Classification: OFFICIAL#
Criteria Category Category Individual Factors to consider Score Weighted Score Score Weighted Score Score Weighted Score Score Weighted Score Notes/ rationale
3
Utility infrastructure - capacity and need for any diversions 7 21 5 15 2 6 5 15
Existing utilities considered, minimal diversions,
opportunities for future heat network connections. Distance
of running utilities.
3 Ground conditions 6 18 5 15 5 15 7 21
Potential for contamination at Site 1. Poorer ground
conditions at Site 2/Site 3 marine deposits etc.
2 Topography 3 6 8 16 9 18 5 10
Existing school site constrained. Site 2/3 both more
devleopable level wise
2 Flood risk & Drainage Assessment 4 8 6 12 5 10 9 18
Next steps would involve flood modelling/assessment.
SEPA engagement key
3 Site abnormals 3 9 8 24 7 21 5 15
2 Habitat constraints 8 16 9 18 5 10 7 14
Impact 53
10 Is the site capable of accommodating the brief in full? 4 40 9 90 9 90 5 50
South tob can be used better than existing, due to
constraints. More space in Craignure/Garmony sites.
5 Quality of external environment to support outside learning, sports activities etc 3 15 9 45 10 50 6 30
2 Does the site provide capacity for future expansion? 4 8 9 18 9 18 5 10
8 Travel times for ELC and primary school pupils 9 72 4 32 4 32 8 64 Systra report
2 Travel times for staff and secondary school pupils 9 18 4 8 5 10 8 16 Systra report
5 Access and connectivity to good community facilities and services 9 45 4 20 1 5 8 40 Ryder place report
2
Impact on family life 4 8 5 10 5 10 4 8
Refer to Stantec report. Impact on families if their child is
away from home during the week was felt to be the greatest
(sites 1 & 4).  Increased travel time affects a greater number
of families (sites 2 & 3).Travel time increase has a bigger
impact for families with young children compared to older
children
2
Equitable - unites north & south of island 4 8 7 14 6 12 4 8
Criteria re-defined to be around uniting north/south island,
as it was felt that better reflects community feedback
2 Sustain and support local economy 7 14 4 8 3 6 7 14 Stantec report
2 Impact of construction activities on existing school/ residential areas 3 6 7 14 6 12 7 14
1
Good public transport links to site and location 5 5 7 7 4 4 6 6
Existing public transport links. Craignure slightly higher
score due to ferry terminal and better links to north & south
2 Existing safe active travel links to site 4 8 3 6 2 4 6 12
Improvements in scoring could be seen as a result of future
development at sites
1 Number of user journeys - bus, car, pedestrian (Pupil/ staff mode split) 8 8 5 5 3 3 7 7
1 Potential impact on public transport network 9 9 7 7 7 7 8 8
Scoring for sites 2 & 3 assumes school bus from Dervaig
would travel via Tobermory
2
Ability of existing (wider) roads infrastructure to service site 3 6 4 8 3 6 7 14
New access roads required for both Craignure/Garmony.
Tob South limitations. Existing site challenging/constrained,
not much space for adjustment - one way in/out. Single
track roads on Mull have an impact
1 Trips with complex dependencies/ multiple stages and modes of travel 5 5 5 5 5 5 5 5 No material difference between site options
2 Potential for re-use of existing infrastructure and buildings (embodied carbon) 4 8 3 6 1 2 3 6
3 Carbon impact of travel (travel distances and mode of transport) 8 24 3 9 4 12 8 24
Personal decisions to drive could impact actual carbon
impact
15
Costs associated with construction abnormals 9 135 8 120 5 75 7 105
Thomson Gray report. Assume demolition included in scope
regardless
Based on assumptions and known information, site
investigations not completed at this early stage
5
Potential acquisition/ disposal costs 4 20 7 35 10 50 3 15
Market value of each site. Updated 28/1/25 to reflect
existing site value excluding common good land, and
cumulative value of Tobermory South site (2 separate land
transactions)
Site 3
Garmony (005)
MULL CAMPUS SITE SELECTION CRITERIA (v5)
Site 4
Tobermory South (013)
Accessibility & Transport
15
32
8
8
Deliverability
Education
Community and Place
Weighting Site 1
Existing Tobermory site
Site 2
Craignure (001)
Affordability
Sustainability 5
25

Page 2

Classification: OFFICIAL#
Criteria Category Category Individual Factors to consider Score Weighted Score Score Weighted Score Score Weighted Score Score Weighted Score Notes/ rationale
Site 3
Garmony (005)
MULL CAMPUS SITE SELECTION CRITERIA (v5)
Site 4
Tobermory South (013)Weighting Site 1
Existing Tobermory site
Site 2
Craignure (001)
5
Other (revenue) cost implications e.g. pupil transport 9 45 2 10 2 10 9 45
4 additional buses for site 2 & 3 (£1,385 per week for 40
weeks  = £222k per annum) plus additional cost for staff
travel for change of base (over 4 years).
Any hostel savings, assuming catchment area change,
negigible as staff shortages already. Main difference would
be cost of food
3 Wayleaves, legal restrictions and site acquisition risk 6 18 7 21 7 21 7 21
Common good land risk on site 1
Sites 2-4 have site acquisition risk
2
Construction Programme risk 3 6 8 16 5 10 7 14
Likely to be a prolonged programme on site 1 due to need
for staged construction and decant. Greater enabling works
required for site 3
2
Planning designation and sensitive receptors 8 16 7 14 6 12 8 16
Site 2 - consider risk with housing development next door.
Countryside zone, but already some development. Site 3 -
also countryside zone, flooding considerations, cat 1 peat
land. Site 4 - Housing allocation, amendment needed to
LDP.
TOTAL 100 625 628 546 645
Impact 53
Deliverability 15
Affordability 25
Risk 7
7Risk
Affordability 25