Page 1

OFFICIAL
OFFICIAL
Clydebank Neighbourhood Board 
Friday 27 March 2026 9.30am 
Clyde Shopping Centre Conference Room, 
170 Kilbowie Road, Clydebank 
Agenda: Lead
1. Welcome by Chair Liz Connolly
2. Apologies Brian McColgan
3. Previous minutes and actions All
4. Regeneration Plan Delivery
 Project Delivery Subgroup Updates
o A1. Three Queens Square  - paper to be shared
with Board
o Bl. Improving connections 
o B2. Walking and cycling trails
o C1. Employability, skills, training, etc. 
o A2. Meanwhile uses
o A3. Community Hub/Accessible Public Welfare
Facilities
 South Sylvania Way Feasibility Group Update 
Group Chairs
5. Marketing and communications Sandie Scott
6. Recruitment of project resource Alan Douglas
7. Finance 
 Financial report 
 Update on use of Capacity Funding for community activities
Liz Connolly/Selina
Ross
8. Any Other Business
 PIPP Monitoring Return to MHCLG
 Community Council/Forum representation 
 Vicinity Outreach approach to establish Digital Platform 
Liz Connolly
9. Date and time of next Board meetings 
Currently scheduled for Fri 1 May, Fri 29 May, Fri 26 June. Frequency
of meetings to be discussed.

Page 2

Pride in Place Programme   
1
Clydebank Neighbourhood Board
Meeting 27 March 2026
Clydebank Shopping Centre
Item 3: Note of previous meeting 
Clydebank Neighbourhood Board 
27 February 2026 9.30am 
Clydebank Library, Clydebank 
Members Attending
Liz Connolly   Chair
Fiona McInnes  Chief Executive, Clydebank Co-op Society
Selina Ross   West Dunbartonshire CVS
Clare Steel   WDC Elected Member
Lawrence O’Neill  WDC Elected Member
Douglas McAllister  Member of Parliament
Gail MacFarlane  Chief Officer, Roads & Neighbourhoods, WDC
Laurence Slavin  Chief Officer Resources, WDC
Anne Campbell  Principal & Chief Executive, West College Scotland
Louise Ewing   Dunbartonshire Chamber of Commerce
Andrew Forrester  Clyde Shopping Centre
Marie McNair   Member of Scottish Parliament 
Apologies
Peter Hessett  Chief Executive, WDC
Alan Douglas   Chief Officer Regulatory & Regeneration, WDC
Sandie Scott   Golden Jubilee Hospital
Jackie Maceira  Shopmobility
Reverend Ishaku Ajibauka Clydebank Churches Together
Captain Ben Ellis  Salvation Army
June Todd   Community Activist 
Other attendees
Brian McColgan  Business Support Officer, WDC
Michelle Lynn  Asset Manager, WDC
Davina Lavery  Regeneration Officer, WDC
Lucy McGovern  Working4U Development Officer, WDC
Colin Smith   Your Community Team Leader WDC

Page 3

Pride in Place Programme   
2
1. Welcome by Chair Action 
Liz Connolly (LC) welcomed everyone to the meeting.  
2. Apologies 
Apologies were noted from Peter Hessett, Alan Douglas, Ben Ellis,
Sandie Scott, Reverend Ishaku Ajibauka, Jackie Maceira and June
Todd. 
3. Previous Minutes and Actions 
Amendents to the Minute were raised:
Laurence Slavin (LS) noted that WDC Asset Management had
offered to participate in the Community Hub Project Delivery Group. 
Fiona Mc Innes (FMcI) sought clarification on her Project Delivery
Group membership. 
LC reminded reminded any members who had not yet submitted a
Declaration of Interest to do so. 
Brian
McColgan 
Board
Members 
4 Regeneration Plan Delivery 
Project Delivery Subgroups
There was discussion around the various Project Delivery
Subgroups:
A1 Three Queens Square – Laurence Slavin (LS) said that
appropriate group members had been contacted and first meeting is
planned for 16th March. 
B1 and B2 Improving Connections and Walking and Cycling
Trails – Meeting to be held in last week of March.  Clarity on
membership of the group was sought. Lawrence O’Neill and a
member of staff from West Dunbartonshire CVS were confirmed as
members. LS said that WDC Asset Management will participate but
will not be a core member. Davina Lavery (DL) suggested that the
John Anderson of West Dunbartonshire Leisure Trust would be a
good member for the group and also suggested potential members
from the Heritage point of view. 
C1 Employability, Skills and Training etc – Anne Campbell (AC)
said that a workshop has been arranged with relevant parties on 9th
March.  AC would catch up with Sandie Scott to review progress. 
A2 Meanwhile Uses – Andrew Forrester (AF) and Louise Ewing
(LE) would participate subject to time constraints but would not be
able to lead the group.  DL suggested that FMcI would be a good
member of the group and FMcI agreed but not in a lead capacity.

Page 4

Pride in Place Programme   
3
LC asked if any Board members would offer to lead and LE agreed
to give it a try. LC thanked LE for this. Michelle Lynn (ML) also
offered to join the subgroup.
DL asked Lucy McGovern (LMcG) about young people's views on
meanwhile uses and it was suggested that having a young person
on the subgroup would be beneficial. LMcG agreed to progress this
but said that young people would also have time constraints around
their potential involvement in the group. 
A3 Community Hub/Accessible Public Welfare Facilities – Clare
Steel (CS) and Ben Ellis (BE) had met with DL to progress this. Ben
Ellis (BE) is happy to chair with the support of CS.  Potential
subgroup members have been contacted and a meeting is
scheduled for 24th March.
DL said that she has been in contact with various groups to invite
their participation and some individuals have expressed an interest. 
LC thanked all for the updates and progress and said that as the
subgroups develop roles and responsibilities will become clearer to
all.  LC also acknowledged that involvement in subgroups will
require significant commitment of time.
LC requested that all groups confirm their membership. 
South Sylvania Way Feasibility Group – Alan Douglas (AD) will
lead on this group which will also involve Clyde Shopping Centre,
WDC Asset Management and other parties.  A first meeting will take
place in late March. 
Use of Standard Reporting Format – LC thanked AC for sharing
the Project Implementation Document used by West College
Scotland.  DL noted that this was not too dissimilar to forms used by
WDC.  LC asked if there were any views on the form.  AC stressed
that she was not precious about the College’s form being used.  LC
asked that subgroup leads consider the forms to be used and report
back to the Board on what would work best. 
LC invited any Board members to join any of the subgroups and said
that subgroup leads should contact potential members.  DL
suggested that Jackie Maceira (JM) might be a relevant member of
subgroups B1 and B2. GMcF acknowledged this and has contacted
JM. 
Project Management Guidance – LC raised the issue of training in
Project Management for Board members and asked if West College
Scotland offerd such training.  AC confirmed that the College does. 
LC asked Board members to let her know if they required such
training. 
Project
Delivery
Leaders 
AD 
Project
Delivery
Subgroups 
Board
members/Proje
ct Delivery
Leaders 
Board
Members

Page 5

Pride in Place Programme   
4
5 Marketing and communications 
Four potential logos were circulated.  LMcG and young people had
been involved in the development of the logos.  Discussion followed. 
Key points included:
Be wary of using “political” colours
Which logo would look best in monochrome?
Which logo did the young people prefer?  Logo 4 was their
preference.
Incorporation of water and boat were good.
Need to differentiate from WDC logo and colour scheme. 
The Board approved logo 4 subject to a tweaking of the colours. 
Website – SS, LMcG and a group of young people have been
investigating the website as noted at an earlier meeting. LMcG said
that the site is quite big and its development is time consuming, but
the young people could potentially look at it during their Easter
break.  LC suggested that the development of the website could be
procured instead.  LC, DL and SS to explore progression of the
website, with option for young people to be involved. 
Lawrence O’Neill (LON) proposed donating to the youth groups
involved in the development of the website. 
Comms
Subgroup 
LC/DL/SS 
6 Recruitment of Project Resource 
An update on the recruitment of the Project Resource was given on
behalf of Alan Douglas (AD).  The necessary Job Evaluation
documentation had been submitted, and progress will be subject to
WDC Council meeting 4th March and the completion of the Job
Evaluation process.  AD
7 Finance – Financial Report and Proposed Allocation of Capacity
Funding 
Financial Report – LC asked DL if there had been any major
changes to the finances.  DL said there hadn’t.  The financial
position was noted. 
Proposed Allocation of Capacity Funding – Selina Ross (SR)
spoke to her paper.  Discussion followed.  Key points included: 
LS asked in relation to the Youth Engagement strand if there was an
idea of the likely demand for funds as the total budget proposed of
£5k seemed low. LMcG said the amount had been based on hourly
costs for the type of activity envisaged.  The budget is for the first
year of the proposed activity and could possibly be increased in
subsequent years if year 1 demand exceeded supply.  LMcG offered
to provide more detail on the costings.

Page 6

Pride in Place Programme   
5
DL raised the possibility of virement of funds from any areas which
may have low take up of grant, e.g. the proposed Spring Clean
strand. 
LC asked if the Board were happy with the proposed allocations. 
The Board approved the proposed allocations. 
In further discussion the need for a publicity of the funding was
raised and a press release will be prepared. 
LON raised the issue of higher than expected take up of capacity
funding and the possibility of increasing the funding available if this
transpired.  LC and SR said that there will be quarterly reporting to
monitor demand for funds. 
LC stressed the difference between this capacity funding, which is
non-recurring, and the revenue funding stream which recurs
annually. 
SR offered draft a press release.  LC agreed and asked that Sandie
Scott review this. 
SR/Board 
SR/SS
8 Any Other Business 
Pride in Place (PiP) Programme Logo – The official UK
Government logo for the PiP had been circulated.  This should be
used in all publicity materials.  There is some guidance on how the
logo should be used and this will be developed further and released
to coincide with the next phase of PiP. 
Scottish Futures Trust (SFT) Inclusive Growth Research – DL
explained the role of the SFT, which is to advise and assist the
Scottish Government on infrastructure projects.  SFT recognise the
changes taking place in West Dunbartonsire and have approached
WDC about Clydebank and Dumbarton being used as case studies
in the SFT inclusive growth research.  This will involve the collection
of a range of baseline information so the long-term impact of
projects, including ones being taken forward through the PIPP, can
be monitored.  LC said that this could be a useful resource for the
Board and could possibly be used to identify specific PIPP impacts.
The Board are to be mindful of the potential impact of PIPP projects
and may have to collect data to demonstrate change. 
Zencity Survey – DL spoke to this item.  Zencity had been
commissioned by the UK Government to carry out survey work in
every PPIP area.  There survey work does not make a clear
distinction between the work of the Board and the work of WDC and
DL has raised this with the UK Government.
Key points from the Zencity survey included:
 70% of Clydebank residents felt they do not have the
opportunity to participate in decision making affecting the
area. 
Comms
Subgroup 
Board/DL/WDC

Page 7

Pride in Place Programme   
6
 Among the top priorities noted by Clydebank residents were
having accessible public toilets and a community hub.  It was
noted that both these priorities had also been identified and
acted upon by the Board.
LC thanked DL for the update and noted that Zencity are an
American based organisation and hence there may be issues
around their understanding of the local structures in place in
Clydebank. 
Kings Foundation – DL, and other Board members, had attended a
webinar held by the Kings Foundation which is a “charity founded by
King Charles when Prince of Wales” and who “advocate for change
His Majesty wants to see in the world”. Cutting across a range of
sectors, disciplines and levels, The King’s Foundation represents
areas where The King has been decades ahead of the curve,
including in education and sustainability, farming and agriculture,
traditional arts and crafts, health and wellbeing, and architecture and
urbanism. The Foundation provides education, public services and
consultancy across these sectors, in the UK and around the world. 
DL said that it was not entirely clear, at this stage, what the KF could
offer to the work of the Board.   
Scottish Charity Regulator PIPP Webinar – It as noted that
several Board members had attended this event which was a basic
introduction to charitable status.  A couple of points worth noting
were:
1. Issues around WDC as accountable body for the work of the
Board possibly conflicting with charitable status
2. The requirement that a charity be free from the influence of
Government
UK Government officials in attendance at the webinar said that they
are working through these and other issues as they try to progress
the move towards PIPP Boards being community led and their
possible acquisition of charitable status. 
SR said that there are ways to work round issue 1 above but these
are not simple.  SR also raised the issue of the Board potentially
generating profits at some point and questioned the focus of the
webinar on the Scottish Charitable Incorporated Organisation status
when other structures are available. 
LC noted that a potential benefit of acquiring some form of charitable
status would be eligibility to apply for some sources of external
funding 
It was also noted that the trustees of a charity have very different
responsibilities than those currently held by Board members in their
capacity as such. 
UK
Government/B
oard

Page 8

Pride in Place Programme   
7
Further consideration will be given as UK Government guidance is
developed. 
Photographs – LC asked Board members if they could wait after
the meeting to have their photograph taken by students from West
College Scotland. 
Approach from Loqiva – DL said that she had been approached by
this organisation who develop digital platforms/applications.  It was
thought that there is no need to engage the company to develop any
digital platform for the Board at this stage. DL to respond to Loqiva. 
Community Councils – Marie McNair (MMcN) noted that the
Community Councils were disappointed not to have a presence on
the Board. LON said that he had raised the issue of the Community
Council Forum at the previous meeting of the Board.  DL said that
the various Community Councils had been invited to participate in
the original engagement exercises but neither they nor the
Community Council Forum had been invited to join the Board.
LC said that there had to be a balance struck between inclusivity
and keeping the Board a manageable size.  MMcN suggested that it
would be beneficial from a communications point of view to have the
Community Councils involved in the Board.  LC acknowledged this
and stressed the importance of getting the message out about what
the Board was doing. Involvement of Community Council’s to be
considered. 
Approval of Regeneration Plan – LC said that a decision on the
submitted Regeneration Plan should be forthcoming in March. 
LC/DL 
9 Dates of Next Meetings 
27 March 2026 Clyde Shopping Centre 
Agend
a Item
Action By Whom
3 Amend minutes BMcC
4 Confirm membership of Project Delivery Subgroups.
Progress work of Project Delivery Groups. 
Map project management skills and experience of Board
members 
Identify appropriate project management template/processes 
Project
Delivery
Subgroups/Bo
ard 
Board 
Board/Project
Delivery
Subgroups

Page 9

Pride in Place Programme   
8
5 Finalise logo/branding 
Progress website development 
Comms
subgroup 
6 Progress recruitment of Project Manager and additional
engagement resources
AD
7 Progress spend of capacity funding 
Monitor and report on take up of funding 
Prepare Press release to publicise capacity funding
Board/SR 
Board/SR 
SR/SS   
8 Liaise with Scottish Futures Trust to progress collection of data
related to inclusive growth. 
Explore representation on Neighbourhood Board from
appropriate Community Councils 
DL 
LC/DL

Page 10

Pride in Place Programme           
1
Clydebank Neighbourhood Board
Meeting 27 March 2026
Clyde Shopping Centre 
Item 7: Pride in Place – financial update 
FOR INFORMATION ONLY 
FOR DECISION  X 
Name of Committee Neighbourhood Board
Date of report 27/03/2026
Name and email of lead contact Magda Swider
Magda.Swider@west-dunbarton.gov.uk 
1. Main Issues
£250,000 capacity funding was received to cover the 2023/24 and 2024/25 financial
years. There was no spend in 2023/24. An additional £200,000 capacity funding
was received for FY 2025/26. The remaining capacity funding of £150,000 for FY
2026/2027 was received on 19 March 2026. The current breakdown of spending is
shown below:
FY 2024/25
Community grants funding £4,300
Consultancy fees for development of the Long-
Term Plan and Community Engagement
£86,939
Board meeting  £130
Board meeting £170
Board meeting £130
Board meeting £170
ICT costs (Adobe license) £185
Contribution to WDC staff costs £60,000
FY 2025/26 
Community grants funding & CVS fees                       £12,400
Board Workshop £3,216
Regeneration Plan preparation (KMA) £29,372
Total spend till end of February 2026 £197,012
The remaining amount of the current funding of £600,000 to be spent is £402,988.

Page 11

Pride in Place Programme           
2
An allocation of £5,000 towards the updating of the Transport Interchange feasibility
study was agreed at the Board meeting on 3 September. The actual costs will be
reported when available.
An allocation of up to £120,000 towards the following initiatives was agreed at the
Board meeting on 27 February 2026: -
 Project Delivery Group Support - £10,000 per project delivery group to
assist with community engagement/consultation activity.
 Community Clean-Up Days - a budget of up to £10,000 to offer grants of
£250 or £500 (depending on scale of activity) to support community clean-
ups.
 Community planting initiatives - a budget of £10,000 to offer grants of
£500-£1000 per applicant towards planting initiatives/enhancements to
pocket areas of greenspace.
 Community/Gala Days - a budget of £20,000 to support a programme of
local summer community gala days with grant of between £1000-£3000
being made available.
 Youth Engagement Budget – the establishment of a £5,000 Youth Choice
Fund allocated to the West Dunbartonshire Youth Council to administer
grants to support youth-based activity venue hire. 
 West Dunbartonshire Heritage Festival - a budget of up to £5000 to offer
grants to support community and third sector local history and heritage
organisations to participate/host events during the May heritage month.
An allocation will also be required to cover:
 additional resources to administer the funding i.e. Board secretariat (including
legal, procurement and other support); Programme Manager, etc.
 Website and other communication, marketing aspects as identified by the
Communications subgroup
Delivery funding
Delivery funding will be released in FY 26/27. The table below shows the schedule
of payments outlined in government guidance.

Page 12

Pride in Place Programme           
3
2. Outline of any issues/risks and how these are being managed
Timescales for release of delivery funding- Delivery funding will be released FY
26/27 (initially £360k of capital and £232k of revenue funding). The Board requires
to prioritise how available funding will be spent. This will tie in with the delivery of the
priority projects and the steps towards delivery being considered by the project
delivery groups. 
3. Outline of the main outputs expected before next meeting 
Agreement on the amount of capacity funding to be allocated towards: -
 Fund administration i.e., Board secretariat (including legal, procurement and
other support); Programme Manager, etc.
 Website and other communication, marketing aspects

Page 13

Pride in Place Programme           
4
4. What are the requirements to achieve the outcomes of this report?
Engage in the delivery process outside the Board meetings (e.g., through the project
delivery groups) to identify how delivery funding will be used and capacity funding
allocated. 
5. Recommendations    
It is recommended that the Board notes the financial information and consider how
much capacity funding is allocated for the activities noted in section 3 above.