Page 1

Plan for Neighbourhoods Fund             
1
Clydebank Neighbourhood Board
Meeting 5 September 2025
Clydebank Housing Association 
Item 5: Plan for Neighbourhoods  – progress update 
FOR INFORMATION ONLY  X
FOR DECISION 
Name of Committee Board
Date of report 28/08/2025
Name and email of lead contact Elaine Troup
Elaine.Troup@west-dunbarton.gov.uk 
1 Main Issues
£250,000 capacity finding has been received to date. £155,240 has been spent, with
£94,760 remining available. Please refer to the breakdown below:
FY 2024/25
Community grants funding £10,000
Consultancy fees for development of the Long
Term Plan and Community Engagement
£86,939
Board meeting  £130
Board meeting £170
Board meeting £130
Board meeting £170
ICT costs (Adobe license) £185
Contribution to WDC staff costs £60,000
FY 2025/26 
Community grants funding (return) - £5,700
Board Workshop £3,216
Total spend till June 2025 £155,240
Additional £200,000 of capacity funding has now been received which means that
the overall budget for FY 25/26 is £294,240
Delivery funding will be released in FY 26/27 and the table below shows the
schedule of payments outlined in the new Plan for Neighbourhoods guidance.

Page 2

Plan for Neighbourhoods Fund             
2
2 Outline of any issues/risks and how these are being managed
Timescales for release of the delivery funding. Delivery funding won’t be
released until FY 26/27, with only £360k of capital funding available in FY 26/27.
The Board requires to prioritise projects/interventions for FY 25/26 and 26/27. 
3 Outline of the main outputs expected before next meeting 
4 What are the requirements of stakeholders to achieve the outcomes of this
report?
If possible, engage in the delivery process outside the Board meetings e.g. through
a working group. 
5 Recommendations                                              
It is recommended that the Board notes the financial information and considers how
the FY 25/26 and 26/27 funding should be allocated.