ARGYLL AND BUTE COUNCIL  COUNCIL
DEVELOPMENT AND
ECONOMIC GROWTH
24 SEPTEMBER 2025
HOUSING EMERGENCY – FEASIBILITY OF TIREE SELF BUILD PLOTS;
CONTRIBUTION TO INCREASED CONSTRUCTION COSTS AT OCCUPIED
PHASE 3 DUNBEG; FEASIBILITY OF GLENCRUITTEN ROAD FOOTPATH
IMPROVEMENTS 
1.0 EXECUTIVE SUMMARY 
1.1 The main purpose of this report is to request the use of Strategic Housing
Funding (SHF) to support three different housing projects; which in their own
but different ways will make valuable contributions to the tackling the Housing
Emergency. 
1.2 Dunbeg Phase 3, built by LINK RSL, was completed in August 2023, and
delivered 300 affordable houses, a significant contribution to housing supply
within Oban and Lorn. Like most construction projects over recent years,
partly due to the Pandemic, time delays and fuel and construction cost
inflation, the final development cost is above budget. Both LINK and Scottish
Government have agreed to pay additional costs towards the development.
Following negotiation to reduce the potential sum, it is considered appropriate
that an additional SHF contribution of £175k be made to cover the additional
costs. 
1.3 Tiree is identified as an area of high housing need and demand and is one of
the Area’s fragile populations.  The Local Housing Strategy set out an aim to
explore the delivery of self-build plots, and the Housing Emergency Action
Plan contains an action to identify public sector land that can be used for
housing solutions.  Two Council owned sites on Tiree are surplus to other
requirements, and following initial investigation are considered potentially
suitable for the delivery of serviced self-build plots.  Further feasibility studies
are required to establish the details of if and how this can be done, and the
costs involved, and the report requests Members approve use of the SHF to
carry out this work. 
1.4 LDP2 identifies a potential development area at Glencruitten Rise, Oban.  The
site could deliver up to 100 affordable houses, if offsite footpath improvements
can be delivered along Glencruitten Road.  In order to establish in detail how
this might be delivered, it is necessary to carry out design and feasibility
studies that will establish costs and landownership required, and the report
requests members utilise the SHF to carry out this work.

Page 2

1.5 It is recommended that Council: -
i. Approve a grant of £175k from SHF to LINK RSL to cover additional unfunded
development costs incurred in Phase 3 Dunbeg; and
ii. Agree use of up to £100k from SHF to cover feasibility studies exploring delivery
of serviced self-build plots on Council owned land in Balemartine and Crossapol,
Tiree.
iii. Agree use of up to £50k from SHF to cover feasibility studies for delivering
footpath improvements on Glencruitten Road, to facilitate affordable housing at
Glencruitten Rise subject to the requirements on the developer to first
demonstrate a contractual agreement with an RSL to develop the site; or
provide written acknowledgment that any offsite road improvement would be
financed by the development of the site as more particularly set out in para 4.23.

Page 3

ARGYLL AND BUTE COUNCIL  COUNCIL
DEVELOPMENT AND
ECONOMIC GROWTH
24th  SEPT 2025
HOUSING EMERGENCY – FEASIBILITY OF TIREE SELF BUILD PLOTS &
CONTRIBUTION TO INCREASED CONSTRUCTION COSTS AT OCCUPIED
PHASE 3 DUNBEG; FEASIBILITY OF GLENCRUITTEN ROAD FOOTPATH
IMPROVEMENTS 
2.0 INTRODUCTION 
2.1 As the strategic housing authority for Argyll and Bute, the Council has a
statutory duty to assess the need and demand for housing in the area
and to ensure that any unmet need for housing is addressed through
the Local Housing Strategy (LHS) and the Strategic Housing
Investment Plan (SHIP), and these have identified the potential for self-
build plots to contribute. 
2.2 Following the declaration of the Housing Emergency, a key priority has
been to identify public sector land which can be utilised to contribute to
housing supply. In addition, there has been a recognition that the
significant increase in construction costs over recent years are a
challenge to delivery. 
3.0 RECOMMENDATIONS 
3.1 It is recommended that Council:-
i. Approve a grant of £175k from Strategic Housing Fund to LINK
RSL to cover additional unfunded development costs incurred in
Phase 3 Dunbeg; and
ii. Agree use of up to £100k from Strategic Housing Fund to cover
feasibility studies exploring delivery of serviced self-build plots on
Council owned land in Balemartine and Crossapol, Tiree.
iii. Agree use of up to £50k from SHF to cover feasibility studies for
delivering footpath improvements on Glencruitten Road, to facilitate
affordable housing at Glencruitten Rise subject to the requirements on
the developer to first demonstrate a contractual agreement with an RSL
to develop the site; or provide written acknowledgment that any offsite
road improvement would be financed by the development of the site as
more particularly set out in para 4.23.

Page 4

4.0 DETAIL 
Dunbeg Phase 3 Increased Construction Costs 
4.1 Dunbeg Phase 3, built by LINK RSL, was completed in August 2023,
and delivered 300 affordable houses, making a significant contribution
to housing supply within Oban and Lorn.  Like most construction
projects over recent years, partly due to the Pandemic, extension of
the construction period, and fuel and construction cost inflation, the
final development cost is above budget.   The proposed final cost of
construction was £62.6m, which was circa £4m above expected. 
4.2 In April, LINK approached the Council to request assistance in
covering the funding gap, proposing that the SHF might contribute
£600k. 
4.3 Members may be aware that the Council has already contributed the normal
SHF award of £12k per unit or £3,600,000 in total. Notwithstanding this
previous contribution, officers consider that, given the additional costs are
generally in line with the wider experience of the development industry over
recent years and combined with the strategic importance of the wider
Dunbeg development to housing supply in the area, there is merit in
considering the request. 
4.4 Officers engaged with Scottish Government More Homes division and
established they had offered to contribute an additional £1.478m to cover the
costs. Utilising the same calculation methodology, officers proposed in
principle an additional SHF award of £118k.  LINK suggested that this would
still leave them struggling to bridge the cost gap.  Considering the ongoing
strategic importance of the remaining Dunbeg development, which will be
delivered by a partnership of LINK, the Council and Scottish Government, it
is proposed a compromise award of £175k be made from the SHF.  LINK has
confirmed that sum will allow them to proceed in covering the outstanding
costs.  Accordingly, this report seeks approval to award LINK £175k (£580
per unit) from the SHF to cover additional Dunbeg Phase 3 costs. 
Background to The Housing Situation on Tiree 
4.5 As of June 2025, there were around 568 homes in Tiree, of which 47% are
not in use as principle homes meeting local need.  155 properties are
classed as second/holiday homes, 58 homes are empty or long term
unoccupied, and there are 55 self-catering units on the Rates Register. 
4.6 There is a total of 43 social rent properties in Tiree, 25 are owned by ACHA
and 18 are owned by WHHA (as per RSL returns 2024/25).  This amounts to
8% of the total dwelling stock. 
4.7 Affordability on the open market remains a significant issue for local
residents. The average archived house price, based on 2023 and 2024
sales, is £174,929, which would require a household income of £49,979 to be

Page 5

considered affordable.  62% of residents in Tiree could not afford to purchase
on the open market and therefore, require alternative affordable options such
as social rent and shared equity. 
4.8 Expressed demand for RSL housing is registered via the HOMEArgyll waiting
list, and as of June 2025, there was 17 active applicants with Tiree as first
preference, and 11 of these were in housing need. There are a further 3
applicants with Tiree as second or third preference, all of which are in
housing need.  There was a turnover of 9 social rented properties in 2024/25
in the area, resulting in a pressure ratio of 2:1 (applicants: lets). 
4.9 A 2023 survey of Tiree community housing need, commissioned by Tiree
Community Development Trust, received a response of 23% of Island
residents.  It identified a strong demand for self-build plots (22% of those
wishing to move) as a first preference for people seeking housing solutions. 
It also identified the lack of available plots, the price of those plots that are
available, and the cost of construction as limiting factors. 
4.10  The delivery of housing on plots has been a traditionally important part of the
new build housing delivery within Argyll and Bute.  Self-build plots are
considered affordable housing. 
4.11 The Council’s last HNDA research and LHS stakeholder engagement
identified an ongoing interest in this form of provision in a number of local
HMAs, particularly on the islands, and this is supported in a recent National
Islands Plan Survey (July 2021) which suggests that 45% of island residents
believe that self-build is a viable option for homeownership. 
4.12 The LHS states that through the SHIP process, and the Rural Growth Deal,
the Council will also explore the potential for providing serviced plots for self-
build projects on select sites within local authority or RSL landbanks, and this
is one of the Key Actions and Targets of LHS Outcome One.  The Housing
Emergency Action Plan also prioritises the identification of public sector land

Page 6

that can provide housing solutions. 
4.13 Although further up to date market research will be required, the provision of
affordable serviced self-build plots would be an important additional tool in
tackling the housing emergency, and will help contribute to sustaining
remote rural fragile populations.  Given the restricted availability of
development land on Tiree, partly due to its crofting nature, this may be an
appropriate use of the surplus land holding the Council has on the Island. 
Tiree Self-Build Plot Feasibility Studies 
4.14 The Council owns two small surplus sites that have the potential to deliver
self-build serviced plots.  One is in Balemartine, and one in Crossapal both
shown below 
Shore St, Balemartine

Page 7

Crossapol 
4.15 The Council has already carried out initial Ground Investigation work that
confirms the sites are potentially suitable for development.  At this stage the
Council needs to undertake more substantive feasibility studies, particularly
the design and consenting of suitable utilities, service connections and
drainage, a detailed road design which would allow for works tendering and
achieving planning consent.  A combined cost estimate to achieve this for the
two sites is £80k, but to allow for unexpected contingencies it is proposed an
allowance of £100k be approved from the SHF. 
4.16 In parallel with this work officers will continue to liaise with the local
community to develop better market understanding, and to explore other
support mechanisms such as: availability and flexibility of mortgages,
potential partners to offer modular custom build options, which would simplify
arranging island construction.  The Council launched a self-build register in
2024 which gives households an opportunity to register their interest in self-
build. This will help us to understand more about the demand for self-build
plots across the area. 
4.17 When all the feasibility work is complete, officers will revert to Council for
Members to consider if they wish to pursue full delivery of the self-build plots
which is likely to be between 5 and 8 plots.

Page 8

Footpath Improvements To Glencruitten Road To Facilitate Potential
Affordable Housing Site 
4.18 LDP2 identifies a Potential Development Area (P4109) at the upper end of
Glencruitten Road and to the West of Glencruitten Rise.  A Masterplan was
approved by the Council in 2020 which showed how the site might potentially be
developed for 100 houses, subject to the identification and delivery of suitable
access arrangements.  It should be noted that a Masterplan consent is not a
planning consent, although it would be considered a material consideration in the
determination of any planning application.  The suitable access arrangements would
include improvements to Glencruitten Road to ensure the safety of pedestrians who
currently need to use the carriageway at certain points. 
4.19 The site has been identified within the Council’s Strategic Housing Investment Plan,
and is a site that, in principle is likely to receive Scottish Government More Homes
funding for affordable housing, if it can be delivered within their financial
benchmarks. 
4.20 Some or all of the access improvements that are required lie in areas outside the
control of the site developer / owner.  Moreover, the improvements that are required
would be likely to require the Council to use its powers as the Roads Authority to
implement.  As such the Developer is reliant on the Council to establish if it is
feasible to undertake a programme of road improvements that would deliver the
required road safety improvements. 
4.21 In light of the housing emergency, and particularly the projected short term lack of
housing supply, the Council has given an undertaking to explore the feasibility of
delivering the required Glencruitten Road improvements which could if delivered
facilitate the potential affordable housing site.  This work involves the design of a
suitable safe footpath provision, the identification of the physical cost of those works,
the identification of the land ownership required and the cost of its acquisition.  It is
likely that the land acquisition required will include parts of more than one residential
garden, and may include residential buildings.  It is anticipated that Compulsory
Purchase Orders would be required to achieve this.  The estimated cost of carrying
out this initial feasibility work is £50,000. 
4.22 This would be a phased process.  Once the feasibility studies had identified a
costed solution, it would be necessary to identify a funding solution.   It had
previously been considered this would be achieved through a Scottish Government
Housing Infrastructure Fund application but this funding route has been stopped by
Scottish Government.  As a result, this would now most likely to be through Scottish
Government More Homes Division award of grant to an RSL who proposed to
deliver an affordable housing scheme on the site.  As such the funding would not be
able to move forward until an RSL was in control of the site. 
4.23 It is officers opinion that in light of the Housing Emergency it makes sense to pursue
the first stage feasibility studies which will identify the acceptable solution and
costing.  This will then create the opportunity for an interested RSL to explore the
necessary funding.  Accordingly, it is requested that Council approve use of up to
£50,000 from the Strategic Housing Fund to carry out the feasibility work, although
this is subject to the developer first either:
• Demonstrating a contractual agreement with an RSL to develop the P4109 site
West of Glencruitten Rise for affordable housing; or

Page 9

• Providing written acknowledgment that any offsite road improvement as
explained in the report, in connection with the development of site P4109, would
be financed by the development of the site. 
4.24 Additionally, and at a later stage the Council would need to make a formal decision
that it was willing to undertake a CPO and implement the road improvement works,
if funding is identified.   
5.0 CONCLUSION 
5.1 The council is asked to approve the recommendation to award a grant
of £175k from the SHF, to cover additional development costs incurred
at the completed Dunbeg Phase 3 development.  In addition, Council is
asked to agree the potential use of up to £100k of SHF to fund feasibility
studies for serviced self-build plots of two Council owned sites on Tiree. 
Lastly the Council is asked to agree feasibility funding of up to £50,000
to identify and design suitable road improvements to Glencruitten Road
to facilitate the potential affordable housing site on Glencruitten Rise,
subject to agreements outlined in the report with the developer. 
6.0 IMPLICATIONS 
6.1 Policy - The proposal is consistent with current Council policy including the
Local Housing Strategy vision and outcomes which are directly aligned with
the overarching objectives of the Outcome Improvement Plan, in particular
Outcome 2 – we have infrastructure that supports sustainable growth. The
proposal does exceed the delegated Officer approval for the use of the
Strategic Housing Fund to enable the delivery of affordable housing which is
£12,000 per unit. 
6.2 Financial - There are sufficient funds in the Strategic Housing Fund to
support the proposal. 
6.3  Legal – None. 
6.4  HR – None. 
6.5 Customer Service – None. 
6.6 Risk – There is a risk of depopulation, damage to the economy, a risk to
delivering essential services in the local authority area if partners cannot
effectively tackle the Housing Emergency. 
6.7 Climate Change - making best use of existing stock by bringing empty
properties back into use and installing energy efficiency measures helps
towards achieving climate change targets. 
6.8  Fairer Scotland Duty – the delivery of housing opportunities across Argyll
and Bute facilitates social-economic opportunities for all. The activity in the
report links to the Child Poverty Strategy.

Page 10

6.9 Equalities - protected characteristics - the activity outlined in the report is
consistent with the aims and objectives set out in the Local Housing Strategy
which is subject to an EQIA. 
6.10 Consumer Duty – none. 
6.11 Island Communities – one of the housing projects detailed in the report is
being delivered on the islands which will provided many benefits such as
employment and the continued delivery of essential services to island
communities. 
6.12 Children’s Rights and Wellbeing - the delivery of more housing options will
enable more children to have a safe secure environment. 
Kirsty Flanagan, Executive Director with Responsibility for Development and
Economic Growth 
August 2025 
For further information contact: 
Fergus Murray, Head of Development and Economic Growth
fergus.murray@argyll-bute.gov.uk 
Matt Mulderrig, Development Policy and Housing Service Manager
Matt.Mulderrig@argyll-bute.gov.uk 
Douglas Whyte, Team Lead – Housing Strategy
douglas.whyte@argyll-bute.gov.uk