WEST DUNBARTONSHIRE COUNCIL 
Report by the Planning, Building Standards and Environmental Health
Manager 
Planning Committee: 5th August 2026
___________________________________________________________________ 
Subject: Planning Charging Charter 2026 
1. Purpose 
1.1 The purpose of this report is to seek approval of the 2026 Planning Charging
Charter to reflect recent changes to planning fees as approved by Full Council
as part of the budget setting for 2026/2027. 
2. Recommendation  
2.1 It is recommended that Planning Committee approves the 2026 Planning
Charging Charter to be published on the Council’s website. 
3. Background 
3.1 The Town and Country Planning (Fees for Applications (Scotland)
Regulations 2022 set out that alongside statutory fees Planning Authorities
were able to charge a range of discretionary fees. Some, such as
preapplication advice, can be set at the local level, whilst others, such as fees
for Non-Material Variations, have their fee set in the regulations and the
discretion is around implementing the charge or not. Since its introduction in
2022, all fees set out in the regulations have been subject to an annual
inflationary uplift and in 2025 new fees for Local Review Bodies and appeals
to The Department of Planning and Environmental Appeals have been
introduced. 
3.2 At its meeting of 4th March 2026, Council agreed the management
adjustments noted in appendix 3 of the General Services Budget Setting
202627 and 20278 Report to be used to set the General Services revenue
budget in 2026/2027. This included option 2627 RR06. This option set out a
review of income generation and savings associated with fees, in addition to
the standard 5% annual uplift. Relevant to the Planning Charging Charter This
included:
• Review Planning Preapplication Service and Associated Fees (£4,500)
• Statutory Local Review Body Fees (£1,500)
• Stopping Up Orders (£2,000) 
4. Main Issues
ITEM 8

Page 2

Review Planning Preapplication Service and Associated Fees 
4.1 Since the approval of the Council report, officers have been conducting a
review of the preapplication charging. Some fees have been subject to only
the standard 5% uplift, whilst others have been amended. The full proposed
Charging Charter is set out at Appendix 1. 
.
4.2 The main change is around residential and commercial applications, with an
additional tiers of advice to better reflect differing scales of proposals and to
reflect the addition fees for reviews. A summary table is provided below. 
Current Provision Current Fee Change Comment
Pre-application advice
(Framework)
£3,638 None Already subject
to annual uplift
Preapplication advice
on Local
developments
£605 Split into
different
categories see
below - but
remaining as a
general
category
Already subject
to annual uplift
Preapplication advice
on single houses
£181 None Already subject
to annual uplift
Preapplication advice
on commercial
developments up to
500sqm
£181 Increase to
£216
To reflect
differing scales
of development
Preapplication advice
for householder
developments
£120 None Already subject
to annual uplift
Preapplication advice
for advertisement
proposals
£120 None Already subject
to annual uplift
Request for Non-
Material Variation
£247 None Fee set in
regulations
Compliance/Discharge
of conditions
£124 None Fee set in
regulations
Retrospective
applications
Fee calculated
in accordance
with fee
regulations,
plus 25%
None Already at
maximum
surcharge as
set in
regulations
Local Developments –
Residential (2-9 units)
£605 £605 New category
Local Developments
Residential (11-49
units)
£605 £692 New Category
Major Developments £3,638* £1,091 New Category

Page 3

Fees for Local Review
Bodies
£0 £varies
depending on
proposal
Fees set in
regulations on a
sliding scale to
reflect proposal. 
* Major Developments currently reviewed through the Preapplication
framework route 
4.3 The residential categories have been altered to better reflect the differing
scale and complexity between, for example, a smaller 2 unit development and
larger 49 unit development, that previously may have been charged the same
fee of £605. This excludes development that may have been suitable to be
addressed via the Preapplication Framework route. 
4.4 In addition, a new category for Major Developments has been introduced. This
is to reflect less complex major applications that do not require to be
considered via the preapplication framework route. This could include for
example, discussions around any smaller scale amendments to a layout, that
could not be considered non-material, or discussions around a Section 42
application to alter or remove a condition. Officers will provide advice to
applicants prior to an application for advice being made to ensure that the
most suitable preapplication type is applied for. 
4.5 There are no changes proposed to any current exemptions. For clarity the
following exemptions are current set out. 
• Advice relating to works or alterations to improve access, safety,
health or comfort for a disabled person at their home – Note the
statutory fee for a planning application is waived in regulations.
• Advice relating to works or alterations to proposals that in the
opinion of the Planning Authority are demonstrated to support the
Council’s food growing strategy – allotments or food banks/hubs –
Note that this also extends to any planning application.
• Preapplication advice for Community Councils – Note that planning
application fees are also reduced by half. 
Whilst it is not explicitly stated in the current Charging Charter, for the
avoidance of doubt, the Proposed Charging Charter also sets out that
preapplication advice relating to works that require only Listed Building
Consent or Conservation Area Consent area also exempt from fees. The
Charging Charter set out in Appendix 1 clarifies that where the statutory fee
would be waived, the preapplication fee would also be waived. The Charging
Charter does not set out all the exemptions set out in regulations, only those
that are in the control of the Planning Authority. 
4.6 As part of the review of these fees, regard was given to the current fee
charges and a comparison was carried out with neighbouring Glasgow City
Region authorities, as well as Argyll and Bute Council, Falkirk Council, Stirling
Council and Loch Lomond and the Trossachs National Park. Preapplication
advice and charges for such advice vary considerably across the authorities,

Page 4

however, where there are similar charges, the proposed charges are
comparable and reflect the types of developments and level of service we can
offer. Preapplication advice is generally a well-received service and officers
wish to continue to support prospective applicants adequately whilst ensuring
that such discretionary activities are resourced sufficiently. 
Statutory Local Review Body Fees 
4.7 Local Review Body fees have a number of exemptions already included in
legislation, such as reviews of an application concerning the access for a
disabled person and reduced fees for applications by Community Councils. It
is open for authorities to consider any further exemptions. In line with existing
exemptions around applications for food growing, it is proposed to also extend
this exemption to any appeal considered by the Local Review Body. 
Stopping Up Orders 
4.8 Stopping Up Orders are a new charge for 2026/2027. Whilst numbers are
small, such applications are currently free and present a cost to the authority
in terms of the administration process and required advertising fees. Available
data would suggest that many authorities do not charge for this process, or
recharge only the cost of the advert. Glasgow City Council would seem to be
an exception to this and advertise a flat fee of £1,992. Given the small number
of orders processed and lack of direct comparison to other authorities, it is
considered that the cost of the advert, plus 10% to account for staffing and
other administrative costs related to placing an advert represents an
appropriate cost recovery level. 
Conclusion 
4.9 In conclusion, it is considered that the Proposed Charging Charter presented
at Appendix 1 fulfils the requirements of the Council’s Budget decision to
review income from discretionary planning charges around preapplication
advice and reflecting the new statutory provision for charges for Local Review
Bodies 
5. People Implications 
5.1 There are no people implications associated with this report. 
6. Financial and Procurement Implications 
6.1 The charges set out in the Charging Charter at appendix 1 reflect either the
statutory provision set out in regulation or comply with the Council’s Budget
decision regarding management adjustment 2627 RR06. 
7. Risk Analysis 
7.1 The Council is unable to implement any revised charging to comply with the
Council’s Budget decision until such time as the revised charges are agreed.

Page 5

Preapplication advice is currently a chargeable service and this review is not
considered to present any unacceptable risk to the Council regarding the use
of the service. 
8. Equalities Impact Assessment (EIA) 
8.1 The Equality Impact Assessments for the Council’s Budget Report were
reported to Full Council as part of the report on 4th March 2026. 
9. Consultation 
9.1 Not applicable. 
10. Strategic Assessment 
10.1 The Charging Charter is considered to be relevant to, and will help
deliver, all of the Council’s strategic priorities:
• Our Communities – Resilient and Thriving
• Our Environment – A Greener Future
• Our Economy – Strong and Flourishing
• Our Council – Inclusive and Adaptable 
Michael Mulgrew
Planning, Building Standards and Environmental Health Manager
Date: 5th August 2026
___________________________________________________________________ 
Person to Contact: Michael Mulgrew, Planning, Building Standards and
Environmental Health Manager, 
Michael.mulgrew@west-dunbarton.gov.uk 
Appendices: Appendix 1: Charging Charter 2026 
Background Papers: General Services Budget Setting 202627 and 202728-
2030-31 Budget Estimates – West Dunbartonshire
Council – 4th March 2026. 
Wards Affected: All