Plan for Neighbourhoods Fund                     
1
Clydebank Neighbourhood Board
Meeting 5 September 2025
Clydebank Housing Association 
Item 3: Plan for Neighbourhoods – Update on Progress 
FOR INFORMATION ONLY  X
FOR DECISION 
Name of Committee Board
Date of report 05/09/2025
Name and email of lead contact Elaine Troup
Elaine.Troup@west-dunbarton.gov.uk 
1 Main Issues
The main issues arising from the previous meeting on 1 August 2025 are
summarised below, together with how they are being addressed/actioned.
Interventions 
Interventions from previous LTP under
categories of:
 Regeneration, high streets, and
heritage
 Transport
 Safety and security 
Following discussions at the last Board
meeting, the interventions from the LTP to
include within the Regeneration Plan have
been agreed. 
For the intervention ‘Make Improvements
to public transport provision’ a meeting is
scheduled for 1 September to discuss
proposals and timescales with Roads. An
update on this can be provided at the
Board meeting. 
New pre-approved interventions under
categories of:
 Housing
 Work, productivity and skills
 Cohesion 
 Health and wellbeing 
 Education and opportunity 
The interventions under these categories
to include in the Regeneration Plan will be
identified through the community
engagement process (see below) and
discussed with the Board. 
Contact has been made with service
leads to determine whether: 
I. any of the pre-approved
interventions are already
happening within Clydebank 
II. there are any gaps in provision. 
Feedback from the service leads is
provided in the paper in Item 4. 
Community Engagement 
WDCVS led engagement with
community organisations
Outline framework prepared based on the
pilot approach undertaken for the LTP.

Page 2

Plan for Neighbourhoods Fund                     
2
Local organisations have been
approached to participate in ‘group level’
discussions using a facilitated survey tool.
Groups will again be offered a one-off
grant of £100, £150 or £200 to support
their participation, depending on group
size
The approach aims to: 
 Update on work since the LTP
engagement (You said, we did)
 Consult on potential inclusion of
additional pre-approved
interventions 
 Encourage expressions of interest
for ongoing involvement in the
delivery of Regeneration Plan
The engagement period will run from w/c
25 August to 26 September. 
Details of the approach and the
questionnaire being used have been
shared with the Board.
WDC engagement with wider
Clydebank community
To compliment the WDCVS engagement
and capture the views of the wider
community on the new set of pre-
approved interventions the WDC
Communities team are undertaking
additional engagement on behalf of the
Board. This is aimed at all parties who
may have an interest in the future of the
town – individuals, businesses, etc. 
This engagement is being planned. It will
use a questionnaire for responses and
reach out to stakeholders not covered by
the CVS engagement including young
people. The opportunity for a drop in
event within Clydebank Shopping Centre
is being explored. Board members will be
advised of dates from the drop in and
their presence welcomed.  
To highlight the purpose of the
engagement it would be beneficial to have
banners produced with Neighbourhood
Board/ PfN branding. These would help
raise awareness of the engagement and
make the distinction between the Board
and WDC. Developing the brand/logo
could be an early task for the
Communications sub team.

Page 3

Plan for Neighbourhoods Fund                     
3
Draft Communications Plan envisaged
actions for Phase 1 community
engagement are as shown. 
It would be helpful to agree who does
what for promotion via:
 Press release
 Social media posts
 Websites
Preparation of the Regeneration Plan 
Kevin Murray Associates (KMA) have
been appointed to assist with the
preparation of the Regeneration Plan
Contract Award letter issued to KMA on
12 August 2025.
Value of the contract shall be no greater
than £30,000 exclusive of VAT. 
The contract completion date is currently
the end November 2025 to tie in with the
28 November deadline for the submission
of the 2-part plan.
Website  
The dedicated PfN/Neighbourhood
Board website will be advanced by the
Communications sub-group. In the
interim a page has been created on
WDC website
Refer Plan for Neighbourhoods | West
Dunbartonshire Council
This can be used to update the PfN
process and host relevant information
until the main webpage is available. 
Recruitment of Project Resource 
Job Profile will be prepared and
provided for review
The job profile needs to be reviewed and
approved by Board members and the
preferred route to recruitment agreed. The
options are open recruitment or internal
recruitment (e.g. from existing employees
of a partner organisation).
The Board should also agree on how the
person will be formally employed and by
whom. As the Board is not formally
constituted, the person could be
employed by one of the partner
organisations, however they would report
to the Board/Chair. 
Board Membership  
Additional representation being
progressed. 
Jackie Maceira has agreed to represent
disabled stakeholders. He is currently
involved with Shop Mobility and a
member of West Dunbartonshire Equality
Forum.
Anne Campbell, the new principal, has
agreed to represent West College
Scotland.
Housing representation is being sought -
Liz has contacted Lynette Lee’s who has
circulated the request to local Housing
CEO's and the members of the CHA
Board.

Page 4

Plan for Neighbourhoods Fund                     
4
Contact has been made with the
Chamber of Commerce and youth sector
regarding future representation. 
2 Outline of any issues/risks and how these are being managed
The UK Government expects a high degree of community engagement during the
development of the Regeneration Plan and its ongoing delivery. Measures are being
put in place to ensure that the views of all sections of the community are captured at
this initial stage and incorporated into the Regeneration Plan. The timescale for the
engagement and ensuring all comments are considered and, where relevant,
included within the Plan is tight given the submission deadline of 28 November
2025. This can be managed by the Board continuing to develop, refine and agree
the interventions to be included with the Regeneration Plan over the next 2 months. 
3 Outline of the main outputs expected before next meeting 
Undertake the community engagement and continue to develop the Regeneration
Plan as informed by this and any other required consultation/input. 
4 What are the requirements of stakeholders to achieve the outcomes of this
report?
To continue to contribute to the development of the Regeneration Plan and the
ongoing work of the Clydebank Neighbourhood Board. 
5 Recommendations                                              