WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS MASTER LIST
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
1
Project Life Financials 450 193 43% 193 (258) -57%
Current Year Financials 0 0 0% 0 0 0%
Project Description
Project Manager Steven Milne
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
2
Project Life Financials 16,155 8,997 56% 13,997 (2,158) -13%
Current Year Financials 4,098 0 0% 4,098 0 0%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-25
3
Project Life Financials 22,213 22,100 99% 22,100 (113) -1%
Current Year Financials 19,984 120 1% 19,984 0 0%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-25 31-Mar-25
4
Project Life Financials 11,220 7,365 66% 11,220 0 0%
Current Year Financials 7,209 150 2% 7,209 0 0%
Project Description
Project Manager Patricia Rowley/ Craig Jardine
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Zero Carbon
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Mitigating Action
Officers will continmue to persue the credit note
Anticipated Outcome
Project to be delivered on programme and within budget once it has been fully set.
LUF
Year one LUF spend includes acquisition cost of Artizan Centre, and design development for Glencairn House and
Connecting Dumbarton
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Following completion of the Developments Strategy the delivery plan has been revised and updated.
District Heating Network Expansion
Network expansion to Golden Jubilee is discussed at every District Heating Project Board
Anticipated Outcome
Main Issues / Reason for Variance
Regeneration Fund
This project has been completed. However a credit is outstanding and should be received this financial year.
ZeroCarbon
Credut note received and project closed
Funding to implement major regeneration projects linked to community charrettes. 
Planned End Date Forecast End Date
Projects ongoing and expected be delivered on time and on budget
Mitigating Action
None required
Anticipated Outcome
Projects delivered on time and on budget
Mitigating Action
None available at this time
Anticipated Outcome
District Heating Network Expansion.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Network expansion to GJNH (Golden Jubilee National Hospital) will commence pending approval to proceed by the GJNH Board including agreeing tariff rates .  Unable
to confirm exact programme until approval has been given.
Mitigating Action
Projects delivered on budget
ITEM 15

Page 2

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS MASTER LIST
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
ZeroCarbon
5
Project Life Financials 33,491 15,790 47% 34,049 558 2%
Current Year Financials 11,845 352 3% 11,845 0 0%
Project Description
Project Manager Patricia Rowley/ Craig Jardine
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-27 31-Mar-27
6
Project Life Financials 8,535 2,583 30% 8,535 (0) 0%
Current Year Financials 2,238 10 0% 2,238 0 0%
Project Description
Project Manager Sharon Jump/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-25 31-Mar-25
7
Project Life Financials 25,439 2,030 8% 24,278 (1,161) -5%
Current Year Financials 2,030 (59) -3% 2,030 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-24 31-Mar-24
8
Project Life Financials 349 349 100% 349 0 0%
Current Year Financials 340 0 0% 340 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-24 31-Mar-24
Delivery of the project on time and within the increased budget
Exxon City Deal
Main Issues / Reason for Variance
As part of the City Deal project the WDC Exxon site at Bowling regeneration with alternative A82 route included.
Planned End Date
A number of H&S works have been carried out in depots with other works planned in the coming months.  Scope and design of future works are currently being
developed. 
The budget for this project was been rephased to FY 2023/2024.
Mitigating Action
None available at this time.
Anticipated Outcome
To deliver new sports changing facility.
Mitigating Action
None available at this time
Anticipated Outcome
Deliver project outcomes within agreed budget
Works progressing.
Mitigating Action
None required at this time
Anticipated Outcome
Full budget spend anticipated.
Forecast End Date
Main Issues / Reason for Variance
Regular updates are provided at every Council meeting and monthly Project Board meetings and to City Deal.  The main issues contained within the new Council's
approved Outline Business Case are still valid, which include Exxon's remediation strategy, land transfer arrangements and issues relating to adjoining owners.  WDC
Consultants are monitoring the remediation process to ensure compliance with specification, also Esso are independently monitoring the remediation works.  Final
Business Case submission was June 2023. Through the Scape framework we are working closely with Balfour Beatty to achieve a formal pre construction agreement to
allow the detailed design works to commence and the full construction programme to be developed. Agreements in principle are progressing with third party land
owners.  Note for Patricia - needs narrative on underbridge not happening this financial year and impact on budget spend for 23/24. Forecast will need to be amended.
Mitigating Action
None Required
Anticipated Outcome
Depot Rationalisation
Depot Rationalisation.
Planned End Date Forecast End Date
Building Upgrades and H&S - lifecycle & reactive building upgrades
Lifecycle and reactive building upgrades.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
New Sports Changing Facility Dumbarton West (Old OLSP site) 
New Sports Changing Facility Dumbarton West (Old OLSP site) 
Planned End Date Forecast End Date
Main Issues / Reason for Variance

Page 3

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS MASTER LIST
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
ZeroCarbon
9
Project Life Financials 2,430 630 26% 2,430 0 0%
Current Year Financials 478 0 0% 478 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
10
Project Life Financials 449 492 110% 492 44 10%
Current Year Financials 446 0 0% 446 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
11
Project Life Financials 250 250 100% 250 0 0%
Current Year Financials 250 0 0% 250 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
12
Project Life Financials 221 221 100% 221 0 0%
Current Year Financials 8 0 0% 8 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 03-Apr-21 31-Mar-23
Main Issues / Reason for Variance
Works progressing
None required at this time.
Planned End Date Forecast End Date
Mitigating Action
Anticipated Outcome
Better access with parks, cemeteries and open spaces.
Allotment Development
To develop an allotment site.
Planned End Date Forecast End Date
Mitigating Action
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Sustainable burial environment for local residents.
None required at this time.
Public non-adopted paths and roads
Upgrades to drainage and lighting to enhance the lifespan of paths and roads within  facilities in public parks, cemeteries
and civic spaces.
Main Issues / Reason for Variance
None required at this time.
Main Issues / Reason for Variance
Projects are currently being developed to deliver better access in our parks, cemeteries and open spaces. Full budget spend anticipated in 2023/2024.
New all weather tennis courts.
Mitigating Action
Anticipated Outcome
Additioanl allotments delivered within budget
Cemetery Extension, North Dalnotter
Cemetery Extension, North Dalnotter
Planned End Date Forecast End Date
Works progressomg
Sports Facilities Upgrades - Argyll Park - Construction of 3 All Weather Tennis Courts
Project is part of wider investment in sporting facilities and is dependent on match funding from Sports Scotland.
Agreement in principle to wider WDC strategic priorities.
Planned End Date Forecast End Date
Project works complete.  Retentions to be paid
None required at this time.
Anticipated Outcome

Page 4

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS MASTER LIST
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
ZeroCarbon
13
Project Life Financials 817 817 100% 817 (0) 0%
Current Year Financials 529 0 0% 529 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
14
Project Life Financials 200 200 100% 200 0 0%
Current Year Financials 200 0 0% 200 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-25
15
Project Life Financials 739 439 59% 739 (0) 0%
Current Year Financials 380 33 9% 380 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-28 31-Mar-28
16
Project Life Financials 210 210 100% 210 0 0%
Current Year Financials 210 0 0% 210 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 30-Nov-23 31-Mar-24
Mitigating Action
None required.
Anticipated Outcome
Consultant and design team fees for resurfacing of 3G pitch at East End Park.
Project is now being developed for tendering, with project commencing May 2023 and completion expected by 31 March 2024. 
Anticipated Outcome
Extension to existing cemetery providing a sustainable burial environment.
East End Park Resurfacing
Resurfacing of 3G pitch at East End Park.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Design fees to develop Mountain bike skills trail in Balloch country park. Invoice for project received
Anticipated Outcome
Mountain bike track
Resurfacing of 3G pitch at East End Park.
Play Parks Grant Funding
Renew and replace play park equipment
Vale of Leven Cemetery Extension
Extension of existing cemetery in Vale of Leven.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Mitigating Action
None available at this time.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Mitigating Action
None required at this time.
Anticipated Outcome
Renewal of play parks
Balloch Mountain Bike Track
Develop a mountain bike skills trail at Balloch Castle Country Park.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Mitigating Action
None required at this time.
Development of play areas to improve accessibility and inclusiveness of play areas throughout West Dunbartonshire. Projects are being developed for implementation
over the next five years.

Page 5

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS MASTER LIST
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
ZeroCarbon
17
Project Life Financials 485 485 100% 485 0 0%
Current Year Financials 430 0 0% 430 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
18
Project Life Financials 1,244 1,051 84% 1,051 (193) -16%
Current Year Financials 905 0 0% 905 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
19
Project Life Financials 60 60 100% 60 0 0%
Current Year Financials 5 0 0% 5 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
20
Project Life Financials 800 800 100% 800 0 0%
Current Year Financials 620 0 0% 620 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
Cycling, Walking and Safer Streets
Introduction of enhanced walking routes and traffic calming schemes to introduce safer streets within West Dunbartonshire.
Planned End Date Forecast End Date
Additional fudning received and projects will be allocated.
Turnberry Homes - traffic calming/ management at Turnberry housing development off Castle Road
To develop projects including Balloch Cycle Way (Pier Road to Mollanbowie/Boturich Road), and other projects principally around National Cycle Network 7 including
Angus Street/Bonhill Bridge and Atlus Street/Cart Street, Clydebank and pedestrian dropped kerbs. Additional funding has been received and will be allocted to
Funding has been received from Turnberry Homes and will be used to introduce traffic calming and traffic management
measures to mitigate the impact of additional traffic accessing the housing development off Castle Road, Dumbarton.
Planned End Date Forecast End Date
Consultation completed 2021/2022 and speed humps  installed prior to 31 March 2023.
River Leven Flood Prevention Scheme
Main Issues / Reason for Variance
Mitigating Action
None required at this time.
Anticipated Outcome
Traffic calming to be installed in Dumbarton East.
Nature Restoration Fund
Nature resource for Faifley Community
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Mitigating Action
None required at this time.
Anticipated Outcome
complettion of project on time and on budget
Main Issues / Reason for Variance
Mitigating Action
None required at this time.
Anticipated Outcome
To improve connectivity and enhanced Cycling routes within West Dunbartonshire.
River Leven Flood Prevention Scheme.
Main Issues / Reason for Variance
Planned End Date Forecast End Date
Awaiting outcome of Scottish Government & SEPA deliberations - project has been carried forward from 2022/23
Mitigating Action
None required at this time.
Anticipated Outcome
Project should be completed within budget.

Page 6

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS MASTER LIST
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
ZeroCarbon
21
Project Life Financials 2,277 2,277 100% 2,277 0 0%
Current Year Financials 1,480 0 0% 1,480 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
22
Project Life Financials 24,658 6,872 28% 27,224 2,565 10%
Current Year Financials 2,195 (64) -3% 2,195 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
23
Project Life Financials 881 112 13% 912 32 4%
Current Year Financials 84 4 5% 84 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
24
Project Life Financials 97 97 100% 97 (0) 0%
Current Year Financials 29 2 7% 29 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Main Issues / Reason for Variance
Infrastructure - Roads
Strathclyde Partnership for Transport - Bus, cycling and walking infrastructure improvements & Park and Rides
Street lighting and associated electrical infrastructure
Main Issues / Reason for Variance
Roads Operations are progressing an extensive surfacing program and have a number of schemes to be completed by the end of the financial year.
Mitigating Action
Planned End Date Forecast End Date
Anticipated Outcome
Intention is to complete works within budget.
Improvement of WDC Roads Depot.
Depot Improvement Works
None available at this time.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Budget will be allocated to ensure maintenance of street lighting.
Mitigating Action
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This budget will be utilised for depot rationalisation works during the financial year.
Strathclyde Partnership for Transport - Bus, cycling and walking infrastructure improvements.
Planned End Date Forecast End Date
Work will be undertaken during this financial year for A8014 Kilbowie Road, Balloch Station Park and Ride and Bus Infrastructure Improvements. A814 Congestion
measures contractor arrived on site mid-August. Works are progressing well. The budget for Balloch Station will be used for consultancy works and planning application
fees. Additional fundinghas been received and approriate projects will be identified.
Mitigating Action
None required at this time.
Anticipated Outcome
Improve accessibility to Public Transport and improve journey time reliability.
Infrastructure - Roads.
None required at this time.
Anticipated Outcome
Intention is to complete various surfacing works by the end of March 2024.
WDC is responsible for the maintenance of 18,000 street lighting columns and associated illuminated signs and bollards. 
This budget is required for this infrastructure.
Mitigating Action
None available at this time.
Anticipated Outcome
Intention is to complete works within budget.

Page 7

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS MASTER LIST
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
ZeroCarbon
25
Project Life Financials 15,053 1,984 13% 15,053 (0) 0%
Current Year Financials 1,530 0 0% 1,530 0 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-25
26
Project Life Financials 1,700 1,700 100% 1,700 0 0%
Current Year Financials 693 0 0% 693 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
27
Project Life Financials 134 134 100% 134 0 0%
Current Year Financials 134 0 0% 134 0 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
28
Project Life Financials 80 80 100% 80 0 0%
Current Year Financials 75 0 0% 75 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
Roads Plant
To purchase equipment.
Gruggies Burn Flood Prevention
A813 Road Improvement Phase 1
Commission of Gruggies Flood Prevention Scheme.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Budget to be used for a detailed design for Gruggies Burn.
Mitigating Action
None available at this time.
Anticipated Outcome
Project should be completed within budget.
Funding has been awarded from Sustrans to assist with social distancing measures required as a result of the COVID-19
pandemic.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Roads Safety
Main Issues / Reason for Variance
New Plant to be purchased
Mitigating Action
None required.
Anticipated Outcome
Officers working with external partners to identify projects to support funding. Project carried frowrd from 2022/23
Mitigating Action
None available at this time.
Anticipated Outcome
To improve journey times and reliability of bus services.
Roads Safety
Planned End Date Forecast End Date
Main Issues / Reason for Variance
New funding which will be allocated to approiate projects.
Mitigating Action
None required at this time.
Anticipated Outcome
Projects delivered on time and on budget
Purchase of Roads plant and equipment.
Planned End Date Forecast End Date

Page 8

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS MASTER LIST
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
ZeroCarbon
29
Project Life Financials 300 300 100% 300 0 0%
Current Year Financials 26 0 0% 26 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
30
Project Life Financials 1,000 1,000 100% 1,000 0 0%
Current Year Financials 878 185 21% 878 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
31
Project Life Financials 1,000 1,000 100% 1,000 0 0%
Current Year Financials 1,000 0 0% 1,000 0 0%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
32
Project Life Financials 12,177 3,857 32% 12,177 0 0%
Current Year Financials 3,314 29 1% 3,314 0 0%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Traffic Signal Upgrades
Mitigating Action
None available.
None required.
Anticipated Outcome
Improvement to pavements.
Vehicle Replacement Strategy
Anticipated Outcome
Replacement of refuse collection vehicles.
Vehicle Replacement
Upgrade Traffic Signals
Planned End Date Forecast End Date
Mitigating Action
Replacement of refuse collection vehicles.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Full budget allocated for this year including the procurement of large vehicles for waste collection.
Replacement of vehicles which have reached end of programmed lifespan (7 year heavy vehicles, 10 year light vehicles).
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The signalisation of Kilbowie roundabout is underway and ocne complete construction will be prgrammed.
Mitigating Action
None required.
Various pavement improvement projects.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects and locations to be decided.
Pavement improvements
To upgrade traffic signals.
Anticipated Outcome
Main Issues / Reason for Variance
Vehicles are being ordered for delivery in this financial year but larger vehicles have been delayed into financial year 2023/2024.
Mitigating Action
None Required.
Anticipated Outcome
Replacement of fleet within budget.

Page 9

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS MASTER LIST
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
ZeroCarbon
33
Project Life Financials 1,980 1,980 100% 1,980 0 0%
Current Year Financials 1,980 0 0% 1,980 0 0%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
34
Project Life Financials 179 80 45% 160 (19) -10%
Current Year Financials 9 0 0% 9 0 0%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
35
Project Life Financials 60 60 100% 60 0 0%
Current Year Financials 16 0 0% 16 0 0%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
36
Project Life Financials 79 79 100% 79 0 0%
Current Year Financials 79 0 0% 79 0 0%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
2022/23 GRANT OFFER FOR ELECTRIC VEHICLE INFRASTRUCTURE
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project in progress
2022/23 GRANT OFFER FOR ELECTRIC VEHICLE INFRASTRUCTURE
Smarter Choices, Smarter Places
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Mitigating Action
Mitigating Action
None Required.
Anticipated Outcome
Project delivered within  budget.
2022/23 GRANT OFFER FOR ELECTRIC VEHICLE INFRASTRUCTURE
New Funding - Project in progress
Mitigating Action
None Required.
Anticipated Outcome
Project delivered within  budget.
None Required.
Anticipated Outcome
Project delivered within  budget.
Waste Transfer Station
The design, development and construction of a recycling and bulk waste transfer facility that will ensure all recycling
material can be sorted and disposed off appropriately to ensure compliance with landfill ban in 2025.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Consultant project nearing completion and spend will be made thereafter.
The purchase of 2 compactors for the Council civic amenity site at Dalmoak.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Compactors have now been delivered.
Anticipated Outcome
Mitigating Action
None Required.
Project delivered within budget.
Replacement of compactors at Dalmoak civic amenity site

Page 10

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS MASTER LIST
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
ZeroCarbon
37
Project Life Financials 20 20 100% 20 0 0%
Current Year Financials 20 0 0% 20 0 0%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
38
Project Life Financials 150 150 100% 150 0 0%
Current Year Financials 150 0 0% 150 0 0%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
None Required.
Anticipated Outcome
Project delivered within  budget.
River bank erosion repair - Levenhowe
River bank erosion repair in the Levenhowe area
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project in progress
Mitigating Action
Project delivered within  budget.
Project in progress
None Required.
Park Improvements and Mulit Games Area - Goldenhill Park
River bank erosion repair in the Levenhowe area
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome