Democracy Spraffa

Approved Minutes - Planning Committee 09 10 24

West Dunbartonshire Council · 9 October 2024
Back to Planning Committee — 9 October 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

PLANNING COMMITTEE 
At a Meeting of the Planning Committee held in the Council Chambers, Clydebank
Town Hall, on Wednesday, 9 October 2024 at 10.02 a.m. 
Present:   Provost Karen Murray Conaghan and Councillors Gurpreet
Singh Johal, Lawrence O’Neill, Chris Pollock, Hazel Sorrell and
Sophie Traynor. 
Attending: Michael Mulgrew, Planning, Building Standards and
Environmental Health Manager; James McColl, Development
Management Team Leader; Amy Melkevik, Lead Planning
Officer; Nigel Ettles, Principal Solicitor and Nicola Moorcroft,
Committee Officer. 
Apologies: Apologies for absence were intimated on behalf Councillors Ian
Dickson, David McBride and Clare Steel. 
Councillor Lawrence O’Neill in the Chair 
DECLARATIONS OF INTEREST 
It was noted that there were no declarations of interest in any of the items of
business on the agenda. 
OPEN FORUM 
The Committee noted that no open forum questions had been submitted by
members of the public. 
MINUTES OF PREVIOUS MEETING 
The Minutes of Meeting of the Planning Committee held on 11 September 2024 were
submitted and approved as a correct record. 
PLANNING APPLICATION 
A report was submitted by the Chief Officer – Regulatory and Regeneration in
respect of the following Planning application:-

Page 2

DC24/073/FUL: Demolition of existing dwelling and the construction of two new
dwellings and upgrading of the existing access road to an adopted road at 29
Roman Hill Road, Hardgate, Clydebank, G81 6NU by Gerald Mulhearn. 
Reference was made to a site visit which had been undertaken in respect of the above
application.  The Development Management Team Leader and the Planning, Building
Standards and Environmental Health Manager were heard in further explanation, and in
answer to Members’ questions. 
The Chair invited Ms Margaret Hogg (objector) to address the Committee Ms Hogg was
heard in respect of the application. 
The Chair invited Ms Amy Ramage (objector) to address the Committee Ms Ramage was
heard in respect of the application. 
The Chair invited Mr Christopher Wright (objector) to address the Committee. Mr Wright
was heard in respect of the application. 
The Chair invited Mr Patrick Delany (objector) to address the Committee. Mr Delany was
heard in respect of the application. 
The Chair invited Mr William Anderson (Applicant’s Agent) and Mr Gerald Mulhearn
(Applicant) to address the Committee. Mr Anderson and Mr Mulhearn were heard in
respect of the application and in answer to Members’ questions. 
After discussion, the Committee agreed to grant planning permission subject to the
conditions set out in Section 9 of the report, as detailed within Appendix 1 hereto. 
The meeting closed at 10. 43 a.m.

Page 3

APPENDIX 1 
DC24/073/FUL: Demolition of existing dwelling and the construction of two new
dwellings and upgrading of the existing access road to an adopted road at 29
Roman Hill Road, Hardgate, Clydebank, G81 6NU by Gerald Mulhearn. 
CONDITIONS:- 
1. Prior to the commencement of development on site, exact details of all
proposed external materials (inclusive of all hard surfaces), to be used in the
development site shall be submitted to and approved in writing by the
Planning Authority.  Thereafter, unless otherwise agreed in writing with the
Planning Authority, the development shall be completed in strict accordance
with the approved material details and palette. 
Reason: In the interest of visual amenity. 
2. Prior to the commencement of development on site, a detailed boundary
treatment and hard and soft landscaping plan, including timescales for
implementation shall be submitted to and approved in writing by the Planning
Authority.  This plan shall also include details of tree loss, replacement
planting and details of root protection areas to safeguard existing trees.
Thereafter, unless otherwise agreed in writing with the Planning Authority, the
development shall be completed in strict accordance with the approved plan. 
Reason: In the interest of visual amenity, protection and enhancement of
biodiversity and tree protection. 
3. Prior to the commencement of development on site, a Biodiversity
Enhancement Plan setting out how the proposal enhances biodiversity
beyond the current baseline, together with the implementation on site, shall be
submitted to and approved in writing by the Planning Authority. All measures
shall then be implemented as approved.  Thereafter, unless otherwise agreed
in writing with the Planning Authority, the development shall be completed in
accordance with the approved plan. 
Reason: In the interest of biodiversity. 
4. That any trees, shrubs or areas of grass which die, are removed, damaged or
become diseased within five years of completion of the landscaping shall be
replaced within the following year with others of a similar size and species. 
Reason: In the interest of visual amenity and biodiversity. 
5. That unless otherwise agreed in writing by the Planning Authority, all
recommendations set out within the submitted Preliminary Roost Assessment
and Bat Activity Survey shall be followed and implemented, inclusive of the
Species Protection Plan as detailed in Appendix 6 of the report, to the
satisfaction of the Planning Authority.

Page 4

Reason: In the interests of the protection of bats. 
6. No site clearance works or works in connection with the demolition of the
existing building shall take place during the bird nesting season March to
August inclusive unless first agreed in writing by the Planning Authority and
nesting bird survey undertaken not more than 48 hours prior to the
commencement of site clearance works, the findings of which shall be
submitted to the Planning Authority. 
Reason: In the interests of the protection of nesting birds. 
7. That prior to the commencement of works on site, full details of the proposed
drainage regime inclusive of calculations and overland flow details shall be
submitted to and approved in writing by the Planning Authority.  The drainage
regime shall then be implemented and maintained thereafter.  For the
avoidance of doubt, the drainage regime shall be implemented
commensurately with the construction of the houses it serves. 
Reason: To ensure adequate drainage of the site. 
8. That all surface water shall be intercepted within the site both during
construction and on completion of the development and full details of
measures to ensure that surface water run-off is contained within the site shall
be submitted to and approved in writing to the Planning Authority prior to the
commencement of any works on site.  The measures shall be implemented
and maintained as approved. 
Reason: To ensure adequate drainage of the site. 
9. Prior to commencement of any works on site, including the demolition of the
existing building, full details regarding the works to be undertaken to upgrade
the section of Roman Hill Road included within the red line shown on the
approved Location Plan to an adoptable standard in accordance with West
Dunbartonshire / National Road Design Guidance specifications, together with
a detailed programme for the implementation and completion of the works,
shall be submitted to and approved in writing by the Planning Authority in
consultation with the Council’s Roads Service.  Thereafter the works shall
proceed in accordance with the approved details unless otherwise agreed in
writing with the Planning Authority. 
Reason: To ensure a suitable road arrangement in the interests of road and
pedestrian safety and that this is implemented in a suitable timescale. 
10. Notwithstanding condition 9 above and for the avoidance of doubt, prior to
commencement of works to construct a second dwellinghouse upon the site,
the upgrade of the section of Roman Hill Road included within the red line
shown on the approved Location Plan shall be completed as agreed under
condition 12 to the satisfaction of the Planning Authority, unless otherwise first
agreed in writing by the Planning Authority.

Page 5

Reason: In order to ensure that the road used to access the additional
number of dwellinghouses is of an acceptable standard. 
11. Prior to commencement of any works on site, a site management scheme for
construction traffic shall be submitted to and approved in writing by the
Planning Authority.  Thereafter work shall proceed in accordance with the
approved scheme unless otherwise agreed in writing with the Planning
Authority. 
Reason: In the interest of road safety. 
12. That prior to the occupation of any house, the off-street parking provision
hereby approved shall be completed and be available for use by residents of
the associated house.  The off-street parking provision shall then remain
unobstructed and available for use by residents of the associated house at all
times thereafter. 
Reason: To ensure adequate parking provision is in place for development. 
13. Prior to the occupation of the houses hereby permitted, the developer shall
install the necessary infrastructure to enable the full development and all
associated properties to be connected to the existing fibre optic network,
where available in West Dunbartonshire, and in accordance with the relevant
telecommunications provider’s standards. 
Reason: To ensure compliance with Policy CON4 of the West Dunbartonshire
Proposed Local Development Plan (2020) and in the interests of securing the
facilities to support communities. 
14. Unless otherwise approved in writing by the Authority, no development shall
commence on site until such time as a scheme for the control and mitigation
of dust has been submitted to and approved in writing by this Authority.  The
scheme shall identify likely sources of dust arising from the development or its
construction and shall identify measures to prevent or limit the occurrence and
impact of such dust.  The approved scheme shall thereafter be implemented
fully prior to any of the identified dust generating activities commencing on site
and shall be maintained thereafter, unless otherwise approved by this
Authority. 
Reason: To minimise the occurrence of dust, in the interests of the amenity of
the area. 
15. During construction, no commercial vehicle making deliveries to or collecting
material from the development shall enter or leave the site before 0800 or
after 1800. 
Reason: To minimise noise and disturbance to nearby residents at unsocial
hours.

Page 6

16. During the period of construction, all works and ancillary operations which are
audible at the site boundary (or at such other place(s) as may first be agreed
in writing with the Planning Authority), shall be carried out between the
following hours unless otherwise approved in writing by the Planning
Authority: 
• Mondays to Fridays: 0800 – 1800
• Saturdays: 0800 – 1300
• Sundays and public holidays: No Working 
Reason: To ensure that the development does not adversely affect the
amenity of neighbouring properties by creating excessive noise and
disturbance at unsocial hours. 
17. Prior to the commencement of works on site, a scheme for the salvage and
reuse of material from the demolition of the existing house shall be submitted
to and approved in writing by the Planning Authority.  Works shall then
proceed as approved. 
Reason: In the interests of zero waste.