
and a variety of community services however the three storey building 
does not overdominant the site or the relationship to the adjacent
residential properties.   Staggered roof terraces on either end of the
edifice reduce the overall building mass and create a visually interesting
building. The terraces will maximise natural daylight and ventilation deep
into the building  and provide views out to the south, including the tree-
covered landscape of the Faifley Knowes. They will also provide
educational benefits with external learning and teaching directly
accessible from internal learning and teaching zones. In contrast to the
brickwork, a light weight cladding is proposed to the upper levels and is
to be finished in a warm metallic copper  tone  which aim to celebrate
the new campus, creating a landmark for Faifley and again influenced
by the Cochno Stone.   Equally proportioned cladding panels and glazing
are designed to create a consistent rhythm to the façade. Overall, the
proposed building is considered to be of a high quality and modern
design which will provide a centrepiece for this part of West
Dunbartonshire and contribute to  and encourage the  wider regeneration
of Faifley. The bold design will continue the high standard set by other
school facilities within West Dunbartonshire (for example the recently
built Renton Campus). 
Low carbon design and technologies
7.12 One of the key elements of the design proposals is the low energy
strategy the new building will adopt.  Passive design principles will
ensure that the development is not only low energy standard but also
maximises visual and thermal comfort for users. The building will be
designed with enhanced fabric thermal performance including high
levels of insulation and airtightness together with shading canopies, low
energy lighting, air source heat pump and photovoltaic panels.  Such an
approach ensures that the proposal minimises greenhouse emissions
and incorporates low carbon infrastructure and thus embraces the
requirements  and aspirations set out by NPF4 and contributes towards
the Council meeting their net zero targets. . 
Residential amenity 
7.13 The new school building has been sensitively sited to ensure an
adequate degree of separation with the closest residential properties to
the north east and south west and to ensure the building is not
overbearing or creating adverse overshadowing or overlooking. This

Page 10

separation ranges from 25 metres to 35 metres at the closest points. A
solar assessment considering potential overshadowing was carried out
as part of the assessment of the application and shows that there would
be no unacceptable overshadowing of these properties. 
7.14 Schools by their nature are busy locations which generate a lot of activity
at either end of the school day, and noise from children playing outdoors
at intervals/ lunchtime is inevitable. However, the site has operated as a
primary school for many years and the proposed increase in the size of
the school is not considered to significantly increase the impact on
nearby residents. 
7.15 Noise from the proposed sports pitch is considered in the applicant’s
noise impact assessment and it is noted that noise impact increases
after 8pm when ambient noise levels reduce and that limitations on the
use of the pitch may be necessary from around 8pm to 9pm. An acoustic
barrier is recommended as are vibration reducers to reduce ball impact
noise. The Council’s Environmental Health Service offers no objections
on the ground of noise subject to conditions relation to noise mitigation
and hours of operation which would require in the use of the pitch
ceasing at 8pm. Considering the wider site, further mitigation in respect
of plant and equipment can also be addressed by condition. 
7.16 Turning to the floodlighting of the proposed pitch, Environmental Health
are content that providing the floodlighting is not used after 10pm, no
adverse disturbance would be caused to nearby residential property
from obtrusive lighting. As the pitch will be restricted to 8pm to address
noise concerns, the floodlighting will not be in use after this time. 
7.17 Any development site whilst under  construction  will produce an element
of short term noise and disruption, the Council’s Environmental Health
Service highlight the requirement that the construction of the
development is undertaken in a way that ensures that adjacent
residential amenity is not adversely affected. A range of conditions are
recommended and it is considered appropriate to attach these. These
include restricting working hours to 8am to 6pm Monday to Friday and
8am to 1pm on Saturdays. Conditions relating to piling and dust control
are also recommended. 
Ecology  
7.18 There are no environmental designations covering any part of the site
nor are there any in the surrounding area. A preliminary ecological
appraisal inclusive of preliminary bat roost assessment has been
undertaken to inform the application proposal. A small watercourse is
noted to the north of the site but this is unlikely to provide for suitable
use by otters due to its screened and culverted character. The school
building have been assessed as having moderate potential to host
roosting bats but negligible suitability for winter hibernation. No trees
were found to have suitable roost features. No field signs of badger were
identified and it is noted that the buildings and vegetation on site may

Page 11

provide opportunities for nesting birds. The appraisal identifies the need
for a minimum of two bat activity surveys within the bat activity season
(May to August inclusive) to determine the presence of bats. 
7.19 As bats are a European Protected Species (EPS) addressing protected
species by suspensive conditions is not an appropriate approach when
it comes to establishing the potential impact on EPS as it must be
ascertained whether protected species are on site and what the
implications of this might be before considering whether to approve a
planning application. In this case, the roost potential of the building have
been established. The demolition of the buildings on site will be the last
phase of the development and likely commence late 2025. Activity
surveys will therefore be required during the 2025 survey season.
Notwithstanding this, a single dusk activity survey has been undertaken
to provide details on bat activity within the area. The ecologist advises
that there were no bats emerging from the buildings. However, there
were foraging and commuting behaviour of soprano pipistrelles along
the treelines and the surrounding building. This ensures that the
application determination is based on an informed position relating to bat
activity. A condition requiring a minimum of two activity surveys [dusk
and dawn] in the survey season prior to the demolition of the buildings
can be addressed by condition. This is considered an appropriate
approach given that the building is still occupied and that preliminary bat
surveys have been undertaken which gives a baseline for future bat
surveys.   
7.20 A variety of further recommendations are contained within the
preliminary ecological appraisal including Tool Box Talks for contractors,
root protection areas for trees, tree and vegetation removal to be avoided
outwith the bird nesting season, and biodiversity enhancement
measures. These matters can be addressed by condition. The Council’s
Biodiversity Officer also offers no objections in respect of the proposal in
respect of ecological impact or the findings of the ecological appraisal
although highlights the requirement for a precautionary position relating
to possible presence of bats. The biodiversity enhancements identified
in the landscaping proposals are welcomed.   
Trees and Landscaping
7.21 A variety of trees exist within the site. The function of these trees was to
provide part of the landscape setting of the school that currently occupies
the site. The trees  are not protected. It is accepted that seven individual
trees and a dense grouping to the eastern boundary are to be removed
to accommodate the development. It is not considered that they are
significant specimens and new tree planting is provided as part of the
new development. The Council’s Biodiversity Officer advises that the lost
trees should be replaced at a ratio of 2:1 and the landscape plan
suggests that will be the case but no planting schedule is provided. This
can be addressed by condition.

Page 12

7.22 The greenspace within the site forms part of the curtilage of the existing
school and not open space provided for the purposes or recreation or
forming part of the wider green network. 
7.23 Considering landscaping and outside space, a high quality approach is
taken with an arrival plaza from Faifley Road creating a sense of arrival
with a combination of hard and soft landscaping.  Screening trees and
shrub planting will soften the car park to the front of the building. Within
the playground, a high quality outdoor learning environment will be
created with varying landscape elements including mounds and
undulating terrain, natural play areas, native tree planting, and wildflower
meadow planting. A specific Additional Support Needs garden area will
be provided including a sensory garden. To Faifley Road, a community
growing space / allotment will be provided, and will be well positioned to
become a focus for the community. Whilst the Council’s Greenspace
Team highlight concerns that this area is too small if it is to be a
replacement for the allotments at Skypoint, the requirement for the
retention of the existing allotments at Skypoint would be a matter to be
considered in any proposals to re-develop the Skypoint  site. The
landscaping approach is also designed to enhance biodiversity. The final
planting schedule can be addressed by condition and will allow the
schedule to be agreed with the Council’s Biodiversity Officer, The
Council’s wider Greenspace Team and Glasgow Airport. 
Traffic, Parking and Road Safety
7.24 A remodelled vehicular and public access to the campus is proposed
accessing from Faifley Rd. This area will comprise 95 parking bays of
which six are disabled bays. 54 of the parking spaces are accessed via
a separate entrance/exit and would be dedicated to staff only; the
remainder are mixed staff/visitor spaces, accessed via the secondary
egress point along the front perimeter of the site in Faifley Rd. This level
of car parking provision is acceptable to the Council’s Roads Service.
Electric vehicle charging points are included in the proposal, with 12
spaces served within the visitor car park. Cycle parking would also be
provided in the form of 50 covered cycle spaces, 10 covered scooter
spaces and 26 uncovered cycle stands within main public plaza (located
close to building so there is natural surveillance). Overall, this provides
a total of 76 cycles and 10 scooter spaces.   
7.25 While an acceptable provision of parking is to be provided, the school is
located in the heart of the community it serves, and is  in close proximity
to the established bus stops in Faifley Rd and walking distance of the
bus turning circle/terminal on the corner of Faifley Rd and the A810
Duntocher Rd .It is intended that the new campus will be  accessed by 
walking, wheeling and cycling by the local community and this will further
be in keeping with reducing the carbon footprint of the new campus.   The
proximity of the established residential areas currently served by the
existing school, Edinbarnet  Primary School  and the various learning
and community facilities currently scattered across Faifley, and the
ready availability of the bus services should encourage walking, cycling

Page 13

and use of public transport to travel to the new campus. A transport
statement has been provided in support of the proposal and this sets out
a variety of recommendations which are incorporated into the design. It
is recommended that a staff travel plan be developed and this can be
addressed by condition. A dedicated service vehicle access area along
the north-western perimeter of the site has been provided for collection
of refuse and deliveries. This will ensure there is no conflict with traffic
flows and service vehicles will not need to enter the school ground. 
7.26  The access, parking and servicing arrangements are all considered to
be acceptable. 
Flooding and Drainage
7.27 With respect to flooding and drainage, no flood risk assessment was
required due to the site being outwith any areas of flood risk within the
current SEPA maps. The Council’s Roads Service is content that there
is no requirement for a flood risk assessment. In terms of drainage, the
application submission is informed by a drainage impact assessment
together with full details of the proposed drainage regime and surface
water flow pathways. Final details and implementation on site can be
addressed by condition. 
Other technical issues 
7.28   A ground investigation report and remediation strategy have been
submitted in support of the proposal and Environmental Health raise no
concerns. Conditions are recommended to ensure the implementation
of the remediation strategy and also to address the presence of any
unexpected contamination. A condition is also recommended in respect
ensuring the suitability of either re-using site won material or importing
material to the site. Scottish Water offer no objections noting sufficient
capacity in the local network for the development. 
7.29 West of Scotland Archaeological Service (WOSAS) advises on a
programme of archaeological works and this can be addressed by
condition. 
Place and Design Panel and Elected Member Briefing
7.30 The applicant and their project team engaged in a pre-application
framework process with West Dunbartonshire Council Planning between
August 2022 and March 2023. Four meetings were held in which
comments were made by the Planning Service which are reflected in the
submitted design. The design proposal was also reviewed by the
Council’s Place and Design Panel in October 2022 The Panel
commended the aspiration to deliver a Passivhaus standard building on
what is a constrained site. Credit was also given to the proposals overal
with the ‘campus concept’ being welcomed. The panel noted the
constraints of the site but welcomed the large entrance plaza. The Panel
also considered the proposed buildings to respond sensitively to the
location and supported the approach to the architectural language and

Page 14

proposed material palette. The Panel considered that that the southern
elevation could do more to announce itself as a key destination. The
Panel also considered that the proposal should seek to maximise active
travel connections and seek to promote a modal shift to reduce reliance
on the private car. The comments of the panel were taken into account
in concluding the final design.   
7.31 In developing the proposal, engagement workshops were held by the
project team involving education, community and library teams. An
online briefing was held on 15th February 2023 attended by 25 people,
with a further community event held at Skypoint on 23rd February 2023
attended by 33 people. Two public consultation events were held as part
of the statutory pre-application process at Edinbarnet Primary School on
22nd February 2023, which 34 people attended, and St Joseph’s Primary
School on 7th March 2023, which 43 people attended. The project team
also undertook a presentation to school staff on 26th April 2023. The
applicant’s pre-application consultation report highlights that general
feedback was very positive with the key themes from the events being
access, parking and boundary treatments. 
7.32 An Elected Members briefing was held on 1st June 2023 where the
project team presented the proposals to Elected Members. The
proposals were well received by Members with  comments  that further
discussion was required about the community facilities to be  sited in the
new campus to ensure they met  requirements for  existing community
facilities which exist in Skypoint. 
8.  CONCLUSION 
8.1 A high quality primary and early education and community facilities will
be provided on a site which has a long history of use for educational
purposes and is therefore consistent with all relevant planning policies.
The new school campus has been designed and positioned to provide a
civic presence within the Faifley community and will enhance the setting
this part of Faifley.  It has been designed to a very high standard and its
bold design and use of quality materials will provide a landmark
presence. It has been designed to ensure that it does not impact on the
amenity of adjacent residential properties. 
8.2 The proposal will result in a high quality new educational and community 
facility that presents no conflict with the policy requirements of NPF4, the
adopted Local Plan and the proposed Local Development Plan and it will 
support the continued  regeneration of the wider Faifley area. 
9.  CONDITIONS 
1. The external materials to be used in the construction of the building
hereby permitted shall accord with the details set out on approved
drawing FC-HML-01-ZZ-D-A-48100 Rev PO3 and no substitutes shall
be used without the prior written agreement of the Planning Authority.

Page 15

2. Further to Condition 1 above, prior to the approved brickwork associated
with the building hereby permitted being constructed  on site, a sample
panel of this brickwork shall be constructed on site in order for it and the
associated mortar to be reviewed, inspected and approved in writing by
the Planning Authority. Thereafter, unless otherwise agreed in writing
with the Planning Authority, the development shall be completed in strict
accordance with the approved brick details. 
3. Prior to the commencement of development on site, full details of all hard
surfaces shall be submitted for the further written approval of the
Planning Authority. The development shall thereafter be completed in
accordance with the approved details prior to the occupation of any unit
within the development. 
4. The phasing of the development shall be undertaken in accordance with
the phasing details hereby approved and following the commencement
of works on site, the development phasing will be undertaken on a
continuous basis until completion, unless otherwise first agreed in writing
by the Planning Authority. 
5. Notwithstanding the approved plans, all recommendations within the
Ecological Constraints Survey and Preliminary Bat Roost Assessment
dated 1st December 2022 shall be followed. Further survey work
undertaken shall be submitted to and approved in writing by the Planning
Authority prior to the commencement of any works on site and
implemented as approved. 
6. Notwithstanding condition 5 above and for the absolute avoidance of
doubt, a minimum of two bat activity surveys (dusk and dawn) shall be
undertaken in the activity season immediately preceding the demolition
of the existing building on site. The survey results shall be submitted to
and approved in writing by the Planning Authority prior to any demolition
commencing on site.   
7. Notwithstanding condition 5 above, no site clearance works shall be
undertaken during any phase during the bird-nesting season March to
September inclusive unless first agreed in writing by the Planning
Authority. For the avoidance of doubt, any such agreement will require
a full nesting bird survey prior to the commencement of works on site,
the methodology and findings of which shall be submitted to the Planning
Authority. 
8. The approved hard and soft landscaping and all associated approved
planting details shall be implemented within a timescale to be agreed
with the Planning Authority prior to the commencement of works on site.. 
9. Notwithstanding the approved  plans, full details of the proposed planting
schedule, inclusive of proposed tree planting on a two for one basis
relative to those being removed, shall be submitted to and approved in

Page 16

writing by the Planning Authority prior to the commencement of  any
works on site and shall be implemented with a timescale to be agreed
with the Planning Authority. 
10. That any trees, shrubs or areas of grass which die, are removed,
damaged or become diseased within five years of completion of the
landscaping shall be replaced within the following year with others of a
similar size and species. 
11. That full details of maintenance and management for the landscaping
approved shall be submitted to and approved in writing by the Planning
Authority prior to the occupation of the new building hereby permitted.
Management and maintenance shall commence upon completion of the
landscaping. 
12. Details of the management and operation of the community allotments
shall be submitted to and approved by the Planning Authority prior to the
occupation of the new building hereby permitted. Management and
operation shall then be undertaken in accordance with the approved
details at all times thereafter. 
13. Notwithstanding the submitted details, that prior to the commencement
of works on site, a final drainage regime inclusive of maintenance
arrangements shall be submitted to and approved in writing by the
Planning Authority. The drainage regime shall then be implemented and
maintained thereafter. For the avoidance of doubt, the drainage regime
shall be implemented commensurately with the construction of the
development. 
14. That all surface water shall be intercepted within the site both during
construction and on completion of the development and full details of
measures to ensure that surface water run-off is contained within the site
shall be submitted to and approved in writing ty the Planning Authority
prior to the commencement of any works on site. The measures shall be
implemented and maintained as approved. 
15. That prior to the commencement of works on site, a bird hazard
management plan shall be submitted to and approved in writing by the
Planning Authority in consultation with Glasgow Airport. The submitted
plan shall include: 
 Management of any flat / shallow pitched / green roofs on
buildings within the site which may be attractive to nesting,
roosting and loafing of birds. The management plan shall comply
with Advice Note 8: Potential Bird Hazards from Building Design 
The Bird Hazard Management Plan shall be implemented as approved
and on completion of the development shall remain in force for the
lifetime of the development. No subsequent alterations to the plan are to

Page 17

take place unless first submitted to and approved in writing by the
Planning Authority in consultation with Glasgow Airport. 
16. No development shall take place until full details of soft and water-
landscaping works have been submitted to and approved in writing by
the Planning Authority. Details shall comply with Advice Note 3: Potential
Bird Hazards from Amenity Landscaping and Building Design. These
details shall include the species, number and spacing of shrubs and
trees
. 
No subsequent alterations to the approved landscaping scheme are to
take place unless submitted to and approved in writing by the Planning
Authority in consultation with Glasgow Airport. The scheme shall also be
implemented as approved. 
17. The noise mitigation requirements detailed in the Noise Impact
Assessment – Report no. 7355-05-00 Rev 00 and Report no. 7355-04-
00 dated 7 June 2023 and 3 May 2023 relating to plant and mechanical
services and sport pitch shall be implemented in full, namely: 
 The roof top plant compounds shall have compliant plant screens
as barriers that is having no gaps at the foot or between panels
and a lifetime surface density of 10kg/m2. 
 The sports pitch shall not be used outwith the hours of 8am to
8pm daily.
 The sports pitch shall have  rubber vibration reducers between
the weldmesh fencing panels to reduce ball impact noise.
18. All plant and equipment (including any ventilation system) to be installed
or operated  shall be enclosed, attenuated and/or maintained such that
any noise there from shall not exceed International Standards
Organisation (ISO) Noise Rating 35 between 0700 and 2300 hours daily,
within any nearby residential property, with windows slightly open for
ventilation, when measured and/or calculated and plotted on an ISO
rating curve chart. 
19. In the event that the sports pitch floodlighting requires to operate outwith
the hours of 8am to 8pm   of use of the sports pitch set out in condition
17 above, it shall be switched off by 10pm. 
20. During the period of construction, all works and ancillary operations
which are audible at the site boundary (or at such other place(s) as may
first be agreed in writing with the Planning Authority), shall be carried out
between the following hours unless otherwise approved in writing by the
Planning Authority: 
 Mondays to Fridays: 0800 – 1800
 Saturdays: 0800 – 1300

Page 18

 Sundays and public holidays: No Working 
21. No commercial vehicle making deliveries to or collecting material from
the development during construction shall enter or leave the site before
0800 or after 1800. 
22. No piling works shall be carried out until a method statement has been
submitted to and approved in writing by the Planning Authority. This
statement shall include an assessment of the impact of the piling on
surrounding properties, taking into account the guidance contained in BS
6472: 1984 ‘Evaluation of Human Response to Vibration in Buildings’. It
shall detail any procedures which are proposed to minimise the impact
of noise and vibration on the occupants of surrounding properties. This
statement shall be prepared by a suitably qualified person, and the piling
works shall thereafter be carried out in accordance with the approved
method statement. 
23. Unless otherwise approved in writing by the Planning Authority, no
development shall commence on site until such time as a scheme for the
control and mitigation of dust has been submitted to and approved in
writing by this Authority. The scheme shall identify likely sources of dust
arising from the development or its construction, and shall identify
measures to prevent or limit the occurrence and impact of such dust.
The approved scheme shall thereafter be implemented fully prior to any
of the identified dust generating activities commencing on site and shall
be maintained thereafter, unless otherwise approved by this Authority. 
24. The approved remediation scheme shall be carried out in accordance
with its terms prior to the commencement of development other than that
required to carry out remediation, unless otherwise agreed in writing by
the Planning Authority. The Planning Authority shall be notified in writing
of the intended commencement of remediation works not less than 14
days before these works commence on site. Upon completion of the
remediation works and prior to the site being occupied, a verification
report which demonstrates the effectiveness of the completed
remediation works shall be submitted to and approved in writing by the
Local Planning Authority. 
25. The presence of any previously unexpected contamination that becomes
evident during the development of the site shall be reported to the
Planning Authority in writing within one week, and work on the site shall
cease. At this stage, if requested by the Planning Authority, an
appropriate investigation and risk assessment shall be undertaken and
a remediation scheme shall be submitted to and approved by the
Planning Authority prior to the recommencement of site works. The
approved details shall be implemented as approved. 
26. If there is a requirement to either re-use site won material or to import
material then the assessment criteria and sampling frequency that would
adequately demonstrate its suitability for use shall be submitted to and

Page 19

approved by the Planning Authority prior to any material being re-used
or imported. In addition to this and in accordance with BS3882:2015 and
BS8601:2013, material to be used in the top 300mm shall also be free
from metals, plastic, wood, glass, tarmac, paper and odours. On
completion of the works and at a time and or phasing agreed by the
Planning Authority, the developer shall submit a validation report
containing details of the source of the material and associated test
results to demonstrate its suitability for use. 
27. That prior to the new building being brought into use, a Travel Plan for
the site shall be undertaken and submitted to and approved in writing by
the Planning Authority.  This shall include what initiatives will be brought
forward in the future to ensure the achievement of a meaningful switch
away from the private car inclusive of staff travel. Any agreed actions
and measures shall be implemented.  
No development shall commence within the development site outlined in
red on the approved plan until the developer has secured the
implementation of a programme of archaeological works in accordance
with a written scheme of investigation which has been submitted by the
applicant, agreed with West of Scotland Archaeological Service and
approved by the Planning Authority,. Thereafter the developer shall
ensure that the programme of archaeological works is fully implemented
and that all recording and recovery or archaeological resources within
the development site is undertaken.   
Pamela Clifford 
Planning, Building Standards and Environmental Health Manager 
Date: 20th September 2023    
______________________________________________________________ 
Person to Contact: Pamela Clifford, Planning, Building Standards and
Environmental Health Manager  
Pamela.Clifford@west-dunbarton.gov.uk 
James McColl, Development Management Team
Leader
james.mccoll@west-dunbarton.gov.uk 
Appendix:   Location Plan

Page 20

Background Papers:  
1. Application forms and plans;
2. Consultation responses;
3. National Planning Framework 4
4. West Dunbartonshire Local Plan 2010;
5. West Dunbartonshire Local Development
Plan Proposed Plan;
6. Creating Places Guidance (2022) 
7. Green Network and Green Infrastructure
Guidance (2022); 
Wards affected:  Ward 4 – Kilpatrick