SUPPLEMENTARY PACK 1 
ARGYLL AND BUTE COUNCIL - ON A HYBRID BASIS IN THE COUNCIL CHAMBER,
KILMORY, LOCHGILPHEAD AND BY MICROSOFT TEAMS on THURSDAY, 26 JUNE 2025 at
10:30 AM 
I enclose herewith amended Appendix 2(b) in relation to item 7(c) (Earmarked Reserves -
2024/25 Year End) which should replace that previously issued with the Agenda for the above
meeting. 
Douglas Hendry
Executive Director 
AMENDED APPENDIX 
7. YEAR END REPORTING PACK 2024/25 
Reports by Section 95 Officer 
(c) Earmarked Reserves - 2024/25 Year End (Pages 3 - 4)
Appendix 2(b) 
Argyll and Bute Council 
Contact: Hazel MacInnes, Senior Committee Officer  Tel:01546 604269
Public Document Pack

Page 2

This page is intentionally left blank

Page 3

Appendix 2b 
ARGYLL AND BUTE COUNCIL COUNCIL
REPORT BY EXECUTIVE DIRECTOR DOUGLAS HENDRY &
EXECUTIVE DIRECTOR KIRSTY FLANAGAN
26 JUNE 2025
PROPOSAL TO EARMARK FUNDS FROM GENERAL FUND RESERVE
STORM EOWYN 
1.  INTRODUCTION 
1.1 The purpose of this report is to request support in earmarking from unspent
budget/unallocated General Fund for a specific purpose, in line with the Policy on
End of Year Flexibility. 
2. DETAIL 
2.1 Initiative/Proposal 
2.1.1 It is proposed that £1.3m be earmarked from a combination of the overall revenue
budget underspend and funds held within the Unallocated General Fund to fund
expenditure in relation to Storm Eowyn.    
2.2 
2.2.1 
2.2.2 
2.2.3 
2.2.4 
Business Case – Storm Eowyn 
A separate report is on the Council agenda today in respect of Storm Eowyn.  Storm
Eowyn struck Argyll and Bute on 24 January 2025, bringing wind speeds of up to 100
mph and causing widespread damage.  The Council’s infrastructure suffered
significant damage, particularly to roads, sea walls, harbour facilities and property. 
Helensburgh Leisure Centre suffered extensive damage to its roof and water damage
to the interior of the building and fixtures and fittings.   
At this stage all costs in relation to Storm Eowyn are not known and figures may be
subject to change.  However, at the present time it is estimated that the total
expenditure amounts to £3.952m.  This figure does not include any shortfall in
relation to Helensburgh Leisure Centre (HLC) in respect of the difference between
insured works and required works.   
For HLC, the Council’s insurers will cover like for like repairs to the building and
contents. However, it is felt that it would be prudent to check that the existing design
and roof covering will withstand future weather incidents of this nature. Should
changes to the design be required there will be re-design, re-engineering and legal
costs involved. 
£2m has already been set aside from the roads reconstruction budget, £0.792m has
been absorbed within the 2024-25 revenue outturn and £0.353m is expected from a
Bellwin Claim.  This leaves a gap of £0.807m.   
Page 3 Agenda Item 7c

Page 4

Appendix 2b
2.2.5 
2.2.6
This gap does not include any costs for Helensburgh Leisure Centre.  On the basis
that the Council will require to undertake a technical assessment that will not be
covered by the Insurers like for like cover and in the knowledge that not all costs
incurred by the Council will ultimately be recoverable, it would be prudent to set aside
some funding to cover:  
a) any additional costs to ensure that the HLC is suitably reinstated for use at the
earliest opportunity, and 
b) potential legal costs incurred by Council in court proceedings in regard to the
design and construction of the Leisure Centre. 
At the budget meeting on 27 February 2025, Council previously agreed to set aside
£2.9m to boost future resilience for severe weather related costs.  As the wording
suggests, this was for future resilience but there is an option that Council could agree
to use some of this funding towards the budget gap.  However, due to the overall
underspend on the revenue budget in 2024-25 and the balance in the unallocated
General Fund, it is recommended that Council set aside a further £1.3m of funding
towards Storm Eowyn related costs on the basis that any funding not required for
such purposes be returned to the General Fund.   
2.3 
2.3.1
Expenditure Profile 
It is anticipated that the sum of £1.3m will be spent over 2025-26 and 2026-27.     
DOUGLAS HENDRY & KIRSTY FLANAGAN
EXECUTIVE DIRECTORS