WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
1
Project Life Financials 83 0 0% 83 0 0%
Current Year Financials 83 0 0% 83 0 0%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
2
Project Life Financials 20 13 66% 20 0 0%
Current Year Financials 7 0 0% 7 0 0%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
3
Project Life Financials 85 55 64% 85 (0) 0%
Current Year Financials 30 0 0% 27 (3) -10%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
Mitigating Action
None required.
Anticipated Outcome
Anticipate some spend this year and the remainder to be rephased into 2023/24.
Automatic Meter Readers - Water
Automatic Meter Readers.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Water meter works to be carried out in the last quarter of the year. Previous works with electricity meter supplier did not meet expectations. Await
resolutions before issuing further orders.
Mitigating Action
None required.
Anticipated Outcome
Delivery of project with full budget spend.
Replace failed heating controls/valves & recommission
Replace failed heating controls/valves & recommission.
Planned End Date Actual End Date
Main Issues / Reason for Variance
Further works ordered. Expect full spend by 31 March 2023.
Anticipated Outcome
Physical works being carried out by 31/3/23.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works are integrated with the new Baths refurbishment. Await design proposals from Vital for approval. Works to be complete by 31 March 2023
to compliment the district heating installation.
Mitigating Action
None available at this time.
Replace existing main hall Air Handling unit at Clydebank Town Hall
Replace existing main hall Air Handling unit at Clydebank Town Hall.
31 August 2022
Budget Details
Project Life Financials
Spend to Date Variance
ITEM 11

Page 2

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details
Project Life Financials
Spend to Date Variance
4
Project Life Financials 16 14 85% 16 0 0%
Current Year Financials 2 0 0% 2 (0) 0%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
5
Project Life Financials 50 0 0% 50 0 0%
Current Year Financials 50 0 0% 50 0 0%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
6
Project Life Financials 2,188 66 3% 1,651 (538) -25%
Current Year Financials 1,651 66 4% 1,250 (401) -24%
Project Description
Project Manager Gillian McNamara
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-24
Water Meter Downsize.
Lighting upgrades to LED in schools and Corporate buildings
Upgrade lighting in schools and corporate buildings.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Mitigating Action
None available at this time.
Anticipated Outcome
Improved town centres and strategic sites across West Dunbartonshire.
Regeneration/Local Economic Development
Budget to facilitate the delivery of Regeneration throughout West Dunbartonshire, aligned to the Economic
Strategy. External funding will be sought to maximise opportunities for redevelopment of these sites.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
LED budget is invested across our town centres and strategic sites and is used to develop and implement projects as well as providing match
funding to lever in external funding. During 2022/2023 the key projects to be developed and delivered include a contribution towards Smollett
Fountain public realm, enabling works at Mitchell Way subject to the timescale of the developer, development costs associated with Dumbarton
Waterfront, the Arc of Attraction Strategy and in Clydebank implementation of the Development Framework and delivery of the Activities Centre.
Many regeneration projects are subject to factors outwith Council control and close monitoring of the programming is required. A contingency is
included for increasing costs and new funding opportunities.
Initial works planned to be done at Knoxland and Gavinburn Primary schools during the October school holiday.
Mitigating Action
None available at this time.
Anticipated Outcome
Works complete 2022/23
Anticipated Outcome
Delivery of project within budget.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project integrated with Water AMR project. All works to be carried out in the last quarter of the year when the existing AMR contract requires
renewal. Expect full spend.
Mitigating Action
None required
Water Meter Downsize

Page 3

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details
Project Life Financials
Spend to Date Variance
7
Project Life Financials 9,782 4,948 51% 9,797 15 0%
Current Year Financials 2,223 50 2% 2,075 (148) -7%
Project Description
Project Manager Gillian McNamara
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-24 31-Mar-24
8
Project Life Financials 1,166 1,023 88% 1,166 0 0%
Current Year Financials 143 0 0% 143 0 0%
Project Description
Project Manager Gillian McNamara
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
9
Project Life Financials 1,456 139 10% 1,456 0 0%
Current Year Financials 1,317 0 0% 1,112 (205) -16%
Project Description
Project Manager Gillian McNamara
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
Anticipated Outcome
Progress towards delivery of planned projects from Economic Development Strategy and Charrette Action Plans albeit later than originally
anticipated.
Town Centre Fund
Scottish Government funding to help improve local town centres.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The remaining Town Centre Fund will be spent on the Smollett Fountain public realm works which will be completed by the end of the financial
year.
Mitigating Action
None available at this time.
Anticipated Outcome
Regenerated Town Centres.
Mitigating Action
Programme involves  expenditure over a number of projects led by different services. Regular reporting between services will help early
identification of risk.
Anticipated Outcome
Place-based improvements that advance Scottish Government's priorities of 20 minute neighbourhoods and carbon zero.
Place Based Investment Programme
Scottish Government Funding to establish a Place-Based Investment Programme to ensure that all place
based investments are shaped by the needs and aspirations of local communities.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The budget includes a £0.641m contribution to Titan Boulevard at Queens Quay and £0.441m towards implementation of Alexandria Masterplan
projects.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The remaining Regeneration Fund projects are Dumbarton Waterfront Path; the contribution towards the costs of Glencairn House; Connecting
Dumbarton; and the Scottish Marine Technology Park at the former Carless site. As Levelling Up Fund is programmed to be spent before
Regeneration Fund for Glencairn House and Connecting Dumbarton, it is not anticipated that any Regeneration Fund will be spent on these
projects during this financial year and will be carried forward. Spend against The £2.0m Clyde Mission funding for SMTP will continue during the
financial year 2022/2023 before an agreement is reached on the £2.0m of Regeneration Fund investment. Dumbarton Waterfront Path will be
developed according to landowner timescales, and only some spend is anticipated this year.
Mitigating Action
Programme management approach to delivery.
Regeneration Fund
Funding to implement major regeneration projects linked to community charrettes.

Page 4

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details
Project Life Financials
Spend to Date Variance
10
Project Life Financials 125 68 55% 125 0 0%
Current Year Financials 69 12 17% 69 0 0%
Project Description
Project Manager Gillian McNamara
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 30-Jun-23
11
Project Life Financials 11,220 0 0% 11,220 0 0%
Current Year Financials 3,720 0 0% 3,720 0 0%
Project Description
Project Manager Patricia Rowley/ Craig Jardine
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-24 31-Mar-24
12
Project Life Financials 34,050 2,774 8% 34,049 (1) 0%
Current Year Financials 986 94 10% 986 (0) 0%
Project Description
Project Manager Patricia Rowley/ Craig Jardine
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-27 31-Mar-27
Mitigating Action
None required.
Anticipated Outcome
Delivery of the project on time and within the increased budget.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Regular updates are provided at every Council meeting and monthly Project Board meetings and to City Deal.  The main issues contained within
the new Council's approved Outline Business Case are still valid, which include Exxon's remediation strategy, land transfer arrangements and
issues relating to adjoining owners.  WDC Consultants are monitoring the remediation process to ensure compliance with specification, also
Esso are independently monitoring the remediation works.  Final Business Case submission is November 2022. Through the Scape framework
we are working closely with Balfour Beatty to achieve a formal pre construction agreement to allow the detailed design works to commence and
the full construction programme to be developed. Agreements in principle are progressing with third party land owners.
Main Issues / Reason for Variance
Network expansion to GJNH (Golden Jubilee National Hospital) will commence pending approval to proceed by the GJNH Board. 
Mitigating Action
None available at this time.
Anticipated Outcome
Project will be delivered on budget.
District Heating Network Expansion
District Heating Network Expansion.
Planned End Date Forecast End Date
Levelling Up
Successful LUF applications that meet UK Government's over-riding objective of Levelling Up and
transformational regeneration.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This capacity funding was awarded by UK Government to assist with development of LUF bids. WDC has been awarded a grant from LUF
Round 1 and the capacity funding will be used in part to produce Artizan Centre redevelopment options. The balance will be used for
Roads/Transportation to develop a major transportation bid for LUF2.
Mitigating Action
None available at this time.
Anticipated Outcome
Successful LUF applications that meet UK Government's over-riding objective of Levelling Up and transformational regeneration.
Exxon City Deal
As part of the City Deal project the WDC Exxon site at Bowling regeneration with alternative A82 route
included.

Page 5

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details
Project Life Financials
Spend to Date Variance
13
Project Life Financials 8,535 169 2% 8,535 (0) 0%
Current Year Financials 1,715 51 3% 1,715 0 0%
Project Description
Project Manager Sharon Jump/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-25 31-Mar-25
14
Project Life Financials 1,912 353 18% 1,912 0 0%
Current Year Financials 1,912 353 18% 1,912 (0) 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-23 31-Mar-23
15
Project Life Financials 350 9 3% 350 0 0%
Current Year Financials 0 0 0% 0 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-24 31-Mar-24
Main Issues / Reason for Variance
The budget for this project has been rephased to FY 2023/2024.
Mitigating Action
None available at this time.
Anticipated Outcome
To deliver new sports changing facility.
Main Issues / Reason for Variance
Design Team have been appointed to develop feasibility options for the DRP Project, currently in stage 1 of this phase reviewing service
requirements.  The conclusion of the feasibility report will provide input for the options appraisal exercise.  The intention would be to bring a
business case to a future IRED Committee.
Mitigating Action
None available at this time.
Anticipated Outcome
Project business case will be brought back to project board, IRED and Council.
Depot Rationalisation
Depot Rationalisation.
Planned End Date Forecast End Date
Anticipated Outcome
Full budget spend anticipated.
New Sports Changing Facility Dumbarton West (Old OLSP site) 
New Sports Changing Facility Dumbarton West (Old OLSP site) 
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works progressing.
Mitigating Action
None available at this time.
Building Upgrades and H&S - lifecycle & reactive building upgrades
Lifecycle and reactive building upgrades.

Page 6

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details
Project Life Financials
Spend to Date Variance
16
Project Life Financials 150 16 11% 150 0 0%
Current Year Financials 134 0 0% 134 (0) 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-21 31-Mar-23
17
Project Life Financials 150 0 0% 150 0 0%
Current Year Financials 150 0 0% 150 0 0%
Project Description
Project Manager Michelle Lynn
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-25 31-Mar-25
18
Project Life Financials 78 0 0% 78 0 0%
Current Year Financials 78 0 0% 78 0 0%
Project Description
Project Manager Martin Feeney
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-22 31-Mar-23
Anticipated Outcome
Project delivered within budget.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Welfare Units will be purchased by the end of the financial year.
Mitigating Action
None available at this time.
Purchase of 3 Welfare Units
At Council meeting on 30th August 2017 it was agreed to purchase 3 Welfare Units as a spend-to-save
proposal.
Changing Places Toilet Provision
Changing places toilet provision in four public buildings - Balloch bus stance toilets, Concord Community
Centre, Dalmuir Community Centre and Clydebank East Community Centre.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Plans have been prepared and projects will be progressed by the end of the financial year.
Mitigating Action
None available at this time.
Anticipated Outcome
Project delivered within budget.
Anticipated Outcome
To deliver new sports changing facility.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project had been delayed due to a number of COVID-19 related issues and utilities issues.  Unit is now in production but delay to site due to the
utility disconnection and demolition works. Demolition works complete and waiting for a date for installation.
Mitigating Action
None available at this time.
New Sports Changing Facility at Lusset Glen in Old Kilpatrick
New Sports Changing Facility at Lusset Glen in Old Kilpatrick

Page 7

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details
Project Life Financials
Spend to Date Variance
19
Project Life Financials 45 0 0% 45 0 0%
Current Year Financials 45 0 0% 45 0 0%
Project Description
Project Manager Martin Feeney
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-22 31-Mar-23
20
Project Life Financials 405 7 2% 405 0 0%
Current Year Financials 405 7 2% 405 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
21
Project Life Financials 1,726 1,718 100% 1,726 0 0%
Current Year Financials 13 5 38% 13 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Mitigating Action
None required at this time.
Anticipated Outcome
Improvements to the environment of West Dunbartonshire.
Environmental Improvement Fund
This fund has been created to deliver environmental improvement projects for communities throughout West
Dunbartonshire.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Remaining budget rephased from 2021/2022 to progress with tree planting in 2022/2023 in line with the Councils Climate Change and
Biodiversity action plans.  Full budget spend anticipated.
Mitigating Action
None required at this time.
Anticipated Outcome
Better access with parks, cemeteries and open spaces.
Public non-adopted paths and roads
Upgrades to drainage and lighting to enhance the lifespan of paths and roads within  facilities in public
parks, cemeteries and civic spaces.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects are currently being developed to deliver better access in our parks, cemeteries and open spaces. Full budget spend anticipated in
2022/2023.
Main Issues / Reason for Variance
It is anticipated that spend will be achieved by the end of the financial year 2022/2023.
Mitigating Action
None available at this time.
Anticipated Outcome
Project delivered within budget.
Elevated Platforms (Building Services)
Elevated Platforms (Building Services).
Planned End Date Forecast End Date

Page 8

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details
Project Life Financials
Spend to Date Variance
22
Project Life Financials 50 37 73% 50 (0) 0%
Current Year Financials 13 0 0% 13 (0) 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
23
Project Life Financials 220 214 97% 220 0 0%
Current Year Financials 7 0 0% 7 (0) 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 03-Apr-21 31-Mar-22
24
Project Life Financials 200 0 0% 200 0 0%
Current Year Financials 30 0 0% 30 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Resurfacing of 3G pitch at East End Park.
Project works complete.  Retentions to be paid in 2022/2023.
Mitigating Action
None required at this time.
East End Park Resurfacing
Resurfacing of 3G pitch at East End Park.
Anticipated Outcome
New all weather tennis courts.
Main Issues / Reason for Variance
Planned End Date Actual End Date
Sports Facilities Upgrades - Argyll Park - Construction of 3 All Weather Tennis Courts
Project is part of wider investment in sporting facilities and is dependent on match funding from Sports
Scotland. Agreement in principle to wider WDC strategic priorities.
Anticipated Outcome
Planned End Date Forecast End Date
Sustainable burial environment for local residents.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This budget will be used to develop an area of the existing Cemetery for additional burials.  Project scope has now been developed and will be
tendered under the minor civils framework.  Budget spend anticipated in 2022/2023.
Mitigating Action
None required at this time.
Main Issues / Reason for Variance
Consultant and design team fees for resurfacing of 3G pitch at East End Park.
Mitigating Action
None required.
Anticipated Outcome
Kilmaronock Cemetery Extension
Extension of existing cemetery at Kilmaronock.

Page 9

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details
Project Life Financials
Spend to Date Variance
25
Project Life Financials 1,365 59 4% 1,365 (0) 0%
Current Year Financials 122 0 0% 122 (0) 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-Mar-22
26
Project Life Financials 210 0 0% 210 0 0%
Current Year Financials 10 0 0% 10 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 30-Nov-23 30-Nov-23
27
Project Life Financials 25 0 0% 25 0 0%
Current Year Financials 25 0 0% 25 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Development of play areas to improve accessibility and inclusiveness of play areas throughout West Dunbartonshire. Projects are being
developed for implementation over the next five years.
Mitigating Action
None required at this time.
Anticipated Outcome
Renewal of play parks
Play Parks Grant Funding
Renew and replace play park equipment
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Large bins for high traffic areas (pilot)
Supply and install extra large litter bins as a pilot project within hotspot problem areas.
Planned End Date Forecast End Date
Balloch Mountain Bike Track
Develop a mountain bike skills trail at Balloch Castle Country Park.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Design fees to develop Mountain bike skills trail in Balloch country park. Application will be submitted to Sport Scotland for match funding.
Project to commence April 2023 and works to be complete by November 2023.
Mitigating Action
None required at this time.
Anticipated Outcome
Mountain bike track
Main Issues / Reason for Variance
Supply and install extra large litter bins as a pilot project within hotspot problem areas. Project will commence when the order is received and
completion is anticipated by March 2023.
Mitigating Action
None required at this time.
Anticipated Outcome
Large bins provided for high traffic areas

Page 10

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details
Project Life Financials
Spend to Date Variance
28
Project Life Financials 228 0 0% 228 0 0%
Current Year Financials 228 0 0% 228 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
29
Project Life Financials 740 350 47% 350 (390) -53%
Current Year Financials 390 0 0% 0 (390) -100%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Jul-22 31-Jul-22
30
Project Life Financials 683 6 1% 566 (117) -17%
Current Year Financials 683 6 1% 566 (117) -17%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Nature Restoration Fund
Nature resource for Faifley Community
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Nature resource for Faifley Community
Main Issues / Reason for Variance
To develop projects including Balloch Park Phase 2, and other projects principally around National Cycle Network 7 and further pedestrian
dropped kerbs.
Mitigating Action
None required at this time.
Anticipated Outcome
To improve connectivity and enhanced Cycling routes within West Dunbartonshire.
Spaces for People
Funding has been awarded from Sustrans to assist with social distancing measures required as a result of
the COVID-19 pandemic.
Planned End Date
Mitigating Action
None required at this time.
Anticipated Outcome
To provide people of West Dunbartonshire additional space to help adhere to social distancing guidelines.
Funding received from Nature Restoration Fund to build nature resource for Faifley community has been completed and additional funding has
been received and projects are currently being developed and to be delivered by March 2023.
Mitigating Action
None required at this time.
Anticipated Outcome
Forecast End Date
Main Issues / Reason for Variance
The programme is now complete and there will be no further expenditure.
Cycling, Walking and Safer Streets
Introduction of enhanced walking routes and traffic calming schemes to introduce safer streets within West
Dunbartonshire.
Planned End Date Forecast End Date

Page 11

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details
Project Life Financials
Spend to Date Variance
31
Project Life Financials 203 0 0% 107 (96) -47%
Current Year Financials 107 0 0% 107 (0) 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
32
Project Life Financials 200 0 0% 5 (195) -97%
Current Year Financials 5 0 0% 5 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
33
Project Life Financials 60 55 91% 60 0 0%
Current Year Financials 5 0 0% 5 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Funding has been received from Turnberry Homes and will be used to introduce traffic calming and traffic
management measures to mitigate the impact of additional traffic accessing the housing development off
Castle Road, Dumbarton.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Consultation completed 2021/2022 and speed humps will be installed prior to 31 March 2023.
Forecast End Date
Main Issues / Reason for Variance
Projects and locations still to be decided.
Anticipated Outcome
To improve Footways in West Dunbartonshire.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Budget to be used for retention payment from last years surfacing of Dumbarton East footways.
Mitigating Action
None required at this time.
Mitigating Action
None required at this time.
Anticipated Outcome
To improve Footways in West Dunbartonshire.
Additional Pavement Improvements
Extra funding to accelerate pavement maintenance and improvements across West Dunbartonshire.
Footways/Cycle Path Upgrades
Renewal and/or enhancement of failed footpaths/cycle paths through West Dunbartonshire.
Planned End Date
Mitigating Action
None required at this time.
Anticipated Outcome
Traffic calming to be installed in Dumbarton East.
Turnberry Homes - traffic calming/ management at Turnberry housing development off Castle Road

Page 12

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details
Project Life Financials
Spend to Date Variance
34
Project Life Financials 314 215 68% 314 (0) 0%
Current Year Financials 100 0 0% 100 (0) 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
35
Project Life Financials 1,257 0 0% 1,257 0 0%
Current Year Financials 1,257 0 0% 1,257 0 0%
Project Description
Project Manager Raymond Walsh/ Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
36
Project Life Financials 500 0 0% 500 0 0%
Current Year Financials 500 0 0% 500 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23Forecast End Date
Main Issues / Reason for Variance
A detailed design for Gruggies Burn will be undertaken by the end of the financial year.
Mitigating Action
None required at this time.
Anticipated Outcome
Project should be complete within budget.
Anticipated Outcome
To provide Electric Vehicle Charging points within West Dunbartonshire.
Flood Risk Management
Enhancement of drainage infrastructure to ensure compliance with Flood Risk Management Act 2009.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Plans are under consideration by officers.
Mitigating Action
None required at this time.
Anticipated Outcome
Projects should be complete within budget.
Flood Prevention
Various flood prevention projects.
Planned End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Charging points to be installed at Moss O' Balloch park by the end of this financial year.
Mitigating Action
None required at this time.
Electrical Charging Points - Rapid Charge
Funding has been awarded from Transport Scotland for the Installation of electrical charging points

Page 13

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details
Project Life Financials
Spend to Date Variance
37
Project Life Financials 149 19 13% 149 0 0%
Current Year Financials 149 19 13% 149 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
38
Project Life Financials 800 181 23% 800 0 0%
Current Year Financials 620 0 0% 620 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
39
Project Life Financials 1,627 5 0% 1,075 (552) -34%
Current Year Financials 1,627 5 0% 1,075 (552) -34%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Main Issues / Reason for Variance
Work will be undertaken during this financial year for A8014 Kilbowie Road, Balloch Station Park & Ride and Bus Infrastructure Improvements.
A814 Congestion measures contractor arrived on site mid-August. Works are progressing well and completion expected by the end of December
2022 . All of these projects will be undertaken by Roads Services.
Mitigating Action
None required at this time.
Anticipated Outcome
Improve accessibility to Public Transport and improve journey time reliability.
Anticipated Outcome
Project should be completed within budget.
Strathclyde Partnership for Transport - Bus, cycling and walking infrastructure improvements & Park and Rides
Strathclyde Partnership for Transport - Bus, cycling and walking infrastructure improvements.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Awaiting outcome of Scottish Government & SEPA deliberations, however officers are hopeful full budget spend can be incurred by the end of
the financial year.
Mitigating Action
None required at this time.
Mitigating Action
None required at this time.
Anticipated Outcome
Intention is to complete works within budget.
River Leven Flood Prevention Scheme
River Leven Flood Prevention Scheme.
Infrastructure - Flooding
Essential renewal of failed drainage assets to minimise flood risk within West Dunbartonshire.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Small value projects to tackle flooding events in various areas.

Page 14

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details
Project Life Financials
Spend to Date Variance
40
Project Life Financials 3,444 21 1% 3,444 0 0%
Current Year Financials 3,444 21 1% 3,444 (0) 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
41
Project Life Financials 12 8 61% 12 0 0%
Current Year Financials 12 8 61% 12 (0) 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
42
Project Life Financials 97 35 36% 97 (0) 0%
Current Year Financials 55 0 0% 55 (0) 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Mitigating Action
None available at this time.
Anticipated Outcome
Intention is to complete works within budget.
Depot Improvement Works
Improvement of WDC Roads Depot.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This budget will be utilised for depot rationalisation works during the financial year.
Main Issues / Reason for Variance
Budget will be used for any service work carried out by Scottish Power before or after column replacement works.
Mitigating Action
None available at this time.
Anticipated Outcome
Intention is to complete works within budget.
Anticipated Outcome
Intention is to complete various surfacing works by the end of March 2023.
Street lighting and associated electrical infrastructure
WDC is responsible for the maintenance of 18,000 street lighting columns and associated illuminated signs
and bollards.  This budget is required for this infrastructure.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Roads Operations are progressing an extensive surfacing program and have a number of schemes to be completed by the end of the financial
year.
Mitigating Action
None required at this time.
Infrastructure - Roads
Infrastructure - Roads.

Page 15

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details
Project Life Financials
Spend to Date Variance
43
Project Life Financials 15,053 421 3% 15,053 (0) 0%
Current Year Financials 1,524 0 0% 1,524 0 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
44
Project Life Financials 2,325 1,007 43% 2,325 0 0%
Current Year Financials 693 0 0% 693 (0) 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-26 31-Mar-26
45
Project Life Financials 2,325 0 0% 2,325 0 0%
Current Year Financials 0 0 0% 0 0 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-26 31-Mar-26
Mitigating Action
None required at this time.
Anticipated Outcome
To provide an improved A813.
A813 Road Improvement Phase 2
A813 Road Improvement Phase 2.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
These works are not due to commence until Phase 1 has been completed.
Main Issues / Reason for Variance
Plans have been developed for carriageway widening and footway and cycleway construction between Strathleven and Lions Gate.  There are
ongoing discussions with Aggreko and other land owners in regards to access and land acquisition with construction commencing during
2022/2023.
Mitigating Action
None required at this time.
Anticipated Outcome
To provide an improved A813.
Anticipated Outcome
Project should be completed within budget.
A813 Road Improvement Phase 1
A813 Road Improvement Phase 1.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Budget to be used for a detailed design for Gruggies Burn.
Mitigating Action
None available at this time.
Gruggies Burn Flood Prevention
Commission of Gruggies Flood Prevention Scheme.

Page 16

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details
Project Life Financials
Spend to Date Variance
46
Project Life Financials 4,300 3,829 89% 4,300 (0) 0%
Current Year Financials 498 27 5% 498 (0) 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-Mar-22
47
Project Life Financials 3,930 3,846 98% 3,846 (84) -2%
Current Year Financials 84 0 0% 0 (84) -100%
Project Description
Project Manager Cameron Muir
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-May-21
48
Project Life Financials 1,039 651 63% 1,039 (0) 0%
Current Year Financials 117 8 7% 117 (0) 0%
Project Description
Project Manager Cameron Muir
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
Main Issues / Reason for Variance
Works to Lomond Bridge were completed May 2021. No further costs expected.
Mitigating Action
None required.
Anticipated Outcome
To provide an improved Lomond Bridge.
Protective overcoating to 4 over bridges River Leven
To overcoat 4 bridges over River Leven.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works to Renton footbridge are now complete and work will commence on the other bridges.
Mitigating Action
None available at this time.
Anticipated Outcome
To upgrade bridges within West Dunbartonshire.
Anticipated Outcome
Project should be completed within budget enhancing the A814 through Clydebank.
A811 Lomond Bridge
Upgrade of Lomond Bridge.
Planned End Date Actual End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works substantially complete. Additional works as a compensation event started on Wallace street in July 2022.
Mitigating Action
None required at this time.
Clydebank Charrette, A814
Clydebank Charrette, A814

Page 17

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details
Project Life Financials
Spend to Date Variance
49
Project Life Financials 80 0 0% 80 0 0%
Current Year Financials 40 0 0% 40 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
50
Project Life Financials 350 0 0% 350 0 0%
Current Year Financials 350 0 0% 350 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
51
Project Life Financials 300 0 0% 300 0 0%
Current Year Financials 300 0 0% 300 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
Purchase of Roads plant and equipment.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
New Plant to be purchased
Mitigating Action
None required.
Anticipated Outcome
To purchase equipment.
Traffic Signal Upgrades
Upgrade Traffic Signals
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Roads Plant
Projects and locations to be decided.
Mitigating Action
None required.
Anticipated Outcome
To upgrade traffic signals.
Mitigating Action
None required.
Anticipated Outcome
Resurface footways.
Footway Resurfacing (RAMP)
Footway resurfacing
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects and locations to be decided.

Page 18

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details
Project Life Financials
Spend to Date Variance
52
Project Life Financials 1,000 0 0% 1,000 0 0%
Current Year Financials 1,000 0 0% 1,000 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
53
Project Life Financials 100 0 0% 100 0 0%
Current Year Financials 100 0 0% 100 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
54
Project Life Financials 1,000 0 0% 1,000 0 0%
Current Year Financials 1,000 0 0% 1,000 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
Roads improvements
Various road improvement projects
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects and locations to be decided.
Mitigating Action
None required.
Anticipated Outcome
Improvements to roads
Street sign renewal
Renewal of street signs
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects and locations to be decided.
Mitigating Action
None required.
Anticipated Outcome
Renewal of street signage.
Pavement improvements
Various pavement improvement projects.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects and locations to be decided.
Mitigating Action
None required.
Anticipated Outcome
Improvement to pavements.

Page 19

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details
Project Life Financials
Spend to Date Variance
55
Project Life Financials 30 0 0% 30 0 0%
Current Year Financials 30 0 0% 30 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
56
Project Life Financials 400 0 0% 400 0 0%
Current Year Financials 400 0 0% 400 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-Mar-23
57
Project Life Financials 1,980 0 0% 1,980 0 0%
Current Year Financials 180 0 0% 45 (135) -75%
Project Description
Project Manager Kenny Lang
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
58
Project Life Financials 160 71 44% 160 0 0%
Current Year Financials 80 71 88% 80 0 0%
Project Description
Project Manager Kenny Lang
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Main Issues / Reason for Variance
Delivery delayed by the supplier. Full budget spend expected before the end of the financial year.
Mitigating Action
None available at this time.
Anticipated Outcome
Project delivered within  budget.
Purchase of gritters
Purchase of gritters.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Consultant project nearing completion and spend will be made thereafter.
Anticipated Outcome
Project delivered within  budget.
Water Safety
To develop Water Safety Policy & enhance water safety equipment in WDC
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Expenditure on water safety equipment will be made as required throughout the year.
Mitigating Action
None required
Anticipated Outcome
Water safety equipment as required.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Compactors have now been delivered.
Mitigating Action
None Required.
Mitigating Action
None Required.
Anticipated Outcome
Project delivered within budget.
Replacement of compactors at Dalmoak civic amenity site
The purchase of 2 compactors for the Council civic amenity site at Dalmoak.
Waste Transfer Station
The design, development and construction of a recycling and bulk waste transfer facility that will ensure all
recycling material can be sorted and disposed off appropriately to ensure compliance with landfill ban in
2025.

Page 20

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details
Project Life Financials
Spend to Date Variance
59
Project Life Financials 1,150 1,136 99% 1,150 (0) 0%
Current Year Financials 26 12 45% 26 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-22 30-Apr-22Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project complete and final account to be agreed.
Mitigating Action
None required.
Dalmonach CE Centre
To create new community facilities with additional space for early years provisions.
Anticipated Outcome
To create new community facilities with additional space for early years provisions.