WEST DUNBARTONSHIRE COUNCIL
Report by the Planning, Building Standards and Environmental Health
Manager
Planning Committee: 6th August 2025
___________________________________________________________________
Subject: National Planning Improvement Framework Update
1. Purpose
1.1 The purpose of this report is to update Planning Committee on the recent
work undertaken by the Planning Service in relation to the National Planning
Improvement Framework and the endorsement by the National Planning
Improvement Team of our Performance Assessment and Improvement Plan.
2. Recommendation
2.1 It is recommended that the Committee notes the outcome of the above
process.
3. Background
3.1 The Planning (Scotland) Act 2019 introduced a new statutory requirement for
a National Planning Improvement Co-ordinator to monitor the performance of
Planning Authorities in the discharge of their functions and to provide advice
to planning authorities on what steps might be taken to improve the
performance.
3.2 The National Planning Improvement Framework (NPIF) has now replaced the
previous Planning Performance Framework (PPF) and requires Planning
Authorities to self-assess themselves against the 12 attributes of a high
performing Planning Authority. In total there are 47 factors/indicators within
those attributes that can be taken account of when scoring against each
attribute. Whilst the statistics of the PPF mainly looked at speed of decision
making, the NPIF looks at a broader range of matters. The assessment is split
into 5 themes, comprising the 12 attributes, as set out in the diagram below.
ITEM 7

Page 2

3.3 The self-assessment results in a score of 1-5, as set out in the diagram below.
Scores of 1-2 suggest that we have good practice and we are asked to
provide best practice examples to share with the National Planning
Improvement Team. Scores of 3-5 would suggest that further improvement is
required or a reprioritisation of current improvements.
3.4 All Planning Authorities were split into 3 cohorts and assigned a peer review
partner. We were in the last cohort, cohort 3, and our partner was
Clackmannanshire Council.
4. Main Issues
Performance Assessment
4.1 Preparatory work for the NPIF commenced in December 2024 and was
largely complete by April 2025. As the process is collaborative, the guidance
requires a stakeholder meeting in order to test our draft documents and to
seek feedback from our partners on both our self-assessment and our
identified performance actions. This meeting took place on 15th May 2025 and
included a variety of stakeholders alongside representatives from the Planning
Service, including from Community Councils, Clackmannanshire Council,
consultees, key agencies and a local architect. The National Planning
Improvement Team were also in attendance and the event was facilitated
independently of the Planning Service.
4.2 The stakeholder meeting largely validated and agreed with many aspects of
our performance and scoring but provided constructive feedback on many
areas. A summary of this feedback is included in our final Performance
Assessment at in Appendix 1.
4.3 The agreed scoring of the Planning Authorities performance is summarised
below:
Attribute Score
(1-5)
Summary of reason for score

Page 3

1. The Planning
Authority has sufficient
resources and skills to
maximise productivity
3 The service is currently maximising
productivity within available resources, but
further workforce, capacity and budget
planning is required
2. The Planning
Authority has a valued
and supported
workforce
3 The service is currently maximising training
and development opportunities within
existing resources, but further work is
required in line attribute 1 to ensure officers
are supported to carry out their role and
continue their professional development
3. This Planning
Authority has
embedded continuous
improvement
1 Despite resource and system challenges
the service continually seeks ways in which
processes can be streamlined or enhanced
4. This Planning
Authority has sound
governance
3 The service has effective governance
structures; however, these are required to
be reviewed
5. This Planning
Authority has effective
leadership
1 The service has a Chief Planning Officer in
place and supports the culture of
continuous improvement
6. The Planning
Authority has a robust
policy and evidence
base
3 Whilst work is underway to prepare LDP3,
the authority does not have an up-to-date
Development Plan in place
7. The Planning
Authority makes best
use of data and digital
technology
3 The service makes extensive use of digital
data and technology with regards to GIS,
but has significant issues with the back-
office system
8. The Planning
Authority has effective
and efficient decision-
making processes
3 The service has effective and efficient
decision-making processes in many
aspects of Development Management
performance but overall performance could
be further enhanced and the Scheme of
Delegation requires review.
9. The Planning
Authority has good
customer care
3 The service generally provides good
customer service, although it is recognised
that certain areas need improvement based
on formal and informal feedback
10. The Planning
Authority has effective
engagement and
collaboration with
stakeholders and
communities
3 The service generally has effective
engagement and collaboration but have
identified areas where this could be
strengthened
11. The Planning
Authority supports the
delivery of sustainable,
liveable and productive
places
1 The service has been recognised in the
past for its approach to placemaking and
we have a dedicated Placemaking Co-
Ordinator post within the service.

Page 4

12. The Planning
Authority supports the
delivery of appropriate
development
2 The service offers 2 different levels of
preapplication advice to prospective
applicants to ensure that they are aware of
development plan requirements and
expectations
Improvement Actions
4.4 The Performance Assessment narrative, and scoring, has then fed into the
development of improvement actions. In conjunction with the stakeholder
group, 11 improvement actions were agreed and these are summarised
below:
 Implement the new back-office document management system and
carry out a full end-to-end review of all workflow processes
 Develop a workforce strategy and service training plan, including any
options/opportunities for restructure of cases for investment
 Complete Scheme of Delegation Review to ensure it is proportionate
 Finalise review of committee and delegated Reports of Handling
templates to ensure that they are proportionate and are clear and easy
to be understood by a variety of audiences
 Produce detailed Team Improvement Plans, focusing on improvements
that increase efficiency, and are clear, including increasing the quality
of our customer communication
 Undertake review of the Development Management and Enforcement
Charters and processes to ensure they remain fit for purpose
 Set up regular agents forum, in conjunction with Building Standards
 Carry out wider service day (with Building Standards and
Environmental Health) to share good practice and workstream updates.
This will inform detailed Team Improvement Plans
 Implement Project Management approach within Development
Management
 Explore how “Added Value” can be better captured and reported on
 Review Development Management conditions
4.5 The Planning Authority also submitted the following Good Practice Examples:
 Attributes 3 and 5 – Culture of Continuous Improvement and
Leadership
 Attribute 7 – Open Space Audit
 Attributes 11 and 12 – Supporting High Quality Development and
Places
National Planning Improvement Team Endorsement

Page 5

4.6 On the 13th June, the service received confirmation that the National Planning
Improvement Team had endorsed the Performance Assessment and
Improvement Action Plan. The National Planning Improvement Champion
wrote to the Council’s Chief Executive to inform them of this and that this has
also been submitted to the Minister for Public Finance.
Next steps
4.7 The Planning Service continues to seek opportunities to learn from, and
share, best practice and a number of best practice case studies are available
on the Improvement Service website. Our own performance assessment and
improvement actions will be publicised on our website. We are currently
working with Clackmannanshire Council as they go through their process and
seek to build on past benchmarking sessions with other authorities later this
year.
4.8 Not all identified improvement actions can be delivered immediately, some are
medium and longer term (2-3 years) but progress has already been made in
several areas, including the review of Reports of Handling, implementation of
a project management approach and the implementation of the new back-
office system. The improvement actions are embedded into service
workstreams to ensure their delivery.
4.9 As the NPIF process is much more intensive than the previous PPF, a
complete review of the Performance Assessment and Improvement actions is
not going to be undertaken on an annual basis. Further guidance on year 2 of
the NPIF has recently been issued and will be actioned by the service iun due
course. This will include a check in with our peer review partner authority and
stakeholder group, meet with the National Improvement Team and to provide
updates on progress with our improvement actions.
5. People Implications
5.1 There are no people implications associated with this report.
6. Financial and Procurement Implications
6.1 There are no financial or procurement implications associated with this report.
7. Risk Analysis
7.1 The Planning (Scotland) Act 2019 introduced a new statutory requirement for
a National Planning Improvement Co-Ordinator to monitor the performance of
Planning Authorities in the discharge of their functions and to provide advice
to Planning Authorities on what steps might be taken to improve the
performance. The endorsement by the National Planning Improvement Co-
Ordinator of the authorities Improvement Plan confirms the authority has met
its statutory requirement.
8. Equalities Impact Assessment (EIA)

Page 6

8.1 There are no equalities issues associated with this report.
9. Consultation
9.1 Consultation was undertaken during the preparation of the documents, as set
out in section 4.
10. Strategic Assessment
10.1 The authority’s assessment and improvement actions are considered
to be relevant to, and will help deliver, all of the Council’s strategic
priorities:
 Our Communities – Resilient and Thriving
 Our Environment – A Greener Future
 Our Economy – Strong and Flourishing
 Our Council – Inclusive and Adaptable
Michael Mulgrew
Planning, Building Standards and Environmental Health Manager
Date: 6th August 2025
___________________________________________________________________
Person to Contact: Michael Mulgrew, Planning, Building Standards and
Environmental Health Service Manager, 
Michael.Mulgrew@west-dunbarton.gov.uk
Appendices: Appendix 1: Performance Assessment
Appendix 2: NPIF Improvement Plan
Appendix 3: Good Practice Example (Attributes 3 and 5)
Appendix 4: Good Practice Example (Attribute 7)
Appendix 5: Good Practice Example (Attributes 11 and
12)
Background Papers: None
Wards Affected: All