WEST DUNBARTONSHIRE COUNCIL 
Report by Planning, Building Standards and Environmental Health Manager 
Planning Committee: 4th June 2025
_____________________________________________________________ 
DC24/197/FUL:  Amendment to Condition 2 and Condition 14 of permission
DC20/253 in relation to proposed site restoration Landfill Site
at Auchincarroch Road, Jamestown, Alexandria by Barr
Environmental Ltd 
1. REASON FOR REPORT 
1.1 The application seeks to amend the terms of two conditions of a planning
application originally determined by the Planning Committee. It therefore requires
to be determined by the Planning Committee. 
2. RECOMMENDATION 
2.1 Grant planning permission for this Section 42 application, subject to the
conditions set out in Section 9 below. 
3. DEVELOPMENT DETAILS 
3.1 Auchencarroch Landfill Site is located to the south-east of Jamestown and lies
between the open hills of Auchencarroch and Pappert Hill. It sits in a natural
plateau and, although the site itself is hidden by the rising landform in front, the
access road is visible from Auchencarroch Road. The site has few neighbouring
sensitive receptors, with the closest residential property being Mid Auchencarroch
Farmhouse, the owner of which is an interested party cited on the existing legal
agreement. Other agricultural holdings, primarily used for livestock grazing,
surround the site in all directions. 
3.2 Landfill operations on the site began in 1995, with planning permission granted in
2004 (DC02/324) to increase the lifespan of the facility by extending the landfill
area. Application DC07/233/FUL allowed for the further extension of the site to the
south-east. This area is a natural valley between Auchencarroch and Pappert Hills
and comprises a mix of semi-improved upland pasture, heathland, and blanket
bog. The DC07/233/FUL permission allowed for land raising to continue the overall
height of the existing restored landform in an easterly direction. The finished
landform of the existing and extended landfill would form a low hill covered with
heathland vegetation. This is a lower height than Auchencarroch Hill (210m) and
Pappert Hill (257m) and maintains the surface drainage profile by having gentle
slopes on the east and west approaches. In terms of site area, DC07/233/FUL
extended the landfill workings by 14.4 ha (8 cells) to 27.4ha within a total area of
43.2ha. Adjacent to the site, also operated by the current applicant (Barr
Environmental Ltd), is a materials recycling facility (MRF) which was granted 
ITEM 5b

Page 2

permission in 2013. The MRF separates out recyclable material from waste before
the latter goes to landfill. 
3.3 In December 2022, planning permission (DC20/253) was granted to amend
Condition 1 of permission DC07/233/FUL in order to extend the time of the
approved landfilling operation and restoration by a further two years, to 2024 and
2026 respectively. There was no physical extension to the landfill. This change
was due to the rate of landfilling (amount of material coming on site) since 2009
being significantly less than originally anticipated due to a number of factors,
including increased recycling and landfill tax rates and the opening of the
Auchencarroch Materials Recycling Facility, which increased on-site recycling
rates. 
3.4 Landfill operations on the site ceased early in March 2024, with only 5 cells out of
the 8 additional cells approved under DC07/233/FUL being constructed and filled
due to the impacts arising from a number of political, environmental and economic
policy changes. This included household waste being recycled at source, landfill
tax escalators and the Biodegradable Municipal Waste Ban, which combined to
make the landfill operation commercially untenable. With the cessation of landfill
activities, site works now relate solely to specific restoration and regulatory
aftercare. 
3.5 The Restoration Masterplan agreed as part of the DC07/233/FUL permission is
based on an approach of progressive capping of the completed landfill cells, with
a total of 8 cells to be developed and restored. The final restoration includes the
planting of woodland, linear strips of hedgerow and typical heathland grass
species, with peat stripped and translocated to the restored profiles to form an acid
heathland habitat. Reedbeds and surface water lagoons will be managed to form
wetland areas with diverse planting, with a small area of agricultural grassland
forming a permanent pasture for sheep grazing. This masterplan was included,
unchanged, in the DC20/253 permission and its implementation secured through
Condition 2.   
3.6 With the early cessation of landfill activities meaning that only 5 cells have been
constructed and filled, the approved restoration masterplan cannot be
implemented in full as 3 cells situated within the eastern part of the site have not
been developed and therefore do not require restoration.   
3.7 This Section 42 application relates to Condition 2 and Condition 14 of permission
DC20/253, which are copied below: 
3.8 Condition 2   
“At all times during the lifetime of this permission, the landfill operations on site,
the operational conduct of the site and the restoration of the site shall be
undertaken as indicated in the Environmental Impact Assessment dated
November 2020 together with all supporting documentation, plans and details that
forms part of this application. For the avoidance of doubt, the landfill operations
shall be undertaken and completed progressively as approved”.   
3.9 Condition 14

Page 3

“On completion of the landfill operations, except in so far as may be required for
leachate and gas monitoring, the site shall be cleared of all buildings, plant and
machinery with details of the phasing of this to be submitted for the approval of the
Planning Authority prior to the cessation of landfill operations on site”. 
3.10 The current application seeks permission to vary Condition 2 to allow for an
updated restoration masterplan to be implemented. The key changes are outlined
below: 
• The proposed restoration masterplan shows 3 cells, which the approved
masterplan identifies for restoration to agricultural grassland, as ‘undeveloped’,
although it is proposed to landscape these areas and return them to heathland
in order to match the surrounding area. 
• A hedgerow shown within the approved restoration masterplan has been
removed from the proposed masterplan as it was intended to delineate
between the agricultural grassland and heathland restoration of the
undeveloped 3 cells.   
• Two settlement lagoons shown in the approved restoration masterplan are
shown as 8 smaller lagoons in the proposed restoration plan, with the overall
lagoon area remaining the same.   
3.11 The application also seeks to vary Condition 14 to allow for the retention of the
Material Recovery Facility (MRF) building, which was constructed in 2014 under
planning permission DC13/216, during the 30 year aftercare period. It is
proposed to use the building for the storage of spare parts and materials required
for the ongoing operation of the leachate treatment plant and to provide a
structure on which to mount solar panels that would provide power to the plant.
4. CONSULTATIONS 
4.1 West Dunbartonshire Council Environmental Health – No comments in respect of
the proposal. 
4.2 West Dunbartonshire Council Biodiversity Officer – No objection. It was noted that
a more biodiverse grassland mix would be preferred. Requested information on
follow up habitat management to ensure the heathland, grassland and woodland
habitats establish.   
4.3 Scottish Environmental Protection Agency – No objection 
4.4 Loch Lomond and the Trossachs National Park – No objection. It was noted that
an area of scattered woodland along the northern boundary of the site, which has
been removed from the proposed restoration masterplan, is important for nature
networks.   
5. REPRESENTATIONS

Page 4

5.1 None received. 
6. ASSESSMENT AGAINST THE DEVELOPMENT PLAN 
National Planning Framework 4 (2023) 
6.1 Policy 1 states that significant weight will be given to the global climate and nature
crises when considering all development proposals. Policy 2 also relates to the
climate in the form of climate mitigation and adaptation, requiring development
proposals to be sited and designed to minimise lifecycle greenhouse gas
emissions and promote adaptation, as far as possible. Policy 3’s intent is to protect
biodiversity, reverse biodiversity loss, deliver positive effects from development
and strengthen nature networks. The amendments to the final restoration would
have a largely neutral impact in respect of Policies 1, 2 and 3, with some additional
biodiversity and climate change benefits delivered through the revised lagoon
arrangement and intention to generate renewable energy by bringing forward
future proposals for mounting solar panels on the MRF building.     
6.2 Policy 5 aims to protect carbon-rich soils, restore peatlands and minimise
disturbance to soils from development, with Policy 6 supporting proposals which
enhance, expand and improve woodland and tree cover. Policy 7 seeks to protect
the historic environment, including archaeological sites. No concerns arise in
respect of these policies. 
6.3 Policy 12 sets out the circumstances in which development proposals for new or
extended landfill sites will be supported. The proposal is not for a new or extended
landfill site and the final restoration arrangements do not conflict with the
requirements of the policy. 
6.4 Policy 22 addresses flood risk and water management, stating that proposals will
not increase the risk of surface water flooding to others, or itself be at risk; manage
all rain and surface water through sustainable urban drainage systems (SUDS),
and seek to minimise the area of impermeable surface. No flooding concerns arise. 
6.5 Policy 23 seeks to protect people and places from environmental harm, mitigate
risks arising from safety hazards and encourage, and promote and facilitate
development that improves health and wellbeing. The amendments to the final
restoration would have a neutral impact in respect of this policy. 
6.6 It is considered that the application complies with the relevant policies above, as
set out in the assessment below. 
West Dunbartonshire Adopted Local Plan 2010 
6.7 Policy PS1 seeks to protect established public utility, social and community
facilities, as identified on the Proposals Map. The application site at Auchencarroch
is identified on the Proposals Map under this policy. 
6.8 Policy E1 aims to ensure the conservation of biodiversity, with Policy E3A seeking
to ensure that development proposals do not have an adverse effect on the
integrity or character of Local Nature Conservation Sites. Policy E9 requires that
development proposals will have regard to the landscape character and

Page 5

distinctiveness of the Plan area and of adjoining areas. Proposals which are
detrimental to the landscape will not generally be supported. Policy BE5 seeks to
ensure that cultural heritage resources, including archaeological sites, are not
adversely affected. Policies F1 and F2 aim to ensure that new development is not
at risk from, and does not increase the risk of flooding, and has suitable SuDS
drainage infrastructure. No concerns arise in respect of these matters. 
6.9 Policy GD1 seeks to ensure that all new development respects the character and
amenity of the area and sets out a range of criteria for the assessment of all
development proposals.   
6.10  The overall principle of the proposal to update the restoration masterplan and
retain the MRF building complies with the policies of the adopted Local Plan, as
discussed in detail in Section 7 below.   
West Dunbartonshire Local Development Plan (LDP2) Proposed Plan
6.11 On 15 March 2023, the Planning Committee took a decision that the Council would
not adopt Local Development Plan 2. The Proposed Local Development Plan 2
(LDP2), incorporating the recommended modifications of the Examination Report
received on 22 April 2020, which were accepted by the Planning Committee of 19
August 2020, remains the Council’s most up to date spatial strategy and is
therefore afforded significant weight in the assessment and determination of
planning applications, subject to compatibility with NPF4. The Scottish Ministers’
Direction relating to the adoption of LDP2, dated 18 December 2020, is also a
material consideration. 
6.12 The site is identified as an existing waste management facility by Policy ZW1 and
associated Table 10. Policy ZW1 requires that all such development meets the
aims of the Zero Waste Plan and follows the development principles of the Waste
Hierarchy. While the policy includes criteria for the assessment of new waste
management facilities, this application is not proposing a new facility, rather the
approval of an updated restoration masterplan and retention of the MRF building.
Policy MIN2 requires appropriate financial guarantees in respect of restoration.
Whilst the policy relates to minerals extraction rather than landfill sites, the general
principles of the Policy are considered relevant.   
6.13 Policy ENV1 addresses nature conservation and requires developments to
conserve biodiversity and habitat networks, both within and adjacent to sites of
special designation, together with non-designated habitats and protected species.
Policy ENV2 requires development to be sited and designed to relate to the
existing landscape character and ensure the integrity of landscape character is
maintained. Policy BE1, ENV4 ENV5 and ENV6 are similar to the cultural heritage,
water environment and flooding policies of the adopted Local Plan. Policy CP1
requires all new development to contribute towards creating successful places. 
6.14 The overall principle of an updated restoration masterplan and the retention of the
MRF building for the aftercare period is considered to comply with the policies of
proposed Local Development Plan 2. 
7. ASSESSMENT AGAINST MATERIAL CONSIDERATIONS

Page 6

7.1 The application is made under section 42 of the Planning Act 1997, which is an
application for planning permission for the development of land but without
compliance with a condition or conditions attached to the original permission. In
this case, the applicant seeks not to comply with the terms of Condition 2 and
Condition 14 of planning permission DC20/253/FUL as worded, with alternative
wording sought. Condition 2 requires landfill operations, operational conduct and
restoration of the site to be undertaken in line with the Environmental Impact
Assessment (Nov 2020), with Condition 14 requiring that upon completion of
landfill operations, except in so far as may be required for leachate and gas
monitoring, the site shall be cleared of all buildings, plant and machinery. The
effect of a Section 42 application, if successful, is to grant planning permission
again for the whole development but with the amended conditions replacing those
that were issued previously. The original application, as approved, has
commenced and therefore if granted it must be ensured that any conditions
attached to the new permission are relevant to the works that are still be
undertaken on site.  Planning Authorities, if minded, may attach new or updated
conditions if permission is granted. 
Principle of Development
7.2 The application site is identified in the adopted Local Plan and proposed Local
Development Plan 2 as a waste management site and operated as a landfill in
accordance with planning permissions DC02/324, DC07/233/FUL and DC20/253
until landfill activities ceased in March 2024. The DC07/233/FUL and DC20/253
permissions also included a Restoration Masterplan. As such, the principle of
landfill operations and site restoration are established. Landfill operations have
ceased in accordance with condition 1 of DC20/053 and this application does not
propose any amendment to Condition 1 to allow further landfilling on site. With
respect to the MRF building, it’s use as a waste management facility, specifically
a recycling facility, was established under planning permission DC13/216. 
7.3 In light of the above, this application does not revisit the principle of a waste
management use and associated site restoration, it only considers the
appropriateness of the conditions attached to the previous consent. In this case
the application seeks not to comply with the terms of Condition 2 and Condition 14
of planning permission DC20/253/FUL, as set out above. 
7.4 With respect to Condition 2, the submitted application seeks to update the
approved Restoration Masterplan, with the proposed Masterplan identifying the 3
cells which were undeveloped when landfill operations ceased as ‘undeveloped’,
with a hedgerow removed, 8 lagoons identified, and an area of new scattered
woodland relocated from the northern boundary to the midpoint of the western
boundary.   Following a full and detailed assessment, set out below, it is concluded
that the proposed amendment to the approved restoration masterplan is
appropriate as the 3 undeveloped cells do not require to be restored, while the
other changes would have positive effects for the water environment and no
detrimental impacts on the overall site restoration, in so far as it relates to human
health and the natural environment. In relation to Condition 14, the proposed
retention of the MRF building during the 30 year aftercare period to support the
ongoing maintenance and operation of the leachate plant is also acceptable as it
would clearly contribute to site restoration.

Page 7

Landscape and Visual Impact
7.5 The updated restoration masterplan raises no concerns with respect to landscape
character and visual impact as the key change, i.e. that three undeveloped cells
would not be restored to agricultural grassland, would have a neutral effect.
Indeed, the proposed Masterplan shows that these areas will be landscaped and
returned to heathland to match the surrounding area, which constitutes an
enhancement beyond the existing position. The removal of a hedgerow shown in
the approved restoration plan would also have a neutral effect as this was only
included to delineate the agricultural grassland and heathland restoration of the 3
undeveloped cells. The consultation response from the Loch Lomond and
Trossachs National Park raised no objection or concerns about landscape and
visual impacts. 
7.6 While the proposed retention of the MRF building would not increase the
landscape and visual impacts of the building beyond the existing position, it still
rests to consider the significance of these effects when assessing its retention for
the duration of the aftercare period. The landscape and visual impacts were
previously considered during the assessment of DC13/216, which noted that the
building would sit at a lower level than much of the surrounding ground to the north,
south and east. It was further noted that the building would not be a prominent
feature in the landscape when viewed from the west and southwest, which includes
views from Balloch and the National Park, due to the separating distances, the
undulating nature of the ground and the excising tree coverage. The DC13/216
assessment concluded that there would be no significant indirect landscape
impacts or magnitude of change. The building as constructed is not prominent
within the landscape and sits notably lower than the surrounding landform, as was
originally envisaged. This results in the building having little impact within the wider
landscape. In light of the limited effects, it is considered that the building’s retention
during the aftercare period is acceptable.     
7.7 Overall, the amendments to the restoration of the site presents no conflict with
Policy 12 of NPF4, Policy E9 of the adopted Local Plan and Policy ENV2 of
proposed Local Development Plan 2. 
Impact on Water Environment 
7.8 While the approved Restoration Masterplan included three large settlement
lagoons, the proposed masterplan shows 8 smaller lagoons covering the same
total area. It is noted that this change was identified in the Environmental Impact
Assessment (Nov2020) submitted with the DC20/253 application in order to
enhance habitat creation and biodiversity, although the permission did not
incorporate this change at the time. As the proposed change would promote
habitat creation and deliver biodiversity enhancements, and the consultation
response from SEPA raised no objection, it is acceptable. 
Impact on Ecology 
7.9 In addition to the ecological enhancements to the water environment noted above,
the consultation response from the Biodiversity Officer advised that the mixed
mosaic habitat proposed ties in with the overall Nature Network plans for the
surrounding land. While the response raised no objection, it noted that a more
biodiverse grassland mix would be preferred over the mostly agricultural mix

Page 8

proposed. As the proposed grassland mix was previously agreed under permission
DC20/253, it is acceptable. The response also requested further information on
follow up habitat management to ensure that the heathland, grassland and
woodland habitats establish. While the current application does not include any
information on follow up habitat management, it is noted that a Habitat
Management Plan (2008) was approved under the DC07/233/FUL and DC20/253
permissions. In light of this, and the significant time since the Habitat Management
Plan was developed in 2008, it is considered appropriate to require an updated
Habitat Management Plan that includes follow up habitat management measures,
which can be secured through condition. While the consultation response from the
Loch Lomond and Trossachs National Park raised no objection, it was noted that
the proposed restoration masterplan does not show an area of scattered woodland
along the northern boundary, which was included in the approved masterplan. The
applicant has advised that this change was required due to the scattered woodland
being within the site boundary but outwith their ownership/control. As
compensation, the applicant submitted a revised restoration masterplan which
shows an additional area of scattered woodland midway along the eastern
boundary. As this area of woodland is the same size as that previously shown
along the northern boundary, it is acceptable.   
Flood Risk
7.10 The application raises no concerns with respect to flood risk as the proposal does
not seek new development or any changes to the existing drainage arrangements. 
Health and Safety
7.11 The proposal would have a neutral effect on health and safety as it seeks only to
remove the requirement to restore undeveloped cells, relocate an area of
woodland, increase the number (not size) of lagoons and retain the MRF building.
It is noted that the consultation from SEPA, who regulate the site, raised no
objection to the proposal. 
Climate change
7.12 The proposal is likely to have a positive effect on climate change adaptation
through the habitat/biodiversity enhancements discussed above. In addition, the
application indicates that the retention of the MRF building would possibly solar
panels to be mounted on the structure, which would contribute to climate change
mitigation, although this is not currently part of this proposal.     
Built and Cultural Heritage
7.13 Two features of archaeological interest are situated within the site and recorded
as being dams associated with the textile/printing industry in the Leven Valley. The
proposal raises no concerns with respect to these assets and there are no conflicts
with Policy 7 of NPF4, Policy BE5 of the adopted Local Plan and Policy BE1 of
proposed Local Development Plan 2.   
Restoration Bond 
7.14 The DC20/253 planning permission requires site restoration to be completed by
30/06/2026. In order to meet this requirement, the current application advises that
site restoration be completed by August 2025 due to the summer months being the
optimal time for such the required works. The application confirms that the overall
cost of the remaining restoration works is £305,101.

Page 9

7.15 The Council holds a financial bond of £1,000,000 for the application site to ensure
that the restoration works are completed in full. It is noted that the bond was
recently extended from 31/12/2024 to 31/12/2025, with a copy of the Bond
Certificate submitted with this application. This time extension ensures that the
bond will be in place for the proposed completion of restoration works by August
2025. The application advises that if the restoration works are not completed by
August 2025, the applicant would continue to hold a bond against the site, with the
value being for the outstanding restoration works only, which is acceptable and
can be secured through an updated legal agreement, if required.       
8. CONCLUSION 
8.1 This proposal seeks permission for an updated Restoration Masterplan which
primarily removes the requirement for the restoration of three cells which were
never constructed and filled due to the early cessation of landfill operations in
March 2024. In addition, the application seeks the retention of the MRF building
for the duration of the aftercare period. This application considers only the above
elements. 
8.2 Overall, subject to the conditions below, the proposal is considered to be
acceptable with reference to NPF4, the adopted Local Plan and proposed Local
Development Plan 2. The updated Restoration Masterplan takes account of the
early cessation of the landfill operation while still ensuring that the developed part
of the site is fully restored, with some additional habitat/biodiversity enhancements.
The retention of the MRF building will support the ongoing maintenance and
operation of the leachate plant while also providing scope for renewable energy to
power the plant. Conditions 8, 17 and 26 as applied to DC20/253 and which relate
to the active landfilling operations are no longer required and have been removed.
However, a variety of conditions previously imposed to DC20/253 are considered
to still be necessary and are recommended to be attached, albeit some have
updated wording to reflect the up-to-date position with the site and to take account
of the cessation of landfill operations. These are as recommended below.
Additional conditions to address Policy 1 of the NPF4, Policies E1 and E9 of the
Local Plan, Policies ENV1 and ENV2 of the proposed LDP2, the points raised in
the consultation responses and to reflect the up-to-date position in relation to the
site are also recommended as part of the updated suite of conditions.
9. CONDITIONS 
1. The development hereby permitted shall ensure for the benefit of the applicant
only, with the final restoration of the site being completed by 30th June 2026 unless
otherwise agreed in writing by the Planning Authority. 
Reason: In order to ensure the timely restoration of the site. 
2. No further landfill material shall be brought on to any part of the site and no further
landfill operations shall take place on any part of the site. 
Reason: To ensure that future works under this permission relate to site restoration
activities only.

Page 10

3. At all times during the aftercare period of the site, the restoration of the site shall
be undertaken as indicated in the Environmental Impact Assessment, dated
November 2020, together with all supporting documentation, plans and details that
form part of this application, including amended restoration masterplan (reference
ED13968-005F). 
Reason: To ensure that the development operates in accordance with the
approved details. 
4. Except in the case of emergency, the hours of working of the site shall be restricted
to between the hours of 7.30am to 5.00pm Monday to Saturday only and not on a
Sunday or on a recognised Public Holiday in West Dunbartonshire without the prior
written approval of the Planning Authority with the exception of essential site
maintenance and the maintenance of plant and machinery. Access to and exit from
the site shall be by way of Auchencarroch Road. 
Reason: In order to minimise disturbance to local resident and to ensure that the
site is accessed in the approved manner. 
5. The site operator shall be responsible for the maintenance of a vehicle register log
book of all deliveries to the site which shall be available for inspection by the
Planning Authority upon request at any time. 
Reason: In order to ensure that the number of vehicle movements and the volume
and type of waste remain within the approved limits. 
6. The applicant shall be responsible for the collection and disposal of any windblown
material emanating from the area of infill. 
Reason: In order to prevent the operation of the site giving rise to litter, which would
detract from the amenities of the surrounding area. 
7. No burning of materials in connection with the infilling operations shall take place
on or adjoining the site. 
Reason: In order to protect the environment and the amenities of local residents. 
8. Within 28 days of the date on which planning permission for the development,
hererby approved, is issued, an updated Habitat Management Plan, which
includes details on follow up habitat management, shall be submitted for the written
approval of the Planning Authority. Thereafter, the Plan will be implemented as
approved. 
Reason: In order to ensure that the developer continues to make appropriate
provision for bird life and natural habitat. 
9. The annual monitoring on the progress of the mitigation areas shall be carried out
as required by the Habitat Management Plan and by the applicant or by any person
engaged by them. An annual report will be made available to the Technical

Page 11

Working Group at least 3 weeks prior to the formal review meeting of that Group
and the annual monitoring report shall be approved by the Planning Authority. 
Reason: In order to ensure that the mitigation measures are operating effectively. 
10. All advance works, including habitat translocation to receptor areas for landfill
restoration shall take place outside the bird nesting season (March to July
inclusive) unless a checking survey confirms the absence of nests. The checking
survey shall be carried out at a time and approved in advance by the Planning
Authority. 
Reason: In order to minimise the impact of the development on bird life. 
11. All diversions of watercourses shall follow the details approved in respect of
condition 18 of planning permission DC07/233/FUL. 
Reason: To ensure that works to watercourses are carried out in an appropriate
manner and do not give rise to pollution. 
12. The access track which runs partly through the active landfill and links up with the
track leading to Paper Muir and the western edge of the commercial forestry
plantation shall not be used for the export of timber without the prior written
approval of the Planning Authority. 
Reason: To ensure that works to watercourses are carried out in an appropriate
manner and do not give rise to pollution. 
13. On completion of the landfill operations, except in so far as may be required for
leachate and gas monitoring, the site shall be cleared of all buildings (except for
the MRF building which will be retained during the aftercare period), plant and
machinery, with details of the phasing of this to be submitted for the approval of
the Planning Authority prior to the cessation of landfill operations on site. 
Reason: In order to ensure the appropriate restoration of the site upon the
conclusion of the landfill operations. 
14. Unless otherwise approved in writing by the Planning Authority, the MRF building
will be removed from the site at the end of the aftercare period on 01/04/2056.   
Reason: In order to ensure the removal of the building following the conclusion of
the aftercare period. 
15. Appropriate measures to prevent mud, dirt, dust, slurry or stones being carried
onto the highway shall be taken and such steps shall include the provision and the
use of hard standing areas and a wheel wash facility for the cleaning of all lorries,
dump trucks, other heavy vehicles and plant leaving the site. 
Reason: In order to minimise nuisance to local residents and in the interest of road
safety and to ensure the measures are in accordance with the approved details.

Page 12

16. The access road and public road adjacent to the site shall be kept clear of mud or
other deposited materials at all times by means of mechanical brushing. 
Reason: In the interests of road safety and the amenities of the area. 
17. Soils to be imported to the site shall share similar profile characteristics as the soil
structure currently on site. Topsoil and sub-soil shall only be stripped when the
soils are sufficiently dry so that when moved, no damage will be done to the
structure of the soils. Apart from the works required to enclose the site, no
operations shall be carried out until the topsoil is fully stripped and stored in the
designated areas within the site.   
Reason:  In order to ensure that the soil used in restoration work is appropriate to
the local environment. 
18. Topsoil shall be stripped to full available depth from all areas within the site except
those areas designated in the approved plans as topsoil dumps. Following topsoil
stripping operations from any areas of land, sub-soil shall be stripped as a separate
operation to a depth, where possible, to achieve topsoil and sub-soil not less than
0.9 metre at restoration. 
Reason: In order to ensure the retention of soil required for restoration purposes
and to ensure that the soil used in restoration is appropriate to the local
environment. 
19. Topsoil and sub-soil shall be carefully stored in separate dumps and prevented
from mixing. Topsoil dumps shall not exceed 5 metres in height. Topsoil dumps
and sub soil dumps shall be evenly graded and tops shaped to prevent water
ponding. Sub-soil dumps shall not exceed 8 metres in height. 
Reason: In order to ensure the retention of soil required for restoration purposes
and to reduce its impact on the local environment. 
20. In the first available seeding season following their formation, all mounds of topsoil,
sub-soil and soil making materials shall be seeded in grass and shall be so
maintained until the soils are required for use in the restoration of the site except
as may be otherwise agreed with the Planning Authority. 
Reason: In order to ensure the retention of soil required for restoration purposes,
and to ensure that soil is an aesthetically acceptable manner. 
21. All water treatment areas and settlement lagoons shall be enclosed by a one metre
high stock-proof fence and shall be implemented prior to any significant soil
stripping. 
Reason: In order to ensure the timely provision and protection of water treatment
and settlement facilities, in the interests of public safety. 
22. Appropriate precautions shall be taken to prevent the discharge of oil from fuelling,
oil storage, plant maintenance and vehicle wash areas within the site.

Page 13

Reason: In order to prevent pollution of the local environment. 
23. Dust monitoring shall be routinely carried out by the applicant and undertaken
using appropriate equipment and recording devices. The results and records shall
be made available to the Planning Authority on a monthly basis during the
operational life of the site. 
Reason: In order to minimise nuisance to local residents and damage to the
environment arising from dust blown from the site. 
24. Noise monitoring programme shall be undertaken during the operational life of the
site using appropriate equipment and recording devices, the results of which shall
be made available to the Planning Authority on a monthly basis. 
Reason: In order to minimise disturbance to local residents arising from noise
generated at the site 
Michael Mulgrew
Planning, Building Standards and Environmental Health Manager 
Date: 4th June 2025  
______________________________________________________________ 
Person to Contact: Michael Mulgrew, Planning, Building Standards and
Environmental Health Manager  
Email: Michael.Mulgrew@west-dunbarton.gov.uk 
James McColl, Development Management Team Leader
Email: james.mccoll@west-dunbarton.gov.uk 
Appendix:   Location Plan 
Background Papers:  1. Application documents and plans
2. National Planning Framework 4 
3. West Dunbartonshire Local Plan 2010
4. West Dunbartonshire LDP - Proposed Plan 2
5. Scotland’s Zero Waste Plan 2010
6. The Landfill (Scotland) Regulations 2003
7. Consultation responses
8. Planning permission DC07/233/FUL
9. Planning permission DC20/253