Appendix 1; Roads & Neighbourhood Delivery Plan 2022/23 - Interim Progress
1. Our communities
Objective 1. Our neighbourhoods are safe, resilient and inclusive
Action Status Progress Due Date Note Owner
Review winter gritting programme and implement a
more effective service provision
31-Mar-
2023
Action complete. Winter Plan reviewed and implemented prior to the start
of the winter season. Liam Greene
Objective 2. Our residents health and wellbeing remains a priority
Action Status Progress Due Date Note Owner
Completion of deliver new gymnasium, changing
facilities and all weather running track
31-Mar-
2023
Action progressing as planned. Running track complete and final remedial
works are underway at Posties Park. Completion expected April 23. Ian Bain
2. Our Environment
Objective 4. Our local environment is protected, enhanced and valued
Action Status Progress Due Date Note Owner
Produce a revised service delivery model that
reflects the changes in quantities of plastic and
31-Mar-
2023
Action progressing but completion will be delayed due to the deposit return
scheme delay, now due August 2023, however preparatory works have
commenced.
Kenny Lang
ITEM 8 - APPENDIX 1

Page 2

Action Status Progress Due Date Note Owner
glass collections due to the introduction of a
national deposit return scheme.
Finalise the delivery of a suitable new allotment site
with provision for 40 traditional plots
31-Mar-
2023
Action progressing as planned. Draft project plans have been developed.
The allotments will be sited Dillichip Loan with an anticipated start date in
Summer 2023.
Ian Bain
Develop a new local bio diversity action plan 22/23 31-Mar-
2023
Action delayed. Consideration has been given to the inputs needed for the
new plan.  However further development of the plan is dependent on the
National Biodiversity Plan being agreed and published. This has been
delayed and is now expected in February 2023.
Ian Bain
Continue to explore alternative methods of weed
control
31-Mar-
2023
Action progressing as planned. Trials of alternative non-chemical methods of
weed control have taken place and analysis has been undertaken the results
show that of those that work effectively there could be significant cost
implications. Further work will be undertaken to prepare potential options
and next steps.
Ian Bain
Ash die back preparation work to inform the action
plan which will be developed in 2023/24
31-Mar-
2023
Action progressing as planned. The audit of affected trees in West
Dunbartonshire is underway. Ian Bain
Objective 5. Our resources are used in an environmentally sustainable way
Action Status Progress Due Date Note Owner
Produce a business case for the development of a
waste transfer station within Council’s boundary
31-Mar-
2023
Action progressing as planned. We now have a detailed feasibility study
which is being discussed at senior level prior to the Business Case being
developed.
Kenny Lang
Rollout further installation of electric vehicle
charging points
31-Mar-
2023
Action progressing as planned. Locations identified and progressing to
procurement. The Council is a partner within the wider Glasgow City Region
project to fund and develop the electric vehicle expansion plan with strategy
work underway. The new EV chargers will be sited in Old Kilpatrick and
Balloch this financial year.
Liam Greene
Action Status Progress Due Date Note Owner
Pavement parking, investigate and develop a
strategy in line with Scottish guidance Phase 2
31-Mar-
2023
Action progressing as planned. Guidance documents from Scottish
Government have been delayed and are now expected end of 2022. All
preparatory work that can be done at this stage has been completed. We
continue to liaison with other Local Authorities and attend the regional
meetings set up to discuss and plan for the upcoming legislation.
Liam Greene

Page 3

Action Status Progress Due Date Note Owner
Progress the Gruggies Burn flood alleviation scheme
Phase 1
31-Mar-
2023
Action progressing as planned. Procurement of consultant to complete the
final detailed design and undertake consultation events has been agreed.
The detailed design is now underway and will be shaped by the consultation
feedback. The consultation is planned for completion by March 23.
Liam Greene
Clydebank Masterplan, progress the next phase
delivery of improved roads and pedestrian
environment within the plan Phase 2
31-Mar-
2023
Action progressing as planned. All major works now complete for Connecting
Clydebank with some remedial work required to close out project. Additional
scope of works will be completed by end of financial year.
Liam Greene
Deliver a design for new traffic control system -
Kilbowie Roundabout
31-Mar-
2023
Action progressing as planned. Initial designs have been completed. Design
is underway for new traffic light systems and additional works in progress
that are related to Levelling Up Fund 2 submission. It is anticipated that we
will know the outcome of the LUF application at the end of January 2023.
Project scope will be determined upon LUF decision.
Liam Greene
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Impact of major adverse
weather incidents on
services
A significant period of adverse
weather may result on failure to
deliver key operational functions of
E&N services
30-Nov-2022
The Business Continuity Plan would come into effect
in the event of a major adverse weather incident.
No change to risk matrix
Ian Bain;
Kenny Lang
Failure to maintain road
network during adverse
weather
A significant period of adverse
weather may result in failure to
deliver key operational functions of
R&T services and other Council
services.
30-Nov-2022
The service continues to put in place contingency
plans to forecast plan and react to adverse weather
conditions.
No change to risk matrix.
Liam Greene;
Failure to manage and
maintain the road network
effectively
Failure to manage and maintain the
road network effectively will have an
adverse impact on user safety, traffic
movement, air quality, economic
growth and reduce access to facilities
and amenities. The Council’s
reputation as a place to live and
work with access to employment,
education, leisure and health
opportunities would be adversely
affected.
30-Nov-2022
The service continued to address urgent defects and
regularly reviews the roads maintenance programme.
No change to risk matrix.
Liam Greene

Page 4

Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Challenges in delivering
effective services in
relation to Roads &
Neighbourhoods
The risk that the Council’s fails to
deliver on the three services within
Roads & Neighbourhood: Roads &
Transportation, Fleet & Waste and
Greenspace. These areas provide
services across a range of areas
including managing and maintain
roads, footpaths and associated
infrastructure, managing flood risk,
grounds maintenance, street
cleaning, burial and cremation,
outdoor facilities, waste and
recycling and vehicle fleet
management. Failing to ensure these
services are not fully fit for purpose
could result in adverse consequences
in relation to delivering efficient and
effective services.
30-Nov-2022
Service continues to provide full service, monitoring
in place to ensure any adverse issues are highlighted
and appropriate actions taken.
No change to Risk Matrix
Gail
Macfarlane
4. Our Council
Objective 10. Our workforce is resilient and skilled where digital technology supports service delivery for our residents
Action Status Progress Due Date Note Owner
Develop and implement wellbeing, employee
engagement, equality and training plans to enable
capabilities, improved resilience and promotion of a
diverse workforce.
31-Mar-
2023
The service have developed and implemented a communications strategy
covering all levels of employee engagement. Employee meetings are in
place and managers at varying levels regularly meet with union
representatives and delegates across the service. Toolbox talks and face to
face meetings are in place.
All Managers
Develop and implement employee life cycle plans in
line with the People First Strategy to attract and
retain the workforce.
31-Mar-
2023
Training and development have been offered where appropriate within the
service, for example Waste services, Driver HGV training will increase
resilience and opportunities not only in waste but potentially for winter
gritting in future. Health & Safety training and development in Grounds has
been shared across other service areas. Engagement with external services
to ensure mechanics are trained in emerging technology.
All Managers

Page 5

Action Status Progress Due Date Note Owner
Implement service review process including role
design, use of new technology and new ways of
working to add resilience, address gaps, and
establish opportunities for efficiencies
31-Mar-
2023
Fit for Future review has identified opportunities and will lead to service
improvements. Data management and gathering has improved allowing
more informed choices and the ability to identify areas of concern or those
requiring support. Service redesign facilitated by investment in Capital such
as the Salt Dome will ensure resilience and improves our overall flexibility
and responsiveness.
All Managers
Develop and implement training plans and
development opportunities to improve capabilities
and resilience within the workforce.
31-Mar-
2023
Training needs and future service requirements are identified through the
ongoing dialogue and engagement with staff along with the services
strategic objectives. Training has been provided to increase resilience across
the workforce, opportunities exist to make this more fluid.
All Managers
Action Status Progress Due Date Note Owner
Review business plans to align activities, identify
opportunities to reduce duplication, an identify
learning opportunities (under R&N services
collaborative programme)
31-Mar-
2023
For all forthcoming activities, regular and continual reviews are carried out
to identify opportunities for collaborative delivery, information sharing or the
potential to procure jointly. For example the joint lead for the LEV expansion
plan and strategy activity.
Gail
Macfarlane
Continue to work collaboratively with Argyll & Bute
and Inverclyde Councils to develop a best value
proposal for procuring the reception, transportation,
treatment and compliant disposal of biodegradable
municipal waste
31-Mar-
2023
Waste services continue to work collaboratively with Argyle & Bute Council
and Inverclyde Council to establish suitable options for the procurement of
our reception, transportation, treatment and compliant disposal of
biodegradable municipal waste. The development of the route to procure for
service delivery post introduction of landfill tax ban is underway.
Kenny Lang
Complete phase 1 of the Fit for Service review of
waste services
31-Mar-
2023
Action progressing as planned. Internal actions and improvements to
website and processes are now concluded. Significant action on revised
delivery model being progressed.
Kenny Lang
Develop an action plan for depot rationalization 31-Mar-
2023
We have reviewed the current delivery model and working practises and
identified where resources can be shared and efficiencies achieved. We have
liaised with the unions and staff and prepared an initial draft plan for depot
rationalisation. This programme will now be progressed further by the
Assets team and we will continue to be a key stakeholder as the plan
progresses.
Liam Greene
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Challenge to delivery of
burial and cremation
services
A number of factors may impact on
ability to deliver these services.  For
example a pandemic would create
significant immediate demand on
services.
30-Nov-2022
We have completed extensions to Dumbarton and
North Dalnottar cemeteries. This will mitigate the
impact of any challenges to the burial and cremation
services. The likelihood of this risk materialising has
reduced from 3 to 1 as we have come out of the
pandemic.
Ian Bain

Page 6

Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Risk assessment reduced
Inability to deliver priority
services as a result of fuel
shortages
A fuel shortage would significantly
impacting on our ability to provide
priority service across West
Dunbartonshire.
30-Nov-2022
Council participates in the Scottish Government
Liquid Fuels Framework and contributes to the work
of the Scottish Government Fuel Resilience Group.
There are no issues with fuel at this time.
No change to risk matrix.
Kenny Lang
Action Status
Cancelled
Overdue
Not on track
In Progress and on track
Completed
Risk Status
Alert
High risk
Warning
OK
Unknown