Appendix 1 - Appendix 1: Roads and Neighbourhood Delivery Plan 2023/24 - Mid-
year Progress 
1. Our communities 
Objective 1. Our neighbourhoods are safe, resilient and inclusive 
Performance Indicator
Q1 2023/24 Q2 2023/24
Owner
Status Value Target Short
Trend Long Trend Status Value Target Short
Trend
Long
Trend Note
Percentage of emergency road
related defects repaired within 2
hours of being reported 
97.4% 95%    97% 95%   Performance exceeded
target. Liam Greene
Percentage of non serious road
related defects repaired within 7
working days of being reported 
90.7% 85%    92% 85%   Performance exceeded
target. Liam Greene
Percentage of routine road related
defects repaired within 28 working
days of being reported 
52.5% 85%    68% 85%  
The service continues to
see a steady increase in
performance over the
quarter in this area with
additional resources
directed to target this
area. 
Some defects reported
within the last 3 weeks
are still within response
time. Q2 final value
expected to by end of
October.
Liam Greene
Percentage of all traffic light repairs
completed within 48 hours  100% 98%    100% 98%   Performance exceeded
target. Liam Greene

Page 2

2
Performance Indicator
Q1 2023/24 Q2 2023/24
Owner
Status Value Target Short
Trend Long Trend Status Value Target Short
Trend
Long
Trend Note
Percentage of all street light repairs
completed within 7 days  100% 95%    100% 95%   Performance exceeded
target. Liam Greene 
Objective 2. Our residents health and wellbeing remains a priority 
Action Status Progress Due Date Note Owner
Upgraded play parks and recreation facilities   31-Mar-2024 Action progressing as planned. Tender documents in progress,
following tender being issued the play parks will be progressed. Ian Bain
Completion of delivery of new sport facilities at Posties
Park   31-Jan-2024
Action progressing. We have had some issues with the water
connection. This is expected to be completed in November. Following
this the final works will be progressed. 
Ian Bain 
Objective 3. Our residents are supported to increase life and learning skills 
Action Status Progress Due Date Note Owner
Progress Faifley Campus in line with agreed
programme   31-Mar-2024
Action progressing as planned. Design complete and approved at
Learning Estate Project Board. Pre-planning Members Seminar
complete with Planning application submitted following seminar.
Planning application now approved and Faifley tendering report
approved. 
Craig Jardine 
2. Our Environment

Page 3

3 
Objective 4. Our local environment is protected, enhanced and valued 
Performance Indicator
Q1 2023/24 Q2 2023/24
Owner
Status Value Target Short
Trend Long Trend Status Value Target Short
Trend
Long
Trend Note
% Residents satisfied with the
Waste service overall  81% 82%    80% 82%  
Marginally missed target.
Where are a number of
waste services
improvement initiatives
underway which should
improve satisfaction
levels.
Ian Bain 
Percentage of missed bins collected
within 3 working days of being
reported 
98% 95%    95% 95%   Target met Ian Bain
Percentage of offensive graffiti
removed within 24 hours of being
reported 
100% 100%    100% 100%   Target met Ian Bain
Percentage of non offensive graffiti
removed within 5 working days of
being reported 
100% 100%    100% 100%   Target met Ian Bain
% of total household waste that is
recycled  38.2% 60%     60%  
Q1 performance
significantly missed
target. Recycling rates
are at the same level as
the year end. This is
being managed closely.
The waste strategy has
now been approved and
sets out the route map to
increase performance in
recycling.
Q2 data available mid
November
Ian Bain
% residents satisfied with the street
cleaning service  70% 73%    65% 73%  
Target marginally
missed. 
Further analysis to
identify areas for
Ian Bain

Page 4

4
Performance Indicator
Q1 2023/24 Q2 2023/24
Owner
Status Value Target Short
Trend Long Trend Status Value Target Short
Trend
Long
Trend Note
improvement are
underway.
% Residents satisfied with Parks &
open spaces  81% 85%    70% 85%  
Target missed. There are
a number of initiatives
underway including
improving play parks
which should increase
satisfaction. 
Ian Bain 
WM5: Percentage of abandoned
vehicles that require to be removed
by the council that are removed
within 14 days 
100% 100%    100% 100%   Target achieved. Ian Bain 
Action Status Progress Due Date Note Owner
Prepare for introduction of Deposit Return Scheme   31-Mar-2024
Action progressing as planned. The introduction of deposit return
scheme has been delayed to 2025. Options Appraisal completed in
partnership with zero waste Scotland to reflect future impact of DRS.
Communications Strategy will be implemented in advance of
introduction which is now expected to be 2025. 
Gail Macfarlane
Develop Strategy for transition to electric fleet   31-Mar-2024
Action progressing as planned. Review of the current vehicle
replacement programme is underway to identify opportunities to
move to electric fleet. 
Gail Macfarlane
Finalise the delivery of suitable new allotment sites   31-Mar-2024 Action progressing as planned. Evaluation of tenders underway to
agree award of contract.  Ian Bain
Develop a new local bio diversity action plan   31-Mar-2024 Action progressing as planned. The consultation is underway and the
outcomes will inform the plan. Ian Bain
Continue to explore alternative methods of weed
control   31-Mar-2024
Action progressing as planned. Demonstration of foam alternative
complete, when the other alternatives are reviewed a full evaluation
will be done. 
Ian Bain
Develop Ash die back action plan   31-Mar-2024
Action progressing as planned. Operational process agreed to deal
with cases that are identified on a risk based approach. Plans
underway to procure a consultant to carry out full audit to inform the
Council wide action plan.   
Ian Bain

Page 5

5   
Objective 5. Our resources are used in an environmentally sustainable way 
Performance Indicator
Q1 2023/24 Q2 2023/24
Owner
Status Value Target Short
Trend Long Trend Status Value Target Short
Trend
Long
Trend Note
Tonnage of biodegradable municipal
waste landfilled  4762 3000     3000  
Q1 Target significantly
missed. Performance has
improved. Although we
are currently over our
target tonnage, we have
made a considerable
decrease from the
previous period. The
waste strategy has been
developed to review
collection and separation
of materials.
Q2 data available mid
November.
Ian Bain 
Action Status Progress Due Date Note Owner
Develop proposal for resource recycling and reuse
centre (RRRC)   31-Mar-2024
Action progressing as planned. Committee approved preferred
location and to proceed to detailed design. Tender Route approved
and appointment of consultant underway.
Gail Macfarlane
Develop Long term waste strategy   31-Mar-2024 Action complete. Waste Strategy and Action Plan approved by August
Committee. Gail Macfarlane
Develop an Implementation Strategy and expansion
plan for EV charging points   31-Mar-2024
Action progressing as planned. The service continues to work as part
of the wider City Region Group with consultant engaged to develop
region wide plan.
Liam Greene
Introduce charging for the use of Council owned EV
charging points   30-Jun-2023
Action completed successfully. New charging tariff introduced and
implemented to Council owned charging points. Charging tariff will be
reviewed regularly going forward.  
Liam Greene

Page 6

6   
Objective 6. Our neighbourhoods are sustainable and attractive 
Performance Indicator
Q1 2023/24 Q2 2023/24
Owner
Status Value Target Short
Trend Long Trend Status Value Target Short
Trend
Long
Trend Note
% of Special Needs Adaptation
projects completed by consultancy
services from receipt of referral to
carrying out survey, design and
submission of building warrant
within 60 day target for type 3
projects 
82% 70%    100% 70%  
All 8 projects undertaken
in Q2 period completed
within 60 days
Craig Jardine
% of capital projects supported by
capital investment team, delivered
within agreed plan 
84% 80% New PI for
23/24   80% 80%  
Good progress continues
to be made on major
capital projects. It should
be noted that some
elements of progress are
out with the control of
the team such as
agreement to proceed
with the District Heating
Expansion project.
Craig Jardine
% Residents satisfied with roads
maintenance  23% 40%    32% 40%  
Target significantly
missed with
improvement from
previous quarter. Review
of road maintenance plan
and roads
communication and
engagement strategy is
underway. A spotlight set
of questions will be in the
telephone survey for the
next 2 quarters to
uncover the issues and
influence satisfaction rate
Liam Greene

Page 7

7
Action Status Progress Due Date Note Owner
Progress new Vale of Leven Cemetery extension   31-Mar-2024 Action progressing as planned. Contract awarded and plan in place to
start the groundworks late October 2023. Ian Bain
Pavement parking, investigate and develop a strategy
in line with Scottish guidance next phase   31-Mar-2024
Action progressing as planned. Scottish Government guidance
reviewed and consultant appointed to undertake analysis against the
defined criteria and provide recommendations for review.   
Liam Greene
Prepare a plan to introduce Parking Enforcement   31-Mar-2024
Action progressing as planned. Draft application submitted to Scottish
Government for feedback, additional information has been requested
and a response is being prepared. Consultants have been appointed
and scope of works agreed.
Liam Greene
Finalise design plan for Gruggies Burn Flood
Management   31-Mar-2024
Action progressing as planned. Hydrology assessment and modelling
completed with scope agreed with designer. Contract has been
finalised to allow progress to design and consultation.
Liam Greene
Undertake flood management Improvement Study for
Dumbarton and Vale   31-Mar-2024
Action progressing as planned. Offer for free property level protection
to high risk properties circulated. Progressing with review of high
level actions and feasibility underway.
Liam Greene
Undertake survey works to support the development of
a Surface Water Management Plan for Clydebank   31-Mar-2024
Action progressing as planned. Flood modelling review and
consultation underway with Scottish Water and SEPA to identify
intervention options.
Liam Greene 
Risk Description Current
Assessment Target Assessment Date
Reviewed Note Owner
Impact of major adverse
weather incidents on
services
A significant period of adverse weather
may result on failure to deliver key
operational functions of E&N services 
02-Oct-2023
The Business Continuity Plan would come
into effect in the event of a major adverse
weather incident. 
No change to risk matrix
Ian Bain
Failure to maintain road
network during adverse
weather
A significant period of adverse weather
may result in failure to deliver key
operational functions of R&T services
and other Council services. 
28-Sep-2023
Winter training for all appropriate staff
has been completed, ready for new winter
season 
No change to risk matrix
Liam Greene

Page 8

8
Risk Description Current
Assessment Target Assessment Date
Reviewed Note Owner
Failure to manage and
maintain the road network
effectively
Failure to manage and maintain the road
network effectively will have an adverse
impact on user safety, traffic movement,
air quality, economic growth and reduce
access to facilities and amenities. The
Council’s reputation as a place to live
and work with access to employment,
education, leisure and health
opportunities would be adversely
affected. 
28-Sep-2023
Significant investment in resurfacing
works over the course of the year with
programme now 80% complete. Service
continues to respond to 
reported defects across the network. 
No change to risk matrix
Liam Greene
Challenges in delivering
effective services in relation
to Roads & Neighbourhoods
The risk that the Council’s fails to deliver
on the three services within Roads &
Neighbourhood: Roads & Transportation,
Fleet & Waste and Greenspace. These
areas provide services across a range of
areas including managing and maintain
roads, footpaths and associated
infrastructure, managing flood risk,
grounds maintenance, street cleaning,
burial and cremation, outdoor facilities,
waste and recycling and vehicle fleet
management. Failing to ensure these
services are not fully fit for purpose
could result in adverse consequences in
relation to delivering efficient and
effective services. 
02-Oct-2023
Service continues to provide full service,
monitoring in place to ensure any adverse
issues are highlighted and appropriate
actions taken. 
No change to Risk Matrix
Gail Macfarlane 
3. Our Economy 
Objective 7. Our area has the infrastructure for sustainable and inclusive growth where businesses can flourish

Page 9

9
Action Status Progress Due Date Note Owner
Progress demolition of Artizan Centre within agreed
timeframes   31-Mar-2024
Action progressing as planned. Building warrant process underway
with application made, approval awaited. Tender evaluation complete
and preferred contractor selected.  
Craig Jardine
Support the progress of Exxon City Deal Project   31-Mar-2024 Action progressing as planned. The full business case has been
prepared, approved by Council and approved by City Deal. Craig Jardine
District Heating Network Expansion Programme (
Golden Jubilee Hospital)   31-Mar-2024
Action progressing as planned. Agreement in principal has been
received from Golden Jubilee Hospital, final decision to proceed is
awaited.  
Craig Jardine 
Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
Failure to deliver the Queens
Quay District Heating
Network into the Golden
Jubilee Hospital
Budget has been set with 50% match
funding agreed by LCITP. Early
negotiations progressing well Golden
Jubilee however work cannot start until
agreement is formalized. 
01-Apr-2022
Awaiting formal contract acceptance from
Golden Jubilee Hospital before works can
commence. 
Craig Jardine 
4. Our Council 
Objective 10. Our workforce is resilient and skilled where digital technology supports service delivery for our residents 
Action Status Progress Due Date Note Owner
Develop and implement wellbeing, employee
engagement, equality and learning and development
plans to enable capabilities, improve resilience and
promotion of a diverse workforce  
31-Mar-2024 Capital Assets team have reviewed communication methods with
Team's following restructure process.   All Managers
Develop and implement employee life cycle plans in
line with the People First Strategy to attract and retain
the workforce.  
31-Mar-2024
Capital Assets Team are Currently reviewing role profiles where
required following restructuring and alternative method for skills
shortage has been found. Green Space have introduced one team
approach over grounds and street cleaning and will start to introduce
All Managers

Page 10

10
Action Status Progress Due Date Note Owner
this across other teams. Roads are undertaking service review,
including role profiles to ensure resources in place to address future
needs
Implement service review process including role
design, use of new technology and new ways of
working to add resilience, address gaps, and establish
opportunities for efficiencies  
31-Mar-2024
For Corporate Assets team, all required savings made for 23/24 and
posts removed from system. Roads and Transport are Undertaking
service review, including role profiles to ensure resources in place to
address future needs  
All Managers
Develop and implement learning and development plan
and development opportunities to improve capabilities
and resilience within the workforce.  
31-Mar-2024
Statutory Compliance training covering asbestos & legionella has
been completed for the first 6 months of the year for Capital Assets
Team.  All Managers 
Objective 11. Our Council is adaptable and focused on delivering best value for our residents 
Performance Indicator
Q1 2023/24 Q2 2023/24
Owner
Status Value Target Short
Trend Long Trend Status Value Target Short
Trend
Long
Trend Note
% Consultancy Services project
deliverables for Housing and
General Services projects that were
delivered to programme 
82% 80% New PI for
23/24   84% 80%  
Good progress continues
to be made in delivering
Consultancy Services
projects. It should be
noted that some
milestones are out with
the team control.
Consultancy Service
currently have 81 live
projects.
Craig Jardine 
Action Status Progress Due Date Note Owner
R&N service review including a strategic and structural
review of roles and responsibilities across the service.   31-Mar-2024
Action progressing as planned. A review of the full role profile of
Service Managers has been undertaken and the reviewed reporting
structure has been implemented. The effectiveness of the reviewed
structure will be monitored. 
Gail
Macfarlane

Page 11

11
Action Status Progress Due Date Note Owner
Continue to identify opportunities to work jointly with
partnership in the City Region both through
procurement and service delivery  
31-Mar-2024
Action progressing as planned. Council represented on City Region
Senior Officers group carrying out further work on determining
recommendation on model. A recommendation on the Electric
Vehicle delivery model has been developed. The strategy and
expansion plan will follow. 
Gail
Macfarlane
Progress development of a best value proposal for the
management of biodegradable municipal waste   31-Mar-2024
Action progressing as planned. Market testing and interviews with
prospective suppliers undertaken. The recommended route to market
is being considered. 
Gail
Macfarlane
Complete phase 2 of the Fit for Service review of waste
services   31-Mar-2024
Action progressing. Routes reviewed and developed with workforce.
Communication strategy has been developed and will be
implemented. Further to management restructure Route
Optimisation will be implemented Nov ‘23.
Gail
Macfarlane
Review of Waste Service Provision following Fit for
Future    Duplicate Action. This has now been cancelled.   Gail
Macfarlane
Undertake Greenspace Service Review   31-Mar-2024
Action progressing as planned. A full review of service staff change
against service provision has been completed. Plans for 24/25
season in development.    
Ian Bain
Progress construction of new Salt Dome   31-Mar-2024
Planning permission has been granted and final floor slab design
completed. Application for building warrant has been submitted,
approval awaited.
Liam Greene
Progress capital projects managed by consultancy
services in line with agreed plans   31-Mar-2024
Action progressing as planned. Projects continue to be reviewed and
monitored each quarter via progress meetings and or project boards.
Consultancy Services currently involved in 81 projects. 
Craig Jardine
Progress Depots Refurbishment Programme in line with
agreed timeframe   31-Mar-2024
Action progressing as planned. Evaluation of essential repairs to all
depots done and essential upgrade works to offices with depots
complete. 
Craig Jardine
Implement revised CAM team structure   31-Mar-2024 Action completed successfully with saving proposals met. Craig Jardine 
Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
Challenge to delivery of
burial and cremation
services
A number of factors may impact on
ability to deliver these services.  For
example a pandemic would create
significant immediate demand on
services. 
02-Oct-2023
We have completed extensions to
Dumbarton and North Dalnottar
cemeteries, and work is underway on the
development of the new Vale Of Level
Cemetery. This will mitigate the impact of
any challenges to the burial and cremation
services. 
Ian Bain

Page 12

12
Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner 
No change to risk matrix.
Inability to deliver priority
services as a result of fuel
shortages
A fuel shortage would significantly
impacting on our ability to provide
priority service across West
Dunbartonshire. 
02-Oct-2023
Council participates in the Scottish
Government Liquid Fuels Framework and
contributes to the work of the Scottish
Government Fuel Resilience Group. There
are no issues with fuel at this time. 
No change to risk matrix.
Gail Macfarlane 
Action Status 
Cancelled 
Overdue 
Not on track 
In Progress and on track 
Completed 
PI Status 
Target significantly missed 
Target narrowly missed 
Target met or exceeded 
Risk Status 
Alert 
High risk
Long Term Trends 
Improving 
No change 
Getting worse 
Short Term Trends 
Improving 
No change 
Getting worse

Page 13

13 
Warning 
OK 
Unknown