WEST DUNBARTONSHIRE COUNCIL
ITEM 9 - APPENDIX 7GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 7
Budget Forecast
Spend
£000 £000 % £000 £000 %
1
Project Life Financials 2,230 2,222 100% 2,230 0 0%
Current Year Financials 2,230 731 33% 2,230 0 0%
Project Description
Project Manager Michelle Lynn
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-24 31-Mar-24
2
Project Life Financials 87 79 91% 79 (8) -9%
Current Year Financials 79 68 86% 79 0 0%
Project Description
Project Manager Steven Milne
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-24
3
Project Life Financials 450 193 43% 193 (258) -57%
Current Year Financials 0 0 0% 0 0 0%
Project Description
Project Manager Steven Milne
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
Anticipated Outcome
Credit note received and project closed
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This project has been completed. However a credit is outstanding and should be received this financial year.
Mitigating Action
Officers will continue to peruse the credit note
Zero Carbon
Zero Carbon
Anticipated Outcome
Projects delivered to required specifications
Building Upgrades and H&S - lifecycle & reactive building upgrades
Lifecycle and reactive building upgrades.
Planned End Date Forecast End Date
Anticipated Outcome
Replace existing main hall Air Handling unit at Clydebank Town Hall.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works are currently being undertaken to upgrade controls in Clydebank Town Hall.
Mitigating Action
None Required.
Replace existing main hall Air Handling unit at Clydebank Town Hall
Replace existing main hall Air Handling unit at Clydebank Town Hall.
31 October 2023
Budget Details
Project Life Financials
Spend to Date Variance
Main Issues / Reason for Variance
Works progressing
Mitigating Action
None required at this time

Page 2

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 7
Budget Forecast
Spend
£000 £000 % £000 £000 %
Building Upgrades and H&S - lifecycle & reactive building upgrades
31 October 2023
Budget Details
Project Life Financials
Spend to Date Variance
4
Project Life Financials 22,213 22,100 99% 22,100 (113) -1%
Current Year Financials 19,984 1,596 8% 19,984 0 0%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-25 31-Mar-25
5
Project Life Financials 478 0 0% 478 0 0%
Current Year Financials 478 0 0% 478 (0) 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
6
Project Life Financials 221 221 100% 221 0 0%
Current Year Financials 8 7 87% 8 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 03-Apr-21 31-Mar-24
7
Project Life Financials 25 25 100% 25 0 0%
Current Year Financials 6 0 0% 6 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
8
Project Life Financials 485 485 100% 485 0 0%
Current Year Financials 430 0 0% 430 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Main Issues / Reason for Variance
Projects identified with a number commenced.
Mitigating Action
None required at this time.
Anticipated Outcome
completion of project on time and on budget
Anticipated Outcome
Large bins provided for high traffic areas
Nature Restoration Fund
Nature resource for Faifley Community
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project complete.
Mitigating Action
None required at this time.
Large bins for high traffic areas (pilot)
Supply and install extra large litter bins as a pilot project within hotspot problem areas.
Main Issues / Reason for Variance
Project works complete.  Retentions to be paid.
Mitigating Action
None required at this time.
Anticipated Outcome
New all weather tennis courts.
Sports Facilities Upgrades - Argyll Park - Construction of 3 All Weather Tennis Courts
Project is part of wider investment in sporting facilities and is dependent on match funding from Sports Scotland. Agreement
in principle to wider WDC strategic priorities.
Planned End Date Forecast End Date
Mitigating Action
None required at this time.
Anticipated Outcome
Better access with parks, cemeteries and open spaces.
Public non-adopted paths and roads
Upgrades to drainage and lighting to enhance the lifespan of paths and roads within  facilities in public parks, cemeteries
and civic spaces.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Full budget committed
Anticipated Outcome
Projects delivered on budget
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Artizan Masterplan approved by IRED in Nov 2023, deigns progressing as planned.
Mitigating Action
None available at this time
LUF
Year one LUF spend includes acquisition cost of Artizan Centre, and design development for Glencairn House and
Connecting Dumbarton

Page 3

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 7
Budget Forecast
Spend
£000 £000 % £000 £000 %
Building Upgrades and H&S - lifecycle & reactive building upgrades
31 October 2023
Budget Details
Project Life Financials
Spend to Date Variance
9
Project Life Financials 561 0 0% 561 0 0%
Current Year Financials 561 0 0% 561 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
10
Project Life Financials 60 60 100% 60 0 0%
Current Year Financials 5 0 0% 5 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
11
Project Life Financials 2,277 1,447 64% 1,447 (830) -36%
Current Year Financials 650 0 0% 650 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
12
Project Life Financials 24,658 5,198 21% 27,224 2,565 10%
Current Year Financials 2,195 35 2% 2,195 (0) 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
13
Project Life Financials 84 7 8% 84 0 0%
Current Year Financials 84 7 8% 84 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Anticipated Outcome
Intention is to complete works within budget.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Ongoing lighting works to be completed by 31/3/24.
Mitigating Action
None available at this time.
Mitigating Action
None required at this time.
Anticipated Outcome
Intention is to complete various surfacing works by the end of March 2024.
Street lighting and associated electrical infrastructure
WDC is responsible for the maintenance of 18,000 street lighting columns and associated illuminated signs and bollards. 
This budget is required for this infrastructure.
Infrastructure - Roads
Infrastructure - Roads.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Roads Operations have completed an extensive surfacing program and  measurement claims received have been processed. A programme of structural patching is
ongoing.
Main Issues / Reason for Variance
For Bus Infrastructure a program of works Is being developed. For A8014 Kilbowie Rd works are being planned awaiting further feedback from Utilities, For A814
Congestion measures further development & expansion of vehicle detection systems and for Balloch P & R Consultants are appointed, agreement in principal with
Network Rail & further investigatory works are planned.
Mitigating Action
None required at this time.
Anticipated Outcome
Improve accessibility to Public Transport and improve journey time reliability.
FALSE
Strathclyde Partnership for Transport - Bus, cycling and walking infrastructure improvements.
Planned End Date Forecast End Date
Mitigating Action
None required at this time.
Anticipated Outcome
Traffic calming to be installed in Dumbarton East.
Turnberry Homes - traffic calming/ management at Turnberry housing development off Castle Road
Funding has been received from Turnberry Homes and will be used to introduce traffic calming and traffic management
measures to mitigate the impact of additional traffic accessing the housing development off Castle Road, Dumbarton.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Speed Humps to be programmed.
Anticipated Outcome
To improve connectivity and enhanced Cycling routes within West Dunbartonshire.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works for a footway/cycleway improvement at Bellsmyre Avenue are now complete. Dropped kerbs at various locations are underway. Proposed further works to
cycleways due to commence late 2023.
Mitigating Action
None required at this time.
Cycling, Walking and Safer Streets
Introduction of enhanced walking routes and traffic calming schemes to introduce safer streets within West Dunbartonshire.

Page 4

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 7
Budget Forecast
Spend
£000 £000 % £000 £000 %
Building Upgrades and H&S - lifecycle & reactive building upgrades
31 October 2023
Budget Details
Project Life Financials
Spend to Date Variance
14
Project Life Financials 97 97 100% 97 (0) 0%
Current Year Financials 29 20 70% 29 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
15
Project Life Financials 134 134 100% 134 0 0%
Current Year Financials 134 0 0% 134 0 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
16
Project Life Financials 81 80 99% 81 0 0%
Current Year Financials 75 9 12% 75 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
17
Project Life Financials 300 300 100% 300 0 0%
Current Year Financials 26 0 0% 26 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
18
Project Life Financials 1,000 1,000 100% 1,000 0 0%
Current Year Financials 878 388 44% 878 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
Mitigating Action
None required.
Anticipated Outcome
Improvement to pavements.
Pavement improvements
Various pavement improvement projects.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Footway resurfacing works in Longden street (Whitecrook), Sycamore Drive (Parkhall) & Beechwood Drive are complete with further projects to be programmed.
Main Issues / Reason for Variance
Upgrade of obsolete equipment will be completed by 31/3/24.
Mitigating Action
None required.
Anticipated Outcome
To upgrade traffic signals.
Anticipated Outcome
To purchase equipment.
Traffic Signal Upgrades
Upgrade Traffic Signals
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
New plant has been purchased.
Mitigating Action
None required.
Roads Plant
Purchase of Roads plant and equipment.
Main Issues / Reason for Variance
New funding which will be allocated to appropriate projects.
Mitigating Action
None required at this time.
Anticipated Outcome
Projects delivered on time and on budget
Roads Safety
Roads Safety
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Detailed design underway. Design will be completed 24/25
Mitigating Action
None available at this time.
Anticipated Outcome
Intention is to complete works within budget.
Depot Improvement Works
Improvement of WDC Roads Depot.
Planned End Date Forecast End Date

Page 5

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 7
Budget Forecast
Spend
£000 £000 % £000 £000 %
Building Upgrades and H&S - lifecycle & reactive building upgrades
31 October 2023
Budget Details
Project Life Financials
Spend to Date Variance
19
Project Life Financials 179 80 45% 160 (19) -10%
Current Year Financials 9 0 0% 9 0 0%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
20
Project Life Financials 79 79 100% 79 0 0%
Current Year Financials 79 0 0% 79 0 0%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
21
Project Life Financials 20 20 100% 20 0 0%
Current Year Financials 20 0 0% 20 0 0%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Main Issues / Reason for Variance
Project underway
Mitigating Action
None Required.
Anticipated Outcome
Project delivered within  budget.
Anticipated Outcome
Project delivered within  budget.
River bank erosion repair - Levenhowe
River bank erosion repair in the Levenhowe area
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
New Funding - Project in progress.
Mitigating Action
None Required.
Smarter Choices
Smarter Choices, Smarter Places
Main Issues / Reason for Variance
Complete
Mitigating Action
None Required.
Anticipated Outcome
Project delivered within  budget.
Replacement of compactors at Dalmoak civic amenity site
The purchase of 2 compactors for the Council civic amenity site at Dalmoak.
Planned End Date Forecast End Date

Page 6

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 7
Budget Forecast
Spend
£000 £000 % £000 £000 %
Building Upgrades and H&S - lifecycle & reactive building upgrades
31 October 2023
Budget Details
Project Life Financials
Spend to Date Variance
22
Project Life Financials 150 150 100% 150 0 0%
Current Year Financials 150 0 0% 150 0 0%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-25
23
Project Life Financials 59 59 100% 59 0 0%
Current Year Financials 59 43 74% 59 (0) 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Anticipated Outcome
Project delivered within  budget.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project Complete
Mitigating Action
None Required.
Mitigating Action
None Required.
Anticipated Outcome
Project delivered within  budget.
Whitecrook Tennis Court Up-grade
Whitecrook Tennis Court Up-grade
Park Improvements and Multi Games Area - Goldenhill Park
Park Improvements and Multi Games Area - Goldenhill Park
Planned End Date Forecast End Date
Main Issues / Reason for Variance
MUGA due for commencement in February and environmental improvements complete