Page 1

Agenda
Infrastructure, Regeneration and
Economic Development Committee
Date:  Wednesday, 7 February 2024
___________________________________________________________________
Time:  10:00 a.m. 
___________________________________________________________________
Format:  Hybrid meeting
___________________________________________________________________
Contact:  Nicola Moorcroft, Committee Officer
nicola.moorcroft@west-dunbarton.gov.uk
committee.admin@west-dunbarton.gov.uk
Dear Member
Please attend a meeting of the Infrastructure, Regeneration and Economic
Development Committee as detailed above. 
Members will have the option to attend the meeting remotely, or in person, at the Civic
Space, 16 Church Street, Dumbarton, G82 1QL.
The business is shown on the attached agenda.
Yours faithfully
PETER HESSETT
Chief Executive
Page 1

Page 2

Distribution:-
Councillor David McBride (Chair)
Councillor Jonathan McColl
Councillor Michelle McGinty
Councillor John Millar 
Councillor Lawrence O’Neill (Vice Chair)
Councillor Lauren Oxley
Councillor Chris Pollock
Councillor Martin Rooney
Councillor Gordon Scanlan
Councillor Hazel Sorrell
Councillor Clare Steel
Councillor Sophie Traynor
All other Councillors for information
Chief Executive
Chief Officer – Regulatory and Regeneration
Chief Officer – Roads and Neighbourhood
Chief Officer – Resources
Date of Issue: 25 January 2024
Audio Streaming
Audio recordings of the meeting (including the attendance or contribution of any party
participating or making a contribution) will be published on the Council’s website and the
Council’s host’s webcast/audio stream platform.
You should be aware that the Council is a Data Controller under the General Data
Protection Regulation.  Data collected during this audio stream will be retained in
accordance with the Council’s Privacy Notice* and Retention Schedules including, but not
limited to, for the purpose of keeping historical records and making those records available
via the Council’s internet site.
*http://www.west-dunbarton.gov.uk/privacy/privacy-notice/
Page 2

Page 3

INFRASTRUCTURE, REGENERATION AND ECONOMIC
DEVELOPMENT COMMITTEE
WEDNESDAY, 7 FEBRUARY 2024
AGENDA
1 STATEMENT BY CHAIR – AUDIO STREAMING
The Chair will be heard in connection with the above.
2 APOLOGIES
3 DECLARATIONS OF INTEREST
Members are invited to declare if they have an interest in any of the items of
business on this agenda and the reasons for such declarations.
4 RECORDING OF VOTES
The Committee is asked to agree that all votes taken during the meeting be done by
roll call vote to ensure an accurate record.
5 OPEN FORUM
The Committee is asked to note that no open forum questions have been
submitted by members of the public.
6 MINUTES OF PREVIOUS MEETING 7 – 12
Submit for approval as a correct record, the Minutes of the Meeting of the
Infrastructure, Regeneration and Economic Development Committee held on 1
November 2023.
7 CLYDEBANK: LONG TERM PLAN FOR TOWNS FUND  13 – 21
Submit report by the Chief Officer – Regulatory and Regeneration, seeking approval
for the establishment of a Clydebank Town Board including appointment of Chair and
Deputy, and procurement of services to help the Council develop and deliver a Long-
Term Plan and Investment Plan to fulfil the requirements of the Long-Term Plan for
Towns Fund.
Page 3

Page 4

8 COLLECTION, HAULAGE, PROCESSING, TREATMENT AND 23 – 26
DISPOSAL OF BULKY WASTE 
Submit report by Chief Officer – Roads and Neighbourhood, advising that the award
of the contract for the Collection, Haulage, Processing, Treatment and Disposal of
Bulky Waste, was approved on 15 December 2023 by the Chief Officer – Roads and
Neighbourhoods, after consulting with the Convenor of the Infrastructure,
Regeneration and Economic Development Committee (IRED).
9 INFRASTRUCUTRE, REGENERATION AND ECONOMIC    27 – 56
DEVELOPMENT BUDGETARY CONTROL REPORT 2023/24
TO PERIOD 7 (31 OCTOBER 2023)
Submit report by the Chief Officer – Resources providing an update on the financial
performance to 31 October 2023 (Period 7) of those services under the auspices of
the Infrastructure, Regeneration and Economic Development Committee (IRED). 
10 DISPOSAL OF 53A GEORGE STREET, BONHILL G83 9JQ 57 – 63
Submit report by Chief Officer – Resources seeking approval for the Council to enter
into a contract for the disposal of 53A George Street, Bonhill G83 9JQ 
to Sava Estates Ltd.
11 SALE OF 7 BANK STREET, ALEXANDRIA G83 0NG 65 – 71
Submit report by Chief Officer – Resources seeking approval for the Council to enter
into a contract for the disposal of 7 Bank Street, Alexandria G83 0NG to Daveed
Malik.
12 SALE OF LAND ADJACENT TO 193 DUMBARTON ROAD, 73 – 76
CLYDEBANK
Submit report by Chief Officer – Resources seeking approval for the sale of land at
Dumbarton Road, Clydebank to David Hamilton.
13 SERVITUDE OF LAND ADJACENT TO DUNTIGLENNAN FIELDS  77 – 80
DUNTOCHER
Submit report by Chief Officer – Resources seeking approval to enter into a
Servitude Agreement of land adjacent to Duntiglennan Fields, Duntocher, with BDW
Trading Limited, trading as Barratt West Scotland (Barratt).
14/
Page 4

Page 5

14 LEASE OF THE HUB, KILBOWIE ROAD, CLYDEBANK  81 – 84
Submit report by Chief Officer – Resources seeking approval for the Council to
transfer The HUB, Kilbowie Road, Clydebank (the Hub) to Dynamite Gymnastics
Club.
15 LEASE OF KNOWES SPORTS PAVILION, FAIFLEY   To Follow
Submit report by Chief Officer – Resources regarding the above.
Page 5

Page 6

Page 6

Page 7

INFRASTRUCTURE, REGENERATION AND ECONOMIC DEVELOPMENT
COMMITTEE
At a Hybrid Meeting of the Infrastructure, Regeneration and Economic Development
Committee held in the Civic Space, 16 Church Street, Dumbarton on Wednesday, 
1 November 2023 at 10.00 a.m.
Present: Councillors David McBride, Jonathan McColl, Michelle McGinty,
John Millar, Lawrence O’Neill, Lauren Oxley, Chris Pollock,
Martin Rooney, Gordon Scanlan, Hazel Sorrell, Clare Steel and
Sophie Traynor.
Attending: Gail Macfarlane, Chief Officer – Roads and Neighbourhood;
Laurence Slavin, Chief Officer – Resources; Alan Douglas, Chief
Officer – Regulatory and Regeneration; Craig Jardine,
Corporate Asset Manager; Michelle Lynn, Assets Coordinator;
Gillian McNamara, Economic Development Manager; Pamela
Clifford, Planning, Building Standards and Environmental Health
Manager; Nicola Moorcroft and Ashley MacIntyre, Committee
Officers.
Councillor David McBride in the Chair
STATEMENT BY CHAIR – AUDIO STREAMING
Councillor David McBride, Chair, advised that the meeting was being audio streamed
and broadcast live to the internet and would be available for playback.
DECLARATIONS OF INTEREST
It was noted that there were no declarations of interest in any of the items of
business on the agenda.
RECORDING OF VOTES
The Committee agreed that all votes taken during the meeting be done by roll call
vote to ensure an accurate record.
OPEN FORUM
The Committee noted that no open forum questions had been submitted by
members of the public.
ITEM 6
Page 7

Page 8

MINUTES OF PREVIOUS MEETING 
The Minutes of Meeting of the Infrastructure, Regeneration and Economic
Development Committee held on 16 August 2023 were submitted and approved as a
correct record. 
REGULATORY AND REGENERATION DELIVERY PLAN 2023/24 - ECONOMIC
DEVELOPMENT MID-YEAR PROGRESS REPORT 
A report was submitted by the Chief Officer – Regulatory and Regeneration, setting
out the mid-year progress of the 2023/24 Plan in relation to Economic Development. 
After discussion, the Committee agreed to note the progress achieved. 
ROADS AND NEIGHBOURHOOD DELIVERY PLAN 2023/24 MID-YEAR
PROGRESS REPORT 
A report was submitted by the Chief Officer – Roads and Neighbourhood, setting out
the mid-year progress of the Roads and Neighbourhood Delivery Plan 2023/24. 
After discussion and having heard the Chief Officer – Roads and Neighbourhood and
the Corporate Asset Manager in further explanation and in answer to Members’
questions, the Committee agreed to note the progress achieved. 
SALE OF 134 A&B, MAIN STREET, ALEXANDRIA G83 0NZ 
A report was submitted by the Chief Officer – Resources seeking approval for the
Council to dispose of 134 A&B Main Street, Alexandria (the Property) to Stephen
Mahan and James Sartain. 
After discussion the Committee agreed:- 
(1) to approve the disposal of 134 A&B Main Street, Alexandria to Stephen
Mahan and James Sartain for a figure of £45,500; 
(2) to authorise the Chief Officer – Resources to conclude negotiations; and 
(3) to authorise the Chief Officer – Regulatory and Regeneration to conclude the
transaction on such conditions as considered appropriate. 
ECONOMIC DEVELOPMENT STRATEGY ACTION PLAN 2022-2027 
A report was submitted by the Chief Officer – Regulatory and Regeneration,
providing an update of work undertaken during 2022/23 to deliver the West
Dunbartonshire Economic Development Strategy 2022-2027 and to obtain approval
for a new Economic Development Strategy Action Plan for the period 2022-2027.
Page 8

Page 9

After discussion and having heard the Chief Officer – Regulatory and Regeneration,
and the Economic Development Manager in further explanation and in answer to
Members’ questions, Councillor McBride moved that the Committee:- 
(1) note the work undertaken during 2022/23 to deliver the West Dunbartonshire
Economic Development Strategy 2022-2027; and 
(2) approve the Economic Development Strategy Action Plan 2022-2027 and
delegate authority to the Chief Officer - Regulatory and Regeneration to
deliver against this plan. 
As an amendment, Councillor Jonathan McColl moved: 
With regards to action CCS-AP/22-23/002, Develop a Renewable Energy
strategy for west Dunbartonshire, on page 63 of the Report, given the legal
and moral responsibility we have to reduce West Dunbartonshire’s carbon
footprint, the Committee asks the Chief executive to work with senior Officers
to identify how this important work can be resourced. 
If a Committee decision is required to approve any future actions, a separate
report will come back to the next IRED Committee, otherwise members would
be updated of progress through normal reporting. 
Councillor McBride accepted the amendment to his motion. 
DEVELOPMENT STRATEGY FOR THE ARTIZAN CENTRE 
A report was submitted by the Chief Officer – Regulatory and Regeneration, seeking
approval for the proposed Artizan Redevelopment Masterplan, submission of an
application for a Planning Permission in Principle for the site, and delivery of the
Phase 1 of the redevelopment. 
After discussion and having heard the Chief Officer – Regulatory and Regeneration,
the Economic Development Manager and the Planning, Building Standards and
Environmental Health Manager, in further explanation and in answer to Members’
questions, the Committee agreed:- 
(1) to note the progress made on Artizan redevelopment proposals; 
(2) to approve the Masterplan for the Artizan redevelopment and that it would
form an application for the Planning Permission in Principle, to be submitted
later in 2023; 
(3) to authorise development, procurement and delivery of Phase 1 of the
redevelopment works, including submission of a detailed planning application
and appointment of one or more principal contractors for the works; and 
(4) to note that the existing tenants would continue to be supported as part of the
strategy.
Page 9

Page 10

INFRASTRUCTURE, REGENERATION AND ECONOMIC DEVELOPMENT
BUDGETARY CONTROL REPORT 2023/24 TO PERIOD 5 (31 AUGUST 2023) 
A report was submitted by the Chief Officer – Resources providing an update on the
financial performance to 31 August 2023 (Period 5) of those services under the
auspices of the Infrastructure, Regeneration and Economic Development Committee
(IRED). 
After discussion and having heard the Chief Officer – Roads and Neighbourhood, the
Economic Development Manager and the Corporate Asset Manager in further
explanation and in answer to Members’ questions, the Committee agreed:- 
(1) to note the contents of this report which showed the revenue budget forecast
to overspend against budget by £1.051m (7.48%) at the year-end taking into
account that this is subject to change, and 
(2) to note the net projected annual position in relation to relevant capital projects
which highlighted a projected variance of £8.746m (11.68%) due to re-
profiling. 
PLACE BASED INVESTMENT PROGRAMME FUND 
A report was submitted by the Chief Officer – Regulatory and Regeneration, seeking
approval for the funding allocation for Years Two (22/23) to Five (25/26), of the 5
year Place Based Investment Programme Fund (PBIP) to projects in Alexandria and
wider West Dunbartonshire Council area. 
After discussion and having heard the Economic Development Manager in further
explanation and in answer to Members’ questions, the Committee agreed:- 
(1) to note the progress on development and delivery of the projects arising from
the Alexandria Masterplan for which PBIP was allocated; 
(2) to approve the 2024/25 allocation of £0.471m and a proportion of the 2025/26
allocation, with an estimated total of £1.149m over three years to projects
arising from the Alexandria Masterplan; 
(3) to approve the 2023/24 allocation of £0.471m of Council’s Place Based
Investment Programme to Community Grants; 
(4) to note that the remaining 2022/23 allocation of £0.310m would go towards
the development of an activity centre in Clydebank; 
(5) to note that recommendations on the allocation of the remaining 2025/26
funding would be made in a future report, and would be subject to
circumstances and priorities near the time; 
(6) to authorise the Chief Officer – Regulatory and Regeneration to conclude on
behalf of West Dunbartonshire Council, the award of the contract(s) to deliver
Page 10

Page 11

the Alexandria projects in line with Contract Standing Orders and the
Financial Regulations; and 
(7) to authorise the Chief Officer – Regulatory and Regeneration to award Grants
to eligible Community groups following a formal selection process. 
LEASE OF GLENHEAD COMMUNITY CENTRE DUNTIGLENNAN ROAD,
DUNTOCHER, CLYDEBANK G81 6HF 
A report was submitted by the Chief Officer – Resources seeking approval for the
transfer of Glenhead Community Centre to the Antonine Sports Centre (a charitable
organisation) which will manage the facility for the benefit of the local community in
the form of a lease arrangement. 
After discussion and having heard the Assets Coordinator in further explanation and
in answer to Members’ questions, Councillor McBride moved that the Committee:- 
(1) note that following the issue of the papers for the meeting, an erratum notice
had been issued which contained a revised version of the report; 
(2) note the content of the revised report; 
(3) approve the lease of Glenhead Community Centre to the Antonine Sports
Centre until 30 June 2056 at a rental of £24,000 per annum; 
(4) authorise the Chief Officer – Resources to conclude negotiations; and 
(5) authorise the Chief Officer – Regulatory and Regeneration to conclude the
transaction on such conditions as considered appropriate. 
Councillor Scanlan submitted the following amendment, to Councillor McBride’s
motion: 
Committee agrees the recommendations and notes that the Antonine Centre
have indicated they may be able to accommodate the After School Club
during term time and this is something the after school club would be
interested in exploring. Council agrees to facilitate discussions between the
Antonine Centre and the After School Club, with a view to making a mutually
agreeable arrangement. 
On a roll call vote being taken, 5 Members voted for the amendment, namely
Councillors McColl, Oxley, Pollock, Scanlan and Traynor and 7 Members voted for
the motion namely, Councillors McBride, McGinty, Millar, O’Neill, Rooney, Sorrell
and Steel.  The motion was accordingly, declared carried. 
Page 11

Page 12

THE REDEVELOPMENT AND MAJOR REFURBISHMENT OF GLENCAIRN
HOUSE 
A report was submitted by the Chief Officer – Resources seeking approval to
conclude the award of the contract for the redevelopment and major refurbishment of
Glencairn House. 
After discussion and having heard the Assets Coordinator in further explanation, the
Committee agreed to authorise the Chief Officer – Regulatory and Regeneration to
conclude, on behalf of West Dunbartonshire Council (the Council), the award of the
contract for the redevelopment and major refurbishment of Glencairn House, to one
the five successful shortlisted contractors invited to tender, subject to such tender
being within the budget figure of £7.2m. 
The meeting closed at 11.21 a.m.
Page 12

Page 13

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer (Regulatory & Regeneration)
Infrastructure, Regeneration & Economic Development Committee
7 February 2024
Subject: Clydebank: Long - Term Plan for Towns Fund
1 Purpose
1.1 This report seeks Members’ approval for the establishment of a Clydebank
Town Board including appointment of Chair and Deputy, and procurement of
services to help the Council develop and deliver a Long-Term Plan and
Investment Plan to fulfil the requirements of the Long-Term Plan for Towns
Fund.
2 Recommendations
2.1 It is recommended that Committee:
(i) Notes that Clydebank has been selected by UK Government as one of
seven towns in Scotland to receive £20m of Long-Term Plan for Towns
Fund split into 75% capital funding and 25% revenue funding;
(ii) Notes that the Council received £50k capacity funding in 23/24 and will
receive further £200k in 24/25 to support the development of the Long-
Term and Investment Plans;
(iii) Notes the summary of the guidance for the Fund provided by UK
Government Department of Levelling Up Housing and Communities;
(iv) Approves the establishment of a Clydebank Town Board with the range
of Members suggested at 4.4;
(v) Invites the meeting of Council on 27th March 2024 to nominate two
elected members to the Clydebank Town Board;
(vi) Approves the appointment of Liz Connolly, Principal of West College
Scotland as Chairperson and delegates authority to the Chief Officer of
Regulatory and Regeneration to appoint a Deputy for the Town Board;
(vii) Delegates authority to the Chief Officer of Regulatory and
Regeneration to procure and appoint consultants required to produce
the Long-Term Plan and Investment Plan.
3 Background
ITEM 7
Page 13

Page 14

3.1 Clydebank is one of seven Scottish towns selected to receive £20m of Long-
Term Plan for Towns grant funding from UK Government, selected on the
basis of their criteria and methodology. In Step 1 Local authorities were
selected according to levelling up need, the population size of Built-Up Areas
in the local authority as well as geographic spread. Levelling Up metrics
covered skills, pay, productivity and health. In Step 2 a population threshold
was applied, for Built-Up Areas of population between 20,000 and 100,000,
and all local authorities without eligible Built-Up Areas were excluded. In Step
3 each Built-Up Area with a population between 20,000 and 100,000 within
each local authority was ranked by the Index of Multiple Deprivation for each
nation (SIMD for Scotland) and the most deprived Built-Up Area within each
local authority was then selected.
3.2 In December 2023, the UK Government’s Department of Levelling Up,
Housing and Communities (DLUHC) published guidance for local authorities
to draw down the £20m investment, 75% of which will be capital funding with
the remaining 25% revenue funding. The guidance includes requirements for
local authorities to set up suitable governance arrangements including a
locally-led Town Board and independent Chair, and provides examples of
where the funding can be invested. To unlock the funding, a Long-Term Plan
will have to be developed by the Town Board, and approved by DLUHC.
Council approval will be required for projects that interact with Council’s
responsibilities such as Planning, and a need for revenue funding that goes
beyond the life of the Plan. In addition to Council responsibilities in respect of
the specifics of the projects, it is proposed that a report on the Town Board
and progress against the Plan is regularly reported to IRED for information.
3.3 Separate capacity funding will be provided to support governance of the fund.
The Council has already received £50,000 to cover the upfront costs of setting
up a Town Board. Further £200,000 in April 2024 is expected to support the
development of the Long-Term Plan, and related administration and
management costs
4 Main Issues
4.1 The Long-Term Plan for Towns Fund takes a new endowment-style approach.
This means that funding is released over a 7-year period and local authorities
have the flexibility to spend it over 10 years. The local authority remains the
accountable body for funding and executing plans. The Town Board,
supported by the local authority and working closely with local people, will be
responsible for developing the Long-Term Plan.
4.2 Town Boards should be chaired by an independent Chair, invited by the Local
Authority. The guidance states that the Chair should be a respected figure in
the community with an obvious passion for the place.  Examples suggested in
the guidance include a philanthropist, the head of a Further Education
College, a Director for the NHS Board or Trust or a director of a football club.
Elected representatives, such as MPs, MSPs, or local councillors are exempt
Page 14

Page 15

from chairing the Town Board. The Town Board should comply with lead
Council governance and finance arrangements.
4.3 It is recommended that Committee approves the appointment of Liz Connolly
as Chair, in her capacity as Principal of West College Scotland. Liz is a
respected member of the wider community of interests, and has confirmed her
willingness and enthusiasm for the role.
4.4 Board Members must include the local MP, a senior Police representative and
a maximum of two Elected Members, and can include a local MSP. It is
proposed that for Clydebank Town Board, in addition to previously mentioned
participants, representatives from the Chamber of Commerce, West
Dunbartonshire Council for Voluntary Services, Golden Jubilee Hospital, West
of Scotland College, Community Council, Clyde Shopping Centre and other
major local businesses, and local community partners. Four senior Council
officers will also be asked to participate on the Board, to include the Chief
Executive and the Chief Officer: Regulatory and Regeneration, together with
the option to nominate substitutes in their absence.
4.5 The guidance sets out the timescales for the Fund governance. By 1 April
2024 a Town Board should be established, including appointment of the
Chair. By 1 August 2024 the Town Board, supported by the Council should
submit their Long -Term Plan which will be assessed and approved by UK
Government. It has been acknowledged that Scottish Councils operate with
different recess periods to their English counterparts and these timescales
may be adjusted to better suit the Scottish context. 
4.6 The Long-Term Plan will comprise a 10-year vision which clearly identifies the
term priorities for the town and 3 year Investment Plan. The Investment Plan
will set out how the funding will be allocated and spent over the next 3 years,
and local authorities will receive the investment from the Long-Term Plan for
Towns over the next 3 years to fund the Town Board’s 3-year Investment
Plan. External expertise will be required to support the development of the
Long-Term Plan and associated community engagement. 
4.7 The Long-Term Fund for Towns guidance provides a list of interventions
across the 3 broad investment themes: safety and security; high streets,
heritage and regeneration, and transport and connectivity. Those interventions
have already been assessed as having a strong case for investment, value for
money and benefit-to-cost ratio and can be included in the Long-Term Plan
and Investment Plan. For any “off-menu” interventions an outline business
case will need to be provided
4.8 The Long-Term Plan should recognise and seek to build on the good work
that is underway, or has been undertaken already in the town. In 2021 the
Clydebank Town Centre Development Framework was approved. It includes a
15 year vision for transformation of the town centre into a vibrant and
attractive place, and was based on the community aspirations from two
previous charrettes. Subject to the endorsement of the Town Board, this
Page 15

Page 16

Development Framework could form basis of the Long-Term Plan and the 3
year Investment Plan. Through the consultation process it will be developed
and updated to ensure that the Long-Term Plan best reflects the current local
priorities and long term aspirations. 
5 People Implications
5.1 The early phases of the programme will be implemented by existing staff
within Regeneration and Business Support in consultation with the new
Chairperson, Deputy Chairperson and Town Board. As with the Levelling Up
Fund in Dumbarton, consideration will be given in future to using some of the
Long Term Fund for Towns to meet the costs of staff required to deliver the
programme of work. The new programme and secretariat support to the Town
Board will have some demands on staff time across Council Services
including Legal, Procurement, Finance, Communities, Planning, Asset
Management, Green Space and Roads and the capacity funding and longer
term revenue funding will, where appropriate, be applied to fund such support.
6 Financial & Procurement Implications
6.1 The Council have already received £50,000 of capacity funding to support
establishment of the Town Board. A further £200,000 will be allocated once
the Board has been established, to support development of the Long-Term
Plan and any associated community engagement. 
6.2 in Autumn 2024 Local authorities will receive the investment from the Long-
Term Plan for Towns over the next 3 years to fund the Town Board’s 3-year
Investment Plan. It is stated that Funding can be spent in a flexible way which
best suits the specific requirements of the town. It is envisaged that further
investment to deliver the Long-Term Plan vision beyond the first 3 year period
will require a new Investment Plan to be prepared. 
6.3 The revenue part of the fund can be used to support the capital investment for
the duration of the long term plan for towns fund and the Council’s support to
the Town Board decision making processes and wider administration. Where
an intervention would commit the local authority to future expenditure beyond
the fund (for example ongoing maintenance of a new leisure facility), Town
Boards must engage with local authorities and ensure that this is agreed.
6.4 Subject to approval of this report, officers from Regulatory and Regeneration
will commence procurement of external consultants to provide expertise
required to develop the Long-Term and Investment Plans. 
7 Risk Analysis
Page 16

Page 17

7.1 Timescales to set up the Town Board and develop the Long-Term Plan are
challenging however if they are not achieved, funding will be delayed.
8   Equalities Impact Assessment
8.1 An EIA has been carried out and is appended.
9  Environmental Sustainability
9.1  It will be a priority to take a ‘zero carbon’ approach to project selection and to
reflect the aims of the Council’s Climate Change Strategy. 
10  Consultation
10.1 The Long-Term Plan and 3 year Investment Plan will be developed by the
Town Board in consultation with the local community and it will reflect their
priorities. Previous engagements with the wider community from the
Development Framework and charrette processes will be taken on board.
11 Strategic Assessment
11.1 The Council has agreed its five main strategic priorities for 2022 –
2027. The Place Based Investment Programme is consistent with the
following objectives:
• Our neighbourhoods are sustainable and attractive.
• Our area has the infrastructure for sustainable and inclusive growth where
businesses can flourish.
• Our residents are engaged and empowered.
Chief Officer: Alan Douglas
Service Areas: Regulatory &Regeneration
Date:  24 January 2024
________________________________________________________________
Person to Contact:  Gillian McNamara
Appendices:  Appendix One: EIA
Background Papers: Clydebank Town Centre Development Framework,
September 2021
Page 17

Page 18

Wards Affected: Clydebank Wards
Page 18

Page 19

AssessmentNo 871 Owner brmccolgan
Resource
Regeneration,
Environment
and Growth
Service/Establishment Regeneration
First Name Surname Job title
Head Officer Alan Douglas Chief Officer
(include job titles/organisation)
Members
Brian McColgan Business Support Officer Gillian McNamara Economic
Development Manager Magda Swider Regeneration Co-ordinator Gillian
Scholes Business Support Co-oerdinator
(Please note: the word 'policy' is used as shorthand for stategy policy
function or financial decision)
Policy Title Clydebank – Long Term Plan for Towns Fund
The aim, objective,purpose and intended out come of policy
Clydebank has been awarded £20m of UK government funding to improve the
town, to be known as the Clydebank Town Fund. This will involve establishing
a Town Fund Board. The Board will then engage with local stakeholders,
including the Council, to develop a 10 year plan for spending the £20m in line
with UK Government regulations. The bulk of the funding should be spent on
infrastructure/physical regeneration activities. The first step is to find
someone to chair the Board. UK Government guidance states that this person
should be “an independent chair, invited by the local authority considering
who is best placed to convene partners and is a respected figure in the
community with an obvious passion for the place.” Hence the aim of this
policy initially is to invite someone to become Chair of the Clydebank Town
Fund Board. The Chair will then, with the support of the Council, seek to
appoint Board Members. Membership must include local elected member(s),
local MP and senior representative of Police Scotland. It can also include
representation from a wide range of local stakeholders. e.g. community
groups, local businesses, the Third Sector, local education providers, local
culture/heritage groups, local Health Authorities. The UK Government then
expects the Council to support the work of the Board, e.g. providing
secretariat support, providing support with impact assessments of projects to
deliver the 10 year Plan and ensuring compliance with Council and UK
Government financial, regulatory and administrative regulations.
Service/Partners/Stakeholders/service users involved in the
development and/or implementation of policy.
Chief Executive, relevant Chief Officers and Senior Managers.
Does the proposals involve the procurement of any goods or
services? Yes
If yes please confirm that you have contacted our
procurement services to discuss your requirements. Yes
SCREENING
You must indicate if there is any relevance to the four areas
Duty to eliminate discrimination (E), advance equal
opportunities (A) or foster good relations (F) Yes
Relevance to Human Rights (HR) Yes
ITEM 7 - APPENDIX 1
Page 19

Page 20

Relevance to Health Impacts (H) No
Relevance to Social Economic Impacts (SE) Yes
Who will be affected by this policy?
Clydebank residents, business and community organisations.
Who will be/has been involved in the consultation process?
Development will include the groups noted in section 1.
Please outline any particular need/barriers which equality groups may have in relation
to this policy list evidence you are using to support this and whether there is any
negative impact on particular groups.
 
Needs Evidence Impact
Age
Council equality
outcome on
increasing
participation of
younger people
Younger people are
unrepresented in
decision making in
Scotland
We will ensure that
equality elements
are given due regard
as this work is
planned and
progresses
Cross Cutting
The Council's
Community
Empowerment
Strategy commits us
to harnessing the
strengths of
community
members. The
Council also has a
legal duty to have
regard to
mainstreaming
equalities. We are
committed to
looking at how
elements can
interact in terms of
participation
Local consultation
and involvement
shows interest from
communities in
being more involved
in what happens in
local areas including
Clydebank. Factors
can and do cross cut,
and it is important
that community
groups eventually
involved represent
the diversity of the
area diversity
We will ensure these
interlinked elements
are given due regard
as this work is
planned and
progresses
Disability
Council equality
outcome on
increasing
participation of
disable people
Disabled people are
under represented
in decision making
in Scotland
We will ensure that
equality elements
are given due regard
as this work is
planned and
progresses
Social & Economic
Impact
We need to have
regard to the Fairer
Scotland Duty (FSD)
when looking at
strategic decisions
The council is
committed to an
inclusive approach
to economic
development
Given the total
investment of £20m
over 10 years it is
important that these
considerations are
taken into account at
an early stage, as the
FSD makes it clear
how equalities and
Socio economic
factors cross cut.
We will ensure that
these elements are
given due regard as
this work is planned
and progresses
Sex
Page 20

Page 21

Gender Reassign
Health
Human Rights
As noted above the
Council has
identified increasing
the involvement of
young as a priority
as part of its equality
outcome set.
additionally its is
likely that the UN
Convention on the
Rights of the child
will be incorporated
into Scottish Law by
July 2024. A key
element of this is
participation.
The council is
working to increase
engagement with
young people
This work may
provide
opportunities for
younger to be
involved
Marriage & Civil
Partnership
Pregnancy &
Maternity
Race
Council equality
outcome on
increasing
participation of BME
groups
BME people are
under represented
in decision making
in Scotland
We will ensure that
equality elements
are given due regard
as this work is
planned and
progresses
Religion and Belief
Sexual Orientation
Actions
Policy has a negative impact on an equality group,but is still to be implemented, please
provide justification for this.
Will the impact of the policy be monitored and reported on an ongoing bases?
Q7 What is you recommendation for this policy?
Intoduce
Please provide a meaningful summary of how you have reached the recommendation
EIA 871: The ongoing work of the Town Fund should have positive impacts on a cross-cutting
basis. Opportunities to advance the Council Equality Outcomes on widening participation,
employing our Community Empowerment Strategy can be explored. As outlined at Section 1,
the Council will support the work of the Town Fund Board and Chair, including any equality
impact assessments.
Page 21

Page 22

Page 22

Page 23

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer – Roads and Neighbourhood Service
IRED:  07 February 2024
___________________________________________________________________
Subject: Collection, Haulage, Processing, Treatment & Disposal of Bulky
Waste
1. Purpose
1.1 The purpose of this report is to advise Members of the award of the contract for
the Collection, Haulage, Processing, Treatment & Disposal of Bulky Waste. 
The contract was approved on 15 December 2023 by the Chief Officer - Roads
and Neighbourhoods after consulting with the Convenor of the Infrastructure,
Regeneration & Economic Development Committee.
2. Recommendations
2.1 It is recommended that Members note that the contract for the Collection,
Haulage, Processing, Treatment & Disposal of Bulky Waste was awarded to J
& M Murdoch & Son Limited: and 
a) Note that the contract shall be for a period of two years with the option of
a one year extension and at a value of £4,953,600 inclusive of VAT over
two years and £7,430,400 inclusive of VAT should the contract be
extended.  The estimated commencement date of the contract is 01
January 2024.
b) The approval was granted in accordance with Standing Orders Standing
Order 35(b)(ii), (iii) and (iv). Due to the urgent need to ensure continuity of
an essential statutory public service.
“35 (b) Officers will exercise those powers referred to above in
accordance with the following scheme: (ii) Delegated powers should
generally not be exercised where any decision by an authorised officer
would represent a departure from Council policy or procedure or would be
contrary to a standing instruction of Council (or Committee), or would itself
represent a significant development of policy or procedure. (iii) Such
decisions will be referred to Council, or the appropriate Committee, except
in the case of urgency, where the officer may, after consultation with the
relevant Service Spokesperson or Convener of the appropriate
Committee, exercise such delegated powers. (iv)Should such powers be
exercised in urgent circumstance, a report will be submitted to the next
appropriate Committee for noting.
ITEM 8
Page 23

Page 24

3. Background
3.1 The Council has a statutory obligation in accordance with the Environmental
Protection Act 1990 and The Waste (Scotland) Regulations 2012, to provide
municipal and household waste service provision, the Council provides bulky
household uplifts and large waste and recycling at civic amenity sites which
requires a competent service provider to carry out the collection, haulage,
processing, treatment and disposal of the bulky waste.
3.2 The overall budget for the Collection, Haulage, Processing, Treatment and
Disposal Bulky of Waste has been approved as an on-going requirement at full
Council as part of the annual budget setting process.
3.3 This procurement exercise has been conducted in accordance with the
Council’s Standing Orders and Financial Regulations and the Public
Procurement Regulations.  A Contract Strategy document was also approved
on 06 October 2023.
4. Main Issues
4.1 The Scotland Excel Dynamic Purchasing System (DPS) for the Treatment and
Disposal of Recyclable and Residual Waste (27-17) Lot 11 Treatment and
Disposal of Bulky Waste was identified as the optimum route to market, as 31
service providers have already gone through the European Single Procurement
Document (ESPD) selection process and being listed on the DPS this will
provide competition in shorter timescales for the Council whereas proceeding
with a bespoke contract, open tender would take longer and duplication of effort
and resources for tenderers and Council.
4.2 An invitation to tender (ITT) was published on the Public Contracts Scotland-
tender on 27 October 2023. 15 potential bidders noted an interest, with four
bidders submitting a response by the deadline on 06 December 2023. The four
tender submissions were evaluated by representatives from Waste Services,
Corporate Procurement Unit against pre-determined award criteria
4.3 The contract was awarded J & M Murdoch & Son Limited, of Neilston,
Glasgow, who had provided the most economically advantageous tender. The
contract shall be for a period of two years with the option of a one year
extension and at a value of £4,953,600 inclusive of VAT over two years and
£7,430,400 inclusive VAT should the contract be extended.
4.4 J & M Murdoch & Son Limited has committed to paying all staff as a minimum
the real Living Wage (£10.90 per hour) and promotes Fair Working Practices
across their organisation. The social benefits will be discussed at the
implementation meeting with J & M Murdoch & Son Limited and actions to take
these forward will be agreed.
Page 24

Page 25

5. People Implications
5.1 There are no people implications.
6. Financial and Procurement Implications
6.1 The financial costs in respect of this will be met from the approved General
Revenue budget of Roads and Neighbourhood - Waste Services.
6.2 This procurement exercise was conducted in accordance with the agreed
Contract Strategy produced by the Corporate Procurement Unit in close
consultation with Roads and Neighbourhood officers and the provisions of
Contract Standing Orders, the Financial Regulations and relevant Public
Procurement Regulation.
7. Risk Analysis
7.1 There was an imperative to award this contract urgently due to the urgent need
to ensure continuity of an essential statutory public service.
7.2 J & M Murdoch & Son Limited has no known links to Serious and Organised
Crime which would have significant political and reputational ramifications for
the Council.
8. Equalities Impact Assessment (EIA)
8.1 An equalities impact assessment screening was undertaken which determined
a full equalities impact assessment was not required.
9. Consultation
9.1 Roads and Neighbourhood, Finance Services and Legal Services have been
consulted on the contents of this report.
10. Strategic Assessment
10.1 The Collection, Haulage, Processing, Treatment & Disposal of Bulky Waste will
contribute to the delivery of the Council’s strategic priorities:
• Our communities are resilient and thriving;
• Our environment promotes a greener future;
Page 25

Page 26

Name:  Gail MacFarlane
Designation: Chief Offer – Roads and Neighbourhoods
Date:  11/01/2024
Person to Contact: Alex Grace, Senior Procurement Officer, 16 Church St,
Dumbarton, G82 1QL, alex.grace@west-dunbarton.gov.uk
Appendices:  None
Background Papers:  Contract Strategy
Wards Affected:      All Wards
Page 26

Page 27

WEST DUNBARTONSHIRE COUNCIL 
Report by Chief Officer - Resources 
Infrastructure, Regeneration & Economic Development Committee: 
7 February 2023
___________________________________________________________________
Subject: Infrastructure, Regeneration & Economic Development Budgetary
Control Report 2023/24 to Period 7 (31 October 2023)
1. Purpose
1.1 This report provides an update on the financial performance to 31 October
2023 of those services under the auspices of the Infrastructure, Regeneration
& Economic Development Committee (IRED). 
2. Recommendations
2.1 Members are asked to:
i) note the contents of this report showing the revenue budget forecast to
overspend against budget by £1.945m (13.91%) at the year-end taking
into account that this is subject to change, and
ii) note the net projected annual position in relation to relevant capital
projects which is highlighting a projected variance of £31.306m
(42.28%) due to re-profiling.
3. Background
Revenue
3.1 At the meeting of West Dunbartonshire Council on 1 March 2023, Members
agreed the revenue estimates for 2023/24. A total net budget of £14.173m
was approved for IRED services. Since then there have been various
adjustments and some services have moved outwith the IRED remit and the
revised budget is therefore now £13.985m, as follows:
£m
Starting Position 14.173
Staff Movements -0.132
Allocation of Income Generalisation -0.056
Revised  Budget 13.985
ITEM 9
Page 27

Page 28

Capital
3.2 At the meeting of Council on 1 March 2023, Members also agreed the
updated 10 year General Services Capital Plan for 2023/2024 to 2032/2033. 
The three years from 2023/24 to 2025/26 have been approved in detail with
the remaining years being indicative at this stage. The total project life budget
approved for projects that have either commenced or are due to commence in
that period total £175.940m.   
4. Main Issues 
Revenue Budget
4.1  The current budgetary position is summarised in Appendix 1.  A more detailed
analysis by service is given in Appendix 2. 
4.2 Of the 14 services monitored 3 are showing either a favourable or nil variance,
with 11 services showing an adverse variance. Comments are shown in
Appendix 3 when there are projected net annual variances greater than
£0.050m and also where the net variance is below £0.050m but there are
offsetting variances of over £0.050m within the service.    
4.3 Appendix 1 shows the probable outturn for the services at £15.930m. As the
annual budget is £13.985m there is currently a projected adverse variance for
the year of £1.945m. 
4.4 Since the budgetary control report presented at IRED committee meeting on 1
November 2023 there has been an increase in the adverse variance of £852k.
The main reasons for this increase are noted below: 
4.5 Further to an in-depth review of the R&N budget overspend a number of
opportunities have been identified that will mitigate the impact in some way.
These include the capitalisation of revenue spend where appropriate within
Roads, the allocation of developer contribution to activities undertaken in
Grounds and a reduction in costs in Waste within year due to an interim
residual collection in place. This should result in an estimated £0.700m
improvement in the projected year end outturn. Note this has not been
factored into the projections detailed in this report.  
Service Increase 
(£,000)
Main Reasons for Variance
Roads
Services
112 Increase in material costs (costs rising by about
9%) and street lighting costs due to costs
inflating more than expected.
Waste
Services
399 Increase in tonnage costs (£271k), vehicle hire
(£26k), additional spend needed for replacement
bins (£31k)  and employee costs due to pay
award (£56k) 
Corporate
Assets
292 Income not anticipated due to delays with Office
Rationalisation project. 
Page 28

Page 29

Capital Budget
4.6 The overall programme summary report is shown in Appendix 5. Information
on projects in the red category for probable underspends or overspends in-
year and in total is provided in Appendix 6 together with additional information
on action being taken to minimise or mitigate reprofiling and/or overspends
where possible and detail on projects within the green category are shown in
Appendix 7. 
4.7 The analysis shows there is a projected in-year variance of £32.849m. This
variance is mainly due to a comprehensive reprofiling exercise being carried
out to review the profiling of all projects in the capital programme to better
align the anticipated spend with project activity. Revised profiles will be
reflected in the updated capital programme to be presented to Council at the
Council Budget Meeting on 6 March 2024.   
4.8 From the analysis within the appendices it can be seen there are a number of
projects with identified re-profiling to date. Those with re-profiling valued at
greater than £0.500m, are listed as follows: 
Project Name
Period 7 
Re-profiling (£m)
Waste Transfer Station 1.780
Exxon City Deal 7.845
New West Bridgend Community Centre 0.990
Strathleven Place 1.540
Regeneration/Local Economic Development 1.911
Regeneration Fund 3.824
Clydebank Can on the Canal 0.707
District Heating Network Expansion 6.959
River Leven Flood Prevention Scheme  0.620
Gruggies Burn 0.930
Vehicle Replacement Strategy 0.500
Depot Rationalisation 1.938 
5. People Implications 
5.1 There are no people implications. 
6. Financial Implications 
6.1 Other than the financial position noted above, there are no financial
implications of the budgetary control report. Officers are currently reviewing
budgets and projections with a view to improving the position by financial year
end and progress will be highlighted in future reports to committee. 
Page 29

Page 30

7. Risk Analysis 
7.1 The present variances should be viewed in the knowledge that there are a
number of variable factors which could arise between now and 31 March and
which could affect the year end results for both the revenue and capital
budgets. 
8. Equalities Impact Assessment (EIA) 
8.1 The report is for noting and therefore no Equalities Impact Assessment was
completed for this report. 
9 Consultation 
9.1 The views of both Finance and Legal services have been requested on this
report and both have advised there are neither any issues nor concerns with
the proposal. As the report is for noting no further consultation is envisaged. 
10. Strategic Assessment 
10.1 Proper budgetary control and sound financial practice are cornerstones of
good governance and support Council and officers to pursue the five strategic
priorities of the Council’s Strategic Plan. This report forms part of the financial
governance of the Council. This report is for noting and, therefore, does not
directly affect any of the strategic priorities. 
Laurence Slavin
Chief Officer  – Resources   
Date:  6 December 2023 
Person to Contact:  Jackie Thomson - Business Unit Finance Partner, 16
Church Street, Dumbarton, G81 1QL.  
e-mail jackie.nicol-thomson@west-dunbarton.gov.uk   
Appendices:  Appendix 1 - Summary Budgetary Position (Revenue)    
Appendix 2– Detailed Budgetary Position (Revenue)    
Appendix 3 – Variance Analysis (Revenue)    
Appendix 4 – Efficiencies & Management Adjustments    
Appendix 5 – Budgetary Position (Capital)                                           
Appendix 6 – Variance Analysis Red Status (Capital)    
Appendix 7 - Variance Analysis Green (Capital)     
Background Papers: None   
Wards Affected:  All 
Page 30

Page 31

WEST DUNBARTONSHIRE COUNCIL ITEM 9 - APPENDIX 1
REVENUE BUDGETARY CONTROL 2023/24
IRED SUMMARY
MONTH END DATE 31 October 2023
Total Budget
2023/24
Spend to
Date 2023/24
Forecast
Spend
2023/24
Annual
RAG
Status
£000 £000 £000 £000 %
0 (120) 0 0 0% 
(601) 346 (366) 236 -39% 
225 548 265 40 18% 
3,014 3,496 3,430 417 14% 
7,416 4,326 7,416 0 0% 
194 104 278 84 43% 
(265) (80) (241) 24 -9% 
(1,101) (421) (983) 118 -11% 
9,757 5,557 10,429 672 7% 
(2,361) 620 (2,060) 301 -13% 
Capital Investment Programme (5) 166 2 7 -140% 
155 499 183 28 18% 
Depots 0 0 0 (0) -100% 
(2,443) 4,306 (2,423) 20 -1% 
13,985 19,347 15,930 1,945 13.91% 
Transport, Fleet & Maintenance Services
Service / Subjective Summary Annual Variance 2023/24
Corporate Asset Maintenance
Consultancy Services
Roads Services
Grounds Maintenance & Street Cleaning Client
Outdoor Services
Burial Grounds
Crematorium
Waste Services
Corporate Assets
Economic Development
Ground Maintenance & Street Cleaning Trading A/c
Total Net Expenditure
Page 31

Page 32

WEST DUNBARTONSHIRE COUNCIL
ITEM 9 - APPENDIX 2REVENUE BUDGETARY CONTROL 2023/24
IRED COMMITTEE DETAIL
PERIOD END DATE 31 October 2023
PERIOD 7
Actual
Outturn
2022/23
Total
Budget
2023/24
Spend to
Date 2023/24
Forecast
Spend
2023/24
RAG
Status
£000 £000 £000 £000 £000 %
19,520 Employee 19,541 10,369 19,701 160 1% 
4,844 Property 3,937 1,909 3,967 30 1% 
5,859 Transport and Plant 4,362 2,281 4,888 526 12% 
12,064 Supplies, Services and Admin 11,128 6,867 12,573 1,445 13% 
9,731 Payments to Other Bodies 9,242 4,737 9,340 97 1% 
1,485 Other 557 0 557 0 0% 
53,504 Gross Expenditure 48,767 26,162 51,025 2,259 5% 
(34,992) Income (34,782) (6,815) (35,095) (313) -1% 
18,512 Net Expenditure 13,985 19,347 15,930 1,945 14% 
£000 £000 £000 £000 £000 %
1,518 Employee 1,854 1,114 1,802 (52) -3% 
65 Property 70 41 70 0 0% 
40 Transport and Plant 67 39 67 0 0% 
1,017 Supplies, Services and Admin 519 432 613 94 18% 
0 Payments to Other Bodies 0 0 0 0 0% 
0 Other 0 0 0 0 0% 
2,640 Gross Expenditure 2,510 1,626 2,552 42 2% 
(2,763) Income (2,510) (1,746) (2,552) (42) -2% 
(123) Net Expenditure 0 (120) 0 0 0% 
£000 £000 £000 £000 £000 %
1,831 Employee 1,855 996 1,851 (4) 0% 
97 Property 99 3 93 (6) -6% 
2,246 Transport and Plant 1,942 829 1,623 (319) -16% 
641 Supplies, Services and Admin 509 358 644 135 26% 
2 Payments to Other Bodies 0 0 (0) (1) -234% 
0 Other 0 0 0 0 0% 
4,817 Gross Expenditure 4,405 2,186 4,210 (195) -4% 
(5,008) Income (5,007) (1,840) (4,576) 431 9% 
(191) Net Expenditure (601) 346 (366) 236 -39% 
£000 £000 £000 £000 £000 %
1,092 Employee 997 542 1,000 3 0% 
0 Property 0 0 0 0 0% 
6 Transport and Plant 7 1 7 0 0% 
4 Supplies, Services and Admin 5 4 6 2 38% 
45 Payments to Other Bodies 0 0 0 0 0% 
0 Other 0 0 0 0 0% 
1,147 Gross Expenditure 1,009 548 1,014 5 0% 
(528) Income (784) 0 (749) 35 4% 
619 Net Expenditure 225 548 265 40 18% 
£000 £000 £000 £000 £000 %
2,882 Employee 2,868 1,511 2,865 (3) 0% 
254 Property 235 108 247 12 5% 
881 Transport and Plant 577 413 842 265 46% 
2,971 Supplies, Services and Admin 2,468 1,459 3,168 700 28% 
941 Payments to Other Bodies 811 13 927 116 14% 
0 Other 0 0 0 0 0% 
7,929 Gross Expenditure 6,959 3,504 8,049 1,090 16% 
(4,490) Income (3,946) (7) (4,619) (673) -17% 
3,439 Net Expenditure 3,014 3,496 3,430 417 14% 
Service Summary Annual Variance
2023/24
All Services
Corporate Asset Maintenance
Transport, Fleet & Maintenance Services
Consultancy Services
Roads Services
Page 32

Page 33

WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
REVENUE BUDGETARY CONTROL 2023/24
IRED COMMITTEE DETAIL
PERIOD END DATE 31 October 2023
PERIOD 7
Actual
Outturn
2022/23
Total
Budget
2023/24
Spend to
Date 2023/24
Forecast
Spend
2023/24
RAG
Status Service Summary Annual Variance
2023/24
£000 £000 £000 £000 £000 %
23 Employee 0 0 0 0 0% 
0 Property 0 0 0 0 0% 
322 Transport and Plant 0 0 0 0 0% 
0 Supplies, Services and Admin 0 0 0 0 0% 
7,503 Payments to Other Bodies 7,416 4,326 7,416 0 0% 
839 Other 0 0 0 0 0% 
8,688 Gross Expenditure 7,416 4,326 7,416 0 0% 
0 Income 0 0 0 0 0% 
8,688 Net Expenditure 7,416 4,326 7,416 0 0% 
£000 £000 £000 £000 £000 %
64 Employee 75 38 73 (1) -2% 
156 Property 147 82 172 25 17% 
0 Transport and Plant 0 0 0 0 0% 
131 Supplies, Services and Admin 117 73 142 24 20% 
29 Payments to Other Bodies 45 0 11 (35) -77% 
0 Other 0 0 0 0 0% 
380 Gross Expenditure 384 193 397 13 3% 
(109) Income (190) (90) (119) 71 38% 
271 Net Expenditure 194 104 278 84 43% 
£000 £000 £000 £000 £000 %
0 Employee 0 0 0 0 0% 
18 Property 28 17 32 5 16% 
0 Transport and Plant 0 0 0 0 0% 
0 Supplies, Services and Admin 0 0 0 0 0% 
442 Payments to Other Bodies 442 258 442 0 0% 
0 Other 0 0 0 0 0% 
460 Gross Expenditure 470 275 474 5 1% 
(639) Income (735) (355) (715) 20 3% 
(178) Net Expenditure (265) (80) (241) 24 -9% 
£000 £000 £000 £000 £000 %
210 Employee 185 118 208 23 12% 
271 Property 257 142 231 (26) -10% 
0 Transport and Plant 0 0 0 0 0% 
18 Supplies, Services and Admin 18 6 21 3 15% 
17 Payments to Other Bodies 33 6 18 (16) -47% 
0 Other 0 0 0 0 0% 
516 Gross Expenditure 494 273 477 (17) -3% 
(1,363) Income (1,595) (694) (1,461) 135 8% 
(847) Net Expenditure (1,101) (421) (983) 118 -11% 
£000 £000 £000 £000 £000 %
3,334 Employee 3,203 1,775 3,317 114 4% 
143 Property 163 42 164 1 1% 
1,328 Transport and Plant 992 631 1,267 275 28% 
6,258 Supplies, Services and Admin 6,736 3,823 7,012 276 4% 
50 Payments to Other Bodies 22 27 27 5 23% 
0 Other 0 0 0 0 0% 
11,114 Gross Expenditure 11,115 6,298 11,787 672 6% 
(1,364) Income (1,359) (741) (1,358) 0 0% 
9,750 Net Expenditure 9,757 5,557 10,429 672 7% 
Grounds Maintenance & Street Cleaning Client
Outdoor Services
Crematorium
Burial Grounds
Waste Services
Page 33

Page 34

WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
REVENUE BUDGETARY CONTROL 2023/24
IRED COMMITTEE DETAIL
PERIOD END DATE 31 October 2023
PERIOD 7
Actual
Outturn
2022/23
Total
Budget
2023/24
Spend to
Date 2023/24
Forecast
Spend
2023/24
RAG
Status Service Summary Annual Variance
2023/24
£000 £000 £000 £000 £000 %
864 Employee 959 412 872 (87) -9% 
2,401 Property 1,941 1,022 1,942 1 0% 
4 Transport and Plant 5 1 5 (0) 0% 
(19) Supplies, Services and Admin (53) 20 (50) 2 -4% 
65 Payments to Other Bodies 102 29 102 0 0% 
0 Other 0 0 0 0 0% 
3,315 Gross Expenditure 2,955 1,485 2,871 (84) -3% 
(5,065) Income (5,316) (865) (4,931) 385 7% 
(1,750) Net Expenditure (2,361) 620 (2,060) 301 -13% 
£000 £000 £000 £000 £000 %
256 Employee 398 166 392 (7) -2% 
0 Property 0 0 0 0 0% 
0 Transport and Plant 1 0 1 0 0% 
1 Supplies, Services and Admin 1 0 1 0 0% 
0 Payments to Other Bodies 0 0 0 0 0% 
0 Other 0 0 0 0 0% 
257 Gross Expenditure 400 166 394 (7) -2% 
(332) Income (405) 0 (392) 13 3% 
(75) Net Expenditure (5) 166 2 7 -140% 
£000 £000 £000 £000 £000 %
620 Employee 753 360 719 (34) -5% 
489 Property 23 12 24 1 4% 
2 Transport and Plant 1 0 0 (1) -100% 
13 Supplies, Services and Admin 87 83 92 5 6% 
618 Payments to Other Bodies 370 78 397 27 7% 
0 Other 0 0% 
1,743 Gross Expenditure 1,234 533 1,232 (2) 0% 
(976) Income (1,079) (34) (1,049) 30 3% 
767 Net Expenditure 155 499 183 28 18% 
£000 £000 £000 £000 £000 %
0 Employee 0 0 0 0 0% 
564 Property 607 363 604 (3) -1% 
0 Transport and Plant 0 0 0 0 0% 
10 Supplies, Services and Admin 13 (2) 13 0 3% 
0 Payments to Other Bodies 0 0 0 0 0% 
0 Other 0 0 0 0 0% 
575 Gross Expenditure 620 361 617 (3) 0% 
(574) Income (620) (361) (617) 3 0% 
1 Net Expenditure 0 0 0 (0) -100% 
£000 £000 £000 £000 £000 %
7,081 Employee 6,393 3,337 6,602 209 3% 
384 Property 367 76 389 21 6% 
1,030 Transport and Plant 771 366 1,076 306 40% 
1,020 Supplies, Services and Admin 707 610 911 205 29% 
19 Payments to Other Bodies 0 0 0 0 0% 
646 Other 557 0 557 0 0% 
10,180 Gross Expenditure 8,794 4,388 9,535 741 8% 
(12,115) Income (11,237) (82) (11,957) (721) -6% 
(1,934) Net Expenditure (2,443) 4,306 (2,423) 20 -1% 
Economic Development
Depots
Ground Maintenance & Street Cleaning Trading A/c
Corporate Assets
Capital Investment Programme
Page 34

Page 35

WEST DUNBARTONSHIRE COUNCIL ITEM 9 - APPENDIX 3REVENUE BUDGETARY CONTROL 2023/24
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Forecast
Spend RAG Status
£000 £000 £000 %
Corporate Asset Maintenance 0 0 0 0% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Transport, Fleet & Maintenance
Services (601) (366) 236 -39% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
31 October 2023
Budget Details
Variance Analysis
Variance
Overspend anticipated at present.
Transport services across WDC
The cost of specialist repairs and materials/parts has increased to levels
not reflected in current budgets. VTU income remains adverse (£55k) due
to continuing restrictions on what MOTs are undertaken.
Expenditure and income  will continue to be monitored.
This service delivers maintenance a services to the council's corporate
property assets
The forecast overspend in supplies and materials is associated with the
type of work that is being undertaken. The higher spend is offset by higher
recharges to client budgets.
None required
Breakeven position
Page 35

Page 36

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2023/24
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Forecast
Spend RAG Status
£000 £000 £000 %
31 October 2023
Budget Details
Variance Analysis
Variance
Roads Services 3,014 3,430 417 14% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Outdoor Services 194 278 84 43% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
An adverse variance is anticipated.
This service relates to Roads operations, design, structures, street lighting,
road safety and school crossing patrols 
Plant hire costs have increased during the year to a level not foreseen
when the budget was set (£268k) . Similarly, electricity and street lighting
costs have increased during the year to a level not anticipated when the
budget was set due to unique inflationary pressures (£289k). Miscellaneous
property costs are also £12k greater than anticipated (the largest being the
depot cost allocation including a higher electricity element). Payments to
contractors/materials (£520k) are anticipated to be higher than anticipated
when the budget was set. As a result of higher operating costs income,
including capital recharges, are anticipated to be greater than budgeted
(£673k)
Management will continue to monitor all budget heads with a view to
minimising the overspend.
This service covers the outdoor sporting facilities provided by WDC and
public conveniences
Income from fees and charges is unlikely to be as budgeted (£71k). Other
costs - principally electricity - higher than when the budget was set.
Income will be monitored to establish whether there has been a downtown
in demand.
Overspend anticipated.
Page 36

Page 37

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2023/24
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Forecast
Spend RAG Status
£000 £000 £000 %
31 October 2023
Budget Details
Variance Analysis
Variance
Crematorium (1,101) (983) 118 -11% 
Service Description This service provides crematorium services within the Council area
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Waste Services 9,757 10,429 672 7% 
Service Description Waste Collection and Refuse disposal services
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
The increased income target is unlikely to be met
Overspend anticipated
Although there are savings on gas costs income from cremations is less
than budgeted with income less than the corresponding period last year.
Income and expenditure will continue to be monitored throughout the year.
Waste removal/tonnage costs in particular will be closely monitored.
Employee costs are higher due to the knock-on effect of the higher pay
award , higher turnover targets and higher overtime than reflected in the
budget (£114k) . Transport costs, principally hires, are greater than
anticipated when the budgets were set because of delays in acquiring new
vehicles (£275k). The number of tonnes going to landfill is also greater than
anticipated (£271k).
Page 37

Page 38

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2023/24
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Forecast
Spend RAG Status
£000 £000 £000 %
31 October 2023
Budget Details
Variance Analysis
Variance
Corporate Assets (2,361) (2,060) 301 -13% 
Service Description This service provides asset and estate management
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Economic Development 155 183 28 18% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome An overspend is anticipated
Income is adverse due to delays in filling staff vacancies on posts that are
budgeted to be internally recharged. While these posts are vacant there is
no possibility of recharging these. This is being partially offset by a
favourable variance in staffing due to the same vacancies.
Income and expenditure will continue to be monitored throughout the year.
Promotion of regeneration activities within West Dunbartonshire Council
Savings options have not been realised in respect of re letting of proposed
sites, which has therefore left the Council liable.
The unachieved amount of saving (£0.427m) will be funded from the
smoothing fund for 2023/24.  It is anticipated that the full saving will be
achieved in future years.
After use of the smoothing fund, a favourable variance is anticipated.
Page 38

Page 39

WEST DUNBARTONSHIRE COUNCIL ITEM 9 - APPENDIX 4MONITORING OF EFFICIENCIES AND MANAGEMENT ADJUSTMENTS 2023/24
Efficiency Detail Ref Chief Officer Budgeted Amount £ 
Projection of Total
Saved £ 
Projection of Total Not
Saved £  Comment
1
Reduce support provided to local businesses and organisations
including  a reduction in officers within the Council's economic
development team RR12 A Douglas 169,000 169,000 -
2 Historical Lease Review SDP06 L Slavin 55,000 55,000 -
3 Consultancy Services Reduction SDP08 G Macfarlane 82,000 82,000 -
4 Reduce Consultancy Services and Capital Investment Team SDP11 G Macfarlane 212,000 212,000 -
5 Structural Patching RN07 G Macfarlane 150,000 150,000 -
6 Environmental Trust Grant Reduction RN17 G Macfarlane 87,000 87,000 -
7
Review the charging policy for the Care of Gardens scheme or
remove provision entirely RN04 G Macfarlane 211,000 211,000 -
8
Reduce or remove the provision of weekend litter collection at key
destinations such as parks and town centres RN06 G Macfarlane 47,000 47,000 -
9
Reduce provision of grass cutting, bin clearing, litter collection and
street sweeping RN09 G Macfarlane 460,000 460,000 -
10 Electric Vehicle Charging RN13 G Macfarlane 91,000 91,000 -
1,564,000 1,564,000 -   TOTAL COMPLETE
STATUS: COMPLETE
Page 39

Page 40

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
MONITORING OF EFFICIENCIES AND MANAGEMENT ADJUSTMENTS 2023/24
Efficiency Detail Ref Chief Officer Budgeted Amount £ 
Projection of Total
Saved £ 
Projection of Total Not
Saved £  Comment
1 Office/ Depot Rationalisation SDP05 L Slavin                        380,000 380,000                    -                                    
2 Commercialisation of Assets (Pavilions/Cafés) SDP07 L Slavin                          41,000 41,000                      -                                    
3 External Consultancy Income SDP09 G Macfarlane                          50,000 10,000                      -                                    
4
Review the use of Municipal Buildings to identify alternative uses
or commercial opportunities SDP14 L Slavin 37,000                         37,000                      -                                    
5
Review possible early closure of Clydebank Town Centre Office
with employees based there relocated to alternative Council
accommodation SDP15 L Slavin 108,000                       108,000                    -                                    
6 Civic Waste Amenity Sites RN02 G Macfarlane                          63,000 63,000                      -                                    
7 Residual Waste Optimisation RN03 G Macfarlane                        138,000 138,000                    -                                    
8 Parking Enforcement RN05 G Macfarlane                        100,000 100,000                    -                                    
9
Improve recycling rates through a review of the programme  of
residual waste collection RN10 G Macfarlane 50,000                         50,000                      -                                    
10
Transfer the provision of Christmas lights to community groups or
traders associations with assistance provided by the Council at
switch on events RN15 G Macfarlane 25,000                         25,000                      -                                    
TOTAL IN PROGRESS                        992,000                      952,000                                         -  
99                    2,556,000                   2,516,000                                         -   TOTAL EFFICIENCIES/MANAGEMENT ADJUSTMENTS
STATUS: IN PROGRESS
Page 40

Page 41

WEST DUNBARTONSHIRE COUNCIL
ITEM 9 - APPENDIX 5GENERAL SERVICES CAPITAL PROGRAMME
OVERALL PROGRAMME SUMMARY
MONTH END DATE
PERIOD
Spend to
Date
Spend to
Date
£000 £000
Red
38 62% 35,195 51% 38 62% 3,289 53%
Amber
0 0% 0 0% 0 0% 0 0%
Green
23 38% 34,036 49% 23 38% 2,904 47%
61 100% 69,231 100% 61 100% 6,193 100%
Budget Spend to
Date
Forecast
Spend
Forecast
Variance Budget Spend to
Date
Forecast
Spend
Forecast
Variance Reprofiling Over/
(Under)
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000
PL CY
120,012 35,195 119,658 (353) 47,478 3,289 14,629 (32,849) (32,849) 0 0% -69%
0 0 0 0 0 0 0 0 0 0 #DIV/0! #DIV/0!
55,929 34,036 57,267 1,338 28,169 2,904 28,169 0 0 0 2% 0%
175,940 69,231 176,925 985 75,647 6,193 42,798 (32,849) (32,849) 0
Projects are on target both in relation to overall budget and the forecast stages in the project life cycle and
no issues are anticipated at this time
TOTAL EXPENDITURE
Projects are forecast to be overspent and/or significant delay to completion
Amber
Projects are either at risk of being overspent and/or delay in completion (although this is unquantifiable at
present) or the project has any issues that require to be reported at this time
Green
Red
% Project
Spend at
RAG Status
Red
Projects are forecast to be overspent and/or experience material delay to completion
Amber
Projects are either at risk of being overspent and/or delay in completion (although this is unquantifiable at
present) or the project has any issues that require to be reported at this time
Green
Projects are on target both in relation to overall budget and the forecast stages in the project life cycle and
no issues are anticipated at this time
TOTAL EXPENDITURE
Project Life Financials Current Year Financials
31 October 2023
P7
Project Status Analysis
Project Life Status Analysis Current Year Project Status Analysis
Number of
Projects at
RAG Status
% Projects at
RAG Status
% Project
Spend at
RAG Status
Number of
Projects at
RAG Status
% Projects at
RAG Status
Page 41

Page 42

WEST DUNBARTONSHIRE COUNCIL
ITEM 9 - APPENDIX 6GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 7
Budget Forecast
Spend
£000 £000 % £000 £000 %
1
Project Life Financials 1,150 1,150 100% 1,150 (0) 0%
Current Year Financials 5 2 33% 5 0 0%
Project Description
Project Manager Michelle Lynn
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-22 30-Apr-23
2
Project Life Financials 349 9 3% 349 0 0%
Current Year Financials 340 0 0% 0 (340) -100%
Project Description
Project Manager Michelle Lynn
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-24 31-Mar-25
3
Project Life Financials 150 150 100% 150 0 0%
Current Year Financials 134 0 0% 134 (0) 0%
Project Description
Project Manager Michelle Lynn
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-21 31-Mar-24
4
Project Life Financials 2,375 185 8% 2,375 (0) 0%
Current Year Financials 1,085 16 1% 95 (990) -91%
Project Description
Project Manager Michelle Lynn
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-22 31-Mar-25
To create new community facilities with additional space for early years provisions.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project complete and final account to be agreed.
Mitigating Action
31 October 2023
Budget Details
Project Life Financials
Spend to Date Variance
Dalmonach CE Centre
New Sports Changing Facility Dumbarton West (Old OLSP site) 
New Sports Changing Facility Dumbarton West (Old OLSP site) 
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Start date anticipated in 24/25.  This will be confirmed when works commence on the wider housing site.
None required.
Anticipated Outcome
To create new community facilities with additional space for early years provisions.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Installation complete.  Utilities connection to be completed by 31st March 2024.
Mitigating Action
None available at this time.
Mitigating Action
None available at this time.
Anticipated Outcome
To deliver new sports changing facility.
New Sports Changing Facility at Lusset Glen in Old Kilpatrick
New Sports Changing Facility at Lusset Glen in Old Kilpatrick
Main Issues / Reason for Variance
Various delays due to Covid and other utility issues. Planning was previously delayed but now resolved. Building warrant applications submitted and tender to be issued.
PQQ complete, and anticipate going to tender February with a site start in spring 2024.   Confirmation has been received that RCGF application was unsuccessful and
confirmation of capital requirements will not know until tender returns have been recieved.
Mitigating Action
None available at this time.
Anticipated Outcome
New build community facility.
Anticipated Outcome
To deliver new sports changing facility.
New Westbridgend Community Centre
New Westbridgend Community Centre
Planned End Date Forecast End Date
Page 42

Page 43

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 7
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 October 2023
Budget Details
Project Life Financials
Spend to Date Variance
Dalmonach CE Centre5 Strathleven Place
Project Life Financials 1,590 50 0 1,590 0 0
Current Year Financials 1,590 0 0 50 -1,540 (1)
Project Description
Project Manager Michelle Lynn
Chief Officer Laurence Slavin
Project Lifecycle Planned End Date 31-Mar-22 31-Mar-25
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
6
Project Life Financials 61 4 6% 61 (0) 0%
Current Year Financials 58 1 1% 1 (57) -99%
Project Description
Project Manager Steven Milne
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-25
Mitigating Action
None Required.
Anticipated Outcome
Works to be undertaken in 24/25
Installation of Solar PV at Clydebank Leisure Centre
Installation of Solar PV at Clydebank Leisure Centre.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Tender works delayed due to Energy Officer being involved in other priority work. Aim to be tendered within this  financial year but  works will not be  completed.
Forecast End Date
This project is linked to Glencairn House and Depot Rationalisation and will free up the current museum store and office space in Poplar Road. Opportunities exist to
attract external funding. Detailed design work ongoing for Glencairn House.
None available at this time
Project delivered on budget with required specifications
Re-development of Strathleven.
Page 43

Page 44

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 7
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 October 2023
Budget Details
Project Life Financials
Spend to Date Variance
Dalmonach CE Centre7
Project Life Financials 20 20 100% 20 0 0%
Current Year Financials 7 1 19% 7 0 0%
Project Description
Project Manager Steven Milne
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-24
8
Project Life Financials 290 63 22% 290 0 0%
Current Year Financials 227 0 0% 0 (227) -100%
Project Description
Project Manager Steven Milne
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-24
9
Project Life Financials 5,064 1,616 32% 4,527 (538) -11%
Current Year Financials 2,933 146 5% 1,022 (1,911) -65%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-25
10
Project Life Financials 16,155 5,172 32% 13,997 (2,158) -13%
Current Year Financials 4,098 21 1% 274 (3,824) -93%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-25
11
Project Life Financials 1,927 1,617 84% 1,927 0 0%
Current Year Financials 1,147 0 0% 837 (310) -27%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-24
Main Issues / Reason for Variance
Expect full spend before 31 March 2024.
Mitigating Action
None required.
Anticipated Outcome
Delivery of project with full budget spend.
Replace failed heating controls/valves & recommission
Replace failed heating controls/valves & recommission.
Planned End Date Forecast End Date
Regeneration/Local Economic Development
Budget to facilitate the delivery of Regeneration throughout West Dunbartonshire, aligned to the Economic Strategy.
Planned End Date Forecast End Date
Mitigating Action
Liaising with Leisure to see if opportunity to carry works between Dec and March . Appoint new external structural engineer to provide SER.
Anticipated Outcome
It is anticipated that Tender will go out this financial year. Depending on feedback from leisure re opportunity to close centre for AHU works,  it is hoped Civil works will at
least be initiated this financial year with AHU works completed next financial year.
Leisure Energy projects - air handling units, upgrade lighting, circulating pumps, and draught proofing
Measures to be installed at both Meadow Centre & Vale of Leven Swimming Pool; new pool hall Air Handling Units, upgrade
lighting, circulating pumps Vale of Leven Swimming Pool, internal and external lighting and draught proofing.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Expecting full spend prior to 31 March 2024.  Other priority projects have contributed to delay. Also require to appoint structural engineer to progress report and it is
anticipated that this will be undertaken in the near future.
Regeneration Fund
Funding to implement major regeneration projects linked to community charrettes. 
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Progress being made by Malin Group with expenditure of Clyde Mission funding at the Scottish Marine Technology Park. Remaining projects are multi-year.
Main Issues / Reason for Variance
LED budget is invested across our town centres and strategic sites and is used to develop and implement projects as well as providing match funding to lever in external
funding. During 2023/2024 the key projects to be developed and delivered include a Alexandria Town Centre Masterplan projects (Smollet Fountain, Green heritage
Corridors). Some projects including Arc of Attraction related projects in Dumbarton Development Framework projects in Clydebank as well and the new Activity Centre will
be progressed in 24/25. Many regeneration projects are subject to factors outwith Council control and close monitoring of the programming is required. A contingency is
included for increasing costs and new funding opportunities.
Mitigating Action
none required
Anticipated Outcome
projects delivered on time and on budget
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects continue to be progressed.23/24 allocation will be distributed as capital grants.
Mitigating Action
None required at this time
Mitigating Action
None required
Anticipated Outcome
Projects delivered on time and on budget
Place Based Investment Programme
Scottish Government Funding to establish a Place-Based Investment Programme to ensure that all place based
investments are shaped by the needs and aspirations of local communities.
Anticipated Outcome
Projects delivered on budget
Page 44

Page 45

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 7
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 October 2023
Budget Details
Project Life Financials
Spend to Date Variance
Dalmonach CE Centre12
Project Life Financials 747 40 5% 747 0 0%
Current Year Financials 707 0 0% 0 (707) -100%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Dec-22 30-Jun-24
13
Project Life Financials 320 134 42% 320 0 0%
Current Year Financials 221 0 0% 35 (186) -84%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 30-Jun-24
14
Project Life Financials 11,220 406 4% 11,220 (0) 0%
Current Year Financials 7,209 312 4% 250 (6,959) -97%
Project Description
Project Manager Patricia Rowley/ Craig Jardine
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
15
Project Life Financials 449 307 68% 492 44 10%
Current Year Financials 446 10 2% 260 (186) -42%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31/09/2024
16
Project Life Financials 50 37 73% 50 (0) 0%
Current Year Financials 13 0 0% 13 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
Main Issues / Reason for Variance
Kier is appointed to design and deliver the Activities Centre at Clydebank Town Centre. Design of the project is underway and a commencement date for construction will
be 2024.
Mitigating Action
None available at this time
Anticipated Outcome
Projects delivered on budget
Clydebank Can On The Canal
New activities centre in Clydebank Town Centre.
Planned End Date Forecast End Date
District Heating Network Expansion
District Heating Network Expansion.
Planned End Date Forecast End Date
Mitigating Action
None available at this time
Anticipated Outcome
Projects delivered on budget
Levelling Up Capacity
Successful LUF applications that meet UK Government's over-riding objective of Levelling Up and transformational
regeneration.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This capacity funding was awarded by UK Government to assist with development of LUF bids. WDC will be awarded LUF and the capacity funding will be used to fund
consultancy work associated with current and future LUF projects development.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works Progressing
Mitigating Action
None required at this time.
Allotment Development
To develop an allotment site.
Main Issues / Reason for Variance 
Network expansion to GJNH (Golden Jubilee National Hospital) will commence pending approval to proceed by the GJNH Board including agreeing tariff rates .  Unable
to confirm exact programme until approval has been given.
Mitigating Action
Network expansion to Golden Jubilee is discussed at every District Heating Project Board
Anticipated Outcome
Project to be delivered on programme and within budget once it has been fully set.
Main Issues / Reason for Variance
Project Underway
Mitigating Action
None available at this time
Anticipated Outcome
Sustainable burial environment for local residents.
Anticipated Outcome
Additional allotments delivered within budget
Kilmaronock Cemetery Expansion
Expansion of existing cemetery at Kilmaronock. 
Planned End Date Forecast End Date
Page 45

Page 46

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 7
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 October 2023
Budget Details
Project Life Financials
Spend to Date Variance
Dalmonach CE Centre17
Project Life Financials 250 0 0% 250 0 0%
Current Year Financials 250 0 0% 0 (250) -100%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-25
18
Project Life Financials 3,576 5,348 150% 5,348 1,772 50%
Current Year Financials 864 907 105% 907 43 5%
Project Description
Project Manager Craig Jardine
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-Mar-24
19
Project Life Financials 817 588 72% 817 (0) 0%
Current Year Financials 529 0 0% 300 (229) -43%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-25
20
Project Life Financials 200 200 100% 200 0 0%
Current Year Financials 210 0 0% 200 (10) -5%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-25
21
Project Life Financials 739 259 35% 739 (0) 0%
Current Year Financials 380 30 8% 200 (180) -47%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-28 31-Mar-28
Mitigating Action
None required at this time.
Anticipated Outcome
Sustainable burial environment for local residents.
Posties Park Sports Hub - New sports hub to include gym & running track
Creation of a sports hub at Posties/Marinecraft to include a new changing pavilion/Gym, new all-weather 6 lane running
track, conversion of blaze sports pitch to grass, new fencing, upgrade of existing floodlights and additional car parking.  This
combines the budget approved by the Council in February 2015 for Community Sports Facilities at Posties Park, draw down
of budget from the generic sports facilities budget line.
Cemetery Extension, North Dalnotter
Cemetery Extension, North Dalnotter
Planned End Date Forecast End Date
Main Issues / Reason for Variance
North Dalnotter will now be delivered in financial year 24/25
Vale of Leven Cemetery Extension
Extension of existing cemetery in Vale of Leven.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project will be completed Summer 2024
Anticipated Outcome
New sports Hub delivered
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Scottish Water connection now complete.  Programme to completion being finalised by Contractor, anticipated February 24
Mitigating Action
None available at this time
Planned End Date Forecast End Date
Main Issues / Reason for Variance
External funding confirmed and design commencing.
Mitigating Action
None required.
Mitigating Action
None available at this time.
Anticipated Outcome
Extension to existing cemetery providing a sustainable burial environment.
East End Park Resurfacing
Resurfacing of 3G pitch at East End Park.
Main Issues / Reason for Variance
Tender documentation complete, commencement programmed February 24.
Mitigating Action
None required at this time.
Anticipated Outcome
Renewal of play parks
Anticipated Outcome
Resurfacing of 3G pitch at East End Park.
Play Parks Grant Funding
Renew and replace play park equipment
Planned End Date Forecast End Date
Page 46

Page 47

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 7
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 October 2023
Budget Details
Project Life Financials
Spend to Date Variance
Dalmonach CE Centre22
Project Life Financials 210 10 5% 190 (20) -10%
Current Year Financials 200 0 0% 10 (190) -95%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 30-Nov-23 31-Mar-25
23
Project Life Financials 217 3 1% 217 0 0%
Current Year Financials 214 0 0% 0 (214) -100%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
24
Project Life Financials 400 400 100% 400 (0) 0%
Current Year Financials 42 0 0% 42 (0) 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
25
Project Life Financials 314 314 100% 314 (0) 0%
Current Year Financials 56 0 0% 56 (0) 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
26
Project Life Financials 237 166 70% 237 0 0%
Current Year Financials 237 166 70% 237 (0) 0%
Project Description
Project Manager Raymond Walsh/ Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Mitigating Action
None required at this time.
Anticipated Outcome
Balloch Mountain Bike Track
Balloch Mountain Bike Track
Develop a mountain bike skills trail at Balloch Castle Country Park.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Design undertaken this financial year.
Auld Street Clydebank - Bond
00 January 1900
Planned End Date Forecast End Date
Mitigating Action
None available at this time.
Anticipated Outcome
To improve journey times and reliability of bus services.
Bus Rapid Deployment Fund
Funding has been awarded from Sustrans to assist with social distancing measures required as a result of the COVID-19
pandemic.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
External Funding bid submitted by City Region to Scottish Government.  If successful Officers will be informed of quantum of funding available for project delivery
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Moss O' Balloch charging points installed 22/23 awaiting commissioning by Scottish Power.  Further locations identified for installation.
Mitigating Action
None required at this time.
Electrical Charging Points - Rapid Charge
Funding has been awarded from Transport Scotland for the Installation of electrical charging points
Main Issues / Reason for Variance
Road construction works completed in previous years. Remaining funds are insufficient to complete footpath construction. Works on hold until such time as additional
funds can be secured.
Mitigating Action
None available at this time.
Anticipated Outcome
To complete remaining civil works required.
Main Issues / Reason for Variance
Ongoing works will be completed by 31/3/24.
Mitigating Action
None required at this time.
Anticipated Outcome
Project should be complete within budget.
Anticipated Outcome
To provide Electric Vehicle Charging points within West Dunbartonshire.
Flood Risk Management
Enhancement of drainage infrastructure to ensure compliance with Flood Risk Management Act 2009.
Planned End Date Forecast End Date
Page 47

Page 48

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 7
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 October 2023
Budget Details
Project Life Financials
Spend to Date Variance
Dalmonach CE Centre27
Project Life Financials 500 18 4% 500 0 0%
Current Year Financials 500 18 4% 350 (150) -30%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
28
Project Life Financials 800 181 23% 800 0 0%
Current Year Financials 620 0 0% 0 (620) -100%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-26
29
Project Life Financials 15,053 1,054 7% 15,053 (0) 0%
Current Year Financials 1,530 0 0% 600 (930) -61%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-27
30
Project Life Financials 1,700 1,207 71% 1,700 0 0%
Current Year Financials 693 0 0% 200 (493) -71%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-26 31-Mar-27
31
Project Life Financials 4,300 4,300 100% 4,300 (0) 0%
Current Year Financials 138 4 3% 138 0 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-Mar-24
32
Project Life Financials 1,000 500 50% 1,000 0 0%
Current Year Financials 1,000 0 0% 500 (500) -50%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
Mitigating Action
None required at this time.
Anticipated Outcome
Projects should be complete within budget.
River Leven Flood Prevention Scheme
River Leven Flood Prevention Scheme.
Flood Prevention
Various flood prevention projects.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Various Flood Prevention Projects being undertaken with limited uptake on property protection scheme. 
Gruggies Burn Flood Prevention
Commission of Gruggies Flood Prevention Scheme.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Detailed design underway. Design will be completed 24/25
Anticipated Outcome
Project should be completed within budget.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Awaiting outcome of Scottish Government & SEPA consideration of submitted study .
Mitigating Action
None required at this time.
Anticipated Outcome
To provide an improved A813.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Detailed design ongoing and will determine programme of delivery.
Mitigating Action
None required at this time.
Mitigating Action
None available at this time.
Anticipated Outcome
Project should be completed within budget.
A813 Road Improvement Phase 1
A813 Road Improvement Phase 1.
Vehicle Replacement Strategy
Replacement of refuse collection vehicles.
Mitigating Action
None available at this time.
Anticipated Outcome
Project will enhance the A814 through Clydebank.
Clydebank Charrette, A814
Clydebank Charrette, A814
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works complete and on maintenance period - retention payment due prior to March 2024.
Anticipated Outcome
Replacement of refuse collection vehicles.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Bin lorries ordered and build slot allocated this financial year.  Expected March 24
Mitigating Action
None available.
Page 48

Page 49

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 7
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 October 2023
Budget Details
Project Life Financials
Spend to Date Variance
Dalmonach CE Centre33
Project Life Financials 3,314 455 14% 3,314 0 0%
Current Year Financials 3,314 455 14% 3,000 (314) -9%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 30-May-24
34
Project Life Financials 400 400 100% 400 0 0%
Current Year Financials 400 0 0% 400 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
35
Project Life Financials 1,980 200 10% 1,980 0 0%
Current Year Financials 1,980 0 0% 200 (1,780) -90%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Dec-25
36
Project Life Financials 60 44 73% 49 (11) -19%
Current Year Financials 16 5 30% 5 (11) -70%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
Vehicle Replacement
Replacement of vehicles which have reached end of programmed lifespan (7 year heavy vehicles, 10 year light vehicles).
Planned End Date Forecast End Date
Purchase of gritters
Purchase of gritters.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Gritters received
Main Issues / Reason for Variance
Vehicles have been ordered including bin lorries, sweepers and tractors.  It is anticipated budget will be fully spent.
Mitigating Action
None Required.
Anticipated Outcome
Replacement of fleet within budget.
Anticipated Outcome
Project delivered within budget.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Detailed design ongoing
Mitigating Action
None Required.
Mitigating Action
None available at this time.
Anticipated Outcome
Project delivered within  budget.
Waste Transfer Station
The design, development and construction of a recycling and bulk waste transfer facility that will ensure all recycling
material can be sorted and disposed off appropriately to ensure compliance with landfill ban in 2025.
Mitigating Action
None Required.
Anticipated Outcome
Project delivered within  budget.
2022/23 GRANT OFFER FOR ELECTRIC VEHICLE INFRASTRUCTURE
2022/23 GRANT OFFER FOR ELECTRIC VEHICLE INFRASTRUCTURE
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project in progress.
Page 49

Page 50

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 7
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 October 2023
Budget Details
Project Life Financials
Spend to Date Variance
Dalmonach CE Centre37
Project Life Financials 33,491 7,946 24% 34,049 558 2%
Current Year Financials 11,845 1,179 10% 4,000 (7,845) -66%
Project Description
Project Manager Patricia Rowley
Chief Officer Gail McFarlane
Project Lifecycle 31-Mar-27 31-Mar-27
38
Project Life Financials 8,535 645 8% 8,535 (0) 0%
Current Year Financials 2,238 17 1% 300 (1,938) -87%
Project Description
Project Manager Michelle Lynn/Craig Jardine
Chief Officer Gail McFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
Forecast End Date
Mitigating Action
None available at this time
Anticipated Outcome
Deliver project outcomes within agreed budget
Depot Rationalisation
Depot Rationalisation.
Planned End Date Forecast End Date
Main Issues / Reason for Variance 
Committee approval given to upgrade and improve depots.  Project delivery will be phased, work underway to determine phasing of spend and scope.
Main Issues / Reason for Variance 
Regular updates are provided at every Council meeting and monthly Project Board meetings and to City Deal.  The main issues contained within the new Council's
approved Outline Business Case are still valid, which include Exxon's remediation strategy, land transfer arrangements and issues relating to adjoining owners.  WDC
Consultants are monitoring the remediation process to ensure compliance with specification, also Esso are independently monitoring the remediation works.  Final
Business Case submission was June 2023. Through the Scape framework we are working closely with Balfour Beatty to achieve a formal pre construction agreement to
allow the detailed design works to commence and the full construction programme to be developed. Agreements in principle are progressing with third party land owners.
Mitigating Action
None Required
Anticipated Outcome
Delivery of the project on time and within the increased budget
Exxon City Deal
As part of the City Deal project the WDC Exxon site at Bowling regeneration with alternative A82 route included.
Planned End Date
Page 50

Page 51

WEST DUNBARTONSHIRE COUNCIL
ITEM 9 - APPENDIX 7GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 7
Budget Forecast
Spend
£000 £000 % £000 £000 %
1
Project Life Financials 2,230 2,222 100% 2,230 0 0%
Current Year Financials 2,230 731 33% 2,230 0 0%
Project Description
Project Manager Michelle Lynn
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-24 31-Mar-24
2
Project Life Financials 87 79 91% 79 (8) -9%
Current Year Financials 79 68 86% 79 0 0%
Project Description
Project Manager Steven Milne
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-24
3
Project Life Financials 450 193 43% 193 (258) -57%
Current Year Financials 0 0 0% 0 0 0%
Project Description
Project Manager Steven Milne
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
Anticipated Outcome
Credit note received and project closed
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This project has been completed. However a credit is outstanding and should be received this financial year.
Mitigating Action
Officers will continue to peruse the credit note
Zero Carbon
Zero Carbon
Anticipated Outcome
Projects delivered to required specifications
Building Upgrades and H&S - lifecycle & reactive building upgrades
Lifecycle and reactive building upgrades.
Planned End Date Forecast End Date
Anticipated Outcome
Replace existing main hall Air Handling unit at Clydebank Town Hall.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works are currently being undertaken to upgrade controls in Clydebank Town Hall.
Mitigating Action
None Required.
Replace existing main hall Air Handling unit at Clydebank Town Hall
Replace existing main hall Air Handling unit at Clydebank Town Hall.
31 October 2023
Budget Details
Project Life Financials
Spend to Date Variance
Main Issues / Reason for Variance
Works progressing
Mitigating Action
None required at this time
Page 51

Page 52

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 7
Budget Forecast
Spend
£000 £000 % £000 £000 %
Building Upgrades and H&S - lifecycle & reactive building upgrades
31 October 2023
Budget Details
Project Life Financials
Spend to Date Variance
4
Project Life Financials 22,213 22,100 99% 22,100 (113) -1%
Current Year Financials 19,984 1,596 8% 19,984 0 0%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-25 31-Mar-25
5
Project Life Financials 478 0 0% 478 0 0%
Current Year Financials 478 0 0% 478 (0) 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
6
Project Life Financials 221 221 100% 221 0 0%
Current Year Financials 8 7 87% 8 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 03-Apr-21 31-Mar-24
7
Project Life Financials 25 25 100% 25 0 0%
Current Year Financials 6 0 0% 6 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
8
Project Life Financials 485 485 100% 485 0 0%
Current Year Financials 430 0 0% 430 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Main Issues / Reason for Variance
Projects identified with a number commenced.
Mitigating Action
None required at this time.
Anticipated Outcome
completion of project on time and on budget
Anticipated Outcome
Large bins provided for high traffic areas
Nature Restoration Fund
Nature resource for Faifley Community
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project complete.
Mitigating Action
None required at this time.
Large bins for high traffic areas (pilot)
Supply and install extra large litter bins as a pilot project within hotspot problem areas.
Main Issues / Reason for Variance
Project works complete.  Retentions to be paid.
Mitigating Action
None required at this time.
Anticipated Outcome
New all weather tennis courts.
Sports Facilities Upgrades - Argyll Park - Construction of 3 All Weather Tennis Courts
Project is part of wider investment in sporting facilities and is dependent on match funding from Sports Scotland. Agreement
in principle to wider WDC strategic priorities.
Planned End Date Forecast End Date
Mitigating Action
None required at this time.
Anticipated Outcome
Better access with parks, cemeteries and open spaces.
Public non-adopted paths and roads
Upgrades to drainage and lighting to enhance the lifespan of paths and roads within  facilities in public parks, cemeteries
and civic spaces.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Full budget committed
Anticipated Outcome
Projects delivered on budget
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Artizan Masterplan approved by IRED in Nov 2023, deigns progressing as planned.
Mitigating Action
None available at this time
LUF
Year one LUF spend includes acquisition cost of Artizan Centre, and design development for Glencairn House and
Connecting Dumbarton
Page 52

Page 53

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 7
Budget Forecast
Spend
£000 £000 % £000 £000 %
Building Upgrades and H&S - lifecycle & reactive building upgrades
31 October 2023
Budget Details
Project Life Financials
Spend to Date Variance
9
Project Life Financials 561 0 0% 561 0 0%
Current Year Financials 561 0 0% 561 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
10
Project Life Financials 60 60 100% 60 0 0%
Current Year Financials 5 0 0% 5 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
11
Project Life Financials 2,277 1,447 64% 1,447 (830) -36%
Current Year Financials 650 0 0% 650 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
12
Project Life Financials 24,658 5,198 21% 27,224 2,565 10%
Current Year Financials 2,195 35 2% 2,195 (0) 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
13
Project Life Financials 84 7 8% 84 0 0%
Current Year Financials 84 7 8% 84 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Anticipated Outcome
Intention is to complete works within budget.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Ongoing lighting works to be completed by 31/3/24.
Mitigating Action
None available at this time.
Mitigating Action
None required at this time.
Anticipated Outcome
Intention is to complete various surfacing works by the end of March 2024.
Street lighting and associated electrical infrastructure
WDC is responsible for the maintenance of 18,000 street lighting columns and associated illuminated signs and bollards. 
This budget is required for this infrastructure.
Infrastructure - Roads
Infrastructure - Roads.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Roads Operations have completed an extensive surfacing program and  measurement claims received have been processed. A programme of structural patching is
ongoing.
Main Issues / Reason for Variance
For Bus Infrastructure a program of works Is being developed. For A8014 Kilbowie Rd works are being planned awaiting further feedback from Utilities, For A814
Congestion measures further development & expansion of vehicle detection systems and for Balloch P & R Consultants are appointed, agreement in principal with
Network Rail & further investigatory works are planned.
Mitigating Action
None required at this time.
Anticipated Outcome
Improve accessibility to Public Transport and improve journey time reliability.
FALSE
Strathclyde Partnership for Transport - Bus, cycling and walking infrastructure improvements.
Planned End Date Forecast End Date
Mitigating Action
None required at this time.
Anticipated Outcome
Traffic calming to be installed in Dumbarton East.
Turnberry Homes - traffic calming/ management at Turnberry housing development off Castle Road
Funding has been received from Turnberry Homes and will be used to introduce traffic calming and traffic management
measures to mitigate the impact of additional traffic accessing the housing development off Castle Road, Dumbarton.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Speed Humps to be programmed.
Anticipated Outcome
To improve connectivity and enhanced Cycling routes within West Dunbartonshire.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works for a footway/cycleway improvement at Bellsmyre Avenue are now complete. Dropped kerbs at various locations are underway. Proposed further works to
cycleways due to commence late 2023.
Mitigating Action
None required at this time.
Cycling, Walking and Safer Streets
Introduction of enhanced walking routes and traffic calming schemes to introduce safer streets within West Dunbartonshire.
Page 53

Page 54

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 7
Budget Forecast
Spend
£000 £000 % £000 £000 %
Building Upgrades and H&S - lifecycle & reactive building upgrades
31 October 2023
Budget Details
Project Life Financials
Spend to Date Variance
14
Project Life Financials 97 97 100% 97 (0) 0%
Current Year Financials 29 20 70% 29 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
15
Project Life Financials 134 134 100% 134 0 0%
Current Year Financials 134 0 0% 134 0 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
16
Project Life Financials 81 80 99% 81 0 0%
Current Year Financials 75 9 12% 75 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
17
Project Life Financials 300 300 100% 300 0 0%
Current Year Financials 26 0 0% 26 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
18
Project Life Financials 1,000 1,000 100% 1,000 0 0%
Current Year Financials 878 388 44% 878 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
Mitigating Action
None required.
Anticipated Outcome
Improvement to pavements.
Pavement improvements
Various pavement improvement projects.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Footway resurfacing works in Longden street (Whitecrook), Sycamore Drive (Parkhall) & Beechwood Drive are complete with further projects to be programmed.
Main Issues / Reason for Variance
Upgrade of obsolete equipment will be completed by 31/3/24.
Mitigating Action
None required.
Anticipated Outcome
To upgrade traffic signals.
Anticipated Outcome
To purchase equipment.
Traffic Signal Upgrades
Upgrade Traffic Signals
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
New plant has been purchased.
Mitigating Action
None required.
Roads Plant
Purchase of Roads plant and equipment.
Main Issues / Reason for Variance
New funding which will be allocated to appropriate projects.
Mitigating Action
None required at this time.
Anticipated Outcome
Projects delivered on time and on budget
Roads Safety
Roads Safety
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Detailed design underway. Design will be completed 24/25
Mitigating Action
None available at this time.
Anticipated Outcome
Intention is to complete works within budget.
Depot Improvement Works
Improvement of WDC Roads Depot.
Planned End Date Forecast End Date
Page 54

Page 55

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 7
Budget Forecast
Spend
£000 £000 % £000 £000 %
Building Upgrades and H&S - lifecycle & reactive building upgrades
31 October 2023
Budget Details
Project Life Financials
Spend to Date Variance
19
Project Life Financials 179 80 45% 160 (19) -10%
Current Year Financials 9 0 0% 9 0 0%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
20
Project Life Financials 79 79 100% 79 0 0%
Current Year Financials 79 0 0% 79 0 0%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
21
Project Life Financials 20 20 100% 20 0 0%
Current Year Financials 20 0 0% 20 0 0%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Main Issues / Reason for Variance
Project underway
Mitigating Action
None Required.
Anticipated Outcome
Project delivered within  budget.
Anticipated Outcome
Project delivered within  budget.
River bank erosion repair - Levenhowe
River bank erosion repair in the Levenhowe area
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
New Funding - Project in progress.
Mitigating Action
None Required.
Smarter Choices
Smarter Choices, Smarter Places
Main Issues / Reason for Variance
Complete
Mitigating Action
None Required.
Anticipated Outcome
Project delivered within  budget.
Replacement of compactors at Dalmoak civic amenity site
The purchase of 2 compactors for the Council civic amenity site at Dalmoak.
Planned End Date Forecast End Date
Page 55

Page 56

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 7
Budget Forecast
Spend
£000 £000 % £000 £000 %
Building Upgrades and H&S - lifecycle & reactive building upgrades
31 October 2023
Budget Details
Project Life Financials
Spend to Date Variance
22
Project Life Financials 150 150 100% 150 0 0%
Current Year Financials 150 0 0% 150 0 0%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-25
23
Project Life Financials 59 59 100% 59 0 0%
Current Year Financials 59 43 74% 59 (0) 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Anticipated Outcome
Project delivered within  budget.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project Complete
Mitigating Action
None Required.
Mitigating Action
None Required.
Anticipated Outcome
Project delivered within  budget.
Whitecrook Tennis Court Up-grade
Whitecrook Tennis Court Up-grade
Park Improvements and Multi Games Area - Goldenhill Park
Park Improvements and Multi Games Area - Goldenhill Park
Planned End Date Forecast End Date
Main Issues / Reason for Variance
MUGA due for commencement in February and environmental improvements complete
Page 56

Page 57

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer: Resources
Infrastructure Regeneration and Economic Development Committee:
7 February 2024
___________________________________________________________________
Subject :    Sale of  53A George Street, Bonhill G83 9JQ
1. Purpose
1.1 The purpose of this report is to seek Committee approval for West
Dunbartonshire Council (the Council) to dispose of 53A George Street, Bonhill
(the property) to Sava Estates Ltd.
2. Recommendations
2.1      It is recommended that the Committee:
(i) Approves the disposal of 53A George Street to Sava Estates Ltd. for
£27,601.
(ii) Authorises the Chief Officer Resources to conclude negotiations.
(iii) Authorises the Chief Officer Regulatory and Regeneration to conclude
the transaction on such conditions as considered appropriate.
3. Background
3.1 The property was previously let to an artist who used the property as a studio
until May 2023.
3.2 An operational decision was taken to market the property for sale rather than
lease as the Council do not own any adjoining properties.
4. Main Issues
4.1 The property is wholly owned by the Council and is currently unused and
surplus to the requirements of any Council service.
4.2 The property was extensively marketed For Sale during October and
November 2023. Marketing details were prepared (Appendix 1).
4.3 The property’s availability was listed on the Council’s website and social
media and also on the main commercial property marketing websites. Details
were also circulated to commercial property agents, local solicitors, and
business development bodies.
ITEM 10
Page 57

Page 58

4.4 A closing date was set for receipt of informal offers of 6 December 2023.  Five
offers were received ranging from £10,000 to £27,601 with Sava Estates Ltd.
submitting the highest offer.    
4.5 The offer from Sava Estates Ltd. is subject only to standard commercial
conditions.  It is currently unknown what the future intended use of the
property will be.
4.6 It is anticipated that the transaction will settle prior to 31 March 2024.
5. People Implications
5.1 There are no significant people implications other than the resources required
by legal services and asset management to negotiate missives and conclude
the transaction.
6. Financial and Procurement Implications
6.1 The Council will benefit from a capital receipt of £27,601 and no longer have
to incur revenue costs for managing and maintaining the property including
utility costs.
6.2 There are no procurement implications arising from this report.
7. Risk Analysis
7.1 The disposal is subject to legal due diligence. There is a risk of the sale not
proceeding due to any emerging issues during the due diligence process. This
is standard for any disposal transaction.
8. Environmental Sustainability
8.1 Any redevelopment or refurbishment of the property will require to be in line
with current building standards.
9. Equalities Impact Assessment (EIA)
9.1 An Equality Impact Assessment is not applicable for the purpose of this
report.
10. Consultation
10.1 Consultations have been undertaken with Finance, Regulatory Services and
Planning.
Page 58

Page 59

11. Strategic Assessment
11.1 By agreeing to this proposal this will be contributing to the Council’s strategic
priority for a strong local economy and improved job opportunities. 
Laurence Slavin
Chief Officer: Resources
Date: 8 January 2024
Person to Contact: Michelle Lynn, Asset Coordinator.
Email: michelle.lynn@west-dunbarton.gov.uk
J David Johnston, Estates Surveyor. 
Email: david.johnston2@west-dunbarton.gov.uk
Appendices: Appendix 1 – Marketing Details.
Background Papers:  None 
Wards Affected: Ward 2
Page 59

Page 60

ITEM 10 - APPENDIX 1: FOR SALE: WORKSHOP / DEVELOPMENT OPPORTUNITY
53A GEORGE STREET,  BONHILL, ALEXANDRIA, G83 9JQ
LOCATION
The town of Alexandria is situated approximately 17 miles
north west of Glasgow City Centre, within the ‘Vale of Leven’. 
Access to the M8 national motorway network can be gained
via the Erskine Bridge or the Clyde Tunnel.
The subject property is located on the east side of George
Street, Bonhill. The surrounding area is predominantly
residential in character.
DESCRIPTION
The subjects comprise a single storey workshop building with
a pitched roof and a pedestrian access door to the front. The
building sits on a level site which is fenced.
The building has an electricity and mains water supply. No
warranty will be provided regarding the condition of these
services and prospective purchasers will require to satisfy
themselves as to the suitability of these utilities.
Page 60

Page 61

Internally the building is divided into a storage/ workshop area to the front with a rear kitchen and
toilet area.
The building itself is in a poor state of repair and no reports will be provided concerning the
condition of the building.
ACCOMODATION
Net Internal Area is as follows: Ground Floor:  51.47 sqm ( 554 sq ft) or thereby.
SITE AREA
The site area extends to 216 sqm or thereby
RATEABLE VALUE
The property is entered in the Valuation Roll at NAV/RV (2023) at £1,450 per annum. Further
information can be obtained by contacting the Assessor’s Office, Clydebank on telephone number
0141-562-1272 or visit their website at: www.saa.gov.uk
PLANNING
We are advised that the property is within a residential area/existing neighbourhood as defined by
the adopted local plan and proposed local development plan. Residential or community use would
be the most compatible uses in this area. A small retail store (but not a hot food take-away) could
also be an acceptable use subject to gaining the appropriate planning consent.
Interested parties are advised  to contact Planning and Building Standards at West Dunbartonshire
Council. TEL: 0141 951 7930 to discuss any proposals they might have for the property.
Email:  development.management@west-dunbarton.gov.uk
ENTRY
Immediate entry is available.
VAT
The property is not elected for vat.
OFFERS
We are seeking offers for the benefit of the Councils interest in the property.
It is likely that a Closing date will be set for receipt of offers and it is strongly recommended that
parties’ register their interest in writing.
FURTHER INFORMATION and VIEWING
Parties are asked to register their interest in writing with:
J David Johnston, Asset Management
West Dunbartonshire Council
Council Offices
16 Church Street
Dumbarton
G82 1QL
Tel: 07785632859
Email: davidjohnston0366@gmail.com
Page 61

Page 62

IMPORTANT NOTICE
1. These particulars are set out as a general outline only for the guidance of intended purchasers
or lessees, and do not constitute, nor constitute part of an offer or Contact.
2. All descriptions, dimensions, reference to condition and necessary permissions for use and
occupation, and other details are given without responsibility and any intending purchasers or
tenants should not rely on them as statements or representations of fact but must satisfy
themselves by inspection or otherwise as to the accuracy of all matters upon which they intend
to rely.
3. No person in the employment of West Dunbartonshire Council has any authority to make or give
any representation or warranty whatever in relation to this property.
4. This brief does not constitute approval under the Planning Act. The purchaser will require
to submit applications for planning permission etc. in the usual manner. Advice in this respect is
available from the Council’s Development Management Team.
5. West Dunbartonshire Council reserve the right to impose title conditions/securities to take into
account the particular circumstances of the transaction.”
Date prepared: November 2023
Page 62

Page 63

Reproduced by permission of Ordnance Survey on behalf of HSMO
(C) Crown Copyright and database right 2015. All rights reserved.
West Dunbartonshire Council Licence No. 100020790.
West Dunbartonshire Council
Title : 53A George Street, Bonhill
Scale : 1:1200Date : 31/10/2023
Map Ref : NS39879EMap No : AM731
GEORG
5557
2
53a
Reproduced by permission of Ordnance Survey on behalf of HSMO
(C) Crown Copyright and database right 2019. All rights reserved.
West Dunbartonshire Council Licence No. 100020790.
West Dunbartonshire Council
Title : 53A George Street Bonhill
Scale : 1:200Date : 31/10/2023
Map Ref : NS3979SEMap No : AM731
Page 63

Page 64

Page 64

Page 65

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer: Resources
Infrastructure Regeneration and Economic Development Committee:
7 February 2024
___________________________________________________________________
Subject:   Sale of 7 Bank Street, Alexandria G83 0NG
1. Purpose
1.1 The purpose of this report is to seek Committee approval for West
Dunbartonshire Council (the Council) to dispose of 7 Bank Street, Alexandria
(the property) to Daveed Malik.
2. Recommendations
2.1      It is recommended that the Committee:
(i) Approves the disposal of 7 Bank Street, Alexandria to Daveed Malik for
£40,144.
(ii) Authorises the Chief Officer Resources to conclude negotiations.
(iii) Authorises the Chief Officer Regulatory and Regeneration to conclude
the transaction on such conditions as considered appropriate.
3. Background
3.1 The property was previously let as a newsagent and then as an Artist studio.
The lease expired in May 2023.
3.2 The Property was marketed for lease but no interest was received.
4. Main Issues
4.1 The property is wholly owned by the Council and is currently unused and
surplus to the requirements of any Council service.
4.2 The property was extensively marketed For Sale during July and August
2023. Marketing details were prepared (Appendix 1).
4.3 The property’s availability was listed on the Council’s website and social
media and listed on the main commercial property marketing websites. Details
were also circulated to commercial property agents, local solicitors, and
business development bodies.
ITEM 11
Page 65

Page 66

4.4 A closing date was set for receipt of informal offers of 25 October 2023. Four
offers were received ranging from £17,711 to £40,144 with Daveed Malik
submitting the highest offer.
4.5 The offer from Daveed Malik is subject only to standard commercial
conditions. The prospective purchaser intends to renovate the shop and
continue to lease it out as a retail unit.
4.6 It is anticipated that the transaction will settle prior to 31 March 2024.
5. People Implications
5.1 There are no significant people implications other than the resources required
by legal services and asset management to negotiate missives and conclude
the transaction.
6. Financial and Procurement Implications
6.1 The Council will benefit from a capital receipt of £40,144 and no longer have
to incur revenue costs for managing and maintaining the property including
utility costs.
6.2 There are no procurement implications arising from this report.
7. Risk Analysis
7.1 The disposal is subject to legal due diligence. There is a risk of the sale not
proceeding due to any emerging issues during the due diligence process. This
is standard for any disposal transaction.
8. Environmental Sustainability
8.1 Any refurbishment of the property will require to be in line with current building
standards.
9. Equalities Impact Assessment (EIA)
9.1 An Equality Impact Assessment is not applicable for the purpose of this
report.
10. Consultation
10.1 Consultations have been undertaken with Finance, Regulatory Services and
Planning.
Page 66

Page 67

11. Strategic Assessment
11.1 By agreeing to this proposal this will be contributing to the Council’s strategic
priority for a strong local economy and improved job opportunities. 
Laurence Slavin
Chief Officer: Resources
Date: 8 January 2024
Person to Contact: Michelle Lynn, Asset Coordinator.
Email: michelle.lynn@west-dunbarton.gov.uk
J David Johnston, Estates Surveyor. 
Email: david.johnston2@west-dunbarton.gov.uk
Appendices: Appendix 1 – Marketing Details.
Background Papers:  None 
Wards Affected: Ward 2
Page 67

Page 68

ITEM 11 - APPENDIX 1: FOR SALE: COMMERCIAL UNIT
7 BANK STREET,
ALEXANDRIA
G83 0NG
LOCATION
The town of Alexandria is situated approximately 17 miles north west of Glasgow City Centre,
within the ‘Vale of Leven’.  Access to the M8 national motorway network can be gained via the
Erskine Bridge or the Clyde Tunnel.
The subject property is located on the east side of Bank Street close to the junction with Main
Street. The adjoining property is occupied by the Fountain Tavern Public House. Other nearby
occupiers include Vale Credit Union, The Paint Pot, Fountain Hairdressers and Mei Beauty . The
attached plan shows the exact location.
DESCRIPTION
The subjects comprise a ground floor lock up unit being part of the ground floor of a traditional
tenement building. There is ample parking in close proximity to the unit.
ACCOMODATION
Net Internal Area is as follows:
Ground Floor: 27.93 sqm ( 300 sq ft)
Page 68

Page 69

RATEABLE VALUE
The property is entered in the Valuation Roll at NAV/RV (2023) at £3,250 per annum. Further
information can be obtained by contacting the Assessor’s Office, Clydebank on telephone number
0141-562-1272 or visit their website at: www.saa.gov.uk
PLANNING
We are advised that Classes 1 & 2 would be appropriate uses for the property.
Interested parties are advised to contact Planning and Building Standards at West Dunbartonshire
Council. TEL  0141 951 7930 to discuss any proposals they might have for the property.
Email:  development.management@west-dunbarton.gov.uk
COMMON CHARGES
The owner will be responsible for their share of the common buildings insurance and for common
repairs to the tenement building of which the property forms part. The share applicable to the
subject property is 7.38%.
ENERGY PERFORMANCE CERTIFICATE
The property has a rating of “G”
ENTRY
Immediate entry is available.
VAT
The property is not elected for vat.
OFFERS
We are seeking offers for the benefit of the Councils interest in the property.
It is likely that a Closing date will be set for receipt of offers and it is strongly recommended that
parties’ register their interest in writing.
FURTHER INFORMATION and VIEWING
Parties are asked to register their interest in writing with:
J David Johnston, Asset Management
West Dunbartonshire Council
Council Offices
16 Church Street
Dumbarton
G82 1QL
Tel: 07785632859
Email: davidjohnston0366@gmail.com
Page 69

Page 70

Page 70

Page 71

Reproduced by permission of Ordnance Survey on behalf of HSMO
(C) Crown Copyright and database right 2015. All rights reserved.
West Dunbartonshire Council Licence No. 100020790.
West Dunbartonshire Council
Title : 130-140 Main Street, Alexandria
Scale : 1:1250Date : 16/05/2017
Map Ref : NS3980SWMap No : AM281
70
38
130
144
72
22.0m
43
44
114
60
25
2
11
22
MAIN
STREET
SUSANNAH STREET
BANK STREET
5
46 to 50
115
Posts
MC
ALISTER
ROAD
102
7
76
Garage
110
132
CREVEUL COURT
95
115
108
134
149
107
1
45
47
43
20.3m
109
74
Sub Sta
2
45
4 to
10
109
105
146
Car Park
21.8m
18.8m
Bank
64
124
78
1
123
111 to
135
Bank
Play Area
Hall
145
138
3
5
125
107
51
PO
36
136
El
Play Area
98 100
113
62
72
117
to
116
14
66 to 78
Medical Centre
6
106
93
Car Park
4
3
127 to
133
3
Library
27
127
129
120
121
21.6m
PH
Car Park
97
121
NORTH STREET
to
39
80
72
12
TCBs
10
89
37
84
52
126
111
PH
68
8
PCs
Oakbank
39
88
El Sub Sta
99 to
105
76
86
24
140
6
1 to 34
72
DW
s
Car Park
LB
5
49
118 to
128
7
2
10
9
Reproduced by permission of Ordnance Survey on behalf of HSMO
(C) Crown Copyright and database right 2015. All rights reserved.
West Dunbartonshire Council Licence No. 100020790.
West Dunbartonshire Council
Title : 7 Bank Street, Alexandria
Scale : 1:1250Date : 16/05/2017
Map Ref : NS3980SWMap No : AM281
Page 71

Page 72

Page 72

Page 73

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer: Resources
Infrastructure Regeneration and Economic Development Committee:
7 February 2024
___________________________________________________________________
Subject:   Sale of land adjacent to 193 Dumbarton Road, Clydebank
1. Purpose
1.1 The purpose of this report is to seek approval for the sale of land at
Dumbarton Road, Clydebank to David Hamilton (private individual).
2. Recommendations
2.1      It is recommended that the Committee:
(i) Approves the sale of the land to David Hamilton at a price of £30,000.
(ii) Authorises the Chief Officer Resources to conclude negotiations.
(iii) Authorises the Chief Officer Regulatory and Regeneration to conclude
the transaction on such conditions as considered appropriate.
3. Background
3.1 The land comprises open space which is wholly owned by the Council, is
currently unused and is not required by the Council for its purposes.
4. Main Issues
4.1 The land is of triangular shape with frontage to Dumbarton Road (A814),
Clydebank as shown in Appendix 1. The land is bounded on its north-eastern
boundary by commercial premises at 193 Dumbarton Road.
4.2 Asset Management were approached by Mr Hamilton for him to purchase the
land from the Council. Mr Hamilton has offered to purchase the land at price
of £30,000.
4.3 It is understood the Council looked in to marketing this land for sale a number
of years ago. However, we believe it was established at the time there is a
Scottish Water water/sewage underground pipe which dissects the site
therefore it is understood any meaningful construction on a significant section
of the land is not therefore possible. Realistically, the land can only be utilised
for surface level use.
ITEM 12
Page 73

Page 74

4.4 Asset Management believe the price offer received from Mr Hamilton
represents fair value for the land, particularly so given the anticipated
difficulties in constructing on the land. The offer received is not subject to any
conditions. 
4.5 It is currently undecided as yet by the purchaser what the future intended use
of the property will be, however, Mr Hamilton has suggested that potential use
as a (surface only) dog exercise area as a service for general public use (at
their cost) is being considered.
4.6 Any Planning and/or Licensing consent in respect of the purchaser’s ultimate
use and/or development of the land will be incumbent on Mr Hamilton to
obtain, at his sole risk and cost.
4.7 It is anticipated that the transaction will settle prior to 31 March 2024.
5. People Implications
5.1 There are no significant people implications other than the resources required
by Legal Services to negotiate missives and conclude the transaction.
6. Financial and Procurement Implications
6.1 The Council will benefit from a capital receipt for the property in the sum of
£30,000.
6.2 The Council will no longer incur resources in maintaining the property, i.e.
grass cutting.
6.3 The Council will therefore generate a revenue savings in maintenance costs.
6.4 No financial outlays are required by the Council to facilitate this arrangement.
6.5 There are no procurement implications arising from this report.
7. Risk Analysis
7.1 The sale will be subject to is subject to legal due diligence. There is a risk of
the sale not proceeding due to any emerging issues during the diligence and
sale process. This is standard for any sale transaction.
8. Environmental Sustainability
8.2 Any development of the property will require to be in line with current building
standards.
9. Equalities Impact Assessment (EIA)
Page 74

Page 75

9.1 An Equality Impact Assessment is not applicable for the purpose of this
report.
10. Consultation
10.1 Consultations have been undertaken with Finance, Greenspace and
Regeneration and Regulatory.
11. Strategic Assessment
11.1 By agreeing to this proposal the Council will benefit from savings in relation to
maintenance costs in line with the budget option approved at Council in
March.
11.2 The recommendation in this report supports the delivery of the Council
Strategic Plan and in particular the achievement of the following priorities:
o Our Communities – Resilient and Thriving
Laurence Slavin
Chief Officer: Resources
Date: x January 2023
Person to Contact: Michelle Lynn, Asset Coordinator.
Email: michelle.lynn@west-dunbarton.gov.uk
Craig Maxwell, Estates Surveyor. 
Email: craig.maxwell@west-dunbarton.gov.uk
Appendices: Appendix 1 - Location Plan
Background Papers:  None 
Wards Affected: Ward 6
Page 75

Page 76

¯
0 0.03 0.05 0.08 0.1
km
Reproduced by permission of Ordnance Survey on behalf of HMSO. (C) Crown copyright and database right 29/08/2023.
All rights reserved. West Dunbartonshire OS Licence Number 100020790.
Scale: 1:1,323@A4
29/08/2023
WDC MapWest Dunbartonshire
Council
16 Church Street
Dumbarton
G82 1QL
I T E M 1 2 -
A P P E N D I X 1
Page 76

Page 77

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer: Resources
Infrastructure Regeneration and Economic Development Committee:
7 February 2024
___________________________________________________________________
Subject:   Servitude of land adjacent to Duntiglennan Fields, Duntocher
1. Purpose
1.1 The purpose of this report is to seek Committee approval for West
Dunbartonshire Council (the Council) to enter into a Servitude Agreement of
land adjacent to Duntiglennan Fields, Duntocher (the land) with BDW Trading
Limited, trading as Barratt West Scotland (Barratt).
2. Recommendations
2.1      It is recommended that the Committee:
(i) Approves a Servitude Agreement of the land to BDW Trading Limited,
trading as Barratt West Scotland.
(ii) Authorises the Chief Officer Resources to conclude negotiations.
(iii) Authorises the Chief Officer Regulatory and Regeneration to conclude
the transaction on such conditions as considered appropriate.
3. Background
3.1 Barratt are requesting a Servitude Agreement from the Council, for the
purpose of installing a new underground drainage pipe, to service their
adjacent site being developed at Duntiglennan Fields, Duntocher.
3.2 Detailed Planning Permission was granted to Barratt for their adjacent
development site on 31 January 2023 (PPA-160-2039) for the construction of
99 new residential housing units.
3.3 A Servitude is a subordinate real right over a property (the burdened property)
for the benefit of another property (the benefited property) which may be
exercised by the owner of the benefited property, in this instance, the Council.
3.4 These include, for example, rights of access, rights to lay pipe(s), as in this
requested instance, under (or over) the burdened property and rights to
overhang the burdened property.
3.5 Servitudes run with the land and can be enforced by successors in title to the
benefited property.
ITEM 13
Page 77

Page 78

3.6 Following completion of the Servitude Agreement, the construction of the new
underground drainage pipe will be undertaken by Barratt, at their sole cost
and expense. 
Main Issues
4.1 The Council has been approached by Barratt to enter into a Servitude
Agreement to allow them to install a new underground drainage pipe at this
location, at their cost.
4.2 The land being sought from the Council for the Servitude is shown on
appendix 1 and is located at Craigielea Road, Duntocher. The land is not
required by the Council for any operational and/or other purposes. 
4.3 The standard process Scottish Water recommend is that a developer engages
to try and reach agreement with the landowner directly. Barratt have complied
with this by engaging with the Council. However where a landowner is
unwilling to reach an agreement and Scottish Water deem this to be
unreasonable Scottish Water can grant statutory powers for laying sewer and
water mains through third party land.  Barratt have confirmed that, should this
request be refused, they will pursue the matter under statutory powers.
4.4 For sewers, as in this instance, this comes in the form of Section 3A powers
which can be served on landowners with the landowner having 56 days to
accept or object to the proposal. If at the point the landowner objects then the
matter will be referred to a Sheriff Court for a legal decision.
5. People Implications
5.1 There are no significant people implications other than the resources required
by legal services and asset management to conclude the Agreement.
6. Financial and Procurement Implications
6.1 There are no financial implications arising from this report.
6.2 There are no procurement implications arising from this report.
7. Risk Analysis
7.1 The disposal is subject to legal due diligence.
7.2 As with any transaction of this nature there is a risk of the Agreement not
proceeding due to issues which arise during the due diligence process and
the land may require to be retained by the Council.
Page 78

Page 79

8. Environmental Sustainability
8.1 Barratt would be required to undertake any installation via the most
sustainable construction technique and methods.
9. Equalities Impact Assessment (EIA)
9.1 An Equality Impact Assessment is not applicable for the purpose of this
report.
10. Consultation
10.1 Consultations have been undertaken with Finance and Regulatory Services,
Planning and Road Services.
11. Strategic Assessment
11.1 By agreeing to this proposal this will be contributing to the Council’s strategic
priority for a strong local economy and improved job opportunities.  
Laurence Slavin
Chief Officer: Resources
Date: 23 January 2024
Person to Contact: Michelle Lynn, Asset Coordinator.
Email: michelle.lynn@west-dunbarton.gov.uk
Craig Maxwell, Estates Surveyor. 
Email: craig.maxwell@west-dunbarton.gov.uk
Appendices: Appendix 1 - Location Plan
Background Papers:  None 
Wards Affected: Ward 4 
Page 79

Page 80

3
3
3
3.5
3.5
SG
BALLOCH-21
E
G
TYPE XXBALLOCH-21
E
G
TYPE XX
BALLOCH-21
E
G
TYPE XX
BALLOCH-21
E
G
TYPE XX
BALLOCH-21
E
G
TYPE XX
BALLOCH-21
E
G
TYPE XX
BALLOCH-21
E
G
TYPE XX
BALLOCH-21
E
G
TYPE XX
DEAN-21
E
G
TYPE XX
AS
BALLOCH-21
E
G
TYPE XX
OPP
DEAN-21
E
G
TYPE XX
AS
FENTON-21
E
G
TYPE XX
OPPDEAN-21
E
G
TYPE XX
OPPDEAN-21
E
G
TYPE XX
OPPFENTON-21
E
G
TYPE XX
OPP
DEAN-21
E
G
TYPE XX
AS
DEAN-21
E
G
TYPE XX
AS
FENTON-21
E
G
TYPE XX
AS
FENTON-21
E
G
TYPE XX
AS
BALLOCH-21
E
G
TYPE XX
AS
DEAN-21
E
G
TYPE XX
OPP
FENTON-21
E
G
TYPE XX
AS
DEAN-21
E
G
TYPE XX
OPP
FENTON-21
E
G
TYPE XX
OPP
Public Open
Space
SuDS
Public Open
Space
Existing Planting
Existing Planting
V
V
VV
V
V
V
V
V
V
V V V V
1
2
3
4
5
6
7
89
10
11
12
13
14
15
16
17
18 19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
3435
36
37 38
39
40
41 42 43 44
45 46 47 48 49 50 51 52 53 54 55
56
57
58
59
60
61
62
63
64
77
76
65
66676869
70
71
72 73 74 75
787980
8182
83
84
85
86
87
88
89
90
9193
94
95
96
92
97
98
99
V
V
V
*
**
V
V
V
V
DEAN-21
E
G
TYPE XX
AS
DEAN-21
E
G
TYPE XX
AS
FENTON-21
E
G
TYPE XX
AS
FENTON-21
E
G
TYPE XX
OPP
FENTON-21
E
G
TYPE XX
OPP
G
KINLOCH-21
E
TYPE XX
AS
BALLOCH-21
E
G
TYPE XX
OPP
DEAN-21
E
G
TYPE XX
AS
DEAN-21
E
G
TYPE XX
AS
DEAN-21
E
G
TYPE XX
AS
DEAN-21
E
G
TYPE XX
AS
DEAN-21
E
G
TYPE XX
AS
FENTON-21
E
G
TYPE XX
OPP
DEAN-21
E
G
TYPE XX
OPP
DEAN-21
E
G
TYPE XX
OPP
FENTON-21
E
G
TYPE XX
OPP
FENTON-21
E
G
TYPE XX
OPP
FENTON-21
E
G
TYPE XX
OPP
DEAN-21
E
G
TYPE XX
OPP
DEAN-21
E
G
TYPE XX
OPP
FENTON-21
E
G
TYPE XX
OPP
DEAN-21
E
G
TYPE XX
OPP
DEAN-21
E
G
TYPE XX
OPP
FENTON-21
E
G
TYPE XXOPP
BALLOCH-21
E
G
TYPE XX
OPP
BALLOCH-21
E
G
TYPE XX
OPP
FENTON-21
E
G
TYPE XX
OPP
CAMPBELL-21
E
G
TYPE XX
OPP
SG
**
*
*
* *
*
*
*
*
*
*
*
DEAN-21
E
G
TYPE XX
AS
FENTON-21
E
G
TYPE XX
AS
BALLOCH-21
E
G
TYPE XX
AS
E
G
CRAIGEND-21
TYPE XX
OPP
S/S
CAMPBELL-21
E
G
TYPE XX
OPP
G
B
GB
Additional
Show home
Parking
FENTON-21
E
G
TYPE XX
OPP
G
KINLOCH-21
E
TYPE XX
BALLOCH-21
E
G
TYPE XX
FENTON-21
E
G
TYPE XX
AS
Play
Area
Existing Dry Stone Dyke Wall to be
reshaped
Extent of Dry Stone Wall to
be retained and re-edged
Extent of Dry Stone Wall
to be repurposed for
enterance feature wall
*
*
EX. SURFACE
MH 0308
CL: 93.64
IL: TBC
EX. FOUL
MH 0304
CL: 93.59
IL: 91.67 TBC
EX. SURFACE
MH 0307
CL: 91.37
IL: TBC
EX. FOUL
MH 0303
CL: 90.68
IL: 88.18 TBC
EX. FOUL
MH 0305
CL: 87.71
IL: 85.21 TBC
EXISTING
150Ø
SURFACE
W
ATER
TBC
EXISTING
150mmØ
FOUL
SEW
ER
TBC
EXISTING
150Ø
SURFACE
W
ATER
TBC
EXISTING
150mmØ
FOUL
SEW
ER
TBC
EX. FOUL
MH 8003
CL: 78.75
IL: 77.23 TBC
EX. FOUL MH
8004
CL: 76.835
IL: 75.105 TBC
EXISTING 225 mmØ
FOUL SEWER
1.1m DEEP SUDS BASIN, VOLUME 480m³
RELEASE RESTRICTED TO 7.5 l/s. TOP OF
BASIN 96.55mAOD, INVERT LEVEL 95.45mAOD.
BASIN LEVELS, VOLUME AND RELEASE
SUBJECT TO CONFIRMATION OF LAYOUT AND
DETAILED DESIGN.
2.0m DEEP SUDS BASIN, VOLUME 1015m³
RELEASE RESTRICTED TO 5l/s. TOP OF BASIN
95.20mAOD, INVERT LEVEL 93.20mAOD.
BASIN LEVELS, VOLUME AND RELEASE
SUBJECT TO CONFIRMATION OF LAYOUT AND
DETAILED DESIGN.
EXISTING SEWERS TO BE SURVEYED AND
PROPOSED CONFIGURATION TO BE
CONFIRMED FOLLOWING DETAILED
DESIGN.
EXISTING SEWERS TO BE
SURVEYED AND
PROPOSED
CONFIGURATION TO BE
CONFIRMED FOLLOWING
DETAILED DESIGN.
DISHED
DEPRESSION WITH
IMPERMEABLE
LINER TO CONVEY
OVERLAND FLOWS
FROM BASIN
OVERFLOW
TOWARDS FARM
ROAD.
375Ø  1/21
375Ø  1/87
ST
ST ST ST
ST
ROADSIDE FILTER
TRENCHES TO PROVIDE
SECOND LEVEL OF
SURFACE WATER
TREATMENT
POROUS PAVING TO
PROVIDE ATTENUATION
AND TREATMENT FOR
SURFACE WATER RUNOFF.
FLOW CONTROL AT S86 TO
RESTRICT FLOW TO 2l/s.
NETWORK PRIVATE
UPSTREAM OF S86.
FLOW CONTROL AT
S83 TO RESTRICT
FLOW TO 2l/s
S63
CL: 76.912
IL: 75.256
S56
IL: 94.753
S55
IL: 95.076
S75
CL: 96.40
IL: 95.129
S53
CL: 97.630
IL: 95.755
S50
CL: 98.095
IL: 96.295
S49
CL: 99.733
IL: 98.008
S47
CL: 101.652
IL: 99.927
S45
CL: 105.821
IL: 104.096
S52
CL: 97.658
IL: 95.417
S51
CL: 98.936
IL: 97.10
S39
CL: 99.716
IL: 97.915
S38
CL: 100.733
IL: 98.933
S37
CL: 103.256
IL: 101.531
S35
CL: 105.441
IL: 102.446
S34
CL: 104.521
IL: 102.661
F21
CL: 105.264
IL: 101.867
F22
CL: 105.483
IL: 101.693
F23
CL: 103.288
IL: 101.081
F24
CL: 100.776
IL: 98.483F25
CL: 99.833
IL: 97.465
F26
CL: 98.979
IL: 96.65
F27
CL: 97.677
IL: 94.967
F34
CL: 77.017
IL: 75.667
F35
CL: 105.791
IL: 103.646
F36
CL: 101.609
IL: 99.477
F37
CL: 99.754
IL: 97.558
F38
CL: 98.143
IL: 95.845
F39
CL: 97.627
IL: 95.305
225Ø 
1/40
150Ø 
1/60
150Ø 
1/60
225Ø 
1/150
150Ø 
1/12
225Ø 
1/13
150Ø  1/16
300Ø  1/19
300Ø  1/18
150Ø  1/19
300Ø  1/21
150Ø  1/18
525Ø  1/149
450Ø 
1/67
300Ø  1/23
150Ø  1/22
150Ø  1/10
225Ø  1/17
150Ø  1/17
225Ø 
1/14
150Ø 
1/13
225Ø 
1/15
150Ø 
1/14
375Ø  1/150
150Ø  1/108
150Ø  1/31
EXMH 6002
CL: 74.358
IL: 72.728
S64
CL: 75.50
IL: 73.85
OVERSIZED PIPE TO
PROVIDE ATTENUATION
ST
F30
CL: 94.637
IL: 91.83
S61
CL: 79.817
IL: 76.904
S59
CL: 83.727
IL: 82.20
S58
CL: 84.345
IL: 83.00
F31
CL: 84.938
IL: 82.96
F32
CL: 84.066
IL: 81.80
F33
CL: 79.718
IL: 76.49
150Ø 
1/10
150Ø 
1/19
150Ø 
1/4
150Ø 
1/4
150Ø  1/110
150Ø  1/85
150Ø 
1/6
G
GGG
G
G
G
G
G
G
G
G
G
G
G
GG
G
G
G
G
G
G
G
G
G
G
G
G G
G
G
S57
CL: 96.30
IL: 94.70
S79
CL: 95.50
IL: 91.598
150Ø 
1/10
150Ø 
1/6
525Ø 
1/183F28
CL: 95.757
IL: 93.936
F29
CL: 95.808
IL: 93.452
150Ø  1/19
150Ø 
1/25
EXISTING SURFACE WATER NETWORK
CONFIRMED VIA SURVEY. LEVEL INFO AND
POSITION TO BE  CONFIRMED PRIOR TO
CONSTRUCTION COMMENCING.
S91
CL: 74.50
IL: 72.825
150Ø  1/73 150Ø  1/73
GG
G
G
G
G
GG
GG
G
G
G
G
G
G
G
S1
CL: 104.102
IL: 102.20
S2
CL: 104.658
IL: 102.143
S3
CL: 103.966
IL: 101.76
S4
CL: 100.751
IL: 98.70
S18
CL: 104.112
IL: 102.228
S19
CL: 103.024
IL: 101.161
S5
CL: 100.595
IL: 98.598
S13
CL: 104.292
IL: 102.373
S14
CL: 102.453
IL: 100.562 S76
CL: 98.266
IL: 96.148
S16
CL: 97.576
IL: 95.382
S11
CL: 94.307
IL: 92.196
S78
CL: 93.483
IL: 91.147
S86
CL: 94.205
IL: 92.537
F1
CL: 104.134
IL: 102.186
F2
CL: 104.688
IL: 102.038
F3
CL: 103.980
IL: 101.091
F4
CL: 100.782
IL: 98.448
F18
CL: 104.088
IL: 101.903
F19
CL: 102.962
IL: 100.825
F20
CL: 100.987
IL: 98.885
F5
CL: 100.616
IL: 98.217
F6
CL: 96.553
IL: 94.087
F14
CL: 104.314
IL: 102.096
F15
CL: 102.483
IL: 100.289 F16
CL: 101.803
IL: 99.636
F17
CL: 97.619
IL: 95.89
F10
CL: 94.117
IL: 92.40
F11
CL: 93.955
IL: 91.83
F12
CL: 93.845
IL: 91.722
F42
CL: 95.66
IL: 93.94
F41
CL: 98.270
IL: 96.469
S15
CL: 101.768
IL: 99.835
150Ø  1/60
300Ø  1/149
150Ø  1/60
300Ø  1/150
150Ø  1/17
150Ø  1/16
150Ø  1/16
150Ø 
1/14
150Ø  1/38
150Ø 
1/10
150Ø 
1/15
150Ø  1/15
225Ø  1/13
225Ø  1/13
150Ø  1/15150Ø  1/17 150Ø  1/13
150Ø  1/22
150Ø  1/14
150Ø  1/19
300Ø  1/17
150Ø 
1/149
150Ø  1/29
150Ø  1/150150Ø  1/91
150Ø 
1/16
150Ø 
1/23
150Ø  1/50
150Ø  1/33
G
G
S6
CL: 96.548
IL: 94.43
S7
CL: 95.988
IL: 93.412
S17
CL: 95.744
IL: 93.68
S8
CL: 96.00
IL: 93.374 HW10
IL: 93.20
S87
CL: 95.637
IL: 91.945
S81
CL: 94.082
IL: 91.788
S82
CL: 93.909
IL: 91.715
S83
CL: 93.811
IL: 91.684
F8
CL: 95.900
IL: 93.930
F9
CL: 95.768
IL: 93.42
HW92
IL: 93.35
S93
CL: 95.872
IL: 93.630
525Ø  1/250
375Ø  1/41
150Ø  1/18
375Ø  1/150
375Ø  1/150
150Ø  1/150
525Ø  1/416
750Ø  1/250
375Ø 
1/19
525Ø  1/250
750Ø  1/250
150Ø  1/16750Ø  1/250
S11 CONTROL
MANHOLE TO
RESTRICT FLOW TO
5l/s AS PER BASIN
CONSTRUCTION
DETAILS DRAWING
S57 CONTROL
MANHOLE TO
RESTRICT FLOW TO
7.5l/s AS PER BASIN
CONSTRUCTION
DETAILS DRAWING
3.5
3
3
LEGEND
DENOTES AREA OF PIPE SERVITUDE
1. ALL ADOPTABLE DRAINAGE TO BE INSTALLED TO
THE COMPLETE SATISFACTION OF SCOTTISH
WATER AND IN ACCORDANCE WITH THE SEWERS
FOR SCOTLAND - 4TH EDITION.
2. ALL BUILDING DRAINAGE TO COMPLY WITH LOCAL
AUTHORITY, DEPARTMENT OF SEWERAGE
STANDARD DETAILS WHERE APPLICABLE AND
STANDARD DETAILS FOR SCOTTISH WATER.
3. ALL EXTERNAL GULLY/SUMP UNIT TAILS AND
BRANCH CONNECTION FROM DISCONNECTING
MANHOLES TO BE 150MM Ø SUITABLY ENCASED IN
CONCRETE.
4. ALL PIPES WITHIN THE SITE BOUNDARIES TO HAVE
A 150MM THICK CONCRETE SURROUND WHERE
CROWN TO COVER OF PIPE IS LESS THAN
a) 1.5M IN AREAS SUBJECT TO TRAFFIC LOADS
b) 1.2M IN AREAS FOR PEDESTRIANS OR SOFT
LANDSCAPING
5. ALL PIPES UP TO 450mm DIAMETER TO BE EITHER
OSMA ULTRA-RIB uPVC PIPES. ALL PIPES OVER
450mm TO BE CLASS M CONCRETE TO BS5911.
6. ALL PIPE MATERIALS TO BE CONSISTENT
BETWEEN MANHOLES.
7. INVERT LEVELS OF EXISTING SEWERS TO BE
CONFIRMED ON SITE BEFORE ANY SEWER WORK
UNDERTAKEN. ANY DISCREPANCIES FOUND
SHOULD BE NOTIFIED TO ENGINEERS.
8. FOR DISCONNECT CHAMBERS THE MINIMUM
INTERNAL DIMENSIONS SHALL BE CIRCULAR
450mm DIAMETER (as per BS 8301)
9. WHERE HOUSE DRAINAGE IS TAKEN THROUGH
BLOCK CARE IS TO BE TAKEN THAT FOUNDATION
LEVELS AND DRAINAGE RUNS DO NOT CLASH.
10. BRANCH CONNECTIONS INTO MAIN LINES TO BE
ACHIEVED VIA ANGLED  BRANCHES. WHERE 90°
BRANCHES ARE REQUIRED THESE SHOULD BE
"SWEPT" BRANCHES. EQUAL 90° BRANCHES ARE
NOT PERMITTED.
11. THE APPROXIMATE POSITION OF SCOTTISH
WATER'S APPARATUS HAS BEEN SHOWN ON THIS
DRAWING. THE CONTRACTOR IS RESPONSIBLE
FOR ESTABLISHING THE TRUE POSITION OF ALL
SERVICES PRIOR TO COMMENCING ON SITE.
12. THE CONTRACTOR IS RESPONSIBLE FOR MAKING
APPLICATION TO CONNECT TO THE PUBLIC SEWER
VIA SCOTTISH WATER. NOTE THE APPLICATION
CAN TAKE SEVERAL WEEKS TO PROCESS.
13. THE CONTRACTOR IS REQUIRED TO INFORM THE
ENGINEER AND SCOTTISH WATER AT LEAST 1
WEEK IN ADVANCE OF STARTING ANY WORKS AT
OR NEAR TO SCOTTISH WATER'S APPARATUS.
14. WHERE POSSIBLE DURING THE WORKS, THE
CONTRACTOR TO PROVIDE CO-ORDINATES OF
SCOTTISH WATER'S EXISTING APPARATUS. THIS
INFORMATION IS TO BE PROVIDED TO THE
ENGINEER FOR ADDITION TO THIS DRAWING.
15. NO DRIVEWAY GRADIENTS GREATER THAN 8%.
16. ACO DRAINS TO BE INSTALLED ON LOW SIDE OF
PRIVATE DRIVEWAYS TO COLLECT SURFACE
WATER RUN OFF.
LEGEND
PROPOSED  SURFACE WATER SEWER
PROPOSED FOUL SEWER
EXISTING FOUL SEWER
EXISTING SURFACE WATER SEWER
PROPOSED ROADSIDE FILTER TRENCH
PROPOSED BIORETENTION UNITS
PROPOSED FOUL DISCONNECT
PROPOSED SW DISCONNECT
NOTE- ALL DISCONNECTION CHAMBERS WITHIN
PLOTS WITH BOUNDARY TREATMENT TO BE SET
0.8-1m BEHIND HEEL KERB
PROPOSED GULLY
ST
BU
G
3
3
EX. FOUL
MH 8003
CL: 78.75
IL: 77.23 TBC
EX. FOUL MH
8004
CL: 76.835
IL: 75.105 TBC
EXISTING 225 mmØ
FOUL SEWER
EXISTING SEWERS TO BE SURVEYED AND
PROPOSED CONFIGURATION TO BE
CONFIRMED FOLLOWING DETAILED
DESIGN.S63
CL: 76.912
IL: 75.256
F34
CL: 77.017
IL: 75.667
150Ø  1/31
S64
CL: 75.50
IL: 73.85
S61
CL: 79.817
IL: 76.904
S59
CL: 83.727
IL: 82.20
F32
CL: 84.066
IL: 81.80
F33
CL: 79.718
IL: 76.49
150Ø 
1/10
150Ø 
1/19
150Ø  1/4
150Ø  1/4
150Ø  1/110
150Ø  1/85
Project Title:
Drawing Title:
Drawn By:
Drawing Number:
Checked By:
Date Drawn:
Revision:
Issue Status:
Scales:
DateDrwnRev Description Chckd
NOTES:
· DO NOT SCALE FROM THIS DRAWING
· THE CONTRACTOR SHALL BE RESPONSIBLE  FOR
CHECKING AND VERIFICATION OF ALL DIMENSIONS
ON SITE  PRIOR TO COMMENCEMENT
· THE CONTRACTOR SHALL CONFIRM AND BRING TO
THE ATTENTION OF THE ENGINEER ANY
DISCREPANCIES CONTAINED IN THIS DRAWING
PRIOR TO COMMENCEMENT.
© Indev Consult Ltd
Phone: 01698 744 610
Email: info@indevconsult.com
Website: www.indevconsult.com
Address: Duart House, 3 Finch Way, Strathclyde Business
Park, Bellshill, ML4 3PR
B21-028-50
AS SHOWN06.04.2023
DWDW
FARM ROAD
DUNTOCHER
SERVITUDE
AGREEMENT
Barratt Homes West Scotland and David Wilson Homes Scotland
7 Buchanan Gate. Cumbernauld Road. Stepps. Glasgow. G33 6FB
Tel : 0141 779 8300
Fax : 0141 779 8301
www.barratthomes.co.uk
www.dwh.co.uk
EXTENTS OF SERVITUDE AGREEMENT
SCALE 1:250
LOCATION PLAN
SCALE 1:1250
0 20
SCALE 1:1250
10 50 100m
0 5 15 20 25m
SCALE 1:250
10
A Amended as per Raeburn
comments
DW 20.04.2023
B Amended as per latest basin
design.
DW 08.01.2024
ITEM 13 - APPENDIX 1
Page 80

Page 81

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer: Resources
Infrastructure Regeneration and Economic Development Committee:
7 February 2024
___________________________________________________________________
Subject:     Lease of The HUB, Kilbowie Road, Clydebank
1. Purpose
1.1 The purpose of this report is to seek Committee approval for West
Dunbartonshire Council (the Council) to transfer The HUB, Kilbowie Road,
Clydebank (the Hub) to Dynamite Gymnastics Club (the club).
2. Recommendations
2.1    It is recommended that the Committee:
(i) Approves lease of the Hub for a period of 25 years, commencing 31
January 2025, to Dynamite Gymnastics Club for £42,000 per annum.
(ii) Authorises the Chief Officer Resources to conclude negotiations.
(iii) Authorises the Chief Officer Regulatory and Regeneration to conclude
the transaction on such conditions as considered appropriate.
3. Background
3.1 In March 2023, as part of savings options put forward to address a £21million
budget gap, members agreed to review community facility provision, across
West Dunbartonshire. The review sought to reduce the provision to a level
more consistent with neighbouring local authorities and address reduced
usage post-pandemic. Transferring responsibility to manage and control
community facilities to voluntary organisations through a combination of
community asset transfers or community lease arrangements would reduce
the costs to West Dunbartonshire Leisure Trust and the Council.
3.2 Whilst the Hub was not part of this initial review the Council continue to
engage with groups across the authority to encourage transfer of ownership
where possible either by disposal, community asset transfer or lease
arrangements.
4. Main Issues
4.1 Dynamite Gymnastics Club was formed in 2004 to provide gymnastics
activities for children and young people. The club is Gymmark Accredited and
currently has around 400 members actively participating in classes on a
ITEM 14
Page 81

Page 82

weekly basis.  They are based in Clydebank with easy road links to Glasgow,
East Dunbartonshire, Erskine and Renfrew. 
4.2 The club activities include general gymnastics classes from ages 3 &
upwards. Gymnasts work towards the British Gymnastics award schemes
along with competitive opportunities in tumbling, floor & vault, trampoline &
double mini tramp.  The club also have two highly successful display teams
who have won titles at various display festivals. 
4.3 The club are currently based in premises at North Avenue in Clydebank
Business Park under a lease due to expire in 2025 and are seeking to secure
alternative premises when their current lease expires. They have identified the
Hub as a potential new location. 
4.4 The market rent for lease has been agreed, in principle, subject to the club’s
formal approval, at £42,000 per annum on a new lease to commence in 2025. 
4.4 The Hub is located on Kilbowie Road, Clydebank and extends to 1,600 m2 or
thereby predominately over ground and first floor levels. 
4.5 The Hub offers a sports hall suitable for a number of activities such as
badminton, short tennis and 5 a-side football. There are also a number of
additional rooms for use for meetings, small conferences, exhibitions and
small functions. 
4.6 The offer of lease to Dynamite is subject to agreement of the usual terms and
conditions associated with a full repairing lease with a target date of entry in
January 2025. 
4.7 The club will work with existing users and West Dunbartonshire Leisure Trust
in the coming months to ensure existing uses can be maintained. 
5. People Implications 
5.1 There are no significant people implications other than the resources required
by Legal Services to negotiate missives and conclude the transaction. 
6. Financial and Procurement Implications 
6.1 The Council will benefit from an annual rent for the Hub in the sum of £42,000
per annum.   
6.2 The Council will no longer incur resources in managing and maintaining the
Hub. 
6.3  The Council will generate a revenue saving of approximately £131,000 per
annum achieved via property and running costs. 
6.4 No financial outlays are required by the Council to facilitate this arrangement.
Page 82

Page 83

6.5 There are no procurement implications arising from this report. 
7. Risk Analysis 
7.1 The lease will be subject to is subject to legal due diligence. There is a risk of
the lease not proceeding due to any emerging issues during the diligence and
leasing process. This is standard for any lease transaction. 
8. Environmental Sustainability 
8.1 An up to date asbestos report and condition survey will be provided for the
Hub and passed to the club. 
8.2 Any refurbishment of the Hub will require to be in line with current building
standards. 
9. Equalities Impact Assessment (EIA) 
9.1 An Equality Impact Assessment is not applicable for the purpose of this
report. 
10. Consultation 
10.1 Consultations have been undertaken with Finance, Regeneration and
Regulatory, Greenspace, Citizen Culture & Facilities and West
Dunbartonshire Leisure Trust. 
11. Strategic Assessment 
11.1 By agreeing to this proposal the Council will benefit from savings in relation to
operating costs and maintenance. 
11.2 The recommendation in this report supports the delivery of the Council
Strategic Plan and in particular the achievement of the following priorities: 
o Our Communities – Resilient and Thriving;
o Our Council – Inclusive and Adaptable 
Laurence Slavin
Chief Officer: Resources
Date: 23 January 2023 
Person to Contact: Michelle Lynn, Asset Coordinator.  
Email: michelle.lynn@west-dunbarton.gov.uk 
Craig Maxwell, Estates Surveyor. 
Page 83

Page 84

Email: craig.maxwell@west-dunbarton.gov.uk 
Appendices: None   
Background Papers:        None 
Wards Affected: Ward 5 