Page 1

ARGYLL AND BUTE COUNCIL COUNCIL
FINANCIAL SERVICES 26 JUNE 2025
STORM EOWYN – ESTIMATE OF COST  
1. INTRODUCTION 
1.1 This report provides an estimate of the costs associated with Storm Eowyn that
struck Argyll and Bute on 24 January 2025, bringing wind speeds of up to 100mph
and causing widespread damage.   
1.2 A report was presented to the Environment, Development and Infrastructure (EDI)
Committee on 20 March in relation to the roads and infrastructure recovery works. 
Initial estimates, at that time, suggested that expenditure on roads and
infrastructure assets (excluding marine) could be as much as £6.7m for fully
engineered resilient solutions.   The EDI Committee agreed to allocate an initial
£2m to the repair of roads and coastal assets affected from the roads
reconstruction annual budget.  Officers were to carry out an assessment and
prioritisation of all works required in order to reduce the initial estimate as close to
the £2m agreed. 
1.3 This report brings together the updated estimates for roads and infrastructure
assets, also outlines the costs associated with other properties across Argyll and
Bute and advises Council of a request from Live Argyll for financial support due to a
significant reduction in income as a result of Helensburgh Leisure Centre being
closed following the storm.  The report also updates on the Bellwin claim submitted
to Scottish Government on 23 May 2025.     
2. RECOMMENDATIONS 
2.1  Council is recommended to: 
a) Consider the estimated costs associated with Storm Eowyn.   
b) Agree that Council commit to Live Argyll to provide an additional service
payment of £65k per month from November 2025 through to when the
Leisure Centre reopens and in addition to up to £65k per month for a further
two months to allow the facility the breathing space to have normal level of
service and income restored.  
c) Agree that Live Argyll can access the Council’s redundancy earmarked
reserve up to the value of £100,000 to pay for the cost of any staff
redundancies required due to their cost reduction plan following the storm.  
d) Agree that the Council set aside a further £1.3m of funding towards Storm
Eowyn costs with any funding not required for such purposes to be returned
to the General Fund.

Page 2

3. DETAIL 
3.1 Background 
3.1.1 Storm Eowyn struck Argyll and Bute on 24 January 2025, bringing wind speeds of
up to 100 mph and causing widespread damage. The storm led to power outages,
cancelled ferry services, blocked roads and tidal flooding affecting communities
across the region. The Council’s infrastructure suffered significant damage,
particularly to roads, sea walls and harbour facilities. Other affected assets
included burial sites, parks, recycling centres, operational depots and Council and
private property. The Council’s initial response was aimed at ensuring public safety,
particularly around buildings that had suffered damage.  Helensburgh Leisure
Centre suffered extensive damage to its roof and water damage to the interior of
the building and fixtures and fittings.   
3.1.2  Once windspeeds had dropped sufficiently to enable safe operations, the clear up
and assessment works began with initial activity commencing overnight 
on Friday 24th January and increasing significantly in scale at first light on 
Saturday 25th January. As an example of scale well over 130 locations were 
identified where roads were blocked by debris with the majority of these and other 
priority clearance works being completed by the close of Monday 27th January. 
3.2 Roads and Infrastructure Assets 
3.2.1 A report was presented to the EDI Committee on 20 March in relation to the roads
and infrastructure recovery works.  A full schedule of the permanent repair works
identified were provided to Members with an initial cost estimate for these works
being £0.620m on marine assets and £6.700m on roads and infrastructure assets,
a total of £7.320m.  It should be noted that these estimates were based on fully
engineered solutions to design standards that provide for 1 in 200-year event
proofing.  Whilst this might be the optimal solution if budget was not a
consideration, it is not considered affordable or necessary.   
3.2.2 A process of prioritisation and options appraisal has been undertaken by Network
and Standards officers, in a similar way to how they assess the road network each
year in terms of allocating the annual roads reconstruction budget.  EDI agreed that
repair works to marine assets that fall outwith the funding that may be provided by
the Bellwin Scheme be funded through increases in fees and charges in future
years where possible (in line with the Marine Asset Management Plan).  The EDI
Committee further agreed to allocate £2m to the repair of roads and coastal assets
affected from the Roads Reconstruction budget. 
3.2.3 Some roads and infrastructure projects are now complete in respect of Ormsary,
Ellary and the slip site at Arrochar, and they amount to £0.454m.  The Bellwin claim
included £0.444m for these works (£0.010m of works were outwith the 2-month
window).  Repairs are ongoing on Dunoon Esplanade by an external contractor and
initial estimates were in the region of £0.250m, however, it is likely that more work
is required and the cost could be considerably more.  Other projects as assessed
by Network and Standards are estimated to cost circa £1m.  It should be noted that
the Design Team have still to confirm for a small number of projects, that the

Page 3

proposed solution is acceptable.  However, based on the costs noted above, it is
expected that the required works will be able to be contained within the £2m capital
budget allocated in March 2025.   
3.2.4 It should be noted that in addition to the costs noted in paragraph 3.2.3, there were
costs associated with debris and tree clearance, minor repairs, purchase of
additional materials and staff overtime and these were included in the Bellwin claim
(see paragraph 3.7). 
3.3 Miscellaneous Property and Building Damage 
3.3.1 Damage to Council property assets was equally as widespread as the damage to
roads and infrastructure assets. Property Services recorded 138nr miscellaneous
Helpdesk callouts on or immediately after the 24th January 2025 in direct response
to effects of Storm Eowyn.  These calls have now been reviewed and the costs
ratified.   
3.3.2 The confirmed commitment value now amounts to £0.146m for various works
including making safe and watertight damaged roofs, broken windows, water
ingress, clearing debris, tree removals, property damage, boiler failure, electricity
issues and fencing works.  All miscellaneous repairs have now been completed or
contracts let to address them.  This has been a resource intensive task in the
course of normal business for Property Services staff.   
3.3.3 Property Services and Finance colleagues have reviewed the callouts eligible for
inclusion in the Scottish Government Bellwin Scheme and have reconciled against
Scottish Government strict guidelines.  The claim to Scottish Government on 23
May included £69,742 property repairs leaving a shortfall of £76,258 (see Bellwin
claim section at paragraph 3.7 below).   
3.4 Major Property Damage 
3.4.1 The £0.146m figure excludes any remedial works cost for four properties which
sustained major damage as a result of Storm Eowyn.  These properties are all
insured and have been subject to a claim and detailed input from an appointed
Loss Adjuster.  The properties subject to insurance claim are: 
Property Description of damage
& repair 
Total
anticipated
cost 
£
Insurer
funded
contribution
(estimate)
£
Council
contribution
(estimate 
£
A- Glencruitten
Hostel,
Oban
Flat roof felt dislodged by
high winds in two
locations.
Recommendation of a
patch repair to only the
North roof. 
£60,000 £40,000 (net
of excess)
£20,000
B- Park
Primary
School,
Section of metal clad
pitched roof dislodged
due to high winds and
£730,000 £95,000 (net
of excess)
£635,000

Page 4

Oban water ingress.  Insurers /
Officers recommend full
roof replacement – not
only damaged area on
basis of potential of
future failure and life
expired nature of entire
roof.  Insurer will only
fund area of storm
damage. 
C - Struan
Lodge care
Home, Dunoon
50% of flat roof felt
dislodged by high winds.
Insurers / Officers have
recommended full
replacement of flat roof.  
Works can progress as
soon as quotes agreed
with Insurer and other
strategic investment /
works at property are
confirmed with HSCP. 
£110,000 £45,000
(net of
excess)
£65,000
D –
Helensburgh
Leisure Centre 
Major damage to roof
and significant water
damage.  Ongoing
protection of asset and
tendering underway to
repair. Ongoing
engagement with insurer
and loss adjuster. 
Included  decant of gym
to Helensburgh library
and business interruption
costs.  
Not yet
quantified 
Not yet
quantified 
Not yet
quantified 
Total excluding Helensburgh Leisure
Centre
900,000 180,000 720,000 
3.5 Helensburgh Leisure Centre 
3.5.1 Members have been briefed (latest updated dated 26 May and Press Statement 30
May) on the damage sustained at the Helensburgh Leisure Centre during Storm
Eowyn, which has resulted in the requirement to replace the entirety of the
building’s roof and associated components, as well as extensive repairs across the
internal first floor in respect of mechanical and electrical plant and equipment,
fixtures, finishes (e.g. wall coverings, ceilings, floor finishes). 
3.5.2 The Council’s Programme and Project Management Services team have been
working with the Loss Adjuster appointed by the Council’s insurer Zurich to assess
the damage and specify the scope of repairs required.  The building is insured on a
‘like-for-like’ basis but a consultancy who specialise in disaster recovery and storm
repair is also designing the fix in cognisance of specific damage and circumstances
of storm Eowyn.   
3.5.3 The repair work has been split into two phases i.e. Phase 1 – Roof Repairs, and

Page 5

Phase 2 – Internal Repairs, sub-contracting with specialist sub-contractors e.g.
roofing, mechanical, electrical, etc. as appropriate.  The priority is to implement the
roof repair works as a matter of urgency, and with a view to having these
substantially completed by the end of this calendar year if at all practical.  At this
time and based on the information available a reasonable estimate for reopening
could be no later than the first quarter of the calendar year 2026. 
3.5.4 As required by the Loss Adjuster / Insurer a competitive tender process for the two
phases of work is underway to demonstrate value for money to the Insurer. In
respect of the roof repairs, 3 specialist roofing subcontractors tendered for the
work, and these were received on 6th June.  Assessment of tenders has taken
place, and a preferred bidder has been identified. We are proceeding to formalise
the contract award w/b 23rd June.  No further details can be provided at the time of
writing this report, but more information about the contractor and programme will be
shared once the appointment is finalised. There will be a gap between the value of
the insured costs (like-for-like) and the specified work costs which the Council will
need to provide for.  This figure is still being discussed and agreed with the Loss
Adjuster and insurer.  A similar exercise will be forthcoming for the internal repairs. 
Further updates will be provided as this repair project continues. 
3.5.5 The allocation of budget for pursuing legal or judicial activity would be prudent
given the circumstances.  It is not appropriate to speculate or comment on potential
fault or failings caused by the extreme weather event as such matters (if deemed
appropriate to pursue) may be the subject of legal action on the part of the Council
and or its insurers.  Speculation may adversely impact legal position of the Council
and / or our insurers at this stage. 
3.6 Live Argyll 
3.6.1 A letter has been received from Live Argyll in respect of their financial position,
directly because of Storm Eowyn.  Prior to the closure of Helensburgh Leisure
Centre following the storm, the facility was generating approximately £125k income
per month which was income that formed part of Live Argyll’s core budget. 
3.6.2 The Live Argyll Board took immediate steps to provide alternative gym and fitness
provision and were able to recover circa £30k lost income per month.  As this left a
significant gap, the Board reluctantly agreed to a cost reduction plan, exploring
every opportunity to reduce cost to deal with the loss of income as much as the
company can across their operations.  This was necessary due to the estimated
timeline for repairs and reopening of the Leisure Centre.  However, the ongoing
shortfall of income presents a significant risk to the ongoing solvency of the
company.     
3.6.3 Some of the options to reduce expenditure identified by Live Argyll may require
consideration by the Council and a further report will be brought forward to
Members in this regard in early course. 
3.6.4 Live Argyll’s external auditors have, for the first time, flagged an audit risk and have
indicated that they will be seeking assurances from Live Argyll Directors as to the
longer-term financial viability of the company. In order that Live Argyll’s statutory

Page 6

accounts are not qualified, the auditors are likely to seek assurance along the lines
of:
• Argyll and Bute Council acknowledge that Live Argyll will not be able to
operate as a going concern without the support of Argyll and Bute Council
as the ultimate parent entity; 
• Confirmation that Argyll and Bute Council will continue to provide current
and future financial support to Live Argyll adequate for its needs. 
3.6.5 Live Argyll are therefore needing assurance/confirmation of further funding.  Live
Argyll holds a reserve balance of approximately £740k after adjusting for the 2024-
25 outturn deficit.  Prudent financial management and their reserves policy mean
they should retain a balance of £200k as a minimum.  This would free up circa
£540k to manage any funding shortfall and cost pressures.  The income gap is
estimated to be circa £90k per month, reducing to £70k in July and £65k per month
from August once the cost reduction plan measures are fully implemented.  The
reserves would be fully exhausted by the end of October at which point Live Argyll
would be seeking a service payment of circa £65k per month from the Council until
the Leisure Centre fully-reopens and returns to normal level of service.   
3.6.6 The table below outlines the estimated monthly impact of the reserve and
demonstrates that they will be exhausted by October.   
Month Net monthly loss of
income
Reserves Balance (after
£200k retained)
Opening Balance April  540
April (90) 450
May (90) 360
June (90) 270
July (70) 200
August (65) 135
September (65) 70
October (65) 5 
3.6.7 It is recommended that the Council provide a commitment to an additional service
payment of £65k per month from November through to when the Leisure Centre
reopens with up to £65k per month for a further two months to allow the facility the
breathing space to have normal level of service and income restored.  If the Leisure
Centre opens no later than the end of the first quarter of 2026 (as noted in
paragraph 3.5.3), then this would result in a worst-case scenario payment of £455k
(5 months pre-opening, 2 months post opening).   It is further recommended that
the Council agree that Live Argyll, in these circumstances, can access the
Council’s redundancy earmarked reserve for the cost of any staff redundancies as
required by their cost reduction plan.  It is estimated that these will cost no more
than £100k.   
3.7 Bellwin Claim 
3.7.1 The Bellwin Scheme is a discretionary scheme, which exists to give special
financial assistance to local authorities who would otherwise be faced with an
undue financial burden as a result of providing relief and carrying out immediate

Page 7

work due to large-scale emergencies. There is no automatic entitlement to financial
assistance. The key criterion of the Scheme is to safeguard life and property and
prevent suffering or severe inconvenience in a local authority’s area or among its
inhabitants. 
3.7.2 The purpose of the Scheme is not to put right all the ill effects resulting from an
emergency incident but to provide a degree of financial protection to both local
authorities and their local council taxpayers as a result of having to deal with an
emergency situation or situations over and above what could reasonably have
been budgeted for (0.2% of their total net revenue budget). The Scheme addresses
revenue and uninsurable expenditure incurred within a two-month period from the
date of the incident.  The scheme does not cover capital expenditure. Most of the
costs associated with the permanent repair of roads and infrastructure assets are
capital in nature and therefore are not eligible to be claimed through the Bellwin
Scheme. 
3.7.3 The Council activated the Bellwin Scheme within the required timeframe following
the storm and submitted a claim on 23 May 2025 (four months after the storm). 
The claim also covered Storm Darragh which occurred on 6-7 December and
caused damage to two road bridges in East Kintyre which required intervention
from the Council to ensure the safety of road users and support to local
communities who rely on the two bridges to access key services in their local area. 
It was agreed with Scottish Government that one claim could cover both weather
events. 
3.7.4 Bellwin grant is paid at a rate of 100% of eligible expenditure above each local
authority’s annual threshold.  Argyll and Bute Council’ claim amounted to £911,098. 
The threshold for 2024-25 was £558,200 resulting in a net grant claim of £352,898. 
This claim is summarised in the table below.   
Detail Cost
£
Storm Darragh 
Saddell Bridge Emergency Repairs 40,516
Torrisdale Bridge Emergency Repairs 49,940
Storm Eowyn 
Piers and Harbours Repairs 21,389
Electric Vehicle Charge Unit Repairs 4,661
Roads and Infrastructure: clear up of debris and fallen trees,
purchase of materials, bus shelter repairs, staff overtime etc. 
280,425
Roads and Infrastructure: Ormsary, Ellary and slip road
Arrochar 
444,425
Property: Various emergency property repairs (refer to
paragraph 3.3.3)
69,742
Total Claim 911,098
Less Threshold (558,200)
Net Claim 352,898 
3.7.5 The net claim has been accrued as income within the Council’s accounts for 2024-
25, however, we have yet to have confirmation from Scottish Government as to

Page 8

whether they will approve our claim, this remains a risk that Council should be
mindful of.  The expenditure showing through the year end outturn report in relation
to the weather event amounts to £0.792m.  This relates to the £0.558m threshold in
addition to other areas of expenditure amounting to £0.234m carried out as part of
the emergency that were not eligible for Bellwin.  Officers will undertake an analysis
to ensure that what has been accounted for here is not double counted elsewhere
in this report.   
3.7.6 The table in the next section of this report summarises the total estimated costs
known at this time.  In respect of the Bellwin claim, £0.444m of roads and
infrastructure projects and £0.070m of miscellaneous property were included in the
claim (as noted above) and as these amounts are included in the roads and
infrastructure assets and miscellaneous property lines, they have been deducted
from the Bellwin claim line to ensure there is no double count.   
3.8 Funding Options 
3.8.1 It should be noted that all costs in relation to Storm Eowyn are not known or
confirmed yet and therefore the figures presented in this report are a snapshot at
this time and may be subject to change.  Any estimates will be confirmed once the
actual work has taken place, and it may be as works are carried that more remedial
work is required than first envisaged.   
3.8.2 The table below summarises the estimated costs at this time: 
£000
Roads and Infrastructure Assets See para 3.2.3 2,000
Miscellaneous Property See para 3.3.2 146
Major Property See para 3.4.1 720
Helensburgh Waterfront See para 3.5 TBC
Live Argyll  See para 3.6.7 455
Bellwin Claim (Storm Eowyn & Storm
Darragh)
See para 3.7.4 & para
3.7.6
397
Other Expenditure associate with storm See para 3.7.5 234
Total Estimated Expenditure*  3,952 
*These are still estimated costs and do not include any shortfall in relation to
Helensburgh Leisure Centre in respect of the difference between insured works
and required works. 
3.8.3 As previously noted, £2m of funding has already been allocated from the roads
reconstruction budget, we expect to receive £0.353m from Bellwin and some costs
have already been absorbed within the 2024-25 revenue reported outturn.  This
leaves an estimated funding gap of £0.807m excluding any uninsured works or
legal claim in relation to Helensburgh Leisure Centre. 
£000
Total Estimated Expenditure as noted in para
3.8.2
3,952
Roads Reconstruction Budget (2,000)

Page 9

Bellwin Claim (353)
Absorbed within 2024-25 revenue reported
outturn
(792)
Estimated Funding Gap* 807 
*Does not include shortfall in relation to Helensburgh Leisure Centre in respect of
the difference between insured works and required works. 
3.8.4 At the budget meeting on 27 February 2025, Council agreed to set aside £2.9m to
boost future resilience for severe weather-related costs.  As the wording suggests,
this was for future resilience but there is an option that Council could agree to use
some of this towards the budget gap noted above.  However, due to the overall
underspend on the revenue budget in 2024-25 and the balance in the unallocated
General Fund, it is recommended that Council set aside a further £1.3m of funding
towards Storm Eowyn on the basis that any funding not required for such purposes
be returned to the General Fund. 
3.8.5 A further update will be provided to Council at a future meeting once estimates in
relation to Helensburgh Leisure Centre have been quantified and once other cost
estimates are more certain.   
4. CONCLUSION 
4.1 This report provides an overall estimate of the costs associated with Storm Eowyn.   
It should be noted that some of the costs are still estimated and all costs are also
not known at this stage.   
4.2 Live Argyll’s financial position has been significantly impacted due to the closure of
Helensburgh Leisure Centre and Live Argyll have implemented a cost reduction
plan.   It is recommended that Council provide a commitment to Live Argyll to
provide an additional service payment of £65k per month from November through
to when the Leisure Centre reopens in addition to up to £65k per month for a
further two months to allow the facility the breathing space to have normal level of
service and income restored.  It is further recommended that the Council agree that
Live Argyll, in these circumstances, can access the Council’s redundancy
earmarked reserve for the cost of any staff redundancies as required by their cost
reduction plan.   
4.3 Based on the estimates within this report, there remains an estimated funding gap
of £0.807m and it is recommended that due to the balance in the unallocated
General Fund, that Council set aside a further £1.3m of funding towards the Storm
costs.   
5. IMPLICATIONS 
5.1 Policy: Policies in place for climate change, coast protection etc where
applicable these policies are being worked to.
5.2 Financial: As outlined within the report, a potential gap of £0.807m with a
request for future funding of £1.3m to cover costs not known at
this stage.

Page 10

5.3 Legal: Any projects with legal implications are progressing as
expected.
5.4 HR: None for Council, however, Live Argyll’s cost reduction plan
had staffing implications.  
5.5 Customer
Service:
Officers quickly reacted to the storm damage which limited the
impact on customers.  The most affected property was
Helensburgh Leisure Centre.
5.6 Risk: There remains a significant risk of future weather events
affecting the Council’s property and infrastructure, there is also
a risk that the estimated costs as outlined in this report could
increase.
5.7 Climate Change: The impact of the storm is likely to be linked to climate change
and has highlighted the need for further adaptation to be made
to infrastructure to increase resilience to future weather events.
The level of investment required to improve resilience is
expected to be significant.
5.8 Fairer Scotland
Duty:
None known.
5.9 Equalities
protected
characteristics:
None known.
5.10 Consumer Duty: None known.
5.11 Islands
Communities:
None known.
5.12 Children’s Rights
and Wellbeing:
None known. 
Kirsty Flanagan
Executive Director/Section 95 Officer
16 June 2025 
Councillor Ross Moreland, Policy Lead for Finance and Commercial Services