WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS MASTER LIST
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
1
Project Life Financials 61 61 100% 61 (0) 0%
Current Year Financials 58 0 0% 58 0 0%
Project Description
Project Manager Steven Milne
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-24
2
Project Life Financials 87 0 0% 0 (87) -100%
Current Year Financials 79 (0) 0% 0 (79) -100%
Project Description
Project Manager Steven Milne
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-24
3
Project Life Financials 20 20 100% 20 0 0%
Current Year Financials 7 0 0% 7 0 0%
Project Description
Project Manager Steven Milne
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-24
4
Project Life Financials 290 290 100% 290 0 0%
Current Year Financials 227 0 0% 227 0 0%
Project Description
Project Manager Steven Milne
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-24
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Main Issues / Reason for Variance
Expect full spend before 31 March 2024.
Mitigating Action
None required.
Anticipated Outcome
Tender works delayed due to Energy Officer being involved in other priority work. Aim to be tendered within this  financial year but  works will not be  completed.
None Required.
Anticipated Outcome
Main Issues / Reason for Variance
Mitigating Action
None Required.
Anticipated Outcome
Replace existing main hall Air Handling unit at Clydebank Town Hall.
Works are being undertaken to upgrade controls which are 90% complete.
Mitigating Action
Main Issues / Reason for Variance
Main Issues / Reason for Variance
Installation of Solar PV at Clydebank Leisure Centre
Installation of Solar PV at Clydebank Leisure Centre.
Planned End Date Forecast End Date
Works to be undertaken in 24/25
Replace existing main hall Air Handling unit at Clydebank Town Hall
Planned End Date Forecast End Date
Replace existing main hall Air Handling unit at Clydebank Town Hall.
Replace failed heating controls/valves & recommission
Replace failed heating controls/valves & recommission.
Planned End Date Forecast End Date
Delivery of project with full budget spend.
Leisure Energy projects - air handling units, upgrade lighting, circulating pumps, and draught proofing
Measures to be installed at both Meadow Centre & Vale of Leven Swimming Pool; new pool hall Air Handling Units,
upgrade lighting, circulating pumps Vale of Leven Swimming Pool, internal and external lighting and draught proofing.
Planned End Date Forecast End Date
It is anticipated that Tender will go out this financial year. Depending on feedback from leisure re opportunity to close centre for AHU works,  it is hoped Civil works will at
least be intiated this financial year with AHU works completed next financial year.
Expecting full spend prior to 31 March 2024.  Other priorty projects have cintributed to delay. Also require to appoint structural engineer to progress report amd it is
anticipated that this will be undertaken in the near future.
Mitigating Action
Liasing with Leisure to see if opportunity to carry works between Dec and March . Appoint new external structural engineer to provide SER.
Anticipated Outcome
ITEM 15

Page 2

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS MASTER LIST
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Installation of Solar PV at Clydebank Leisure Centre
5
Project Life Financials 1,456 1,456 100% 1,456 0 0%
Current Year Financials 676 0 0% 676 0 0%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-24
6
Project Life Financials 747 747 100% 747 0 0%
Current Year Financials 707 0 0% 707 0 0%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Dec-22 30-Jun-24
7
Project Life Financials 125 125 100% 125 0 0%
Current Year Financials 26 0 0% 26 0 0%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 30-Jun-24
8
Project Life Financials 150 150 100% 150 0 0%
Current Year Financials 134 0 0% 134 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-21 31-Mar-24
Anticipated Outcome
Anticipated Outcome
New Sports Changing Facility at Lusset Glen in Old Kilpatrick
New Sports Changing Facility at Lusset Glen in Old Kilpatrick
Planned End Date Forecast End Date
None available at this time.
Project was delayed due to a number of COVID-19 related issues and utilities issues.  Unit is now in production but delay to site due to the utility disconnection and
demolition works. Demolition works complete and waiting for a date for installation.
Mitigating Action
Mitigating Action
None available at this time
Main Issues / Reason for Variance
Projects contiue to be progressed and expected to complete this fiancnial year
Mitigating Action
None required at this tinme
Anticipated Outcome
Main Issues / Reason for Variance
Kier is appointed to design and deliver the Activities Centre at Clydebank Town Centre. Design of the project is underway.
Mitigating Action
None available at this time
Main Issues / Reason for Variance
This capacity funding was awarded by UK Government to assist with development of LUF bids. WDC has been awarded a grant from LUF Round 1 and the capacity
funding will be used in part to produce Artizan Centre redevelopment options. The balance will be used for Roads/Transportation to develop a major transportation bid for
LUF2.
Anticipated Outcome
Projects delivered on budget
Levelling Up
Successful LUF applications that meet UK Government's over-riding objective of Levelling Up and transformational
regeneration.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Place Based Investment Programme
Scottish Government Funding to establish a Place-Based Investment Programme to ensure that all place based
investments are shaped by the needs and aspirations of local communities.
Planned End Date Forecast End Date
Projects delivered on budget
Clydebank Can On The Canal
New activities centre in Clydebank Town Centre.
Planned End Date Forecast End Date
Projects delivered on budget
To deliver new sports changing facility.

Page 3

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS MASTER LIST
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Installation of Solar PV at Clydebank Leisure Centre
9
Project Life Financials 2,375 1,175 49% 2,375 (0) 0%
Current Year Financials 1,085 6 1% 1,085 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-22 31-Mar-25
6 (0) 6 0
10
Project Life Financials 50 50 100% 50 (0) 0%
Current Year Financials 13 0 0% 13 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
11
Project Life Financials 2,712 5,305 196% 5,305 2,593 96%
Current Year Financials 864 421 49% 864 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 30-Nov-23
12
Project Life Financials 25 25 100% 25 0 0%
Current Year Financials 6 0 0% 6 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
Main Issues / Reason for Variance
This budget will be used to develop an area of the existing Cemetery for additional burials.  Project scope has now been developed and will be tendered under the minor
civils framework.  Budget spend anticipated in 2023/2024.
Various delays due to Covid and other utility issues. Planning was previously delayed but now resolved. Building warrant applications submitted and tender to be issued.
Mitigating Action
None available at this time.
Anticipated Outcome
Main Issues / Reason for Variance
Mitigating Action
None available at this time
Anticipated Outcome
Main Issues / Reason for Variance
Mitigating Action
None available at this time
Anticipated Outcome
Kilmaronock Cemetery Extension
Extension of existing cemetery at Kilmaronock. 
Planned End Date Forecast End Date
Project start was delayed due to planning issues and COVID-19 restrictions. Work commenced January 2021 with a proposed completion date of March 2022 which
was  extended to May 2023 due to design changes required by Planning. There is still a significant amount of work to be undertaken to complete the project and the cost
of this work has been affected by Covid, Brexit and supply chain issues. The project overspent on budget last year and the project will  overspend  overall. Ongoing
connection issues with Scottish Water. Delay issues have been highlighted at a senior level within Scottish Water and communication seems to be improving. Expected
completion date is estimated to be November 2023. However, this is dependent on when water connection is made.
Supply and install extra large litter bins as a pilot project within hotspot problem areas. Project has commenced.
Main Issues / Reason for Variance
Mitigating Action
None required at this time.
Anticipated Outcome
Large bins provided for high traffic areas
New Westbridgend Community Centre
New Westbridgend Community Centre
Planned End Date Forecast End Date
New build community facility.
Sustainable burial environment for local residents.
Posties Park Sports Hub - New sports hub to include gym & running track
Creation of a sports hub at Posties/Marinecraft to include a new changing pavilion/Gym, new all-weather 6 lane running
track, conversion of blaze sports pitch to grass, new fencing, upgrade of existing floodlights and additional car parking.  This
combines the budget approved by the Council in February 2015 for Community Sports Facilities at Posties Park, draw
Planned End Date Forecast End Date
New sports Hub delivered
Large bins for high traffic areas (pilot)
Supply and install extra large litter bins as a pilot project within hotspot problem areas.
Planned End Date Forecast End Date

Page 4

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS MASTER LIST
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Installation of Solar PV at Clydebank Leisure Centre
13
Project Life Financials 217 217 100% 217 0 0%
Current Year Financials 214 0 0% 214 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
14
Project Life Financials 400 400 100% 400 0 0%
Current Year Financials 42 0 0% 42 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
15
Project Life Financials 314 314 100% 314 (0) 0%
Current Year Financials 56 0 0% 56 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
16
Project Life Financials 2,485 350 14% 2,485 0 0%
Current Year Financials 237 16 7% 237 0 0%
Project Description
Project Manager Raymond Walsh/ Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
Mitigating Action
None required at this time.
Anticipated Outcome
Main Issues / Reason for Variance
Road construction works completed in previous years. Remaining funds are insufficient to complete footpath construction. Works on hold until such time as additional
funds can be secured.
Mitigating Action
Anticipated Outcome
Main Issues / Reason for Variance
A detailed design for Gruggies Burn will be undertaken. Project has been carried forward from 2022/23
Main Issues / Reason for Variance
Bus Rapid Deployment Fund
Funding has been awarded from Sustrans to assist with social distancing measures required as a result of the COVID-19
pandemic.
Main Issues / Reason for Variance
Charging points to be installed at Moss O' Balloch park - project carried forward from 2022/23
Mitigating Action
None required at this time.
Planned End Date Forecast End Date
To improve journey times and reliability of bus services.
Auld Street Clydebank - Bond
Officers working with external partners to identify projects to support funding. Project carried frowrd from 2022/23
Mitigating Action
None available at this time.
Anticipated Outcome
Completion of roadworks associated with Auld Street housing development. Creation of a footpath to Golden Jubilee
Hospital.
Planned End Date Forecast End Date
To complete remaining civil works required.
None available at this time.
Anticipated Outcome
Electrical Charging Points - Rapid Charge
Funding has been awarded from Transport Scotland for the Installation of electrical charging points
Planned End Date Forecast End Date
To provide Electric Vehicle Charging points within West Dunbartonshire.
Flood Risk Management
Enhancement of drainage infrastructure to ensure compliance with Flood Risk Management Act 2009.
Planned End Date Forecast End Date
Project should be complete within budget.

Page 5

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS MASTER LIST
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Installation of Solar PV at Clydebank Leisure Centre
17
Project Life Financials 500 500 100% 500 0 0%
Current Year Financials 500 0 0% 500 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
18
Project Life Financials 4,300 4,300 100% 4,300 (0) 0%
Current Year Financials 138 0 0% 138 0 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-Mar-24
19
Project Life Financials 400 400 100% 400 0 0%
Current Year Financials 400 0 0% 400 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
Main Issues / Reason for Variance
Main Issues / Reason for Variance
Works substantially complete. Additional works as a compensation event started on Wallace street in July 2022.
Mitigating Action
None available at this time.
Anticipated Outcome
Flood Prevention
Various flood prevention projects.
Planned End Date Forecast End Date
Projects should be complete within budget.
Main Issues / Reason for Variance
Plans are under consideration by officers and will be submitted to Elected Members for approval. Project has been carried forward from 2022/23
Mitigating Action
None required at this time.
Anticipated Outcome
Clydebank Charrette, A814
Clydebank Charrette, A814
Planned End Date Forecast End Date
Projectwill enhance the A814 through Clydebank.
Purchase of gritters
Purchase of gritters.
Planned End Date Forecast End Date
Project delivered within  budget.
Delivery delayed by the supplier. Full budget spend expected before the end of the financial year.
Mitigating Action
None available at this time.
Anticipated Outcome