WEST DUNBARTONSHIRE COUNCIL 
Report by the Planning, Building Standards and Environmental Health
Manager 
Planning Committee: 5th November 2025
___________________________________________________________________ 
Subject: Scottish Government Consultation on Expansion of Permitted
Development Rights 
1. Purpose 
1.1 The purpose of this report is to seek formal committee approval of the
response to the consultation. 
2. Recommendation  
2.1 It is recommended that Planning Committee agrees the response noted at
Appendix 1 that was submitted to Scottish Government with the agreement of
the Chair of the Planning Committee. 
3. Background 
3.1 The Scottish Government is consulting on proposed changes to Permitted
Development Rights (PDR’s) to address the nationally declared housing
emergency and to support the deployment of heat networks and domestic air
source heat pumps. 
3.2 The consultation can be grouped into 3 main areas:
• Rural homes
• Town Centre/Class 1A 
• Increasing the scope of householder permitted development rights and
renewables (including heat networks) 
3.3  The consultation period (3rd September 2025 to 27th October 2025) clashed
with committee deadlines for October Committee meeting and allowing
sufficient officer time to review the consultation content. An extension to
Friday 7th November to allow consideration at the Committee meeting on 5th
November was sought, but this was declined by Scottish Government. The
Planning, Building Standards and Environmental Health Service Manager
expressed disappointment in this stance to Scottish Government officials.
Scottish Government confirmed we could submit a response after the
deadline but that they may not be able to take this into account as it would be
a late response. 
3.4  In this circumstance, officers are able to prepare a draft response and have
that agreed by the Chair of the relevant committee and submit on that basis.
The response is then formally ratified by the relevant committee at its next
meeting.

Page 2

3.5 Officers engaged with the Chair of Planning Committee on the consultation
and the proposed response. The Chair agreed the response set out at
Appendix 1 and this was submitted to the Scottish Government prior to the
deadline. 
4. Main Issues 
Summary of the proposed response 
4.1 The full response to all questions is set out in Appendix 1, with the general
position of the Council being that the Council supports the targeted expansion
of PDR’s but stresses the need for appropriate controls to avoid unintended
consequences, especially in unsustainable locations. 
Rural Homes
.
4.2 The proposed response notes that within a West Dunbartonshire context we
have not had any notifications under Classes 18B or 22A which allow the
conversion of agricultural buildings/forestry buildings to residential use as we
a primarily urban authority. 
4.3 Whilst we would support small extensions to converted buildings, we do
however express caution about increasing unit and floor space limits under
these classes due to concerns around individual and cumulative impact on
infrastructure and increasing housing development in potentially
unsustainable locations distant from services. Similarly, we do not support
expansion of new build homes via PDR in rural areas due to concerns around
landscape impact, infrastructure, sustainability and impact on Green Belt. We
consider that this type of development should still be assessed via the
standard planning application process. 
Town Centre Living/Class 1A 
4.4 The consultation is aimed at Town Centre living, however, it is difficult to
restrict this due to varying definitions at a local level and no single agreed
national definition. Such designations are noted in Local Development Plans
and subject to change over time. The consultation therefore notes that any
changes would apply to Class 1A units. Class 1A covers a broad range of
uses such as shops, hairdressers, post officers, cold food shops, banks,
estate agents and other services which is appropriate to provide in a shopping
area and where the sale, display or service is principally to visiting members
of the public. In this regard, whilst generally covering town and local centres,
any changes would also apply to Class 1A units outwith these defined
centres. The consultation does explicitly exclude areas such as covered
shopping malls and retail parks. 
4.5 The consultation seeks views on allowing ground floor Class 1A units and/or
the upper floors of such units to be converted to residential use. The response

Page 3

notes that we would oppose the conversion of ground floor units due to the
loss of active frontages and impacts on the viability and vitality of Town
Centres. Such blanket use could result in a detriment of a Town Centre’s
offer. We also express general placemaking concerns around amenity,
parking and infrastructure etc. In relation to upper floors, the response is more
supportive and in principle this could be achieved but the parameters of any
permitted changes need to ensure that:
• They address amenity impacts from other uses, such as those that
generate noise and odour.
• They should include minimum space standards to avoid substandard
units.
• They ensure that separate access from ground floor commercial units
to residential units are provided.
• Limits on unit numbers and parking impacts are considered.
• Short term lets and Houses in Multiple Occupancy are excluded from
any proposed PDR.
• Flood risk and accessibility is considered.
• Covered shopping malls and retail parks are clearly excluded from
PDR. 
4.6 Development, as defined in section 26 of The Town and Country Planning
(Scotland) Act 1997, requires planning consent. For an effective and
proportionate planning system not all works meeting this definition require
express planning consent from the relevant Planning Authority and a variety of
Permitted Development Rights exist. Permitted Development is further split
into 2 main methods. Permitted development can be unambiguous and clear
on exact parameters (size, location etc) without the need for express planning
consent. The other is known as Prior Notification/Prior Approval. This requires
notification to the Planning Authority that works are to be carried out that is
permitted development but often allows the Planning Authority to convert this
to a Prior Approval on certain matters. It is not open to Planning Authorities to
query the principle, but it does allow consideration of specific matters such as
materials. The Prior Notification/Prior Approval route is generally not
supported by Planning Authorities as these processes generally cause
confusion for applicants, officers and communities due to their complexity and
often narrow focus of what can be controlled. Due to their short timescale and
limited fee, these types of application do not reflect the workload and
complexity experienced by Planning Authorities. It is also important to note
that this route, in the vast majority of circumstances, does not allow for
notification or consultation by the Planning Authority to neighbours or
consultees. This route also carries legal risk to the Planning Authority as,
unlike a planning application, Prior Notifications have to be responded to no
later than 28 days after their submission, otherwise deemed consent exists
and the Planning Authority has no further control over the development. It is
for these reasons that the response reinforces our view that we would not be
supportive of any new Prior Notification/Prior Approval mechanisms and any
changes should be unambiguous as to whether they are permitted
development or require planning permission.

Page 4

4.7 Should the Scottish Government proceed with requiring Prior
Notifications/Prior Approval, we seek to ensure appropriate matters are
considered and that the fee and timescale to respond to these are
substantially increased. For this reason, we do note that in that event, such a
process would be no quicker than a traditional planning application.   
Increasing the scope of householder permitted development rights and
renewables (including heat networks) 
4.8 The response sets out that we are supportive of changes that may expand
householder PDR to allow homeowners to make better use of their existing
properties. Matters under consideration include:
• Increasing the maximum ground area covered by an extended building.
• Amending the external dimension restrictions, for example in
Conservation Areas.
• Increasing the amount of side and rear curtilage that can be developed
under PDR.
• Amending the PDR for alterations to roofs to allow greater use of loft
space. 
4.9 We also support clearer standards for Air Source Heat Pumps and the
expansion of existing permissions to allow for 2 pumps on detached homes,
subject to noise safeguards. We also set out that we are supportive of the
view that Air Source Heat Pumps for heating and cooling but not solely
cooling. 
4.10 In relation to heat networks, we are supportive of measures to enable easier
and more simpler connections, but we would seek there to be a clear
exclusion or restriction in sensitive areas, such as Conservation Areas of sites
of archaeological interest. 
Key summary of the response 
4.11 West Dunbartonshire Council is supportive of Permitted Development
expansion where it improves housing delivery, respects local context and
infrastructure capacity, and maintains planning oversight where necessary.
However, the Council urges caution that any PDR expansion has to avoid
undermining strategic local and national planning goals, particularly in rural
and town centre settings, and recommends robust safeguards to ensure
quality, sustainability and overall community benefit.   
5. People Implications 
5.1 There are no people implications associated with this report. 
6. Financial and Procurement Implications 
6.1 There are no financial or procurement implications associated with this report.

Page 5

7. Risk Analysis 
7.1 There is no financial, reputational or legal risk associated with this report. The
Council is not statutorily required to respond to this Scottish Government
consultation but will be bound by the outcome of the consultation and any
resulting changes to Permitted Development Rights. 
8. Equalities Impact Assessment (EIA) 
8.1 Not required. 
9. Consultation 
9.1 This is a Scottish Government consultation seeking the views of all
stakeholders. The Council has been consulted as Planning Authority and the
Council is not required to consult with any other party to form its response. 
9.2 As set out in section 3 of this report, officers consulted with the Chair of
Planning Committee on the content of Appendix 1 that was submitted as the
Council’s response to the consultation within the set deadline. 
10. Strategic Assessment 
10.1 The new Local Development is considered to be relevant to, and will
help deliver, all of the Council’s strategic priorities:
• Our Communities – Resilient and Thriving
• Our Environment – A Greener Future
• Our Economy – Strong and Flourishing
• Our Council – Inclusive and Adaptable 
Michael Mulgrew
Planning, Building Standards and Environmental Health Manager
Date: 22 October 2025
___________________________________________________________________ 
Person to Contact: Michael Mulgrew, Planning, Building Standards and
Environmental Health Manager, 
Michael.mulgrew@west-dunbarton.gov.uk 
Appendices: Appendix 1 – Permitted Development Rights
Consultation Response 
Background Papers: Permitted development rights to support provision of
new homes - Scottish Government consultations -
Citizen Space 