Democracy Spraffa

Item 5 - Local Heating and Energy Efficiency Strategy 24 - 29

West Dunbartonshire Council · 21 February 2024
Back to Infrastructure, Regeneration & Economic Development Committee — 21 February 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer Regulatory & Regeneration
Infrastructure Regeneration and Economic Development Committee:
21 February 2024
Subject: Local Heat and Energy Efficiency Strategy (LHEES) 2024-2029
1. Purpose
1.1  The purpose of this report is to obtain approval for a draft Local Heat and
Energy Efficiency Strategy (LHEES) 2024-2029.
2. Recommendations
2.1  The Committee is invited to:
(i) Approve the draft Local Heat and Energy Efficiency Strategy 2024-2029 and
delegate authority to the Chief Officer Regulatory & Regeneration to deliver
against this plan;
(ii) Authorise commencement of public consultation of draft LHEES, following
approval; and
(iii)Authorise development of Local Heat and Energy Efficiency Delivery Plan
(LHEEDP) in line with the draft LHEES.
3. Background
3.1 Scottish Government has set ambitious targets that aim to ensure our homes
and buildings produce net zero carbon emissions and no longer contribute to
climate change or fuel poverty by 2045. To meet these targets almost all
homes, public buildings and businesses will need to increase their energy
efficiency and install zero emissions heating. A statutory order was passed by
the Scottish Government that requires all local authorities to develop Local
Heat and Energy Efficiency Strategies (LHEES) and Delivery Plans. Locally-
led planning, coordination and delivery of heat transitions across public and
private sectors will ensure the specific needs of communities are met and
LHEES will be the principal mechanism to develop this approach.
3.2 The LHEES for West Dunbartonshire will underpin an area-based, local
authority wide approach to heat and energy efficiency planning and delivery.
An LHEES sets out the strategic framework for decarbonising heat and
improving energy efficiency within buildings in West Dunbartonshire. This
Strategy is the first for West Dunbartonshire, and will be required to then be
updated at intervals of no more than five years. The strategic plan has been
ITEM 5

Page 2

developed by following Scottish Government’s LHEES methodology and is
therefore framed around the following considerations:
• Heat Networks;
• Off Gas Buildings;
• On Gas Buildings;
• Poor Building Energy Efficiency / Poor Building Energy Efficiency as a Driver
for Fuel Poverty; and
• Mixed Tenure, Mixed Use and Historic Buildings.
3.3 Delivering on their LHEESs is the principal way in which local authorities will
contribute to achieving the ambitious targets set out in Scotland's Heat in
Buildings Strategy. The Heat in Buildings Strategy (2021) sets the Scottish
Government’s vision for the future of heat in buildings, with targets for 2030
including:
• Emissions from homes and non-domestic buildings to fall by 68% (versus
2020);
• At least 22% of heat in buildings is to be directly supplied from renewable
sources;
• Where technically and legally feasible, and cost-effective, a large majority of
buildings should achieve a good level of energy efficiency; and
• Over 50,000 non-domestic buildings are converted to zero emissions heat.
3.4  LHEES Strategies should also consider how they contribute to meeting
statutory targets for greenhouse gas emissions reduction and fuel poverty,
including:
• Net zero emissions by 2045 and 75% reduction by 2030; and
• In 2040, as far as reasonably possible, no household in Scotland is in fuel
poverty.
3.5  West Dunbartonshire Council’s LHEES is further driven by local emissions
and fuel poverty ambitions set out in Climate Change Strategy and Climate
Change Action Plan. The Council aims to:
• Achieve ‘net-zero’ by 2045, with interim carbon reduction targets of 61% by
2030-31 and 87% by 2040-41;
• Continue to take action to reduce energy consumption and improve energy
and water efficiency in our buildings and across our operations;
• Continue to reduce energy demand and decarbonise heat supply in the
Clydebank area and Queens Quay heat network; and
• Further reduce energy consumption and improve energy efficiency in our
social housing and fuel poor households, ensuring fuel poverty and the
decarbonisation of housing are key to achieving a net zero carbon future.

Page 3

4. Main Issues
4.1 The aim of the LHEES document is to:
• Set out how the building stock needs to change to meet national and local
objectives, including achieving net zero carbon emissions in the building
sector, and the removing poor energy efficiency as a driver of fuel poverty;
• Identify strategic heat decarbonisation zones, and set out the principal
measures for reducing buildings emissions within each zone; and
• Prioritise areas for delivery, against national and local priorities.
4.2 West Dunbartonshire’s current building stock was modelled in terms of its
characteristics, energy efficiency and level of heat decarbonisation, split by
domestic and non-domestic properties to provide a baseline analysis.
Domestic building stock equates to a total of 93.6% of all the buildings within
the local authority, with a total count of 46,252, and a heat demand of 517.4
GWh per year (80% of the local authority’s total). Of the c.46,000 homes in
West Dunbartonshire:
• Almost half (44%) of domestic properties are small blocks of flats/converted
flats and blocks of flats; 23%, and 21% respectively, presenting greater
opportunities for more holistic energy efficiency and heat decarbonisation
interventions;
• Four in ten (40%) of all wall types remain uninsulated, including 15% cavity
wall construction, and 8% of lofts have less than 99mm of insulation, showing
potential for low regrets energy efficiency improvements (low regrets are
relatively low cost interventions, with relatively large benefits based on
projected future climate changes); and
• The vast majority of domestic properties (91%) use gas as their main heating
fuel, this is significantly higher than the national average (80%), and present a
greater heat decarbonisation challenge.
4.3  Within West Dunbartonshire the non-domestic building stock equates to a
total of 6.4% of all the buildings, with a total count of 3,147, and a heat
demand of 144.5 GWh per year (20% of the local authority total).
The c.3k non-domestic building stock within West Dunbartonshire have been
summarised by various characteristics, providing counts and heating demand
for each characteristic category:
• The majority of non-domestic buildings, 68%, are comprised of retail, office
and light manufacturing and account for 51% of heat demand across the local
authority area; and
• Over one third of buildings were built before 1919, which will like make it more
challenging to significantly increase energy efficiency.

Page 4

4.4 Data on the building stock of West Dunbartonshire has been analysed to
inform the selection of LHEES Strategic Zones, which are large areas of focus
for wide-scale delivery of heat decarbonisation solutions. Strategic Zones are
useful to understand the baseline performance, the scale of potential and
initial areas of focus, which can be used to inform the identification of Delivery
Areas and follow-on engagement.
Heat Network Strategic Zones
4.5 The LHEES has developed a series of Heat Network Zones, within which a
focus will be given to developing heat networks. In order to identify Heat
Network Zones, “heat-dense” areas have been identified – that is, areas in
which a heat network would be able to deliver a lot of heat with a small length
of pipework. As an initial indication of heat network viability, a linear heat
density threshold of 4 MWh/year/m has been used. Anchor loads are
buildings in heat networks with high heat demand and that would be simple to
connect to – for example public sector buildings like leisure centres and
schools. Heat Network Zones with a higher number of anchor loads –
buildings with high heat demand and simple connection potential, such as
leisure centres and schools - have been prioritised. Through stakeholder
engagement, fuel poverty has been identified as an ongoing focus for West
Dunbartonshire. Therefore, indicators of fuel poverty and extreme fuel poverty
have been used to identify Heat Network Zones within which there is a
greater number of properties in fuel poverty. Five Heat Network Zones ranked
highest for overall viability were selected for inclusion in the Strategy. A total
of seven Heat Network Strategic Zones were identified using this analysis and
further stakeholder consultation:
• Clydebank, including existing Queens Quay Heat Network;
• Golden Jubilee Hospital;
• Dalmuir;
• Littleholm;
• Kilbowie;
• Dumbarton; and
• Alexandria.
Clydebank Combined Heat Network Strategic Zone
4.6 The three most southerly networks of the five top ranking zones (Clydebank,
Littleholm and Kilbowie) were combined into a larger Combined Heat Network
Zone. This provides a larger area in the vicinity of the existing Queens Quay
heat network in which new heat networks, or extensions of existing, may be
delivered.
4.7 In addition to the three Zones identified through the LHEES analysis and
ranking exercise, the stakeholder consultation recommended the addition of
two other Heat Network Zones within the Combined Heat Network Zone; the
Golden Jubilee Hospital, and Dalmuir Flats. Radnor Park Kilbowie is also
highlighted within the Combined Heat Network Zone as an additional potential
area of expansion.

Page 5

4.8 Expansion options for the existing Queens Quay heat network were assessed
in an Outline Business Case (OBC) in 2022, which indicated initial economic
viability of a potential for expansion of the network from Clydebank to the
Golden Jubilee Hospital (currently being actively pursued) and Dalmuir Flats.
Another future expansion to Radnor Park, Kilbowie was also identified in this
study, although not an initial priority. Further expansion potential of the
network may be possible at Exxon and Carless site and will be reviewed as
the sites progress.
4.9 A heat network in this Combined Heat Network Zone could be supplied by the
existing Queens Quay Energy Centre, which currently houses two Water
Source Heat Pumps with a heating capacity of 2.65 MW each, and two
backup boilers (7 MW each), supplying flow temperatures of approximately
75°C, and return temperatures of 45°C. A cross-boundary extension of heat
networks eastwards into Glasgow is a further possibility following engagement
with Glasgow City Council. The case is strengthened by the presence of West
Dunbartonshire’s large area of interest for heat networks north of Clydebank,
on the local authority boundary.
Dumbarton Heat Network Strategic Zone
4.10 Analysis identifies Dumbarton as an area of strategic interest for Heat
Network Zone development due to a high heat demand of 23.1GWh/year,
with 10.2GWh/year from five anchor loads within the zone (St James Retail
Park; Morrisons Superstore; Dumbarton Football Stadium; Unit 23
Skatepark; Castle Street (Local Development Plan (LDP) Site). Two Local
Development Plan sites are located within the zone with a total of 305
residential units. Potential heat sources within the zone include: River Clyde
and Leven with possibility for Water Source Heat Pumps, and potential heat
resources at Energie Fitness; and Dumbarton Primary Substation. There
are constraints at this site, namely A814 Glasgow Road isolating St James
Retail Park from other four anchor loads and limiting any expansion North.
This site would require initial preliminary feasibility studies to determine
financial viability and identify low carbon heat opportunities in the area.
Alexandria Heat Network Strategic Zone
4.11 Due to a high proportion of publicly owned anchor loads, Alexandria has also
been identified as an area of strategic interest for Heat Network Zone
development. Four identified anchor loads (Vale of Leven District Hospital;
The Vale Centre GP Practice; Vale Of Leven Swimming Pool; Lomond
Galleries Shopping Centre) have a combined heat demand of 5.1 GWh/year;
8.8GWh/year total heat demand for the strategic zone. A Biomass Boiler is
present within the Vale of Leven District Hospital with greenspace South in
Christie Park potential for Ground Source Heat Pump boreholes. The zone is
also within an area of “Hot Sedimentary Aquifers”, which are potential good
sources of geothermal energy. Balloch Primary Substation is also a potential
heat resource. There are no major infrastructure constraints for heat network

Page 6

deployment within the identified zone. As with Dumbarton Heat Network
Strategic Zone, this site would require preliminary feasibility studies to
determine financial viability and certainty of low carbon heat opportunities.
Heat Network Strategic Zones Summary
4.12 The LHEES has identified a total of 7 Heat Network Strategic Zones, with a
combined heat demand of 162.6 GWh/year. Delivering these heat networks
could therefore deliver 19% of the total heat demand for West Dunbartonshire,
exceeding the 8% target for heat networks set nationally in the Heat Networks
(Scotland) Act.
Off Gas and On Gas Grid Strategic Zones
4.13 The LHEES Off Gas Grid and On Gas Grid Considerations focus on how to
decarbonise homes by installing heat pumps. Heat pumps operate most
efficiently in buildings that are well insulated and therefore can operate
heating systems at lower temperatures. For this reason, analysis of the impact
of the Off Gas Grid and On Gas Grid Considerations include energy efficiency
interventions that may need to be carried out to properties to be able to install
heat pumps. The analysis separates buildings into four different categories
depending on their “heat pump readiness” based on several different
characteristics of the building fabric:
• Heritage – listed buildings and those in conservation areas can be more
difficult to install heat pumps due to affordability of energy efficiency retrofit
and visual amenity of the Heat Pump unit;
• Building fabric - properties with insulated walls, loft insulation and double
glazing already installed are more readily suitable for heat pump retrofit; and
• Current heating fuel – properties already heated with low carbon systems are
excluded from the analysis. Properties heated by solid fuels, LPG and oil
indicate more immediate potential for heat pump retrofit.
4.14 Each Off Gas and On Gas Data Zone undergoes a second weighted ranking
process encompassing additional indicators relating to Fuel Poverty and the
Scottish Index of Multiple Deprivation (SIMD) which impact West
Dunbartonshire’s roll-out of retrofitting within the local authority. This analysis
indicates five top ranking Off Gas Strategic Zones where heat pump
installation could be considered:
• Singer and Clydebank South;
• Drumry;
• Leven;
• Drumry; and
• Clydebank East.
A further five On Gas Strategic Zones are also indicated as potentially suitable
areas to focus heat pump installation:

Page 7

• Lomond;
• Alexandria;
• Dumbarton;
• Bonhill; and
• Dalreoch.
Poor Building Energy Efficiency and Poor Building Energy Efficiency as
a Driver of Fuel Poverty Strategic Zones
4.15 These LHEES considerations aim to tackle poor building energy efficiency in
West Dunbartonshire by identifying Strategic Zones to focus rolling out retrofit
programmes that bring homes up to a higher standard. For properties in fuel
poverty, additional consideration is given to how poor energy efficiency may
be impacting the ability of occupants to afford heating their homes. Some
simple indicators of poor building energy efficiency and fuel poverty have
been used to identify properties with poor energy efficiency and poor energy
efficiency as a driver of fuel poverty in West Dunbartonshire:
• Uninsulated walls;
• Loft insulation <100mm;
• Fuel poverty: estimated fuel bill is >10% of income after housing costs;
• Extreme fuel poverty estimated fuel bill is >20% of income after housing costs;
and
• SIMD is also used to identify areas with other causes of deprivation.
4.16 Poor building energy efficiency is a recognised factor that can contribute to
fuel poverty, thus the removal of poor energy efficiency measures will impact
and contribute to Scotland’s statutory target of no households being in fuel
poverty as far as reasonably possible by 2040. The top ranking Poor Building
Energy Efficiency Strategic Zones where energy efficiency retrofit
programmes should be focused are:
• Singer and Clydebank South;
• Drumry;
• Alexandria;
• Clydebank; and
• Balloch;
Mixed tenure, mixed use and buildings in Conservation Areas Strategic
Zones
4.17 This LHEES consideration aims to highlight areas in which heat
decarbonisation may be difficult to deliver, due to ownership and tenure of the
properties, or the potential heritage impacts of installing heat pumps and
retrofitting buildings to higher levels of energy efficiency. This analysis covers
four main focus areas:
• Mixed tenure buildings;

Page 8

• Mixed use buildings;
• Listed buildings; and
• Conservation areas.
4.18 To enable the identification of the top five Data Zones for integration and
further interrogation within an LHEES Delivery Plan, all 121 Data Zones within
West Dunbartonshire have been ranked based upon aggregated counts of
properties within each indicators, with a weighting per indicator rank also
applied to generate an overall ranking. The Strategic Zones for Mixed Tenure,
Mixed Use and Conservation Areas are:
• Dumbarton;
• Dalreoch;
• Kilpatrick;
• Dumbarton; and
• Dumbarton.
Local Heat and Energy Efficiency Delivery Plan
4.19 Local Heat and Energy Efficiency Delivery Plan (LHEEDP) for West
Dunbartonshire will be developed over the coming months. This Delivery Plan
will cover the first five-year period of heat decarbonisation and energy
efficiency interventions, based on the priorities set out in the Strategy. This will
focus on projects at a more granular scale and Delivery Areas, which includes
smaller clusters of buildings and individual streets. Stakeholder engagement
is a key theme through LHEES, and as part of the Delivery Plan a Monitoring
and Evaluation Plan will be developed. This will set out how the Council will
approach engagement with stakeholder groups and may also include more
targeted awareness and engagement campaigns in the prioritised Strategic
Zones and Delivery Areas. The Council will ensure Delivery Areas and actions
set out in the LHEEDP will align with existing heat decarbonisation and energy
efficiency programmes and plans in the local authority, and can draw on
existing funding programmes and schemes. LHEEDP will be subject to a
further report to Committee prior to publication.
Challenges
4.20 The delivery of heat network zones and energy efficiency retrofit across the
entire local authority area is a vast undertaking and there are many
challenges that West Dunbartonshire Council and our businesses and
communities will have to address:
• Funding gap – financing large scale infrastructure and energy efficiency
interventions is expected to have colossal costs. Funding from Scottish
Government and other public funding sources needs to be maximised, private
sector funding needs to be leveraged in, and support is required for local

Page 9

businesses and communities to ensure they access available funding
streams;
• Viability – heat networks require electricity for operation, irrespective of the
renewable heat source, and many potential developments will only be viable
if electricity can be supplied directly from a renewable source;
• Retrofit – progress is being made in the retrofit of energy efficiency
measures, however a more holistic ‘whole home’ approach is needed to
maximise available funding and ensure a no regrets delivery;
• Skills gap – both within the Council and across the market there is a
significant gap in skills and knowledge. We need to consider training for staff
internally to ensure concerns about renewable technologies and procedures
for retrofit heat and energy efficiency measures are addressed. There is a
significant lack of skilled workforce within the green jobs sector and this
requires our influence to boost education and training in green industries
within the local authority area;
• Behaviour change – heat decarbonisation and energy efficiency retrofit can
change the way that homes and buildings operate to ensure efficiency. Public
acceptance of new technologies and behaviour change towards heating
controls and operating systems will need a clear focus; and
• Just Transition – when making evidence based decisions on the delivery of
LHEES, there needs to be an assurance that we do not adversely affect our
communities and businesses; the cost to achieve net zero should not burden
those least able to pay.
5. People Implications
5.1 There are no additional people implications related to this Strategy.
6. Financial and Procurement Implications
6.1 Scottish Government funding of £75,000 per year has been allocated to the
development of LHEES and has enabled the appointment of an LHEES
Officer and Consultancy for data analysis. There is scope to use this funding
for further engagement and feasibility studies to inform the development of the
Local Heat and Energy Efficiency Delivery Plan. More detailed costings will be
provided for specific projects in the LHEEDP, alongside plans to access
Scottish Government, private sector and external funding mechanisms.
6.2 There are no procurement issues in relation to the Strategy within this paper;
however each potential project identified during the development of the
Delivery Plan will require an appropriate procurement process.
7. Risk Analysis
7.1 The consultation process with partners and key stakeholders ensured that the
content of the strategy is appropriate, and through development of the
Delivery Plan risk will be assessed and managed.

Page 10

8. Environmental Sustainability
8.1 The Environmental Assessment (Scotland) Act 2005 sets a statutory
requirement for Scottish public bodies to carry out a Strategic Environmental
Assessment (SEA) of the expected environmental impacts of strategies
expected to have a significant environmental impact. At this stage, the
Strategy is in Draft and following consultation, a screening assessment will be
completed to determine the need for an SEA.
9 Equalities Impact Assessment (EIA)
9.1 The Strategy has been impact assessed and is relevant to the general
equality duty. The Strategy will assist with reducing inequality and has
potential to produce positive impacts. A range of actions in support of this are
noted in the EIA which is available as Appendix 2 to this report.
10. Consultation
10.1 An internal stakeholder consultation process across Council services was
undertaken to obtain feedback the baselining data and proposed Strategic
Zones. Finalised Delivery Areas were interrogated at an external stakeholder
consultation with key contributors including: RSLs; NHS; Police Scotland;
Scottish Water; and low carbon heating specialists. The draft Strategy was
also presented to Chief Officers for initial comment.
10.2 Following the approval of the draft Strategy, a full public consultation will
commence over a six week period. The Consultation plan will be developed to
ensure meaningful and targeted engagement with groups and organisations
of interest through surveys and social media. Comments from the consultation
will be included in revisions to the final Strategy.
11. Strategic Assessment
11.1 The Local Heat and Energy Efficiency Strategy 2024-2029 provides a clear
strategic area-based, local authority wide approach to heat and energy
efficiency planning and delivery. The Strategy will help determine how and
where we focus our resources and to achieve our ambitious net zero and fuel
poverty aims. It responds to various local, regional and national policies and
strategies. These include:
• West Dunbartonshire - Council Strategic Plan;
• West Dunbartonshire - Climate Change Strategy;
• Scottish Government - Heat in Buildings Strategy (2021);
• Scottish Government – Tackling Fuel Poverty in Scotland: A Strategic
Approach (2021); and
• Scottish Government – Heat Networks (Scotland) Act 2021.

Page 11

Alan Douglas
Chief Officer, Regulatory & Regeneration
Date: 14 February 2024
Person to Contact: Gillian McNamara, Economic Development Manager,
Council Offices, Church Street, Dumbarton, G82 1QL.
T: 07815705769
Email: Gillian.mcnamara@west-dunbarton.gov.uk
Appendices: Appendix 1 - Glossary
Appendix 2 - EIA- Local Heat and Energy Efficiency
Strategy (LHEES) 2024-2029
Appendix 3 - Local Heat and Energy Efficiency Strategy
(LHEES) 2024-2029 Draft
Wards Affected: All Wards