WEST DUNBARTONSHIRE COUNCIL
Report by Planning, Building Standards and Environmental Health Manager
Planning Committee: 11th September 2024
DC23/086/FUL: Erection of activity centre incorporating a community
hub and bicycle workshop, together with associated
work on land adjacent to the south bank of the Forth and
Clyde Canal, Clydebank by West Dunbartonshire
Council.
1. PURPOSE
1.1 To provide the Committee with the opportunity to further consider the
planning application with the applicant in attendance for Members
questions following continuation from August Planning Committee, and to
seek the Committee’s decision on the application.
2. RECOMMENDATION
2.1 Grant planning permission subject to the conditions set out in Appendix
2.
3. BACKGROUND
3.1 The above planning application was to be considered by Planning
Committee on 5th June 2024. Due to the relevant Officer from the Planning
Service being unable to attend Committee, it was determined by the
Planning Committee to continue the application without consideration, to
allow for the relevant Officer to attend, present the application and answer
Members questions. It was subsequently considered by Planning
Committee on 7th August. Due to the applicant being unable to attend
August Committee, it was determined to further continue the application to
allow the applicant to attend and answer Members questions. 
4. MAIN ISSUES
4.1 There are no material changes to the Development Plan position, the
circumstances of the site, proposal or the assessment since August
Committee. 
4.2 It remains the case that the proposal is welcomed and would provide a
high quality, community focused activity centre that would contribute to the
ITEM 6

Page 2

mix of uses and vitality of the Town Centre and help connect people with
the canal, without any detrimental effects on local amenity.
4.3 The proposal presents no conflict with the policy requirements of NPF4,
the adopted Local Plan, the proposed Local Development Plan 2 and
associated Planning Guidance.
4.4 During consideration of the application at Committee on 7th August,
Members raised questions relating to the possible retention and reuse of
the existing granite features within the site and also the management of
construction traffic during the development. Members were advised that
additional conditions could be added to address these matters.  Two
additional planning conditions, relating to a Construction Traffic
Management Plan and the retention and reuse of the granite feature
seating, are therefore recommended in addition to those proposed in the
Committee Report (05/06/2024), attached as Appendix 1. These
conditions have been added to an updated listed of conditions, set out in
the attached Appendix 2.
5. PEOPLE IMPLICATIONS
5.1 None.
6. FINANCIAL AND PROCUREMENT IMPLICATIONS
6.1 There are no financial or procurement implications in terms of this report.
7. RISK ANALYSIS
7.1 No risks have been identified.
8. EQUALITIES IMPACT ASSESSMENT (EIA)
8.1 Not required.
9. ENVIRONMENTAL SUSTAINABILITY
9.1 There are no environmental sustainability issues in terms of this report.
10. CONSULTATION
10.1 Consultation was undertaken as part of planning processes associated
with the planning application.
11. STRATEGIC ASSESSMENT

Page 3

11.1 There are no strategic issues.
Alan Douglas
Chief Officer – Regulatory and Regeneration
Date: 11th September 2024
Person to Contact: James McColl, Development Management Team
Leader
James.McColl@west-dunbarton.gov.uk
Appendix 1: DC23/086/FUL Committee Report (05/06/2024)
Appendix 2:
Appendix 3:
Updated Recommended Conditions
Location Plan
Wards affected: Ward 5 (Clydebank Central)