WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer – Regulatory & Regeneration
Committee: Infrastructure, Regeneration and Economic Development
Committee 24 May 2023
Subject: Regulatory & Regeneration Delivery Plan 2022/23 - Economic
Development Year-end Progress
Regulatory & Regeneration Delivery Plan 2023/24 - Economic
Development
1 Purpose
1.1 This report sets out the year-end progress of the 2022/23 Plan and presents
the new Plan for 2023/24 in relation to Economic Development.
2 Recommendations
2.1 It is recommended that Committee notes the progress achieved at year-end
and the new Plan for 2023/24.
3 Background
3.1 In line with the Strategic Planning & Performance Framework, each Chief
Officer develops an annual Delivery Plan which sets out actions to help deliver
the Strategic Plan and address the performance challenges and service
priorities identified in the planning process. The Plan also provides an
overview of services and resources, including employees and budgets, sets
out the performance indicators for monitoring progress and considers the
relevant risks.
4 Main Issues
2022/23 Year-end Performance
4.1 The 2022/23 Plan was presented to Infrastructure, Regeneration and
Economic Development Committee on 2 November 2022 and interim
progress reported on 1 February 2023.
4.2 Full details of year-end progress are set out in Appendix 1.
4.3 Of the 6 actions due to be completed by 31 March, all were completed as
planned.
4.4 Data is available for one of the five performance indicators set out in the Plan
and this met the target set.
4.5 The full set of performance indicators will be reported through the Council’s
annual performance reporting process once all data becomes available.
ITEM 7

Page 2

2023/24 Plan
4.6 An extract from the Regulatory & Regeneration 2023/24 Delivery Plan is
included in Appendix 2. This sets out the achievements and challenges for
Economic Development over the past year, as well as the priorities for the
year ahead, namely:
• monitoring and reporting the progress of the 2023/24 Economic
Development action plan;
• delivering key regeneration sites across West Dunbartonshire;
• promoting the next phase of Queens Quay Housing;
• identifying and developing commercial opportunities;
• supporting business recovery;
• supporting town centre revitalisation;
• monitoring and reporting the progress of the Climate Change Action Plan;
and
• developing a Local Heat and Energy Efficiency Strategy.
4.7 Implementation of the Plan will be monitored by the management team with
mid-year and year-end progress reported to Infrastructure, Regeneration and
Economic Development Committee around November 2023 and May 2024
respectively.
5 People Implications
5.1 There are no direct people implications arising from this report.
6 Financial & Procurement Implications
6.1 There are no direct financial or procurement implications arising from this
report.
7 Risk Analysis
7.1 Failure to deliver on the actions assigned to Economic Development may
have a direct impact on the delivery of the Council’s Strategic Plan. It is
essential that remedial action is taken to ensure strategic delivery plans
achieve the commitments detailed and approved.
8 Equalities Impact Assessment
8.1 Screening and impact assessments will be carried out on specific activities as
required.
9 Consultation
9.1 The delivery plans were developed through consultation with officers from the
strategic service areas.

Page 3

10 Strategic Assessment
10.1  The delivery plans set out actions to support the successful delivery of the
strategic priorities and objectives of the Council.
Chief Officer: Alan Douglas
Service Area: Regulatory & Regeneration
Date:  3 May 2023
_____________________________________________________________
Person to Contact:  Lynn Henderson
lynn.henderson@west-dunbarton.gov.uk
Appendices: Appendix 1: Regulatory & Regeneration Delivery Plan
2022/23 - Economic Development Year-end Progress
Appendix 2: Regulatory & Regeneration Delivery Plan
2023/24 - Economic Development
Background Papers: Regulatory & Regeneration Delivery Plan 2022/23 -
Economic Development, Infrastructure, Regeneration and
Economic Development Committee, 2 November 2022
Regulatory & Regeneration Delivery Plan 2022/23 -
Economic Development Interim Progress, Infrastructure,
Regeneration and Economic Development Committee, 1
February 2023
Strategic Planning & Performance Framework 2022/27
Wards Affected: All