Appendix 1 - R&N Delivery Plan Year-end Progress 22/23
1. Our communities
Objective 1. Our neighbourhoods are safe, resilient and inclusive
Performance Indicator
2021/22 2022/23
Owner
Value Status Value Target Short Trend Long Trend Note
Percentage of emergency road related defects
repaired within 2 hours of being reported 100% 96% 95% Performance exceeded target. Liam Greene
Percentage of non-serious road related defects
repaired within 7 working days of being reported 72.2% 92.65% 85% Performance exceeded target. Liam Greene
Percentage of routine road related defects repaired
within 28 working days of being reported 38.8% 37.7% 85%
Significantly missed target. Service
has prioritised emergency and
serious defects due to recovery from
the pandemic and activity that was
restricted during that period. The
percentage of non serious defects
repaired within timescales is likely to
increase now the winter period has
come to an end. Roads Operations
will undertake a review of working
practises and procedures including
implementation of the structural
patching project as approved
through the budget setting process
to improve performance and ensure
targets are achieved.
Liam Greene
Percentage of all traffic light repairs completed
within 48 hours 100% 100% 98% Performance exceeded target. Liam Greene
Percentage of all street light repairs completed
within 7 days 99% 98.75% 95% Performance exceeded target. Liam Greene
Action Status Progress Due Date Note Owner
ITEM 8 - APPENDIX 1

Page 2

Action Status Progress Due Date Note Owner
Review winter gritting programme and
implement a more effective service provision
31-Mar-
2023
Action complete. Winter Plan reviewed and implemented prior to the start
of the winter season. Liam Greene
Objective 2. Our residents health and wellbeing remains a priority
Action Status Progress Due Date Note Owner
Completion of deliver new gymnasium, changing
facilities and all weather running track
31-Mar-
2023
Action completion delayed. Running track complete and final remedial
works underway at Posties Park. Due to connection issues with Scottish
Gas and Scottish Water the project has been delayed with an estimated
completion date of 31st July 2023. This action will be carried over to
2023/24.
Ian Bain
2. Our Environment
Objective 4. Our local environment is protected, enhanced and valued
Performance Indicator
2021/22 2022/23
Owner
Value Status Value Target Short Trend Long Trend Note
Percentage of residents satisfied with the Waste
service overall 81% 82% 85%
Marginally missed target with
performance marginally improved
from last year. The route
optimisation project has been
approved through the budget setting
process and will deliver
improvements set out in the fit for
future service review.
Kenny Lang
Percentage of missed bins collected within 3
working days of being reported 98.5% 98.7% 95% Exceeded target. Kenny Lang
Percentage of offensive graffiti removed within 24
hours of being reported 100% 100% 100% Target met. Ian Bain
Percentage of non offensive graffiti removed within 100% 100% 100% Target met. Ian Bain

Page 3

Performance Indicator
2021/22 2022/23
Owner
Value Status Value Target Short Trend Long Trend Note
5 working days of being reported
Percentage of total household waste that is
recycled 37% 38.1% 60%
Target significantly missed.
Performance has marginally
improved since last year.  The
service has reviewed the waste
strategy including collection and
separation of materials and are
developing a project that will create
a better recycling solution for WDC.
The feasibility study is complete for
the recycling reuse and resource
centre (RRRC) and approval is being
sought to move to detailed design.
Kenny Lang
Percentage of residents satisfied with the street
cleaning service 72% 72% 70% Performance exceeded target. Kenny Lang
Percentage of residents satisfied with Parks & open
spaces 87% 84% 85%
Marginally missed target and
performance marginally down from
last year. The planned improvement
to play parks and recreational
facilities should help improve this.
Ian Bain
Percentage of abandoned vehicles that require to
be removed by the council that are removed within
14 days
100% 100% 100% Target met. Ian Bain
Action Status Progress Due Date Note Owner
Produce a revised service delivery model that
reflects the changes in quantities of plastic and
glass collections due to the introduction of a
national deposit return scheme.
31-Mar-
2023
Due to the delay in the implementation of deposit return scheme, now due
March 2024, there will be changes to the delivery of the milestones
however preparatory works are at an advanced stage. This action will be
carried forward to 2023/24.
Kenny Lang
Finalise the delivery of a suitable new allotment
site with provision for 40 traditional plots
31-Mar-
2023
Action completion delayed. Following increase in funding allocated within
the Council Budget the scale of the project has been increased. Sites
identified and procured and the allotments will be sited at Dillichip
Loan and Dumbarton Common with an anticipated start date in Summer
2023. This action will be carried over to 2023/24.
Ian Bain
Develop a new local biodiversity action plan. 31-Mar-
2023
Action delayed. A draft Scottish Biodiversity Strategy was published in
December 2022. The delivery plan of the Scottish Biodiversity Strategy has
not yet been published although it has a due date of Spring 2023 for a
consultation period with the full document expected to be published in late
Ian Bain

Page 4

Action Status Progress Due Date Note Owner
summer 2023.  The actions of our plan will be directly related to this
document. Stakeholder engagement is underway setting out the priorities
for delivery.
Continue to explore alternative methods of weed
control
31-Mar-
2023
Action complete. Trials of alternative non chemical methods of weed
control have taken place and analysis has been undertaken the results
show that of those that work effectively there could be either significant
cost implications. Further work will be undertaken in 2023/24 to prepare
potential options and next steps.
Ian Bain
Ash die back preparation work to inform the
action plan which will be developed in 2023/24
31-Mar-
2023
Action complete. Following work to audit of affected trees in West
Dunbartonshire a plan will be prepared to agree options and next steps in
2023/24.
Ian Bain
Objective 5. Our resources are used in an environmentally sustainable way
Performance Indicator
2021/22 2022/23
Owner
Value Status Value Target Short Trend Long Trend Note
Tonnage of biodegradable municipal waste
landfilled 17,263 16,402 13,300
Target significantly missed.
Performance has improved over the
last two years. Although we are
currently over our target tonnage,
we have made a considerable
decrease from the previous period
and are on our way to achieving our
target. The waste strategy has been
developed to review collection and
separation of materials.
Kenny Lang
Action Status Progress Due Date Note Owner
Produce a business case for the development of a
waste transfer station within Council’s boundary 31-Mar-2023
Action complete. We now have a detailed feasibility study and Business
Case to allow progression towards development of a resource recycling and
reuse centre (RRRC). Next steps will progress in 2023/24.
Kenny Lang
Rollout further installation of electric vehicle
charging points 31-Mar-2023
New fleet charge points were installed and maintenance and upgrade work
was carried out or underway on the current charging points. In line with
partnership working the service continues to work as part of City region
group to develop a long term EV charging point strategy and expansion
plan. This will progress in 2023/24.
Liam Greene

Page 5

Objective 6. Our neighbourhoods are sustainable and attractive
Performance Indicator
2021/22 2022/23
Owner
Value Status Value Target Short Trend Long Trend Note
Percentage of Class A roads that should be
considered for maintenance treatment 19.5% 16.81% 24% Target exceeded. Liam Greene
Percentage of Class B roads that should be
considered for maintenance treatment 18.9% 14.6% 24.5% Target exceeded. Liam Greene
Percentage of Class C roads that should be
considered for maintenance treatment 26.9% 21.42% 30% Target exceeded. Liam Greene
Percentage of unclassified roads that should be
considered for maintenance treatment 33.4% 30.19% 37% Target exceeded. Liam Greene
Percentage of residents satisfied with roads
maintenance 38% 29% 41%
Target significantly missed with
performance down from previous
year. Review of road maintenance
plan and roads communication and
engagement strategy will be
developed.
Liam Greene
Action Status Progress Due Date Note Owner
Pavement parking, investigate and develop a
strategy in line with Scottish guidance Phase 2 31-Mar-2023
Action complete. Guidance documents received in January 2023 and the
service is currently reviewing these with a strategy to be developed during
2023/24.
Liam Greene
Progress the Gruggies Burn flood alleviation
scheme Phase 1 31-Mar-2023
Action complete. Cost increase and design timescales have extended the
proposed plan for completion. The team have now procured a new design
team with design to be progressed over 2023/24.
Liam Greene
Clydebank Masterplan, progress the next phase
delivery of improved roads and pedestrian
environment within the plan Phase 2
31-Mar-2023 Action complete. All improvement works complete. Liam Greene
Deliver a design for new traffic control system -
Kilbowie Roundabout 31-Mar-2023
Action complete. Design works now complete with materials purchased.
Future installation linked with possible Levelling Up Fund Round 3 Bid. If not
progressed through this LUF3 works will be completed with existing
infrastructure budget. This will be progressed in 2023/24.
Liam Greene
Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner

Page 6

Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
Impact of major adverse
weather incidents on
services
A significant period of adverse weather
may result on failure to deliver key
operational functions of E&N services
31-Mar-2023
The Business Continuity Plan would come
into effect in the event of a major adverse
weather incident.
No change to risk matrix
Ian Bain;
Kenny Lang
Failure to maintain road
network during adverse
weather
A significant period of adverse weather
may result in failure to deliver key
operational functions of R&T services and
other Council services.
31-Mar-2023
The service continues to put in place
contingency plans to forecast plan and
react to adverse weather conditions.
No change to risk matrix.
Liam Greene
Failure to manage and
maintain the road network
effectively
Failure to manage and maintain the road
network effectively will have an adverse
impact on user safety, traffic movement,
air quality, economic growth and reduce
access to facilities and amenities. The
Council’s reputation as a place to live
and work with access to employment,
education, leisure and health
opportunities would be adversely
affected.
31-Mar-2023
The service continued to address urgent
defects and regularly reviews the roads
maintenance programme.
No change to risk matrix.
Liam Greene
Challenges in delivering
effective services in relation
to Roads & Neighbourhoods
The risk that the Council’s fails to deliver
on the three services within Roads &
Neighbourhood: Roads & Transportation,
Fleet & Waste and Greenspace. These
areas provide services across a range of
areas including managing and maintain
roads, footpaths and associated
infrastructure, managing flood risk,
grounds maintenance, street cleaning,
burial and cremation, outdoor facilities,
waste and recycling and vehicle fleet
management. Failing to ensure these
services are not fully fit for purpose could
result in adverse consequences in
relation to delivering efficient and
effective services.
31-Mar-2023
Service continues to provide full service,
monitoring in place to ensure any adverse
issues are highlighted and appropriate
actions taken.
No change to Risk Matrix
Gail Macfarlane

Page 7

4. Our Council
Objective 10. Our workforce is resilient and skilled where digital technology supports service delivery for our residents
Action Status Progress Due Date Note Owner
Develop and implement wellbeing, employee
engagement, equality and training plans to
enable capabilities, improved resilience and
promotion of a diverse workforce.
31-Mar-
2023
Action complete. The service have developed and implemented a
communications strategy covering all levels of employee engagement.
Employee meetings are in place and managers at varying levels regularly
meet with union reps and delegates across the service. Toolbox talks and
face to face meetings are in place and request and actions taken forward.
Be the Best Discussions in place identifying opportunities for training and
upskilling.  Employees are encouraged to attend training events run by
external organisations.
Fit for the future structural review underway identifying single points of
failure in addition to the aging demographic and where there are
recruitment difficulties.
All Managers
Develop and implement employee life cycle plans
in line with the People First Strategy to attract
and retain the workforce.
31-Mar-
2023
Action complete. Training and development have been offered where
appropriate within the service, for example Waste services, Driver HGV
training will increase resilience and opportunities not only in waste but
potentially for winter gritting in future. Health & Safety training and
development in Grounds has been shared across other service areas and
simplified our response and approach to H&S. Engagement with external
services to ensure mechanics are trained in emerging technology. Reviewing
services (led by Fit for Future ) and ensuring that the service is aligned to
meet future service requirements (Route optimisation)
All Managers
Implement service review process including role
design, use of new technology and new ways of
working to add resilience, address gaps, and
establish opportunities for efficiencies
31-Mar-
2023
Action complete. Fit for Future review has identified opportunities and will
lead to service improvements. Data management and gathering has
improved allowing more informed choices and the ability to identify areas of
concern or those requiring support. Service redesign facilitated by
investment in Capital such as the Salt Dome will ensure resilience and
improves our overall flexibility and responsiveness.
A structure review is underway to identify skills gaps, opportunities for
upskilling, single point dependencies and training needs.  This will be
continued into 23/24.
All Managers
Develop and implement training plans and
development opportunities to improve
capabilities and resilience within the workforce.
31-Mar-
2023
Action complete. Training needs and future service requirements are
identified through the ongoing dialogue and engagement with staff along
with the services strategic objectives. There is limited scope in this area
All Managers

Page 8

Action Status Progress Due Date Note Owner
given the relative repetitive and manual nature of the works. Training has
been provided to increase resilience across the workforce, but opportunities
exist to make this more fluid.
External and internal opportunities to upskill are encouraged such as
attendance at CPD events. Mentoring and upskilling being implemented
where appropriate.
Objective 11. Our Council is adaptable and focused on delivering best value for our residents
Action Status Progress Due Date Note Owner
Review business plans to align activities, identify
opportunities to reduce duplication, an identify
learning opportunities (under R&N services
collaborative programme)
31-Mar-
2023
Action complete. For all forthcoming activities, regular and continual reviews
are carried out to identify opportunities for collaborative delivery,
information sharing or the potential to procure jointly. For example the joint
lead for the LEV expansion plan and strategy activity.
Gail Macfarlane
Continue to work collaboratively with Argyll &
Bute and Inverclyde Councils to develop a best
value proposal for procuring the reception,
transportation, treatment and compliant disposal
of biodegradable municipal waste.
31-Mar-
2023
Action complete. Waste services continue to work collaboratively with Argyle
& Bute Council and Inverclyde Council to establish suitable options for the
procurement of our reception, transportation, treatment and compliant
disposal of biodegradable municipal waste. The development of the route to
procure for service delivery post introduction of landfill tax ban is underway
with the procurement timelines having been defined. The next phase of this
project will progress in 2023/24.
Kenny Lang
Complete phase 1 of the Fit for Service review of
waste services
31-Mar-
2023
Action complete. Improvements to website and processes are now
concluded to improve and streamlining the customer journey for waste
services including recycling, missed bins, and assisted uplifts.
Communications strategy was implemented and addition skills training to
support resilience across the service. The next phase will progress in
2023/24.
Kenny Lang
Develop an action plan for depot rationalization 31-Mar-
2023
Action complete. Roads service continues to liaise with Asset team to
support rationalization process. Liam Greene
Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner

Page 9

Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
Challenge to delivery of
burial and cremation
services
A number of factors may impact on
ability to deliver these services.  For
example a pandemic would create
significant immediate demand on
services.
31-Mar-2023
We have completed extensions to
Dumbarton and North Dalnottar
cemeteries. This will mitigate the impact of
any challenges to the burial and cremation
services.
No change to risk matrix.
Ian Bain
Inability to deliver priority
services as a result of fuel
shortages
A fuel shortage would significantly
impacting on our ability to provide
priority service across West
Dunbartonshire.
31-Mar-2023
Council participates in the Scottish
Government Liquid Fuels Framework and
contributes to the work of the Scottish
Government Fuel Resilience Group. There
are no issues with fuel at this time.
No change to risk matrix.
Kenny Lang
Action Status
Cancelled
Overdue
Not on track
In Progress and on track
Completed
PI Status
Target significantly missed
Target narrowly missed
Target met or exceeded
Long Term Trends
Improving
No change
Getting worse
Short Term Trends
Improving
No change
Getting worse

Page 10

Risk Status
Alert
High risk
Warning
OK
Unknown