WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer : Supply, Distribution & Property
Chief Officer : Roads & Neighbourhood 
Infrastructure Regeneration and Economic Development Committee:
24 May 2023
___________________________________________________________________
Subject: Depot Rationalisation Project Delivery Phase 2
1. Purpose
1.1 The purpose of this Report is to update IRED Committee on the current
status of the Depot Rationalisation Project and to seek approval to progress
with Phase 2 which would see the delivery of refurbished depot
accommodation across two sites.
2. Recommendations
2.1 It is recommended that the Committee:
(i) Note the Depot Rationalisation Project update;
(ii) Agree proposals as set out within the Report to progress with the
refurbishment of depot accommodation across two existing
sites;
(iii) Agree proposals as set out within the Report to agree new
Recycling Reuse and Resource Centre (Waste Transfer Station)
on existing Poplar Road site in Dumbarton;
3. Background
3.1 Discussions around the depot provision had been put on hold during 2020 to
assess service provision and to review the impact of Covid 19.
3.2 Prior to this, the Depot Rationalisation Project Board last met in June 2019
where it was agreed the Project Board would meet again in the Autumn of
that year once the status was known on the options for a future Depot
location, as well as the potential impact of service delivery implications on
future depot requirements.
3.3 Further to the above, as a result in changing legislation within the Waste
Environment, there is a requirement for the Council to consider options to
develop and implement a Recycling, Reuse & Resource Centre (Waste
Transfer Station). This requires to be considered in conjunction with the
development of the Depot Rationalisation Project due to
interdependencies.
ITEM 12

Page 2

3.4 A paper was presented to the Strategic Assessment Management Group
in December 2021 providing an update on the current status of the Depot
Rationalisation Project and an indicative timeline to conclude the Business
Case.. In addition it was noted that the implementation of a salt dome
should be delivered as Phase 1 of the project. 
3.5 The Depot Rationalisation (DRP) Project Board met in January 2022 and
agreed to progress with: 
a. Phase 1 - Procurement and installation of the salt dome; and
b. Options appraisal to be considered and full Business Case developed. 
3.6  Options appraisal considered : 
The options involved comparing the Business Case scenarios against the
existing estate baseline of ‘do- nothing’ for the following proposed
alternatives: 
• Demolish and rebuild facilities on Elm Road Dumbarton in a
phased/tandem build approach to accommodate continuity of existing
services delivery. Remodel Richmond and Stanford Street areas
retaining Waste Transfer station and providing satellite base and
welfare facilities for Greenspace, Roads, Waste, Fleet and Building
Services; and 
• As above but include all Depot provision currently split over both the
Dumbarton and Clydebank ends of the authority into one existing site
footprint. 
3.7 A procurement exercise has undertaken for long term waste contractor
and tenders received were unaffordable.  Feedback was assessed and it
was identified that a Waste Transfer station was required.  A feasibility
study was commissioned to determine the size location requirements and
sites were then assessed by officers for viability. 
4. Main Issues 
4.1 Phase 1 of the Depot Rationalisation was approved by Committee on
16 February 2022 which was the requirement to progress with the
provision of a new salt storage area.   
4.2 A Royal British Institute of Architects (RIBA) Stage 1 report was
produced in September 2022 which indicated costs are outwith the
existing budget provision of £8.4m and will therefore make the
continuance of the project for a new build facility no longer financially
viable.   
4.3 An alternative option to refurbish the existing depot estate with the
existing £8.4m budget set aside in the capital plan has been reviewed.

Page 3

4.4 This alternative option would be to rationalise the existing Depot sites in
Dumbarton and Clydebank.  These sites would be redesigned and
improved for this purpose (Appendix 1). 
4.5 These new improved sites would provide capacity for a cohesive
workforce in the two existing locations whilst endeavouring to reduce
ongoing revenue costs for satellite offices.  They would also provide
services and employees with a fit for purpose, high quality working
environment. 
4.6 Refurbishment work would be carried out whilst the sites remained
operational and will be programmed accordingly using existing facilities
where appropriate.  Detailed discussions will be held with the workforce
and trade unions in advance of any temporary decants which may be
required. 
4.7 It is anticipated that the depot refurbishment works would be carried out
by Building Services incorporating specialist contractors where
appropriate with the Recycling, Reuse & Resource Centre (Waste
Transfer Station) being subject to a future procurement exercise. 
4.8 With the revised proposal we would be able to retain the economic
benefits that the two areas currently experience by having WDC in
these locations.  This would reduce the general running costs for the
services by providing a refurbished depot that is more energy efficient
and requires less maintenance 
4.9 The proposal would look at retaining Building Services functions across
both Dumbarton and Clydebank, with Waste, Greenspace, Roads and
Fleet being split across both locations which supports the fit for the
future service delivery model. 
4.10 The strategic service delivery review will determine the operational
requirements but it is anticipated Roads and Grounds would be
predominately in Dumbarton with Waste and Fleet in Clydebank with
small satellite bases.     
4.11 It is also anticipated that a number of smaller satellite sites will be
surplus assets which would be available for disposal as a result of this
new proposal.  Workstyle returns will also feed into what appropriate
office accommodation is now required across both locations.   
4.12 Initial visual surveys have been completed but detailed condition
surveys will be required with architectural input in terms of efficient
layouts and traffic management around both the two main locations
and any satellite provision.   
4.13 WDC require to meet Government targets to reduce biodegradeable
waste going to landfill by 95% as of 2025.   The Council also require to
be compliant with the landfill tax ban due for introduction in December

Page 4

2025. Following an unsuccessful procurement exercise for a long term
waste solution it was identified that a waste transfer station was
required. A feasibility study has been completed and following the
identification of a site, detailed design can commence.  This will
provide detailed costs for consideration.   
4.14 As both the future waste transfer station project and depot
rationalisation share a number of interdependences, incorporating both
projects into one would realise economies of scale and ensure that
both projects are in line with each other. 
4.15 A number of sites within WDC ownership have been reviewed by
officers from Waste, Greenspace and Asset Management with the
current site at Poplar Road being the proposed option for a transfer
station (Appendix 2).  Operationally it is far more cost effective to start
and finish refuse collection from the same base as the transfer facility
and it would therefore be proposed that waste operations are moved to
this site to retain flexibility in the service design. 
4.16 Waste transfer stations are designed specifically to aid the sorting and
storing of materials before they are moved on to larger sites for
disposal or treatment. Our waste transfer site will be able to house
recyclable material, general household waste, food waste, and green
waste, before it is treated or disposed of at an Energy from Waste
facility, or to a processor that will ensure our waste is suitably reused
or recycled in accordance with regulations. 
4.17 Disposal of Poplar Road is part of a savings option by Citizens Culture
& Facilities and it is anticipated being vacant in March 2025.  Utilising
this site would be an effective use of a surplus asset and ensure
maximum occupancy of Broadmeadow Industrial Estate with income
coming into Common Good Fund. 
5. People Implications 
5.1 There are no significant people implications other than the resources required by
officers within Supply, Distribution and Property and Roads and Neighbourhood. 
6. Financial and Procurement Implications 
6.1 The Depot Rationalisation project has a budget of £8.4k with spend to date
at £119k and an additional £2m allocated for the Recycling, Reuse &
Resource Centre.  The anticipated spend for installation of new salt dome
has not been achieved due to the project being delayed  as a result of site
conditions. The construction will commence Summer 2023.   
6.2 The cost for the refurbishment works are currently unknown but it is 
anticipated that full budget will not be required.  This will be reported via the
normal capital reporting via BCR process going forward.

Page 5

6.3 There are no procurement implications arising from this report. 
7. Risk Analysis 
7.1 Should any unforeseen issues arise in terms of the existing buildings which
affect the refurbishment design and deliverables the project may require to be
redefined.   
8. Environmental Sustainability 
8.1 The repurposing of existing assets will improve service efficiencies by reducing
duplication of work and allow for the sharing of resources. 
9. Equalities Impact Assessment (EIA) 
9.1 Screening and impact assessments will be carried out on specific activities as
required as the project progresses. 
10. Consultation 
10.1 All Services involved with the Depots will be consulted during each key
stage of the project development and delivery. 
10.2 Procurement, Legal and Finance colleagues have been consulted and are
members of the Project Board. 
10.3 Joint Trade Unions have been consulted and are members of the Project
Board. 
11. Strategic Assessment 
11.1 A full Strategic Assessment was not required for this Report but will
be included in any future assessment. 
Angela Wilson
Chief Officer: Supply, Distribution and Property 
Gail MacFarlane
Chief Officer: Roads & Neighbourhood 
11 April 2023 
Person to Contact: Michelle Lynn, Asset Coordinator.  
Email: michelle.lynn@west-dunbarton.gov.uk 
Appendices: Appendix 1 – Current Depot Sites    
Appendix 2–  Draft Layout of Future Waste Transfer Station

Page 6

Background Papers:        Report to Infrastructure, Regeneration and Economic Growth
Committee: 16 February 2022 - Depot Rationalisation Project
Delivery Phase 1 : Salt Storage 
Wards Affected: All